CSHP Project 1
CSHP Project 1
Dear Sir:
Greetings!
In relation to the Project Construction of Super Health Center (PCF) Phase 1, Barangay
Puro, Magsingal, Ilocos Sur we would like to submit our Construction Safety and Health
Program with your office as one of the requirements upon start of construction of the above-
mentioned project.
Thank you.
Respectfully yours,
Instructions: This form shall be duly accomplished and submitted by the MAIN/GENERAL
CONTRACTOR in applying for an approval of a Construction Safety and Health Program intended for a
specific construction project.
Only an application form with complete requirements and attachments will be processed. Application
found with incomplete requirements will be given 15 calendar days to comply. Failure to comply within
the prescribed period, the application will be deemed disapproved.
[email protected]
FERDINAND A. BUTALON
b. per Rule 1020, OSHS (one time registration) January 28, 2019 01-1901-043
Sub-contractors’ Profile/License
No. of PCAB Validity Date of
Name of Sub-contractors (If, any) Scope of Work and Workers License Date DOLE
Project Cost Registration
1. N/A
2.
3.
4.
5.
B. Project Profile/Description
Name of the Project: (Please attach copy of Invitation to Bid/other documents indicating name and details of the
project)
Email : [email protected]
Brief Description of Activities/Work Flow (You may attach additional sheet, if necessary)
Site Works
Concrete Works
Masonry Works
Metal Works and Steel Works
Ceiling Works / Carpentry
Doors and Windows
Architectural Works
Plumbing Works
Electrical Works
Date of his COSH training: April 11, 18, 25 and May 2, Date of First –Aid Training: September 28-30,
2021
2021
(Pls. attach photo copy of Certificate of Completion on the
Basic OSH Course for Construction Site Safety Officers issued ID: PRC 654503
by DOLE-BWC accredited Safety Training Organizations or
recognized institutions) (Pls. attach photo copy of Certificate of First-Aid Training
and Valid First Aider ID from PNRC
Other OH personnel (if more than 50 workers will be deployed in the project)
Name Date of BOSH Training
OH Nurse N/A
OH Physician N/A
Dentist N/A
N/A N/A
Profile of the person who prepared the CSH Program for the abovementioned Project:
Name and Signature Educational Background:
Information Technology
Submitted By:
Position: PROPRIETOR/MANAGER
i. Specific name of project and Name of Owner ii. Location of the project
□ others, specify: _
_ _
v. Name of Construction Project Manager /Consultant, if any (a vi. Name of Project Manager/Contact Number (the overall
person or entity who is hired by the project owner, to act in the technical personnel of the general constructor and or the
owner’s behalf concerning supervision and monitoring of all subcontractor in charge of the actual execution of this project)
matters related to the overall execution of this project. It shall be a
separate entity from the general constructor or any subcontractor
of the construction project
FERDINAND A. BUTALON
vii. Name of Resident Engineer, if any (a duly licensed engineer viii. Name and Classification of Constructors (synonymous to
who shall be tasked to be present at the construction site at all builders who undertake or offers to undertake or purports to
times, whenever work is being undertaken, and shall have the have the capacity to undertake or submits a bid to, or does
responsibility of assuring the technical conformance of all designs, himself or by or through others, construct, alter, repair, add to,
materials, processes, work procedures rendered for the execution subtract from, improve, move, wreck or demolish any building,
of this project, including safety and health of all persons within the highway, road, railroad, excavation or other structure, project,
construction site) development or improvement, or to do any part thereof,
including the erection of scaffolding or other structures or works
in connection with this project. The term constructor includes
subcontractor and specialty contractor.)
Name Classification
1. N/A
2.
3.
Others: _
xi. Estimated number of heavy equipment xii. Projected dates of commencement and completion
□ others, specify: _
_ _
xiii. Name and Address of Emergency Health Provider (any person or organization who is certified or recognized by the Department
of Health and who can provide the same or equivalent emergency health services as an emergency hospital, including emergency
treatment or workers on site, emergency transport and care during transport of injured workers to the nearest hospital, with
adequatepersonnel, supplies and facilities for the complete immediate treatment of injuries or illnesses)
6,447,793.00
26,100.00
Section 11 of D.O. No. 13 requires that rules of Construction Safety and Health Program must be
observed and enforced at the project site, each site shall, at the start of the construction have a
construction safety and health committee. With respect to this project, the committee will be
organized in accordance with the requirements of Rule 1040 of the Occupational Safety and Health
(OSH) Standards of the Department of Labor and Employment (DOLE).
Our CSHC at the PROJECT 1: CONSTRUCTION OF SUPER HEALTH CENTER (PCF) PHASE 1,
BARANGAY PURO, MAGSINGAL, ILOCOS SUR (IB-2022-14-108) consist of:
4.1.2 General Construction Safety and Health Officer/s (overall in charge in the implementation
of the OSH program of this project hired by the General Constructor. Please attach certificate of
training/s prescribed by DOLE. Numbers will be dependent on the numbers of workers and heavy
equipment)
4.1.3 Construction Safety and Health Officer/s from Subcontractors (any employee/worker
trained and, in addition to their regular duties and responsibilities tasked by his employer to
implement occupational safety and health program in accordance with the provisions of the OSH
Standard. Please attach certificate of training/s prescribed by DOLE).
Name _________________________________________________
Company Name: _ _ _ _ _ _ _
Name _________________________________________________
Company Name: _ _ _ _ _ _ _
Name _________________________________________________
Company Name: _ _ _ _ _ _ _
4.1.4 Occupational Health Personnel (qualified first-aider, nurse, dentist, or physician, engaged
by the employer to provide occupational health services in the establishment/undertaking.
Please attach certificate of training/s prescribed by DOLE):
Name _________________________________________________
Designation _______________________________________
Name _________________________________________________
Designation _______________________________________
Name _________________________________________________
Designation _______________________________________
4.2 Duties of the CSH Committee shall include but are not limited to the following:
4.2.1 Plans, develops and oversees the accident prevention programs for the construction
project;
4.2.2 Directs the accident prevention efforts of the establishment in accordance with the safety
programs and performance and government regulations in order to prevent accidents from
occurring in the worksite;
5| P a g e
4.2.3 Conducts safety meetings at least once a month. The committee will hold a safety
meeting every 1st Monday of the month;
4.2.4 Submits reports to the project manager (is this pm of the owner or pm of the gen con?)
on its meetings and activities one day after the meeting;
4.2.7 Submits the monthly the following safety and health reports to the DOLE Regional Office
having jurisdiction over the project:
4.2.7.2 Summary of all accident investigation reports using DOLE/BWC/ OHSD/IP-6 form;
4.2.7.3 Periodic hazards assessment with the corresponding remedial measures/actions for
each hazard;
4.2.7.4 Annual Medical Report using the form DOLE/BWC/HSD/OH-47-A (if the duration of
the project is more than one (1) year);
4.2.7.5 Initiates and supervises safety and health training for employees. (Check on the boxes
or list down the training to be provided for workers and employees).
The principal function of the Safety Man assigned to this project is to act as the employer’s (needs
identification) principal assistant and consultant in the application of programs to remove the
hazard from the workplace and to correct unsafe work practices. For this purpose, the Safety
Man has the following duties:
4.3.1 Serves as Secretary to the SHC, as such will perform the following:
4.3.1.4 submit (needs identification) to the employer a report of the activities of the committee,
including recommendations made.
4.3.2 Acts as an advisory capacity on all matters pertaining to health and safety for guidance of
the employer and the workers.
4.3.3 Conducts investigation of accident as member of the Health and Safety Committee and
submits his separate report and analysis of accident to the employer (needs identification).
4.3.4 Coordinates all health and safety training programs for the workers/employees and
employer (needs identification).
6| P a g e
4.3.6 Maintains or helps in the maintenance of an efficient accident record system and
coordinates actions taken by supervisors to eliminate accident causes.
4.3.7 Provide assistance to government agencies in the conduct of safety and health
inspection, accident investigation or any other related program.
4.3.8 For the purpose of effectiveness in the project site, the Safety Man is to report directly to
the employer (needs identification).
In case of any dangerous occurrence or major accident resulting to death or permanent total
disability, we will notify the DOLE Regional Office within twenty-four (24) hours from occurrence.
After the conduct of investigation by our concerned safety and health officer, we will report all
permanent total disabilities to the DOLE Regional Office on or before the 20 th of the month
following the date of occurrence of accident using the DOLE/BWC/HSD-IP-6 form.
Section 8 of D.O. No. 13 states that the construction project owner or his representative shall
provide competent emergency health personnel within the worksite duly complemented by
adequate medical supplies, equipment and facilities based on the total number of workers in the
site.
The FIB CONSTRUCTION AND SUPPLY is committed at ensuring that all workers or employees
are given orientation/briefing or induction prior to deployment to the site. It is our continuing effort
to promote safety and health consciousness to all people involved in this project by providing them
with the necessary safety and health training and education to enhance their knowledge and skills
to enable us to attain a safe and healthful project site.
We require new workers to attend our Safety & Health Orientation before they are deployed to
this project site in consonance to Section 12 of the D.O. 13. The assigned Safety Officer, Mr.
EROLL M. BAUTISTA will coordinate the conduct of this orientation.
7| P a g e
We ensure that they receive instruction and training regarding the general safety and health
measures we plan to implement for this project, specifically:
6.1.2 means of access and egress both during normal work and in emergency situation;
6.1.4 location and proper use of welfare amenities and first –aid facilities;
Below is the list of workers who have undergone the DOLE prescribed safety and health
trainings and orientation
Section 12.6 of the D.O. No. 13 requires specialized instruction and training be given to any
person holding critical occupation.
The inventory lists of our workers who hold critical occupation and attended the specialized
trainings are listed below. (Please attach training certificates)
D.O. No. 13 define toolbox meeting or gang meeting as a daily meeting among workers and their
respective supervisors for the purpose of instruction, discussion and proper briefing on the planned
work, the assessment of past work, the possibility or actual occurrence of accidents at the site, tips
and suggestions on how to prevent possible accidents and other related matters.
8| P a g e
The following supervisor or any designated person (e.g., foreman, leadman, gang boss, etc.) is
required to conduct daily toolbox or similar meetings prior to starting the tasks for the day to discuss
with the workers and anticipate safety and health problems related to every task and the potential
solutions to those problems. The supervisor will remind the workers on the necessary safety
precautions that need to be undertaken.
In this project the following person/s will be assigned to conduct accident/incident investigation:
In conducting the accident/illness investigation, we gather facts, analyze them and make the
necessary recommendation. (Please attach sample forms that will be used to document your investigation)
9| P a g e
We will submit the following reports to the DOLE Regional Office concerned:
8.3.1 In case of any dangerous occurrence or major accidents resulting to death or permanent
total disability using the form (DOLE/BWC/OHSD/IP – 6). Notification of major accidents to
DOLE Regional Office concerned within 24 hours.
8.3.2 Summary of Work Accident/Illness Exposure Data Report will be submitted on or before
the 20th of the month following the date of occurrence of accident (for those projects with short
duration or less than one year duration).
8.3.3 Annual Work Accident/Illness Report using the form DOLE/BWC/OHSD/IP – 6B for
those construction projects with more than one year duration.
Section 6 of D.O. No. 13 requires that every employer shall, at his own expense, furnish his workers
with protective equipment for eyes, face, hands, feet, lifeline, safety belt/harness, protective shields
and barriers whenever necessary by reason of the hazardous work process or environment,
chemical or radiological or other mechanical irritants or hazards capable of causing injury or
impairment in the function or any part of the body through absorption, inhalation or physical agent.
Provision of PPE shall be in accordance with Rule 1080 of the OSHS (must include Rule 1070 for
noise). The equivalent cost for the provision of PPE (life span, depreciation, replacement, etc.) shall
be an integral part of the project cost.
It is important that all PPE be kept clean and properly maintained. Cleaning is particularly important for
eye and face protection where dirty or fogged lenses could impair vision. Our workers or
employees inspect, clean, and maintain their PPE according to the manufacturers’ instructions before
and after each use. Our supervisors are responsible for ensuring that users properly maintain their
PPEs in good condition.
We enforce our rule that PPEs must not be shared between workers or employees until it has been
properly cleaned and sanitized. PPE are distributed for individual use whenever possible.
If workers or employees provide their own PPEs, we make sure that it is adequate for the work place
hazards, and that it is maintained in a clean and stored in a conducive condition.
We never allow the use of defective or damaged PPEs. We immediately discard and replace them to
avoid any unintentional use.
10 | P a g e
We also consider the importance of ensuring that any contaminated PPE which cannot be
decontaminated is disposed of in a manner that protects workers or employees from exposure to
hazards
We comply with Rule 1412.09 of the DOLE OSH standard in providing a safe covered walkway over
the sidewalk for use by pedestrians in a building construction work less than 2.3 meter (7ft.) from a side
walk or public road.
We comply with Rule 1412.10 of the OSH Standard, Protection from Falling Materials. We observe the
following:
10.1 We will take the steps to protect worker from falling materials, such as the provisions of safety
helmets and safety shoes.
10.2 We will ensure that tools, objects and materials including waste materials) will not be thrown or tipped
from a height, but will be properly lowered by crane, hoist or chutes. If such is not practicable,
the area where the material is thrown will be fenced and no person will be allowed in the fenced
area.
Our Safety Signages provides warning to workers and employees and the public about the hazards
around the project site. These will be posted in prominent positions at strategic location visible as
far as possible in a language understandable to most of the workers and employees as well as the
public.
11.1 The specific safety signages we intend to set-up for this project include but not limited to:
11.1.1 Mandatory requirement on the usage of PPE prior to entry to the project site (attach sample
picture of this signage that you plan to use for this project);
11.1.2 Areas where there are potential risks of falling objects (if applicable, attach sample picture of
this signage that you plan to use for this project);
11.1.3 Areas where there are potential risks of falling (if applicable, attach sample picture of this
signage that you plan to use for this project);
11.1.4 Areas where explosives and flammable substances are used or stored (if applicable, attach
sample picture of this signage that you plan to use for this project);
11.1.5 Areas where there are tripping or slipping hazards (if applicable, attach sample picture of this
signage that you plan to use for this project);
11.1.6 Approaches to working areas where danger from toxic or irritant airborne
contaminants/substance may exist which should indicate the name of the
contaminant/substance involved and the type of respiratory equipment to be worn (if applicable,
attach sample picture of this signage that you plan to use for this project);
11.1.7 All places where contact with or proximity to electrical/facility equipment can cause danger
(if applicable, attach sample picture of this signage that you plan to use for this project);
11.1.8All places where workers may come in contact with dangerous moving parts of the
machineries or equipment (if applicable, attach sample picture of this signage that you plan to use for
this project);
11 | P a g e
11.1.9 Location of the fire alarms and fire-fighting equipment (attach sample picture of this signage
that you plan to use for this project);
11.1.10 Instructions on the usage of specific construction equipment (if applicable, attach sample
picture of this signage that you plan to use for this project);
We will regularly inspect and maintain in good condition all safety signages that we will be
providing for this project. The person in charge in inspecting is LEO N. CALLANTA he is our
Construction Foreman. Inspection will be carried out on a Daily basis.
Our Construction Foreman will remove and replaced any signages that are damaged,illegible,
or no longer apply with the current hazard.
The company will ensure that all workers assigned in the critical occupations as defined in Section
15 of D.O. No. 13 and those who will be assigned in the operation of construction heavy equipment
(CHE) will undergo mandatory skills testing for certification by TESDA (Attach TESDA certificates of
those workers certified by TESDA.)
To ensure safe and healthy working conditions throughout the duration of the project the following
control measure activities will be enforced and disseminated to all the workers in the site:
Major activities for this project include but not limited to the following: (please check on the box all that
applies)
□ Demolition □ Excavation
□ Earthmoving □ Piling
□ Scaffold □ Formwork
□ Structural Steel □ Crane Operation
□ Concreting □ Rebarworks
□ Welding □ Electrical
□ HVAC □ Plumbing
□ Painting □ interior Decoration
□ Others (please specify)
Based on the list of activities for this project, we found the following potential hazards that we may
possibly encounter in the course of project implementation:
Physical hazards are the most common in most workplaces. The physical hazards that we
identified for this project include but are not limited to the following: (please check on the box all
that applies)
Chemical hazards are present workers handle chemical preparations in any form (solid, liquid
or gas). Some are safer than others, however, some workers are more sensitive to chemicals,
even the common solutions causing illness, skin irritation or breathing problems.
The chemical hazards that we identified for this project include but are not limited to the
following: (please check on the box all that applies)
Biological hazards come from working with infectious people, plants, and other living materials.
The biological hazards that we have identified for this project includes but not limited to the
following: (please check on the box all that applies)
Ergonomic hazards occur when the type of work, body position and working conditions put strain
on the body. They are the hardest to spot since one does not immediately notice the strain on
your body or the harm these hazards pose. Short-term exposure may result in "sore muscles"
on the days following exposure, but long-term exposure can result in serious musculoskeletal
injuries.
The ergonomic hazards that we identified for this project includes but not limited to the following:
(please check on the box all that applies)
(Enumerate control measures to address those hazards identified, Use additional sheet if necessary)
Safe work practices are procedures adopted for carrying out specific tasks that ensures workers'
exposure to hazardous situations, substances, and physical agents is controlled in a safe
manner. Safe work practices are generally written methods outlining how to perform a task with
minimum risk to people, equipment, materials, environment, and processes. It should be
developed as a result of completing a Hazard Assessment and should closely reflect the
activities in this project.
All safe work practices should be kept in a location central to the work being performed and
readily available to the workforce. Some safe work practices will require specific job procedures,
which clearly set out in a chronological order each step in a process.
(Enumerate below the safe work practices that you intend to perform relative to the hazards you
previously identified above.)
The company will provide first-aid kit and health care medicines and facilities for workers in the
site in accordance with the requirements of Rule 1960 of the OSHS.
The following welfare facilities will be provided in the site to ensure human working conditions:
16.2 Adequate sanitary, washing and sleeping facilities separate for men and women workers
16.3 Adequate facilities for changing and for the storage and drying of work clothes.
To assure that the company provides adequate welfare facilities for the workers in the site the
company will implement the provision of toilets and other facilities in accordance with the
requirements of the Sanitation Code.
14 | P a g e
The company will require all employees to undergo a baseline or initial medical health examination
prior to assigning to a potentially hazardous activity. The examination will include but not limited to
the following:
17.3 Other special examination (Pulmonary function test, blood panel, ECG >40 years of age,
audiogram);
The work schedule will be on (please check on the boxes that apply):
□ Mon. □Tue. □Wed. □Thur. □Fri. □Sat. □Sun
Check on the shift and indicate the work hours for the shift that applies.
□ 1st Shift from 8__(am/pm) to _ _5 (am/pm)
□ 2nd Shift from _ _(am/pm) to _ __________ (am/pm)
rd
□ 3 Shift from __ (am/pm) to ________ (am/pm)
Check on the shift and indicate the break for the shift that applies.
□ 1st Shift from __(am/pm) to ___ (am/pm)
nd
□ 2 Shift from _ _ (am/pm) to ___________ (am/pm)
□ 3rd Shift from __ (am/pm) to ________ (am/pm)
The company including subcontractors will be responsible for minimizing waste generated during
the implementation of the project. The following procedures for disposal of wastes will be
implemented in the site:
19.1 Ensure that the construction wastes are segregated from that of domestic waste.
19.3 Construction debris (broken hollow blocks, spoiled concrete, loose concrete, etc) should be
taken out on the staging area.
19.4 Oil spills and spoiled greases should be wrapping in the black garbage bag and will be
properly disposed.
The objectives of this are to ensure that the company has developed and communicated plansthat
will allow for the effective management of emergencies. Attach copy of company emergency
preparedness plan.
21.0 Penalties/Sanctions
For every offense and violation of any safety rules, regulations and general practices promulgated
by the project and/or the company, the company recommended the following penalties and
sanctions for violation of CSH program: (Please attach company policy on penalties, if there are any).
22.0 Attachments
I. Abbreviations
Occupational Health refers to the Philippine Registered Nurses who underwent formal Post
Nurses Graduate Course Training on Basic Occupational Safety and Health for
Nurses. Engaged by the employer to provide occupational health
services.
Safety Officer designated regular employee who underwent formal training on Basic
Occupational Safety and Health or itsequivalent to oversee the overall
management of the occupational safety and health programs.
III. Coverage
This policy shall apply to all workers of the FIB CONSTRUCTION AND SUPPLY regardless of
status, including its contractors/subcontractors, clients and guests.
This policy is prepared by the members of the Occupational Safety and Health Committee with
the concurrence of its workforce and managementrepresentative.
V. Objectives
The following safety and health standards shall be implemented in the FIB CONSTRUCTION AND
SUPPLY with the objectives of the minimum health standards of the Department of Health:
1. The FIB CONSTRUCTION AND SUPPLY shall emphasize to all workers the everyday
actions to stay healthy, such as:
a. Eat nutritious and well-cooked food;
b. Drink plenty of fluids and avoid alcoholic beverages;
c. Strengthen the body’s immune system by having enough rest, taking in multivitamins
and having adequate sleep of at least 8 hours; and
d. Exercise regularly.
2. The company shall provide referral for workers needing counselling or presenting with
mental health concerns.
B. Reducing Transmission of COVID-19
i. Always wear face masks and remove the same only whendrinking. The company
shall provide the appropriate face masksfor workers. In case only cloth masks
(washable type) are made available, additional filter material such as tissue
papers inside the masks may be added;
ii. All employees are expected to daily accomplish the health checklist and submit
to the guard or designated safety officer prior to entry;
iii. All employees must have their temperature checked and recorded in the health
checklist. (refer to picture 1.) For any personnel with temperature >37.50 C, even
after a 5-minute rest, or if their response in the questionnaire needs further
evaluation by the Occupational Health Nurse/clinic staff/designated personnel,
the person shall be isolated in an area identified by the company and not allowed
to enter the premises. The isolation area should be well ventilated and
disinfectedfrequently. OHN/Clinic staff/designated personnel assigned to assess
the workers held in isolation area shall be provided the appropriate medical grade
PPEs by the establishment which shall include but not limited to, face masks,
goggles/face shields, and/or gloves; and
iv. Spray alcohol/sanitizers to both hands; and provide disinfectantfoot baths at the
entrance if practicable.
Table 1. Illustration of Screening Protocol (to be posted)
Name:
[ ] Employee [ ] Client/Guest [ ] Contractor/Subcon
Contact Number:
Denver B. Sandoval, RN
Option B. Health Checklist (Produced for Monthly use)
a. Equipment or vehicle entering the hub operational area must go through a disinfection
process; and
b. If there will be a long queue outside the office or store premises, roving officers are
expected to instill physical distancing of onemeter.
2. Inside the workplace
a. All work areas and frequently handled objects such as doorknobs adhandles, shall be
cleaned and disinfected regularly, at least once every (2) hours;
b. All washrooms and toilets shall have enough clean water and soap, workers are
encouraged to wash their hands frequently and avoid touching their eyes, nose and
mouth;
c. Sanitizers shall be made available in corridors, conference areas, elevators, stairways
and areas where workers pass;
d. Workers, whether in the office workstation or in operations area, shallalways practice
physical distancing meaning at the minimum one
(1) meter radius space (side, back and front) between workers;
e. Eating in communal areas is discouraged. It is best to eat in individualwork area and all
wastes shall be disposed properly.
If eating individual work areas is not possible, the employer shall ensure that physical
distancing is maintained in dining areas with oneworker per table and 1-meter distance
per worker. It is discouraged that workers engage in conversation with masks off during
mealtimes. Tables and chairs shall be cleaned or disinfected after every use of the area,
and before as well as the end of the work; and
f. Canteens and kitchens should be cleaned and disinfected regularly.
C. Minimize Contact Rate
1. Alternative work arrangements, such as working-hour shifts, work from home (WFH),
where feasible and on rotation basis;
2. Prolonged face-to-face interaction between workers and with clients are discouraged
and masks shall always be worn and not removed. Meetings needing physical presence
shall be kept to a minimum number of participants and with short duration. Video
conferencing shall be utilized for lengthy discussions among workers;
3. Office tables should be arranged in order to maintain proper physicaldistancing. Barriers
may be provided between tables;
4. Workstation layout should be designed to allow for unidirectional movement in aisles,
corridors or walkways;
5. To maintain physical distancing, number of people inside an enclosed space such as a
room, store or hall shall be limited. Elevatoruse should consider physical distancing and
limit number of persons in order to observe the 1-meter physical distancing;
6. Use of stairs should be encouraged subject to physical distancing requirements. If more
than 2 stairways are accessible, one stairway may be used exclusively for going up and
another for going down;
7. Online system shall be highly encouraged to be utilized for clients needing assistance
from offices including the use of videoconferencing; and
8. Roving officers shall always ensure physical distancing and observance of minimum
health protocols.
a. The worker shall immediately proceed to the isolation area designatedin the workplace and
never remove his/her mask;
b. Occupational Health Nurse/Clinic personnel attending to the workers should wear
appropriate PPEs and if needed should require the transport of the affected worker to
the nearest hospital. Companyprotocols for transport for suspect COVID-19 cases and
for PCR testing, should be in place including providing for ambulance conduction.
Hospitals will report to the DOH for COVID-19 suspect; and
c. Decontamination of workplace
2. In the event that a worker is sick or has a fever but is not suspected to haveCOVID-19 (ex. urinary
infection wound infection or any diseases not relatedto lungs or respiratory tract) the employer
must advice the worker to take prudent measures to limit the spread of communicable diseases,
as follows:
1. Provide the necessary company policies for the prevention and control of COVID-19 in
consultation with workers. Advocacy and IEC programs shouldbe taken from DOH, WHO and
reliable sources of information on COVID-19;
2. Provide resources and materials needed to keep the workers healthy and the workplace safe,
e.g., masks, soap, sanitizer, disinfectant, PPEs, includingCOVID-19 testing kits, etc;
3. Designate a safety officer to monitor COVID-19 prevention and control measures such as
physical distancing, wearing of masks, regular disinfection, compliance to thermal scanning and
accomplishing health symptoms questionnaire;
4. Enhance health insurance provision for workers;
5. When feasible, provide shuttle services and/or decent accommodation onnear-site location to
lessen travel and people movement;
6. Enjoin the hiring from the local community; and
7. Put up a COVID-19 Hotline and Call Center for employees to report if symptomatic, and a daily
monitoring scheme of our “suspect” employee condition.
Workers shall:
1. Comply with all workplace measures in place for the prevention and controlof COVID-19, such as,
frequent hand washing, wearing of masks, observe physical distancing always, etc;
2. Observe proper respiratory etiquette;
3. Coughing and sneezing into tissue or into shirt sleeves if tissue is not available.
4. Disposing used tissues properly; and
5. Disinfecting hands immediately through proper washing with soap and water or alcohol-based
sanitizer immediately after a cough or sneeze.
Workers with a negative test shall continue to work. They should be given appropriate advise
and instructions once they develop any health complaints or symptoms. The company OHN/SO shall
continue to monitor all workers.
A. The implementation of this policy and its programs shall be monitored and evaluated
periodically through the Company’s Occupational Safety, Health Committee (OSH Com).
XIII. Funding
The FIB CONSTRUCTION AND SUPPLY shall allocate a budget for this purpose to include but
not limited to:
a. IEC Materials;
XIV. Effectivity
Signed and approved this 10th day of January. 2023 at Urdaneta City, Pangasinan, Philippines.
DEFINITION OF TERMS
EMERGENCY- A sudden, unexpected occurrence demanding immediate action and
a potential life- threatening situation.
DISASTER- a sudden, calamitous event bringing great damage, loss or destruction.
RESCUE- the removal of human being from a place of danger and convey them to
the place of safety.
EVACUATION- the removal of personnel, materials and equipment from a place of
danger to a safe zone/area.
EXTRICATION- the removal of the victim from difficult situation or position; or the
removal of a patient from a wrecked car or other place of entrapment.
2 TYPES OF EMERGENCIES
• MAN-MADE EMERGENCY- events caused by man’s negligence in handling
his technology
• NATURAL EMERGENCY- events that are caused by the forces of nature.
MAN-MADE EMERGENCY
➢ Vehicular accidents
➢ Fire
➢ Hazardous materials
➢ Public demonstrations
NATURAL EMERGENCY
➢ Flood
➢ Tornado
➢ Thunderstorm
➢ Earthquakes
EARTHQUAKE
o Earthquakes happen in unexpected time. Every day, between 50 to 80
earthquakes occur around the globe. Most of these are either under water or
mild enough not to cause problems, but each year there are around 100
earthquakes around the globe strong enough to cause damage. Seismologists
cannot predict earthquakes accurately enough for construction sites to plan
ahead.
o That said, construction sites take some measures to protect their work and
crews from unnecessary injuries or damage during and after an earthquake.
Earthquakes have four main risks. These are;
✓ Ground Displacement can cause uneven surfaces. Be aware of this
when entering the construction site and preparing for repairs after an
earthquake.
✓ Fire is a serious risk. Broken power and gas lines leave the site
vulnerable to fire.
✓ Flooding is possible near waterways. Broken dams or levees can allow
flooding in normally safe areas.
✓ Building can topple in an earthquake. This includes buildings that are not
yet complete, and some construction projects will be at higher risk
because their earthquake protection measures may not be completed.
In preparing for an earthquake in construction sites, here are the precautions to take;
✓ Have a safe place designated on the construction site for earthquakes.
The safe places normally chosen, like under the table or desk or against
an interior wall, will not work in construction site. Aim to be away from
the building, which could collapse, and away from any large equipment.
However, try not to move too far from the current position, as farther
someone moves during an earthquake event, the greater the chance of
injuries.
✓ Practice “Drop, Cover, and Hold on”. Drop, cover, and hold on is an
earthquake safety measure that anyone can practice, regardless of
where they are when an earthquake hits. It refers to dropping to hands
and needs, covering your head and neck with one arm and crawling to
the closest shelter, then holding on to something steady until the shaking
stops. Finding shelter is the challenge during an earthquake on a
construction site, but even large piece of equipment or a tree can serve
as a shelter when needed. This is a recommended technique at least
twice a year, and at least once per construction site;
✓ Hold earthquake drills to ensure that construction crew members know
the proper response during an earthquake.
✓ If operating equipment when an earthquake hits, stop and exit the vehicle
as soon as safely possible.
✓ Watch for fires. Broken gas lines, even near construction sites, and
damaged electrical components or electrical lines can cause fires. Also,
the motion of the earthquakes itself can release sparks, leading to a fire.
FIRE
o To protect a construction site from fire, here is what you need to know and do;
o Identify the fire risk on the site. Fire risk are found everywhere on construction
sites. Gas leaks from lines that are not completed properly, sparks from
electrical equipment, and even the flames from soldering equipment are just
some of the risks.
o Create a fire safety plan before starting the construction project. Every crew
member needs to know what to do in case of a fire and how to properly put out
the various types of fire possible on a construction site.
o Practice good housekeeping. Keeping the construction cite clean will leave
less material to start and spread fire. Insist on cleaning well after jobs.
o Designate a smoking area far from the construction site. Ashes and sparks
from lighters are one of the primary causes of fire in construction sites. If crew
members must smoke, they need to do it in a safe location.
FLOODS
o Floods are risk that construction sites need to be aware of and protect against.
Often floods do come with little warning, except in the event of levy or dam
breaking, but they can cause delays and costly damage to the construction site.
Here are some ways to help protect the site and those around it;
o Identify any risks based on the site location. Is the site near water? IS there a
way to add drainage? Does it have a natural drainage? Take measures to
ensure the area can properly drain when needed.
o Have a plan to protect equipment and personnel if the site floods. Creating a
site flooding plan if you are at risk for a flood will save lives and money.
o Asses the materials that will be damages by flood waters. If you suspect a flood
is coming, elevate those materials that need to be kept dry. If you are caught by
a flood without warning, dispose of damage material before moving on with the
project.
o If a flood warning is issued, evacuate the area. Flash floods can kill in an instant,
so take these warnings seriously. Even construction equipment is not safe from
flash floods.
Emergency Hotline Numbers in Magsingal, Ilocos Sur
▪ Magsingal District Hospital – (077)726-3514
▪ Magsingal Police Station – 0915-390-3286
▪ Magsingal Fire Station – 0915-390-3288
Work Scope : STEEL TRUSS AND ROOFING
Date Created : January 10, 2023
Prepared by : Zendi Mikhaela H. Butalon
Subject : JOB HAZARD ANALYSIS
PERSONAL
TASK HAZARD CONTROL PROTECTIVE
EQUIPMENT (PPE)
Safety Gloves, Safety Shoes
Shock/Electrocution Inspect all cordsets on tools and equipment for damage. Safety Goggles
Welding of steel truss Cuts/Lacerations Use leather gloves when handling steel bars Safety Gloves
Eye Injury Use safety goggles when handling power tools Safety Goggles
Employee fall protection will be provided thru guarding of the
Fall Hazard work platform with guard rails Safety Harness
Use of safety mask Safety Face Mask
Painting of Steels Lung Problem
Provide proper ventilation
Cuts/Lacerations Use leather gloves when handling GI Sheet Safety Gloves
Installation of Roof Employee fall protection will be provided thru guarding of the
Fall Hazard work platform with guard rails Safety Harness
Work Scope : Form Works and Concrete Pouring
Date Created : January 10, 2023
Prepared by : Zendi Mikhaela H. Butalon
Subject : JOB HAZARD ANALYSIS
PERSONAL
TASK HAZARD CONTROL PROTECTIVE
EQUIPMENT (PPE)
Safety Gloves, Safety Shoes
Shock/Electrocution Inspect all cordsets on tools and equipment for damage. Safety Goggles
Form Work for Footing
Cuts/Lacerations Use leather gloves when handling rebar and tie wire Safety Gloves
Eye Injury Use safety goggles when handling power tools Safety Goggles
Sprains/Strains Team lift any material, tools or equipment as needed.
Safety Gloves
Shock/Electrocution Inspect all cordsets on tools and equipment for damage. Safety Goggles
Form Work for Columns Cuts/Lacerations Use leather gloves when handling rebar and tie wire Safety Gloves
Eye Injury Use safety goggles when handling power tools Safety Goggles
Sprains/Strains Team lift any material, tools or equipment as needed.
Sprains/Strains Team lift any material, tools or equipment as needed.
Injury while using Vibration
Concrete Pouring on Footing Tools Inspection of tools
Safety Goggles and Wearing
Concrete Exposure Employee Training in concrete safety of Proper Uniform
Sprains/Strains Team lift any material, tools or equipment as needed.
Injury while using Vibration
Tools Inspection of tools
Concrete Pouring on Columns Safety Goggles and Wearing
Concrete Exposure Employee Training in concrete safety of Proper Uniform
Employee fall protection will be provided thru guarding of the
Fall Hazard work platform with guard rails Safety Harness
CONSTRUCTION SAFETY SIGNAGES
Prepared by:
Prepared By: