0% found this document useful (0 votes)
10 views

Plinths

The document provides a breakdown of costs for various construction elements including formwork, natural stone walling, ramp construction, reinforced concrete work, walling and roofing. It lists multiple line items with descriptions, quantities, rates and totals for each construction element.

Uploaded by

PNN1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views

Plinths

The document provides a breakdown of costs for various construction elements including formwork, natural stone walling, ramp construction, reinforced concrete work, walling and roofing. It lists multiple line items with descriptions, quantities, rates and totals for each construction element.

Uploaded by

PNN1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Formwork to: -

K Sides of foundations and bases SM 84 600 50,400.00


L Sides of column SM 4 600 2,400.00
M Edges of beds etc., 75 to 150mm high LM 105 150 15,750.00
Natural stone walling in cement sand mortar (1:3) -
A 200mm Thick walling SM 242 2,000 484,000.00
Bituminous felt damp proof courses laid on and -
including levelling screed of cement mortar (1:3) -
B 200mm Wide in walling LM 169 200 33,800.00
C 150mm Ditto LM 27 150 4,050.00
Plinths -
D 19mm Thick cement sand rendering (1:3) to plinth walls SM 32 345 11,040.00
E Prepare and apply three coats black bituminous paint to rendered plinths SM 32 300 9,600.00
externally
Ramp -
Vibrated reinforced concrete class 20/20 in: -
F Ramp CM 1 13,000 13,000.00
BRC A142 Mesh -
G BRC A142 Mesh reinforcement weighing 2.22KG/SM including end and side laps SM 3 450 1,350.00

Formwork to: -
H Sides of ramp SM 1 600 600.00
Imported filling -
I 300mm Thick approved hardcore bed to receive concrete well compacted in SM 3 140 420.00
layers
SUB TOTAL ELEMENT NO. 1 2,225,030.00
ELEMENT NO. 2
R.C. SUPERSTRUCTURE
Vibrated reinforced concrete class 20/20
A Beams CM 13 13,000 169,000.00
B Columns CM 16 13,000 208,000.00
Reinforcement
High yield deformed steel bar reinforcement to B.S. 4461
C 8mm Diameter bars KG 287 150 43,050.00
D 12mm Ditto KG 815 150 122,250.00
Sawn formwork to:
E Sides and soffits of beams SM 144 600 86,400.00
F Sides of columns SM 23 600 13,800.00
SUB TOTALELEMENT NO. 2 642,500.00
ELEMENT NO. 3
WALLING
Machine cut natural stone walling bedded in and including cement and sand
mortar and gauge 16 hoop iron
A 200mm Thick walling SM 277 1,900 526,300.00
B 150mm Thick ditto SM 90 1,600 144,000.00
SUB TOTAL ELEMENT NO 03 670,300.00