Bom A
Bom A
TILE WORKS
FF01
60x60cm Living Area 6.59 5.3 34.93 97
Kitchen 4.79 5.5 26.35 73
Kitchen Counter 0.6 2.35 1.41 4
0.6 1.5 0.90 3
Bar Counter 0.5 2.35 1.18 3
FF01
60x60cm Family Area 12.7 7.1 19.8 55
Total 55
FF02
30x30cm Toilet & Bath 2.15 1.7 3.85 43
30x30cm -wall 2.15 1.66 7.62 85
- 1.7 1.66 3.36 37
- 9.5 1.66 11.16 124
30x30cm MB-Toilet & Bath 2.65 1.43 4.08 45
30x30cm -wall 2.65 1.66 4.31 48
- 1.43 1.66 6.17 69
- 1.9 1.66 3.56 40
Total 490
FF03
30x30cm Bedroom 2 3.65 3.21 11.72 130
Bedroom 3 3.65 3.21 11.72 130
Masters Bedroom 4.26 3.05 12.99 144
Total 405
FF04
60x60cm Balcony 3.10 1.75 5.43 15
MB-Balcony 4.3 1.5 6.45 18
Total 33
5% Total
FF01 GROUND 181 11.8
60x60cm SECOND 55 248
FF02 GROUND 194 34.2
30x30cm SECOND 490 718
FF03 GROUND 112 25.9
30x30cm SECOND 405 543
FF04 GROUND 106 6.9
60x60cm SECOND 33 146
ABC Grout
unit TOTAL
Total sqm
Area Total of T&B 61.58 bags 8
Area Total of flooring 243.17 bags 30
Tile Adhesive
Total sqm
Area Total of T&B 61.58 bags 7
Area Total of flooring w/ counter except vinyl
196.63 bags 22
Cement
Total sqm
Area Total of T&B 61.58 bags 5
Area Total of flooring 225.05 bags 19
ABC Multibond Vinyl Type Adhesive
Total sqm
Area Total of flooring 46.54 kgs 8
CEILING WORKS
Gypsum Board Ceiling Board 3.0
DIM
GROUND FLOOR area qty
CF01
60x60cm Living Area 6.59 5.3 34.93 11.73
Kitchen 4.79 5.5 26.35 8.85
Total 21
CF02
30x30cm Toilet & Bath 2.85 1.50 4.28 1.44
Total 1
CF03
30x30cm Bedroom 1 3.15 3.21 10.11 3.40
Total 3
CF04 Carport 5.00 3.21 16.05 5.39
60x60cm Porch 2.35 2.29 5.38 1.81
Lanai 4.50 1.80 8.10 2.72
Dirty Kitchen/
Laundry Area 4.00 2.15 8.60 2.89
Total 13
TOTAL PCS 38
SECOND FLOOR DIM sqm. qty.
CF01
60x60cm Family Area 12.7 7.1 19.8 6.64
Total 7
CF02
30x30cm Toilet & Bath 2.15 1.7 3.85 1.29
30x30cm MB-Toilet & Bath 2.65 1.43 4.08 1.37
Total 3
CF03
30x30cm Bedroom 2 3.65 3.21
11.72 3.94
Bedroom 3 3.65 3.21
11.72 3.94
Masters Bedroom 4.26 3.05
12.99 4.36
Total 12
TOTAL PCS 12
TOTAL GYPSUM BOARD 51
PAINTING WORKS
Concrete Neutralizer
sqm unit TOTAL
Total sqm
Exterior Wall 185.95 gal 23
Interior Wall 75.73 gal 9
Flat Latex Paint
Total sqm
Ceiling 61.58 gal 7
Interior Wall
196.63 gal 22
Acrylic Paint
Total sqm
Exterior wall 61.58 gal 5
Skimcoat
Total sqm
Area Total of wall 42.85 gal 7
Paint Thinner
Total sqm
Area Total of flooring gal 0
Waterproofing
Total sqm
Area Total 63.64 sqm 11
Toilet & Bath 4.28
Toilet & Bath 2F 3.85
MB-Toilet & Bath 4.08
Dirty Kitchen/
Laundry Area 8.60
Lanai 8.10
Kitchen 26.35
Wall height 8.4 Total 64
Paint Accessories
Total sqm
Area Total of wall 46.54 gal 8
Metal Furring (0.4mm thk)
CF04 - GF L S W Total
DK/LA 4.00 0.60 6.67 2.15 0.43 2.87
Carport 5.00 0.60 8.33 3.21 0.64 5.35
Porch 2.29 0.60 3.82 2.29 0.46 1.75
CF03 - GF
B1 3.21 0.60 5.35 3.15 0.63 3.37
CF01 - GF
LA 5.50 0.60 9.17 4.30 0.86 7.88
5.30 0.60 8.83 5.50 1.10 9.72
CF03 - 2F
B1 3.65 0.60 6.08 3.21 0.64 3.91
B2 3.65 0.60 6.08 3.21 0.64 3.91
MB 4.26 0.60 7.10 3.05 0.61 4.33
CF02 - 2F
T&B 2.15 0.60 3.58 1.70 0.34 1.22
MB-T&B 2.65 0.60 4.42 1.60 0.32 1.41
CF01 - 2F
FA 5.05 0.60 8.42 6.21 1.24 10.45
Total pcs 56
CF01 - GF
LA 5.50 1.20 4.58 4.30 0.86 3.94
5.30 1.20 4.42 5.50 1.10 4.86
CF03 - 2F
B1 3.65 1.20 3.04 3.21 0.64 1.95
B2 3.65 1.20 3.04 3.21 0.64 1.95
MB 4.26 1.20 3.55 3.05 0.61 2.17
CF01 - 2F
2ND FLOOR
2B1 4.3 0.2 0.4 0.34
3.1 0.2 0.4 0.25
4.3 0.2 0.4 0.34
2.3 0.2 0.4 0.18
4.3 0.2 0.4 0.34
3.5 0.2 0.4 0.28
4.8 0.2 0.4 0.38
3.5 0.2 0.4 0.28
3.9 0.2 0.4 0.32
5.5 0.2 0.4 0.44
4.6 0.2 0.4 0.36
4.8 0.2 0.4 0.38
3.2 0.2 0.4 0.26
2B2 2.5 0.2 0.4 0.20
2B3 1.4 0.2 0.3 0.08
2B4 2.3 0.2 0.3 0.14
4.1 0.2 0.3 0.25
3.2 0.2 0.3 0.19
2.8 0.2 0.3 0.17
2B5 2.1 0.2 0.3 0.12
2CB1 3.0 0.2 0.4 0.24
5.0 0.2 0.4 0.40
2RB1 8.0 0.2 0.4 0.64
5.4 0.2 0.4 0.43
Total 7.0
FORM
Left Hook
m m Concrete Cover
(m)
Concrete
Left Hook Clear Span Right Hook
L W Cover
(m) (m) (m)
(m)
F1 1.3 1.3 0.075 0.2 1.15 0.2
F2 1.6 1.6 0.075 0.2 1.45 0.2
F3 1.4 1.4 0.075 0.2 1.25 0.2
F4 0.8 0.8 0.075 0.2 0.65 0.2
F5 0.6 0.6 0.075 0.2 0.45 0.2
CF1 1.3 2.25 0.075 0.15 1.15 0.15
CF1 1.3 2.25 0.075 0.25 1.15 0.25
STF1 0.6 1.15 0.075 0.25 0.45 0.25
TOTAL
Rebars
Footing
Clear Span Right Hook
Total Short Side Long Side
(m) (m)
Co
Unit weight Total L No. of bars
7850 2772.82 C1 3.2 8
7850 866.51 PC1 3.2 4
REBARS
Volume of
Total Unit Weight
Long Rebar Dia. Rebar
Total Short Side Total Rebar of Rebar
Side (m) Required
Length (kg/m3)
(m3)
1.55 10 10 20 31 0.012 0.003506017 7850
1.85 12 12 24 44.4 0.012 0.005021522 7850
1.65 11 11 22 36.3 0.012 0.004105433 7850
1.05 5 5 10 10.5 0.012 0.001187522 7850
0.85 4 4 8 6.8 0.012 0.000769062 7850
1.45 10 6 16 23.2 0.01 0.001822124 7850
1.65 10 6 16 26.4 0.016 0.005308035 7850
0.95 6 3 9 8.55 0.016 0.00171908 7850
Long Side Total Total Rebar Length Rebar Diameter Volume of Rebar
Required
10 20 31 0.012 0.003506017401406
12 24 44.4 0.012 0.005021521697498
11 22 36.3 0.012 0.004105433279711
5 10 10.5 0.012 0.001187522023057
4 8 6.8 0.012 0.000769061881599
6 16 24.8 0.012 0.002804813921125
6 16 13.6 0.012 0.001538123763198
Total
Weight of
Weight of
Rebar Qty of
Rebar
Required Member
Required
(kg)
27.5222366 9 (kg)
247.7001294
39.41894533 2 78.83789065
32.22765125 1 32.22765125
9.322047881 3 27.96614364
6.037135771 1 6.037135771
14.30367135 1 14.30367135
41.66807434 1 41.66807434
13.49477408 1 13.49477408
462.2354705
Total 485
Unit Weight of Weight of Rebar Total
Rebar Required QTY
VOLUME
BEDDING DIM VOLUME qty.
TOTAL
F1 1.30 1.30 0.75 1.27 9 11.41
F2 1.60 1.60 0.75 1.92 2 3.84
F3 1.40 1.40 0.75 1.47 1 1.47
F4 0.80 0.80 0.75 0.48 3 1.44
F5 0.60 0.60 0.75 0.27 1 0.27
CF1 1.30 2.25 0.75 2.19 1 2.19
STF1 0.60 1.15 0.75 0.52 1 0.52
WF 69.25 0.25 0.60 10.39 1 10.39
SOG1 5.35 4.30 0.10 2.30 1 2.30
5.35 2.30 0.10 1.23 1 1.23
3.45 4.88 0.10 1.68 1 1.68
2.00 8.00 0.10 1.60 1 1.60
4.80 3.20 0.10 1.54 1 1.54
SOG2 4.00 3.20 0.15 1.92 1 1.92
Total 42
VOLUME
BACKFILL DIM VOLUME qty.
TOTAL
F1 1.30 1.30 1.50 2.54 9 22.82
F2 1.60 1.60 1.50 3.84 2 7.68
F3 1.40 1.40 1.50 2.94 1 2.94
F4 0.80 0.80 1.50 0.96 3 2.88
F5 0.60 0.60 1.50 0.54 1 0.54
CF1 1.30 2.25 1.50 4.39 1 4.39
STF1 0.60 1.15 1.50 1.04 1 1.04
C1 0.40 0.20 4.58 0.37 12 4.39
C2 0.30 0.20 4.58 0.27 5 1.37
Total 37
GROUND FLOOR
EXTERIOR
GF L H sqm opening 1 opening 2 Total
W1 6.8 2.7 18.36 w3 1.8 w6 0.25 16.31
W2 4 2.7 10.8 10.8
W3 2.15 2.7 5.805 d2 1.89 3.915
W4 4 2.7 10.8 w5 1.2 9.6
W5 5.5 2.7 14.85 gd1 4.515 10.335
W6 2.5 2.7 6.75 6.75
W7 2.2 5.5 12.1 w1 5.4 6.7
W8 3.1 2.7 8.37 8.37
W9 4.3 2.7 11.61 w2 6 5.61
W10 2.35 2.7 6.345 6.345
W11 2.29 2.7 6.183 d1 3.36 2.823
W12 1.85 2.7 4.995 w4 1.2 3.795
W13 3.21 2.7 8.667 8.667
INTERIOR
GF L H sqm opening 1 opening 2 Total
IW1 4.65 2.7 12.555 d4 1.365 d3 1.68 9.51
IW2 3.21 2.7 8.667 8.667
SECOND FLOOR
EXTERIOR
2F L H sqm opening 1 opening 2 opening 3
EW1 7.6 2.4 18.24 w3 1.8 w3 1.8
EW2 8 2.4 19.2 w6 0.25
EW3 3.45 2.4 8.28 w3 1.8
EW4 1.8 2.4 4.32
EW5 2.2 5.5 12.1
EW7 4.6 2.4 11.04
EW8 4.3 2.4 10.32 gd2 6.3
EW9 1.2 2.4 2.88
EW10 5.5 2.4 13.2 w7 0.85 w7 0.85 w7 0.85
INTERIOR
2F L H sqm opening 1 Total
IW1 3.21 2.7 8.667 8.667
IW2 3.65 2.7 9.855 d3 1.68 8.175
IW3 1.6 2.7 4.32 d4 1.365 2.955
IW4 3.65 2.7 9.855 d3 1.68 8.175
IW5 1.795 2.7 4.8465 4.8465
IW6 2.25 2.7 6.075 6.075
IW7 1.05 2.7 2.835 2.835
IW8 4.34 2.7 11.718 d3 1.68 10.038
IW9 2.65 2.7 7.155 d4 1.365 5.79
TOTAL CHB
No. of
1st floor 2nd floor area qty. (pcs)
CHB
CHB 150 ext (6") 100.02 85.93 185.95 12.5 2324.4
CHB 100 int (4") 18.177 57.5565 75.7335 12.5 946.7
Total 3271
153 12.74
Total Sand
44.63
17.92
62.55
Electrical Works Qty
Electrical Roughing - ins
a. Panel Board (12 Branches) 1
b. Circuit Breaker (20amp) 8
c. Circuit Breaker (30amp) 4
d. Circuit Breaker (100amp) 1
e. PVC Orange Pipe (15mm) 200
f. PVC Orange Pipe Elbow (15mm) 30
g. 3.5mm2 THHN wire Duraflex 250
h. 8.0mm2 THHN wire Duraflex 31
i. 22.0mm2 THHN wire Duraflex 31
j. Electrical Accessories 1
Lighting Fixtures
a. Pinlights 71
b. Center Light 11
c. Wall Lamp 2
d. Drop Light at Bar Counter 1
Devices
a. Convenience Outlet 33
b. Weather Proof Convenience Outlet 7
c. 1 gang Switch 5
d. 2 gang Switch 13
e. 3 gang Switch 3
f. 3-way Switch 4
g. ACU Outlet 4
h. CATV Outlet 6
Unit
pcs
pcs
pcs
pcs
pcs
pcs
m
m
m
lot
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
pcs
PVC Pipe 1/2"Ø x 3m
horizontal vertical
1.5 1
2 1
11.8 1
4 1
2.15 1
5 1
0.5 1
3 2.5
0.5 2.5
3.45 2.5
3.65 3.475
1.7
2.1
TOTAL 54
BILL OF MATERIALS
ITEM DESCRIPTION AMOUNT
DIV. 01 GENERAL REQUIREMENT ₱207,634.00
DIV. 02 SITE WORKS ₱82,843.68
DIV. 03 CIVIL / STRUCTURAL WORKS ₱3,721,572.08
DIV. 04 WINDOWS/DOOR/DOOR JAMBS/CASEWORKS ₱204,371.00
DIV. 05 ROOFING / TINSMITHRY WORKS ₱72,571.84
DIV. 06 CEILING WORKS ₱30,356.84
DIV. 07 FINISHES / PAINTING WORKS ₱356,653.98
DIV. 08 ELECTRICAL ₱92,180.00
DIV. 09 SANITARY ₱141,707.67
DIV. 10 SPECIALTY WORKS ₱131,000.00
MATERIAL COST ₱5,040,891.08
LABOR COST (40%) ₱2,016,356.43
CONTINGENCIES (5%) ₱252,044.55
GRAND TOTAL ₱7,309,292.07
ITEM DESCRIPTION
DIV. 03 CIVIL / STRUCTURAL WORKS Qty Unit Unit Price (Mtls) Amount
CONCRETING WORK
a. Footing
a.1 Concrete 9.7 m3 4200 40587.75
a.2 Form Rebars 29.7 m2 1240 36778.4
a.3 Rebars 485.0 kgs. 192 93120
b. Grade Beams
b.1 Concrete 4.1 m3 4200 17400.6
b.2 Form Rebars 69.1 m2 1240 85622
b.3 Rebars kgs. 341 0
c. Column from GF To 2nd Flr.
c.1 Concrete 5.8 m3 4200 24210.9
c.2 Form Rebars 88.8 m2 2584 229342.92
c.3 Rebars 5378.0 kgs. 341 1833906
d. Ground flr. Slab 0
d.1 Concrete 8.3 m3 4200 34654.2
d.2 Form Rebars 82.3 m2 1240 102027.2
d.3 Rebars 3298.6 kgs. 133 438713.31
e. Column from 2nd To Roof
e.1 Concrete 2.9 m3 4200 12230.4
e.2 Form Rebars 42.6 m2 2584 109975.04
e.3 Rebars kgs. 341 0
f. Second flr. Slab
f.1 Concrete 8.2 m3 4200 34454.438
f.2 Form Rebars 65.6 m2 914 59983.535
f.3 Rebars kgs. 133 0
g. Beams @ 2nd flr.
g.1 Concrete 7.0 m3 4200 29479.8
g.2 Form Rebars 110.0 m2 1240 136400
g.3 Rebars kgs. 341 0
h. Roof Beams
h.1 Concrete 2.03 m3 4200 8534.4
h.2 Form Rebars 5.05 m2 1240 6259.52
h.3 Rebars kgs. 341 0
i. Stair/ Landing
i.1 Concrete 1.28 m3 4200 5376
i.2 Form Rebars 6.2 m2 1240 7688
i.3 Rebars 182.51 kgs. 192 35041.92
MASONRY
a. 6" Concrete Hollow Blocks 2324.375 pcs. 16 37190
b. 4" Concrete Hollow Blocks 947 pcs. 15 14200.031
c. Reinforcing Steel Bar 540 kls. 36 19440
d. Sand 12.74 m3 700 8921.1733
e. Cement 152.93 bags 218 33339.699
f. G.I # 16 6 rolls 85 510
g. Plastering
g.1 Concrete 750.61 bags 218 163633.94
g.2 Sand 62.55 m3 1000 62551.2
SUB-TOTAL 226185.14
a. D-1 1.60m X 2.10m Double Leaf Swing Door Panel Door with 1 set 24300 24300
Door Jamb at Entrance
b. D-2 0.90m X 2.10m Single Leaf Swing Door Panel Door with 1 set 7585 7585
Door Jamb at Kitchen
4 set 10500 42000
c. D-3 0.80m x 2.10m Flush Door Type at Bedrooms
3 set 3262 9786
d. D-4 0.65m x 2.10m PVC Door Type at T&B
e. GD-1 2.15m x 2.10m Sliding Glass Door in Aluminum Frame at 2 set 12000 24000
Dining Room/Family Area
f. GD-2 3.00m x 2.10m Sliding Glass Door in Aluminum Frame at 1 set 16000 16000
Master BR Balcony
WINDOWS
a. W-1 1.80m x 3.0m Awning + Fixed Type Window 1 set 18000 18000
b. W-2 3.0m x 2.0m Awning + Fixed Type Window 1 set 14000 14000
c. W-3 1.50m x 1.20m Sliding Type Window 4 set 5000 20000
d. W-4 1.00m x 1.20m Sliding Type Window at Foyer 1 set 4500 4500
e. W-5 1.50m x 0.80m Sliding Type Window at Kitchen 1 set 4200 4200
f. W-6 0.50m x 0.50m Awning Type Window at T&B - GF&2F 2 set 2500 5000
SUB-TOTAL 204371
SUB-TOTAL 141707.67