0% found this document useful (0 votes)
67 views

Unit Cum

The document provides a rate analysis for plain/reinforced cement concrete in open foundation. It lists the materials, labor, and machinery required along with their unit rates. It then calculates the basic cost per cubic meter and adds overhead charges, contractor's profit, and sewerage charges to determine the final rate of Rs. 4698 per cubic meter.

Uploaded by

anon_789699787
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
67 views

Unit Cum

The document provides a rate analysis for plain/reinforced cement concrete in open foundation. It lists the materials, labor, and machinery required along with their unit rates. It then calculates the basic cost per cubic meter and adds overhead charges, contractor's profit, and sewerage charges to determine the final rate of Rs. 4698 per cubic meter.

Uploaded by

anon_789699787
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Ref.

to
Remarks/
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Input ref.
Spec.
12.8 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation
& 2100 complete as per Drawing and Technical Specifications.

A PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 4380.00 18089.40 M-081
Coarse sand cum 6.75 605.00 4083.75 M-005
40 mm Aggregate cum 8.10 881.25 7138.13 M-055
20 mm Aggregate cum 4.05 1418.75 5745.94 M-053
10 mm Aggregate cum 1.35 977.50 1319.63 M-051
b) Labour
Mate day 0.86 530.00 455.80 L-12
Mason day 1.50 585.00 877.50 L-11
Mazdoor day 20.00 490.00 9800.00 L-13
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 626.20 3757.20 P&M-009
Generator 63 KVA hour 6.00 1269.00 7614.00 P&M-019
Per Cum Basic Cost of Labour, Material & Machinery 3926.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2355.25
of material, labour and machinery

e) Overhead charges @ 4.615% on (a+b+c+d) 2826.07


f) Contractor's profit @ 10% on (a+b+c+d+e) 6406.27
Cost for 15 cum = a+b+c+d+e+f 70468.93
Rate per cum = (a+b+c+d+e+f)/15 4697.93
say 4698
g) seinarage charges per cum
Coarse Sand 0.45 100.00 45.00
Aggregate 0.90 90.00 81.00
Rate per cum say 126.00
Note Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.

You might also like