Plumbing 2 - tcp2022
Plumbing 2 - tcp2022
FOR
PLUMBING INSTALLATION
IN
GOVERNMENT BUILDINGS
OF
2022 EDITION
This Testing and Commissioning (T&C) Procedure aims to lay down the minimum testing and
commissioning requirements to be carried out on Plumbing Installation in Government Buildings of the
Hong Kong Special Administrative Region (HKSAR). Such requirements are applicable to both new
installations upon completion and existing ones after major alteration.
The present edition was developed from the General Specification for Building Services
Installation in Government Buildings of the Hong Kong Special Administrative Region 2022 Edition
that was established by the Architectural Services Department (ArchSD).
Electronic version of this T&C Procedure is to be viewed on and free for download from the
ArchSD Internet homepage. As part of the Government’s efforts to limit paper consumption, hard copies
will not be put up for sale.
The ArchSD welcomes comments on this T&C Procedure at any time since the updating of this
T&C Procedure is a continuous process to tie in with technological advances.
DISCLAIMER
This T&C Procedure is solely compiled for Plumbing Installation carried out for or on behalf of
the ArchSD in Government premises of the HKSAR.
There are no representations, either expressed or implied, as to the suitability of this T&C
Procedure for purposes other than that stated above. Users who choose to adopt this T&C Procedure for
their works are responsible for making their own assessments and judgement of all information contained
here. The ArchSD does not accept any liability and responsibility for any special, indirect or
consequential loss or damages whatsoever arising out of or in connection with the use of this T&C
Procedure or reliance placed on it.
The materials contained in this document may not be pertinent or fully cover the extent of the
installation in non-government buildings and there is no intimated or implied endorsement of the sales,
supply and installation of the materials and equipment specified in this T&C Procedure within the
territory of the HKSAR.
TABLE OF CONTENTS
Page
1. Introduction 1
5. Calibrated Equipment/Instruments 24
Annex
Annex III List of Calibrated Equipment/ Instruments Necessary for the Testing and
Commissioning Works
1. Introduction
The procedures stated in this Testing and Commissioning (T&C) Procedure cover the activities
in preliminary tests and inspections, functional performance tests and the commissioning of
newly completed Installations and existing ones after major alteration. They are so compiled to
facilitate the work of Project Building Services Engineer (PBSE) and Project Building Services
Inspector (PBSI) / Project Electrical and Mechanical Inspector (PEMI), who are appointed as
the Supervising Officer’s Representatives, in the following aspects with respect to testing and
commissioning :
(a) to vet and approve the T&C procedures proposed and submitted by the contractor for
the Plumbing Installation (Contractor);
The Contractor shall carry out the T&C works as detailed in this T&C Procedure.
Supplementary T&C plans may be proposed by the Contractor as appropriate and agreed by
PBSE, e.g. for special equipment supplied and/or installed by the Contractor.
The administrative requirements for T&C works are in general as specified in the General
Specification for Building Services Installation in Government Buildings of the Hong Kong
Special Administrative Region 2022 Edition and all current corrigenda/amendments thereto
published before the date of first tender invitation for the Contract issued by the ArchSD (the
General Specification).
All words and expressions shall have the meaning as assigned to them under the General
Specification unless otherwise specified herein.
(b) to verify that the performance of the installed equipment/systems meet with the
specified design intent and statutory requirements, if any, through a series of tests and
adjustments; and
(c) to capture and record performance data of the whole Installation as the baseline for
future operation and maintenance.
For the avoidance of doubt, depending on the specific demands of individual installation, the
PBSE may require additional or substitute T&C works in regard to any elements in the
Installation other than those indicated in this T&C Procedure.
The purpose of these tests is to ensure that all components and systems are in a satisfactory and
safe condition before start up. Preliminary adjustment and setting of equipment at this stage
shall also be carried out at the same time to pave way for the coming functional performance
tests.
Before carrying out any test, the Contractor shall ensure that the Installations comply with all
relevant statutory requirements and regulations. The T&C works shall also comply with all site
safety regulatory requirements currently in force. In particular, the Contractor shall note the
statutory requirements listed in the General Specification in carrying out the works.
The purpose of functional performance tests is to demonstrate that the Installations can meet the
functional and performance requirements as specified in the Contract. Functional performance
tests should proceed from the testing of individual components to the testing of different systems
in the Installations.
The Contractor may have to make temporary modifications as the tests proceed. The specific
tests required and the order of tests will vary depending on the type and size of systems, number
of systems, sequence of construction, interface with other installations, relationship with the
building elements and other specific requirements as indicated in the Contract. The testing of
systems may have to be carried out in stages depending on the progress of work or as proposed
by the Contractor.
Part of the tests may be required to be carried out in suppliers’ premises in accordance with the
provisions in the Contract.
Any performance deficiencies revealed during the functional performance tests must be
evaluated to determine the cause. After completion of the necessary corrective measures, the
Contractor shall repeat the tests.
If any test cannot be completed because of circumstances that are beyond the control of the
Contractor, it shall be properly documented and reported to the PBSE, who shall then liaise with
the relevant parties to resolve the situation. The Contractor shall resume his testing work
immediately upon the attainment of a suitable testing environment.
Commissioning is the advancement of the Installations from the stage of static completion to full
working conditions and to meet the performance requirements as specified in the Contract. This
will include setting into operation and regulation of the Installations. Fine-tuning of the
commissioned system shall be done by the Contractor to match system performance to the actual
needs of the building occupier more closely.
The Contractor shall submit his proposed T&C procedures together with the Testing and
Commissioning Progress Chart shown in Annex I to PBSE for approval.
All inspection and T&C results shall be recorded by the Contractor in the appropriate test record
forms. A complete set of these forms can be found in Annex II.
Data recorded in other formats may also be acceptable subject to prior approval of the PBSE.
Upon completion of all the required T&C works, the Contractor shall complete and sign a testing
and commissioning certificate as shown Annex II to the effect that the agreed T&C works have
been duly carried out.
A functional performance test report covering all measured data, data sheets, and a
comprehensive summary describing the operation of the system at the time of the functional
performance tests shall be prepared and submitted to the PBSE. Deviations in performance as
specified in the Contract or the design intent should be recorded, with a description and analysis
included.
Where required in the Contract, the Contractor shall conduct a final evaluation of the
performance of the Installations, the results of which shall be included in the commissioning
report.
3.5.1 Systems shall be properly commissioned to demonstrate that all the equipment deliver
the designed capacities and that water flow rate is properly balanced in accordance
with the design. Prior to any commissioning works, the Contractor shall check the
completion of the associated builder’s work and the building services installations, to
ensure that commissioning can be proceeded without obstruction.
(v) All external doors, all stairs and lobbies, and toilet doors are
completed and securable.
(iii) All functional and safety devices are installed and operational.
Where necessary, after the proper testing and commissioning of the Installations, the
Contractor shall notify the appropriate Authority as specified in the Contract, through
the PBSE on the completion of the Installations and its readiness for final inspection.
3.5.2 All aspects of the commissioning procedure shall follow the recommendations
including but not limited to:-
(a) Preliminary checks to ensure that all systems and system components are
in a satisfactory and safe condition before start up;
(b) Preliminary adjustment and setting of all plant and equipment consistent
with eventual design performance;
(d) Final regulation and demonstration that the installation delivers the
correct rate of flow of fluids at the conditions specified in the Contract
documents.
The Contractor shall not wait for completion of every part of the work but shall
arrange for a progressive commissioning programme to achieve practical overall
completion and have the whole work ready to be handed over by a date to suit the
Contract completion date or any other agreed programme date.
The final tests shall be carried out in the presence of Licensed Plumber or his
representative (for plumbing installation).
(a) Work tests shall be carried out in accordance with the type normally
associated with the specified item of equipment and to the standards as
laid down in the Contract.
(b) Work static pressure tests shall be carried out for all items of plant and
equipment, as laid down in the Contract.
4.1.2 Tests for Jointing of Copper Pipes for Potable Water Supply
(a) All soldering/brazing joints of copper pipes for potable water supply shall
be in compliance with the chemical composition of lead-free grade to
Table 3 of BS EN ISO 9453:2020 and cadmium-free grade to Table 7 of
BS EN ISO 17672:2016 respectively.
(b) All pipe-fittings integrated with solder materials shall undergo random
lead checks. Upon delivery of pipe-fittings with integral solder materials
to site, samples shall be taken randomly from each batch of such pipe-
fittings under the same GA Reference Number for conducting lead check
on soldering materials prior to using that subject batch in plumbing
installations. The number of samples to be taken for lead check will
depend on the overall batch size. Pipe-fittings of different sizes and types
under the same GA Reference Number delivered to site on the same date
can be regarded as one batch for the purpose of sampling for lead check,
i.e. minimum 1% of the total number of fittings (for all types and sizes in
the batch) with a max of 10 samples. Pipe-fittings of different GA
Reference Numbers are regarded as different batches even if they are
delivered to site on the same date. All the samples in a batch shall pass
the lead check before the batch shall be allowed to be used in the project.
(c) The Contractor shall keep samples of soldering/ brazing joints done by
each individual plumber(s)/ worker(s) and submitted to project site staff
for checking.
4.1.3 Mandatory Lead Check for Soldering Materials in Pipe-fittings with Integral Solder
Ring upon delivery to Site
(c) Pipe-fittings of different sizes and types under the same GA Reference
Number delivered to site on the same date can be regarded as one batch
for the purpose of sampling for lead check, i.e. minimum 1% of the total
number of fittings (for all types and sizes in the batch) with a max of 10
samples. Pipe-fittings of different GA Reference Numbers are regarded
as different batches even if they are delivered to site on the same date.
(d) All the samples in a batch shall pass the lead check before the batch shall
be allowed to be used in the project.
(a) divide the pipework system into self-draining sections so that the
maximum possible flushing rate is achieved;
(b) that the system has been cleaned in accordance with para.
4.1.3.1; and
(c) that temporary water for pipe flushing is available, or, permanent
water connections have been made.
(a) that probes, pockets, pressure gauges, taps and air vents are
installed;
(b) that drains and overflows are connected and free from blockage;
(d) that control and non-return valves are installed the right way
round;
(e) that relief valves are installed as specified and are free to operate;
(f) that relief valve outlets are piped away to suitable drain points;
(h) that the strainer meshes are of the correct grade and material;
(k) that drain cocks are closed and other valves are left open or
closed according to the plan for filling;
(m) that all pipework and fittings are adequately supported, guided
and/or anchored where applicable.
(a) Pumps
(3) that all components, bolts, fixings, tie bars etc., are
secured;
(5) the level and plumb of pump and motor shaft and slide
rails; (direct drive pumps require particular attention in
this respect);
(14) that glands are correctly packed and the gland nuts are
finger-tight only, pending adjustment to correct drip
rate after start-up; and
(15) that drive guards are fitted and the access for speed
measurement is provided.
(2) that all components, bolts, fixings, tie bars etc., are
secured;
(1) that the valves are installed the correct way round;
(4) that the motor and surrounding areas are clean and dry;
(9) that all power and control wirings have been completed
in detail to the circuit diagram, paying special attention
to circuit for start-delta connected or specially wound
motors;
All water tanks shall, after erection, be filled with water and shall remain
filled for at least 24 hours during which all joints shall be carefully
examined. Any defect shall be rectified immediately and the test repeated.
Before finally charging, the water systems shall be thoroughly flushed and
all strainers, filters, etc. cleaned or replaced.
(a) General
The hydraulic test pressure shall be 1.5 times the maximum static
pressure whichever is higher if it does not exceed 1.5MPa or 1.3
times the maximum static pressure if it exceeds 1.5MPa.
- Date of test
- Apparatus or section under test by mark up the vertical
plumbing diagram / plumbing plan with colour
- Makers number (if any)
- Nature, duration and conditions of test
- Result of test
- Name of Contractor’s representative (in block letter) in
charge of test
- Name of Supervisor Officer’s Representative at witness of
the test
(a) all normally open isolating and regulating valves are fully open
and that all normally close valves are closed;
(b) the direction sign of all non-return valves is along the same
discharge direction of associated pumps;
(d) fully open the return and close the flow valve on the pump, close
valves on standby pump. Closing the flow valve on the duty
pump will limit the initial starting current, which is usually
excessive at the first time a pump is running due to bearing
stiffness.
(d) check that the bearings and motor temperature remain steady,
that no noise or vibration develops and that no bolts or fixing
works is loosen;
(e) open the drain valve of the pressure vessel and drain out the
water from the vessel to monitor the cut in and cut out pressure.
(b) this pump can be checked against the other duty pump. In the
unlikely event of failure of the duty pump, commissioning can
continue using standby pump; and
(c) carry out a full diagnosis of the reasons for the failure of the duty
pump before energising the standby pump to ensure that any
contributory causes are remedied.
Provided that all pipes and fittings intended to be installed are approved by the Water
Authority, the Contractor shall engage designated persons under WWO Chapter 102
to carry out / to supervise installation and to submit Waterworks Form WWO46 (Part
I and II) to Water Supplies Department (WSD) for notification before commencement
of plumbing work.
The Contractor shall maintain a sample board on site which shall display samples of
taps, shower mixers, valves and pipes listed in the Form WWO1149 as well as solder
materials if used, relevant certificates/testing reports/catalogues, etc. as appropriate
are also required to be provided together with the sample board relevant
certificates/testing reports/catalogues, etc. for checking by WSD.
Each sample, with clear numbering and labelling, shall be firmly fixed onto a rigid
wooden or metal board. A list shall also be affixed on the sample board to show the
item description, make and brand, country of origin and locations of installation.
The Contractor shall arrange all necessary inspections and approvals from the
statutory authorities, i.e. WSD, in accordance with the Waterworks Ordinance (Cap.
102), for the following provisions: (a) Connection pipe provision; (b) Water meter/
check meter provision; (c) Water storage cistern provision.
During the final inspection of the inside service by WA, non-destructive tests of lead
content at solder joints selected by the WA shall be carried out and WA will then
randomly select water sampling points for conducting the water quality tests by the
Contractor.
4.1.7 Tests and Inspections for Projects Adopting Modular Integrated Construction (MiC)
Method
(b) satisfactory results of the interim inspections carried out by the Inspection
Agent of the WA on the concealed parts of the plumbing works before
they are covered up in the MiC factory
All water distribution pipework and water storage tanks shall be thoroughly flushed
clean to remove rust, sludge and sediment upon commissioning. Potable water
distribution pipework and associated water storage tanks shall be further disinfected
before they are put into operation in accordance with the requirements in WSD ’s
Guide to Application for Water Supply, to remove organic matter which encourages
the growth of biofilms and subsequently deterioration of water quality.
The Contractor shall submit a systematic flushing, cleansing & disinfection plan
indicating the scope of work, detail of the compartmentation if any, work schedule,
method statement for the disinfection work, detailed work sequence/procedures and
equipment/tools for checking and testing, location of sampling, method statement for
the de-chlorination, etc. for PBSE’s approval prior to carrying out the disinfection
work.
The Contractor shall arrange all necessary cleaning and disinfection of the water
pipework upstream of the water meter, i.e. from the incoming fresh water mains to
the water meter/check meter of the premise and the inside service, to the satisfaction
of WSD.
(c) Thoroughly flush the inside services at all drinking water taps
after (b);
(d) Allow the water in the inside services to stand overnight for at
least 12 hours;
(e) Conduct three flushing cycles for (a) to (d) above; and
(f) Final thorough flushing at all drinking water taps after three
cycles of the systematic flushing.
For underground fresh water mains, it shall be swab to remove the dirt
and materials inadvertently left in the water mains and flush them with
potable water. Then, it shall be completely filled with a homogeneous
solution of chloride of lime for disinfection. The concentration of the
solution has to meet the requirement that when the water mains are filled
up with water, the free chlorine in the water will be at least 30 ppm. Keep
the water mains under disinfection for at least 24 hours. After
disinfection, flush the water mains thoroughly with potable water.
Persons undertaking the disinfection shall be suitable trained and
qualified.
For other fresh water inside service, follow one of the three procedures
stated below to disinfect the inside service concerned:-
(c) Fill the inside service concerned with the disinfectant solution
other than chlorine at the initial concentration and for the
contact time specified by the manufacturer of the disinfectant.
The disinfectant solution shall not contain any substances in
quantities capable of causing deleterious or injurious health
effects to consumers using the inside service disinfected in
accordance with the manufacturer’s instructions/
recommendations. If the residual of the disinfectant at the end
of the contact time is less than the manufacturer’s
recommendation, the disinfection procedure shall be repeated.
After successful disinfection, the inside service shall be
immediately drained and thoroughly flushed with potable
water. Flushing shall continue in accordance with the
disinfectant manufacturer’s instructions/ recommendations or
until there is no evidence of the disinfectant chemical being
present, or it is at a level that is no higher than that present in
the potable water supplied.
The Contractor shall arrange all necessary cleaning and disinfection of the
potable water supply pipework downstream after the water meter/check
meter and water storage tanks not more than 7 days before hand over the
water supply system to users for operation. Where the potable water
supply system is not brought into use immediately after disinfection, it
shall be disinfected before use unless it has been flushed weekly at full
flow for a minimum period of one minute. If the water supply installation
is partially handed over for operation by the users, the Contractor shall
continuously flush the remaining portion of the system at regular interval
until the whole system has been handed over for operation to the user or
after the issue of Building Hand-Over Certificate (Form No. D/CA.320)
by the Supervising Officer.
The Contractor shall carry out Water Sampling Tests after systematic
flushing, cleansing and disinfection of the plumbing system. Prior to
conducting any tests, PBSE shall request the contractor to submit
sampling and analysis methodology, including name of the accredited
laboratory to be appointed and procedures from collection of test samples
to submission of test results, for approval. The contractor shall declare in
writing that the accredited laboratory appointed has no affiliation as a
legal entity to the contractor and its sub-contractors.
Water samples shall not be taken at the following drinking water tap or
sampling tap:
(b) Drinking water tap installed with an inline water filter or a point-
of-use filter with no bypass switch;
PBSE/project site staff shall agree with the contractor either (i) to appoint
representative(s) from the accredited laboratory to collect test samples
on site or (ii) to arrange contractor’s representative(s) to collect test
The number and location of Water Samples and its collection procedures
for Heterotrophic Plate Count (HPC) test and metal, chemical, physical
& E. coli tests shall follow WSD’s procedure, Section 4.4 and Appendix
19 of Guide to Application for Water Supply. The sampling and analysis
of the on-site water samples shall be carried out by organisations
accredited by the Hong Kong Laboratory Accreditation Scheme
(HOKLAS) or Hong Kong Accreditation Service (HKAS), or
organisations accredited by an accreditation scheme mutually recognised
by HOKLAS or HKAS. All water samples shall be properly labelled
immediately after collection, packed in a plastic bag and stored in a cold
box for the transportation before delivered to an accredited organisation.
Licensed Plumber shall supervise the sampling process.
The test parameters of water samples shall include but not limited to the
following:-
PBSE/project site staff shall supervise the transport and delivery of test
samples to the accredited organisation. If the contractor appointed
representative(s) from the accredited organisation to collect test samples
on site, PBSE/project site staff shall witness that representative(s) from
the accredited organization kept the test samples in sealed container
before leaving the site. If the contractor arranged their own
representative(s) to collect test samples on site, PBSE/project site staff
shall escort the representative(s) on delivery of test samples in sealed
container from the site to the accredited laboratory.
If any result(s) of the water sampling test(s) fails to comply with any of
the acceptance criteria mentioned above, re-testing shall be carried out
as below:-
Parameters Scenarios
Physical and Pass or Fail Fail Pass
Chemical
Bacteriological Pass or Fail Pass Fail
(E.coli and HPC)
Parameters to be All parameters All parameters other than
retested metal
(a) record the operating speeds of the equipment (i.e. driving speed of
motor) indicated on the nameplates, drawings or measured by speed-
measuring device;
(c) perform visual and audible checks for any apparent rough operation of
the equipment or any defective bearings, misalignment, etc;
T&C of hot water boiler and calorifier system shall follow the T&C Procedure for
Steam Boiler and Calorifier as published by ArchSD.
T&C of solar hot water heating system shall follow the T&C Procedure for Air-
conditioning, Mechanical Ventilation and Refrigeration Installation as published by
ArchSD.
T&C of the whole hot water supply distribution system, except the Hot Water Boiler
and Calorifier System as stipulated in Clause 4.2.1 and the Solar Water Heating
System as stipulated in Clause 4.2.2 shall follow the Cold Water Supply Installation
as stipulated in Clause 4.1, including the cleaning and disinfection of potable water
supply installation and water storage tank as described in clause 4.1.6.
T&C of the whole flushing water supply distribution system shall follow the Cold Water Supply
Installation as stipulated in Clause 4.1, except that disinfection of the pipework and water
storage tanks is not required.
The Contractor shall inspect the supplied equipment for verification of the brand,
model, capacity, clock speed, ratings, specifications, serial numbers of the hardware
as well as the brand, version, serial number, licence keys, licence documents of all
hardware, software and firmware supplied.
The Contractor shall carry out equipment test including, but not limited to, the
following procedures:
(b) Demonstrate that all spare memory, equipment capacity and system
expansion requirements;
(c) Demonstrate that all input and output expansion requirements have been
met, including wiring and signal isolation, and verify that power supplies
are capable of supporting the increased load for this expansion;
(f) Verify proper earth connections and isolation of instrumentation earth for
all equipment;
(g) Demonstrate that all preloaded software and firmware have been properly
installed and are operating correctly;
After completing the installation of the AMR Outstation and prior to setting to work,
individual equipment shall be tested to ensure that it performs in accordance with the
specified requirements and is in satisfactory working conditions.
Before carrying out the required site test, the Contractor shall ensure the following:
(b) All cables and individual conductors are labelled and ferruled as per the
relevant drawings;
(c) All items of the AMR Outstation are adequately and correctly labelled
and identified;
(d) The insulation resistance and continuity of all conductors of cables, etc.
are acceptable;
(e) The earthing arrangements are completed and a satisfactory value of earth
loop impedance has been achieved; and
The test procedures and format of test records shall be submitted to the WSD for
approval prior to the scheduled commencement of testing and commissioning.
The Contractor shall submit a comprehensive T&C procedure including, but not
limited to, the following items for approval:
(a) Integrity of the AMR data on the data concentration unit (DCU);
(d) Configuration and operation check on the meter interfacing units (MIUs);
(g) Operation check on the AMR Outstation upon a.c. power supply failure;
Final acceptance test for full function of the AMR Outstation including successful
data transmission to the AMR Master Station shall be conducted by the Contractor to
the satisfaction of the WSD.
The Contractor shall supply calibrated equipment/instruments and shall make available to the
PBSE the calibration certificate of the testing equipment/instruments and the associated
calibration records etc. before the relevant test is performed as stipulated in the Contract for the
inspection, measuring and testing of the Installations. (Remarks: The equipment shall be
calibrated by by organisations accredited by the Hong Kong Laboratory Accreditation Scheme
under the (HOKLAS) or by the Hong Kong Accreditation Service (HKAS), or organisations
accredited by an accreditation scheme mutually recognised by HOKLAS or HKAS.)
A list of testing equipment/ instruments proposed by the Contractor to be used for T&C (Annex
III) must be agreed with the PBSE prior to commissioning the work.
Contract Number :
Contract Title :
Name of Sub-contractor :
Testing and Commissioning Progress Chart for Plumbing Installation (Rev. ) (Note 1)
Dates Remark
(Note 2)
Activities Reference S A S A S A S A S A S A S A S A
to T&C
Procedure
1. Cold Water Supply 4.1
1.1 Cleanliness & State 4.1.4.1,
Check 4.1.4.2
1.2 Mechanical Check 4.1.4.4
1.3 Electrical Check 4.1.4.5
1.4 Hydraulic testing for 4.1.4.7
water distribution
pipe work system
1.5 Solder Joint 4.1.2
Sampling Check
1.6 Check for Pump 4.1.5
head and flow
1.7 Statutory Inspection 4.1.6
by Licensed Plumber
1.8 Connection Pipe Ditto
Provision
1.9 Water Meter/ Check Ditto
Meter Provision
1.10 Water Storage Ditto
Cistern Provision
1.11 Systematic Flushing. 4.1.8
Cleaning,
Disinfection and
Water Sampling
1.12 Vibration Tests 4.1.9
Activities Reference S A S A S A S A S A S A S A S A
to T&C
Procedure
Activities Reference S A S A S A S A S A S A S A S A
to T&C
Procedure
Notes
* Delete as appropriate
(1) Insert revision no.
(2) Insert additional columns as necessary
S - schedule % completion
A - actual % completion
2.2 I also certify that site tests have been performed in accordance with the requirements
set in this T&C Procedure and that the results are satisfactory. A record of the tests
has been prepared and submitted to the *PBSE.
a) General Requirements as indicated in the T&C Procedure have been *Yes/No/N.A. *Yes/No/N.A.
complied.
b) Licensed Plumber (LP) shall be appointed to carry out the plumbing work *Yes/No/N.A. *Yes/No/N.A.
and undertake the correctness of the installation to WSD.
c) Upon delivery of soldering and brazing materials to site with LP for *Yes/No/N.A. *Yes/No/N.A.
connection of copper pipes, verification is done on checking the approved
materials including samples and document submission.
e) All pipes and fittings intended to be installed are approved by the WSD. *Yes/No/N.A. *Yes/No/N.A.
a) Size of the Connection Pipe shall be adequate to supply all plumbing *Yes/No/N.A. *Yes/No/N.A.
installations. (TR 4.3.5.3)
b) All Piping including the Connection Pipe before meter positions shall be *Yes/No/N.A. *Yes/No/N.A.
exposed or laid in a proper service duct. (TR 3.3.2.2, 4.2.4.1, 4.3.5.3 &
5.4.1.4)
a) Meters on indirect supply systems shall be sited at roof level or at other *Yes/No/N.A. *Yes/No/N.A.
convenient locations and housed in meter rooms/boxes.
b) Check meter positions will be required at the connections to the common *Yes/No/N.A. *Yes/No/N.A.
inside service and to the sump tank.
c) Proper drainage, lighting and flood prevention facilities shall be provided at *Yes/No/N.A. *Yes/No/N.A.
the water meter room. (WW Reg 27, TR 3.1.9, 3.2.2.4, 3.2.2.5, 3.2.3.1,
3.2.4.1 & 3.3.5)
d) All domestic units shall be separately metered (TR 3.1.3). *Yes/No/N.A. *Yes/No/N.A.
Water supplies for metering types are classified into domestic, construction,
shipping and trade purposes.
(WW Reg. 2)
f) Meters shall be arranged in groups and sited at convenient locations in *Yes/No/N.A. *Yes/No/N.A.
communal area and housed in meter rooms/boxes. (TR 3.2.1.2, 3.2.2.4,
3.2.2.5, 3.2.3.1, 3.2.4.1 & 3.3.5)
g) Brass fittings shall be used at meter position if copper, lined galvanised steel *Yes/No/N.A. *Yes/No/N.A.
or thermal plastic materials are used inside service. PVC-U fittings shall be
used at meter position if PVC-U materials are used as inside service. (TR
3.2.1.4)
a) Every cistern shall be located so as to minimise the risk of contamination of *Yes/No/N.A. *Yes/No/N.A.
the stored water. (WW Reg. Sch. 2 Pt III Para 4 & 9, TR 6.2.1.2 & 6.2.3.1)
b) Every cistern shall be constructed of concrete, galvanised steel or other *Yes/No/N.A. *Yes/No/N.A.
approved material. Fibreglass storage cisterns for potable water shall be of
an approved type. (WW Reg Sch 2 Pt III Para 2 & 3, TR 4.3.2 & 6.2.2.4)
c) Cisterns shall be fitted with a ball valve controlled inlet in the case of a *Yes/No/N.A. *Yes/No/N.A.
gravity supply or with an automatic control switch in the case of a pumped
supply.
d) Ball valves of the water cistern are readily accessible. *Yes/No/N.A. *Yes/No/N.A.
e) An overflow pipe of one commercial size larger than the inlet pipe, and in no *Yes/No/N.A. *Yes/No/N.A.
case less than 25 mm diameter, shall be fitted to each cistern and shall be
extended to terminate in a conspicuous position in a communal area easily
visible and accessible by the occupants.
f) No part of the overflow pipe shall be submerged inside the storage cistern. *Yes/No/N.A. *Yes/No/N.A.
The top of the overflow pipe shall be not less than 25mm below the invert of
the inlet pipe or the face of the outlet nose of the ball valve. (TR 6.2.4.2.9)
g) A stop valve shall be provided on the outlet of every cistern and provision *Yes/No/N.A. *Yes/No/N.A.
shall be made for a drain off pipe to enable the cistern to be emptied.
h) Safe access shall be provided to all cisterns by means of a secure permanent *Yes/No/N.A. *Yes/No/N.A.
ladder or readily available portable ladder.
i) A grating and a self-closing non-return flap shall be provided at the overflow *Yes/No/N.A. *Yes/No/N.A.
pipe outside the storage cistern.
j) Double sealed covers with locking devices shall be provided for all storage *Yes/No/N.A. *Yes/No/N.A.
cisterns other than cisterns for flushing and fire-fighting purposes. (WW Reg
k) Cistern shall be fitted with a ball valve and a fullway gate valve at the inlet *Yes/No/N.A. *Yes/No/N.A.
in the case of a gravity supply or with an automatic control switch and
without any stop valve in the case of a pumped supply.
l) Float switches in the water tanks for controlling the water pumps function *Yes/No/N.A. *Yes/No/N.A.
properly.
m) High and low water level indications for the water tanks function properly. *Yes/No/N.A. *Yes/No/N.A.
n) Size of the water pump suction water pipe from the water tank is matched *Yes/No/N.A. *Yes/No/N.A.
with the size of the pump suction inlet.
o) Each water pump is provided with an independent suction pipe from supply *Yes/No/N.A. *Yes/No/N.A.
tank.
q) Cleaning and disinfection of each potable water storage tank not more than *Yes/No/N.A. *Yes/No/N.A.
7 days in advance before handed over.
3.1.5 Piping
a) Pipes and fittings shall conform to Part I of Schedule 2 of the Waterworks *Yes/No/N.A. *Yes/No/N.A.
Regulations.
b) Hydraulic tests are performed satisfactorily for water tightness of all sections *Yes/No/N.A. *Yes/No/N.A.
of the pipework.
c) Lead-free and Cadmium-free solder which shall comply with BS EN ISO *Yes/No/N.A. *Yes/No/N.A.
9453:2014 and BS EN ISO 17672:2016 are used respectively for copper pipe
and fitting connections
d) Pipes on fresh water inside service shall be made of cast iron, ductile iron, *Yes/No/N.A. *Yes/No/N.A.
PVC-U, polybutylene, steel or copper or any approved material.
e) No pipe shall be less than 20 mm diameter, except that a branch pipe may be *Yes/No/N.A. *Yes/No/N.A.
15 mm diameter if the pipe run is short and the pipe supplies only one draw-
off point. (WW Reg Sch. 2 Pt. I Para. 2)
f) All pipework before meter positions shall be exposed or laid in proper service *Yes/No/N.A. *Yes/No/N.A.
duct.
(TR 3.3.2.2, 4.2.4.1, 4.3.5.3 & 5.4.1.4)
g) The piping which solely serve a particular flat/unit shall not run through other *Yes/No/N.A. *Yes/No/N.A.
flats/units as far as practicable.
h) A loose jumper type stopcock shall be provided and placed with spindle in *Yes/No/N.A. *Yes/No/N.A.
the vertical position before the meter position.
j) Cisterns shall be fitted with a ball valve and a fullway gate valve at the inlet *Yes/No/N.A. *Yes/No/N.A.
in the case of a gravity supply or with an automatic control switch and
without any stop valve in the case of a pumped supply.
k) Fullway gate valve shall be provided on the outlets of every cistern. *Yes/No/N.A. *Yes/No/N.A.
l) Spring taps, of non-concussive type and of approved pattern, shall be used *Yes/No/N.A. *Yes/No/N.A.
for public or communal lavatory basins.
m) For connections larger than 40 mm diameter, a gate valve shall be provided *Yes/No/N.A. *Yes/No/N.A.
before the meter position and a non-return or check valve fitted on the
delivery side as close as possible to the meter. (TR 3.1.5, 3.1.6, 3.1.7,
6.2.4.2.9, 6.2.4.3.3 & 6.7.1.2)
n) Individual stop valves shall be provided at all draw-off points or at a series *Yes/No/N.A. *Yes/No/N.A.
of draw-off points if situated close together. (TR 6.6.1)
o) Boundary valves shall be provided at the connection points as close to the lot *Yes/No/N.A. *Yes/No/N.A.
boundary as possible. (TR 3.1.9, 3.3.5 & 3.3.4.12)
q) Stop valve shall be provided to the supply pipe serving the series of draw-off *Yes/No/N.A. *Yes/No/N.A.
points.
(TR 6.6.1)
s) The number and length of spur of the piping shall be minimised. *Yes/No/N.A. *Yes/No/N.A.
t) Purge valves is provided at the pipe ends of all unavoidable spurs or stagnant *Yes/No/N.A. *Yes/No/N.A.
points for weekly purging.
u) When infra-red sensor operated automatic taps are used as inside services, a *Yes/No/N.A. *Yes/No/N.A.
stop cock or gate valve must be installed at the upstream of each fitting for
manual isolation of water supply.
v) Self-closing taps, of non-concussive type and of approved pattern, shall be *Yes/No/N.A. *Yes/No/N.A.
used for the public or communal lavatory basins.
w) Flow rate of each draw-off tap, shower fitting and float-operated valve shall *Yes/No/N.A. *Yes/No/N.A.
be the same as the specified requirement.
x) All pipework is properly electrically bonded for equipotential bonding. *Yes/No/N.A. *Yes/No/N.A.
a) All piping are properly flushed and ensure no foreign objects trapped inside. *Yes/No/N.A. *Yes/No/N.A.
b) The equipment associated with the system has undergone the mechanical and *Yes/No/N.A. *Yes/No/N.A.
electrical checks and the results are satisfactory.
e) By-pass arrangement shall be incorporated with the provision of a second *Yes/No/N.A. *Yes/No/N.A.
pressure reducing valve, except for fire service installations for ease of
replacement.
f) Pressure indicator shall be installed at the Pressure Reducing Valve system *Yes/No/N.A. *Yes/No/N.A.
for pressure monitoring.
h) The hot-water draw-off point shall be at the left hand side. *Yes/No/N.A. *Yes/No/N.A.
i) The water flow rates of the system have been regulated and balanced in *Yes/No/N.A. *Yes/No/N.A.
accordance with this T&C Procedure. The results are satisfactory meeting
the specified requirements.
j) Cleaning and disinfection of the potable cold water piping system is *Yes/No/N.A. *Yes/No/N.A.
conducted not more than 7 days in advance before being put into operation.
k) The potable cold water piping system is flushed thoroughly after *Yes/No/N.A. *Yes/No/N.A.
disinfection.
m) After disinfection of the potable cold water piping system as described in *Yes/No/N.A. *Yes/No/N.A.
clause 3.1.9(k), the system is maintained for regular flushing weekly until
hand over to clients for operation.
n) Proper record of cleaning and disinfection is provided during handover. *Yes/No/N.A. *Yes/No/N.A.
o) Proper record of water sampling test for four additional test parameters, i.e. *Yes/No/N.A. *Yes/No/N.A.
Lead, Cadmium, Chromium and Nickel as required. (Guide to Application
for Water Supply)
p) Sample board(s) for taps, shower mixers, valves, pipes, solder material (if *Yes/No/N.A. *Yes/No/N.A.
used), etc. as listed in the Form WWO1149 Guide to Application for Water
Supply)
b) Water pumps and motors are run at the designed discharge water pressure *Yes/No/N.A. *Yes/No/N.A.
and operating electrical current.
c) Water pumps are run at an acceptable noise and vibration levels. *Yes/No/N.A. *Yes/No/N.A.
d) Water pump control switches and indicating lights function properly. *Yes/No/N.A. *Yes/No/N.A.
f) The temperatures of the water pump bearings at running condition are *Yes/No/N.A. *Yes/No/N.A.
normal.
g) The temperatures of the pump motors at running condition are normal. *Yes/No/N.A. *Yes/No/N.A.
h) Non-return valves connected to the pumps function are installed properly. *Yes/No/N.A. *Yes/No/N.A.
i) A fullway gate valve shall be provided on the drain-off pipe. (TR 6.2.4.3.3) *Yes/No/N.A. *Yes/No/N.A.
j) Prior to pump start-up, the contractor shall check the horizontal or vertical *Yes/No/N.A. *Yes/No/N.A.
alignment of all flexible joints is within the tolerances recommended by the
manufacturers’ installation guideline.
k) Measurement
a) The electrical wiring system shall be tested satisfactorily in accordance with *Yes/No/N.A. *Yes/No/N.A.
the T&C Procedure No. 2 for Electrical Installation and to Electricity
Ordinance requirements.
b) Starter overloads are set currently in relation to the motor name-plant full *Yes/No/N.A. *Yes/No/N.A.
load current.
c) All conductors shall be correctly and securely connected and identified. *Yes/No/N.A. *Yes/No/N.A.
d) Methods of protection against direct contact shall be properly applied. *Yes/No/N.A. *Yes/No/N.A.
e) Isolation and switching devices are properly and correctly installed. *Yes/No/N.A. *Yes/No/N.A.
f) Protective devices and monitoring devices are properly and correctly *Yes/No/N.A. *Yes/No/N.A.
installed and set (e.g. MCB, control fuse, ammeter & voltmeter).
g) The electric circuits, fused, switches, terminals, bonding, etc. are properly *Yes/No/N.A. *Yes/No/N.A.
and correctly labelled.
h) Danger notices, warning notices, schematic diagrams, instructions and *Yes/No/N.A. *Yes/No/N.A.
similar information are correctly and adequately provided.
b) Nuts and bolts are tightened and connected properly. *Yes/No/N.A. *Yes/No/N.A.
f) All level switch/ level sensor (i.e. Low level cut-in, low level cut-out, high *Yes/No/N.A. *Yes/No/N.A.
level cut out) are set correctly and performed properly.
h) Buzzer is set correctly in relation to the system / equipment failure and *Yes/No/N.A. *Yes/No/N.A.
performed properly.
Installation of hot water mixing valves is approved by WSD provided that *Yes/No/N.A. *Yes/No/N.A.
both the cold and hot water are drawn from the same source, i.e. both hot and
cold water supplied from a common storage cistern, or under direct mains
pressure.
The following types of water heaters may, with the written permission of the
WSD, be connected direct to a main: -
(i) non-pressure type water heaters where no restriction of flow can be *Yes/No/N.A. *Yes/No/N.A.
effected beyond the inlet control valve;
(iii) instantaneous water heaters where the guaranteed test pressure of the *Yes/No/N.A. *Yes/No/N.A.
water heater is at least 1½ times the static head available at the water
heater;
(iv) electric water heaters of the thermal storage type: - *Yes/No/N.A. *Yes/No/N.A.
a. having a storage capacity not exceeding 200 litres;
b. having a guaranteed test pressure at least 1½ times the static head
available at the water heater;
c. and not being provided with an individual expansion pipe but
complying with WWReg Sch 2 Pt IV Para 11.(WWReg Sch 2 Pt IV
Para 1(2)(a)(b)(c) & (d))
(WWReg Sch. 2 Pt. IV & TR 4.2.7)
a) Unvented type electric thermal storage water heaters shall comply with TR *Yes/No/N.A. *Yes/No/N.A.
4.2.7 and equip with safety devices that comply with Electrical Products
(Safety) Regulation.
b) Storage cistern of pressure type thermal storage heaters, other than unvented *Yes/No/N.A. *Yes/No/N.A.
heaters shall be equipped with a vented pipe.
c) Water released out of the relief valves of unvented electric thermal storage *Yes/No/N.A. *Yes/No/N.A.
type water heaters shall be discharged to a safe and visible location.
a) The centralised hot water systems utilising a boiler and cylinder shall be *Yes/No/N.A. *Yes/No/N.A.
provided with a vent or an expansion pipe taken from the highest point of the
cylinder or calorifier.
b) Safety valve or pressure relief valve shall be provided to the boiler or to the *Yes/No/N.A. *Yes/No/N.A.
primary flow pipe.
d) Cleaning and disinfection of each water storage type calorifier is done not *Yes/No/N.A. *Yes/No/N.A.
more than 7 days in advance before handed over.
e) Cleaning and disinfection of the potable hot water piping system is conducted *Yes/No/N.A. *Yes/No/N.A.
not more than 7 days in advance before hand over.
f) The portable hot water piping system is flushed thoroughly after disinfection. *Yes/No/N.A. *Yes/No/N.A.
h) After disinfection of the potable hot water piping system as described in *Yes/No/N.A. *Yes/No/N.A.
clause 3.2.2(e) of Annex II, the system is maintained for regular flushing
weekly.
i) Proper record of cleaning and disinfection is provided during handover. *Yes/No/N.A. *Yes/No/N.A.
j) Proper record of water sampling test for four additional test parameters, i.e. *Yes/No/N.A. *Yes/No/N.A.
Lead, Cadmium, Chromium and Nickel as required. (WSD Circular Letter
No. 1/2015Guide to Application for Water Supply)
k) Sample board(s) for taps, shower mixers, valves, pipes, solder material (if *Yes/No/N.A. *Yes/No/N.A.
used), etc. as listed in the Form WWO1149 (WSD Circular Letter No. 8/2015
Guide to Application for Water Supply)
3.2.4 Comments
Visual Inspections
c) Panel absorber surface has obvious sign of oxidation or de-colourisation *Yes/No/N.A. *Yes/No/N.A.
d) Pipework, heat exchangers and solar hot water calorifier are well insulated *Yes/No/N.A. *Yes/No/N.A.
and with UV protection layer
Chemical treatment
___________(chemical) (ppm)
___________(chemical) (ppm)
___________(chemical) (ppm)
System Controller
Calorifier
Insulation type
Circulation Pumps
Voltage (V)
Current (A)
Power (W)
a) Size of the Connection Pipe shall be of 40mm diameter minimum for flushing *Yes/No/N.A. *Yes/No/N.A.
water supply.
(TR 4.3.5.3)
b) All piping including the Connection Pipe before meter positions shall be *Yes/No/N.A. *Yes/No/N.A.
exposed or laid in a proper service duct. (TR 3.3.2.2, 4.2.4.1, 4.3.5.3 &
5.4.1.4)
a) Salt water supply for flushing water system will not be metered, but a space *Yes/No/N.A. *Yes/No/N.A.
reserved for meter position shall be provided.
b) Proper drainage, lighting and flood prevention facilities shall be provided at *Yes/No/N.A. *Yes/No/N.A.
the water meter room. (WW Reg 27, TR 3.1.9, 3.2.2.4, 3.2.2.5, 3.2.3.1,
3.2.4.1 & 3.3.5)
a) Cisterns shall be fitted with a ball valve controlled inlet in the case of a *Yes/No/N.A. *Yes/No/N.A.
gravity supply or with an automatic control switch in the case of a pumped
supply.
b) Ball valves of the water cistern are readily accessible. *Yes/No/N.A. *Yes/No/N.A.
c) An overflow pipe of one commercial size larger than the inlet pipe, and in no *Yes/No/N.A. *Yes/No/N.A.
case less than 25 mm diameter, shall be fitted to each cistern and shall be
extended to terminate in a conspicuous position in a communal area easily
visible and accessible by the occupants.
d) No part of the overflow pipe shall be submerged inside the storage cistern. *Yes/No/N.A. *Yes/No/N.A.
The top of the overflow pipe shall be not less than 25mm below the invert of
the inlet pipe or the face of the outlet nose of the ball valve. (TR 6.2.4.4.2)
e) A stop valve shall be provided on the outlet of every cistern and provision *Yes/No/N.A. *Yes/No/N.A.
shall be made for a drain off pipe to enable the cistern to be emptied.
f) Safe access shall be provided to all cisterns by means of a secure permanent *Yes/No/N.A. *Yes/No/N.A.
ladder or readily available portable ladder.
g) A grating and a self-closing non-return flap shall be provided at the overflow *Yes/No/N.A. *Yes/No/N.A.
pipe outside the storage cistern.
h) Cistern shall be fitted with a ball valve and a fullway gate valve at the inlet *Yes/No/N.A. *Yes/No/N.A.
in the case of a gravity supply or with an automatic control switch and
without any stop valve in the case of a pumped supply.
j) High and low water level indications for the water tanks function properly. *Yes/No/N.A. *Yes/No/N.A.
k) Size of the water pump suction water pipe from the water tank is matched the *Yes/No/N.A. *Yes/No/N.A.
size of the pump suction inlet.
l) Each water pump is provided with an independent suction pipe from supply *Yes/No/N.A. *Yes/No/N.A.
tank.
b) The flushing volume of the flushing devices shall be compatible with the *Yes/No/N.A. *Yes/No/N.A.
toilet bowl to ensure that effective clearance can be achieved by a single flush
of water.
c) The maximum flushing cistern volume including that of dual flush cisterns *Yes/No/N.A. *Yes/No/N.A.
shall not exceed 7.5 litre per flush.
d) For dual flush devices, the reduced flushing volumes shall not be more than *Yes/No/N.A. *Yes/No/N.A.
two-third of its larger flushing volume.
e) The component of all valve flushing devices shall be resistant to salt water *Yes/No/N.A. *Yes/No/N.A.
corrosion.
b) The cartridge and other valve components shall be easily replaceable. *Yes/No/N.A. *Yes/No/N.A.
d) The flushing volume of the flushing valves shall be adjusted to suit the toilet *Yes/No/N.A. *Yes/No/N.A.
bowl to ensure that effective clearance can be achieved by a single flush.
e) Flushing valves shall be used within the range of working pressures specified *Yes/No/N.A. *Yes/No/N.A.
by the manufacturer.
f) The maximum flushing volume of the flushing valves to be installed shall *Yes/No/N.A. *Yes/No/N.A.
not exceed 7.5 litres.
g) Flushing valves shall be set to be height which is operated by hand except *Yes/No/N.A. *Yes/No/N.A.
for those operated by foot.
a) Pipes and fittings shall conform to Part I of Schedule 2 of the Waterworks *Yes/No/N.A. *Yes/No/N.A.
Regulations.
b) Hydraulic tests are performed satisfactorily for water tightness of all sections *Yes/No/N.A. *Yes/No/N.A.
of the pipework.
c) Pipes on salt water inside service shall be made of salt water resistant *Yes/No/N.A. *Yes/No/N.A.
materials.
d) Final connection of the underground water mains to both newly installed *Yes/No/N.A. *Yes/No/N.A.
fresh water and flush water supply, utmost clear identification for the
connection shall be made by the Licensed Plumber and arranged WSD for
inspection before they put into operation.
e) All pipework is properly electrically bonded for equipotential bonding, *Yes/No/N.A. *Yes/No/N.A.
except non-metallic material is used, such as PVC pipe.
a) All piping are properly flushed and ensure no foreign objects trapped inside. *Yes/No/N.A. *Yes/No/N.A.
b) The water inside service has been properly cleaned to WSD’s requirement *Yes/No/N.A. *Yes/No/N.A.
and then filled with water.
c) The equipment associated with the system has undergone the mechanical and *Yes/No/N.A. *Yes/No/N.A.
electrical checks and the results are satisfactory.
f) By-pass arrangement shall be incorporated with the provision of a second *Yes/No/N.A. *Yes/No/N.A.
pressure reducing valve, except for fire service installations for ease of
replacement.
g) Pressure indicator shall be installed at the Pressure Reducing Valve system *Yes/No/N.A. *Yes/No/N.A.
for pressure monitoring.
a) A standby pump set for both fixed water pump system and booster water *Yes/No/N.A. *Yes/No/N.A.
pump system shall be provided.
(TR 4.2.4.10)
b) Water pumps and motors are run at the designed discharge water pressure *Yes/No/N.A. *Yes/No/N.A.
and operating electrical current.
c) Water pumps are run at an acceptable noise and vibration levels. *Yes/No/N.A. *Yes/No/N.A.
d) Water pump control switches and indicating lights function properly. *Yes/No/N.A. *Yes/No/N.A.
f) The temperatures of the water pump bearings at running condition are *Yes/No/N.A. *Yes/No/N.A.
normal.
g) The temperatures of the pump motors at running condition are normal. *Yes/No/N.A. *Yes/No/N.A.
i) A fullway gate valve shall be provided on the drain-off pipe. (TR 6.2.4.3.3) *Yes/No/N.A. *Yes/No/N.A.
j) Prior to pump start-up, the contractor shall check the horizontal or vertical *Yes/No/N.A. *Yes/No/N.A.
alignment of all flexible joints is within the tolerances recommended by the
manufacturers’ installation guideline.
a) The electrical wiring system shall be tested satisfactorily in accordance with *Yes/No/N.A. *Yes/No/N.A.
the T&C Procedure No. 2 for Electrical Installation and to Electricity
Ordinance requirements.
b) Starter overloads are set correctly in relation to the motor name-plant full *Yes/No/N.A. *Yes/No/N.A.
load current.
c) All conductors shall be correctly and securely connected and identified. *Yes/No/N.A. *Yes/No/N.A.
d) Methods of protection against direct contact shall be properly applied. *Yes/No/N.A. *Yes/No/N.A.
e) Isolation and switching devices are properly and correctly installed. *Yes/No/N.A. *Yes/No/N.A.
f) Protective devices and monitoring devices are properly and correctly *Yes/No/N.A. *Yes/No/N.A.
installed and set (e.g. MCB, control fuse, ammeter & voltmeter).
g) The electric circuits, fused, switches, terminals etc. are properly and correctly *Yes/No/N.A. *Yes/No/N.A.
labelled.
h) Danger notices, warning notices, schematic diagrams, instructions and *Yes/No/N.A. *Yes/No/N.A.
similar information are correctly and adequately provided.
b) Nuts and bolts are tightened and connected properly. *Yes/No/N.A. *Yes/No/N.A.
f) All level switch/ level sensor (i.e. Low level cut-in, low level cut-out, high *Yes/No/N.A. *Yes/No/N.A.
level cut out) are set correctly and performed properly.
h) Buzzer is set correctly in relation to the system / equipment failure and *Yes/No/N.A. *Yes/No/N.A.
performed properly.
3.3.11 Comments
b) All spare memory, equipment capacity and system expansion requirements *Yes/No/N.A. *Yes/No/N.A.
are met.
c) All input and output expansion requirements have been met, including wiring *Yes/No/N.A. *Yes/No/N.A.
and signal isolation, and verify that power supplies are capable of supporting
the increased load for this expansion.
d) All hardware and software boot-up and diagnostics are in normal. *Yes/No/N.A. *Yes/No/N.A.
f) Proper earth connections and isolation of instrumentation earth for all *Yes/No/N.A. *Yes/No/N.A.
equipment.
g) All preloaded software and firmware have been properly installed and are *Yes/No/N.A. *Yes/No/N.A.
operating correctly.
h) Connectivity and speed of the communications network equipment are in *Yes/No/N.A. *Yes/No/N.A.
normal.
a) AMR Outstation is installed in accordance with all relevant drawings, circuit *Yes/No/N.A. *Yes/No/N.A.
diagrams and the specified requirements
b) All cables and individual conductors are labelled and ferruled as per the *Yes/No/N.A. *Yes/No/N.A.
relevant drawings
c) All items of the AMR Outstation are adequately and correctly labelled and *Yes/No/N.A. *Yes/No/N.A.
identified
d) The insulation resistance and continuity of all conductors of cables, etc. are *Yes/No/N.A. *Yes/No/N.A.
acceptable
e) The earthing arrangements are complete and a satisfactory value of earth loop *Yes/No/N.A. *Yes/No/N.A.
impedance has been achieved
a) Integrity of the AMR data on the data concentration unit (DCU). *Yes/No/N.A. *Yes/No/N.A.
c) Integrity of the AMR data on the AMR Master Station. *Yes/No/N.A. *Yes/No/N.A.
d) Configuration and operation check on the meter interfacing units (MIUs) *Yes/No/N.A. *Yes/No/N.A.
g) Operation check on the AMR Outstation upon a.c. power supply failure *Yes/No/N.A. *Yes/No/N.A.
h) 6-hour discharge test on the battery of the AMR Outstation *Yes/No/N.A. *Yes/No/N.A.
Proforma for recording following data can be found in the succeeding pages and these shall
be properly filled in before submission to the PBSE with any relevant comments related to
site conditions.
- Vibration Test – Equipment Vibration Measurement Record
Name of project :
Date and time of measurement :
Weather condition :
Measured by :
Equipment Indicated operation Measured speed Visual Vibration Vibration measured Other
speed /audible acceptance observations
(rev/s) (rev/s) check criteria /remarks
(mm/s) (mm/s)
Motor Equipment Motor Equipment Horizontal Vertical Axial
Attachment includes a sketch showing the positions of measuring points for each equipment.
List of Calibrated Equipment/ Instruments Necessary for the Testing and Commissioning Works
Serial No. of
Type Model Date of Calibration
Instrument
Sampling Report
This *sampling report form is served as reference for water sampling and analysis as stipulated in this
T&C Procedure and General Specification of Building Services Installation.
Storage in transit:
Sampler’s name: Signature:
Sampler’s contact no.:
Analysis required:
Hazards:
Sampler’s comments:
Time received in laboratory: Date:
Received by: Signature:
Laboratory comments:
Special instructions to the analyst: