Trade Project
Trade Project
This Project is submitted to the Kenya National Examination Council in partial fulfillment of the course
diploma in any other institution. This project is submitted in partial fulfilment of the examination requirements
for the award of Diploma in Building Technology certificate, Department of Building and Civil Engineering,
Author
Mr …………
Supervisor
DEDICATION
I would like to extend my bona fide obligation towards all the people who have helped me, not only during the
With a great profound sense of reverence, I’d like to express my gratitude to my parents Joseph, Pamela and
Millicent Odiembo. Thank you for all the sacrifices, kindness and encouragement. Thank you for teaching me
to be patience and that even the greatest achievements are made a step at a time.
To my sibling, Jared, thank you for always leading by example. Your support, prayers and motivation
Mr Wamai, my Tutor and Project Coordinator, I am grateful for your fastidious commitment to excellence,
encouragement to go above and beyond, insight, timely critique and guidance, without which, I would not have
made headway in this project. I appreciate your critical guidance and input, which went a long way in bettering
this research. ‘A good teacher is like a candle; it consumes itself to light the way for others’-Mustafa Kemal
Ataturk
Special thanks to my brother Arch.Victor Ouru, your timely critiques were instrument in the formulation of this
project.
Last but not least, my gratitude goes to classmates. It has been a challenging journey which you all have made a
delight through your resilience, thoughtfulness and sacrifice. May the moments we’ve shared yield lifelong
camaraderie.
Contents
DECLARATION.......................................................................................................................................................................2
DEDICATION..........................................................................................................................................................................3
ACKNOWLEDGEMENT..........................................................................................................................................................4
ABSTRACT............................................................................................................................................................................. 7
PROJECT OBJECTIVES............................................................................................................................................................8
CHAPTER 1: SURVEYING.......................................................................................................................................................9
Introduction...................................................................................................................................................................... 9
Preliminary Surveys...........................................................................................................................................................9
Reconnaissance Survey.....................................................................................................................................................9
Actual Survey..................................................................................................................................................................... 9
Contouring...................................................................................................................................................................... 10
Chain survey....................................................................................................................................................................10
CHAPTER 2: SOIL INVESTIGATION......................................................................................................................................14
Introduction....................................................................................................................................................................14
Field density....................................................................................................................................................................14
Proctor test..................................................................................................................................................................... 14
Procedure....................................................................................................................................................................14
California bearing ratio.....................................................................................................................................................15
Procedure of CBR........................................................................................................................................................15
Atterberg limits............................................................................................................................................................... 16
Procedure................................................................................................................................................................... 16
Plastic limit......................................................................................................................................................................17
Procedure................................................................................................................................................................... 17
Shrinkage Limit...............................................................................................................................................................18
Procedure................................................................................................................................................................... 18
Grading........................................................................................................................................................................... 18
Procedure....................................................................................................................................................................18
Conclusion.......................................................................................................................................................................19
CHAPTER 3: BUILDING SERVICES........................................................................................................................................20
Introduction....................................................................................................................................................................20
Electrical distribution......................................................................................................................................................20
Heating, ventilation and air conditioning........................................................................................................................20
Plumbing......................................................................................................................................................................... 20
Storm water management and disposal.........................................................................................................................20
Fire detection and protection system.............................................................................................................................20
Fire detection..............................................................................................................................................................20
Fire protection.............................................................................................................................................................21
Lighting protection system..............................................................................................................................................21
Security and alarm system..............................................................................................................................................21
CHAPTER 4: ARCHITECTURAL REQUIREMENTS..................................................................................................................22
CHAPTER 5: STRUCTURAL DESIGN......................................................................................................................................23
CHAPTER 6: MEASUREMENTS, ESTIMATING AND COSTING..............................................................................................45
CHAPTER 7: ESTIMATION AND COSTING............................................................................................................................55
CHAPTER 8: SITE ORGANIZATION AND CONSTRUCTION MANAGEMENT.........................................................................60
Feasibility Study..............................................................................................................................................................60
Method Statement..........................................................................................................................................................60
Contract Program............................................................................................................................................................61
Site Layout Plan...............................................................................................................................................................62
ABSTRACT
Structural design is the primary aspect of building and civil engineering. The very basis of construction of any
building, residential apartment is designing, survey works, building services, estimation and planning.
The foremost basic is the design of simple basic components and members of the proposed residential
apartment i.e., slab, beams, column and footing in which their both structural and architectural designs has been
prepared using computer aided designs software. In this project plan has been obtained i.e., positioning of the
particular rooms such that they serve their respective purpose and suiting to requirement and comfort of the
inhabitant. Thereby depending on the suitability; plan layout of the beams and the position of column are fixed.
Thereafter the vertical loads (dead and live loads) are calculated. Grade concrete and steel are to be used.
In the project, the planning of G+1 floors student hotel complex has been done in accordance to the required
building standards and also estimated building cost through all stages of design and the construction of the
project. It is a single block modern residential building. The project is to be constructed within Kabete National
Polytechnic area where soil tests has been carried by various method to determine the soil bearing capacity.
The project is to develop independent and creative thinking fundamental theoretical knowledge I obtained
The aim of surveying is to know the topography of the site, the interest and establish boundaries before the
project begins. It also assists in the establishing other features of the site and the surrounding e.g. adjacent
structure within the site. We undertook the survey work in a group of five students and our surveying was;
Preliminary Surveys
Preliminary survey was conducted to identify the general features of the site such as vegetation and building in
the site. We also allocated possible survey station and collected information on the location of the site and
Reconnaissance Survey
The main objective of this was to establish the site existing features, the topography and the activities taking
This was assisted in determining the equipment to be used in the actual survey chain survey. The survey was
carried out on 5th April. It was found that the following equipment was used:
Ranging rods
Steel tape
Wooden pegs
Actual Survey
The survey was done when the wind was still and there was a warm temperature and the sky was clear that
Pegs
Hammer
Steel tape
Wooden pegs
Ranging rods
Leveling staff
Contouring
The main objective of the contouring was to establish contours and plot them on a plan for ease of interpretation
where dumpy level, pegs, tape measure and ranging rods were used.
Chain survey
This was done with help of 30metres steel tape and ranging rods. first we established a base running between the
existing complex building corners adjacent to the action block corner. From this we located a corner of the
other buildings on the site and other feature e.g. trees by introducing offsets.
The data was collected and recorded was used to come up with the site plan.
1.800 1.310
0.015 1000.025
1.800
CHECKCS -0.05
Contour diagram
CHAPTER 2: SOIL INVESTIGATION
Introduction
According to the soil investigation guidelines, a series of experiments were conducted at a soil laboratory in
Karen government laboratory. The test was done on a sample of soil collected from the projects proposed site
that is located at the main field. The test conducted were the following;
Proctor test
Grading test
Plasticity test
Field density
The test were done so as to acquire the specific soil properties or the characteristics of the soil in the question so
as to determine whether it is fit for construction works that were proposed for being excavated for basement,
The sample collected from the field in question were subdivided into a number of division for the various tests
to be carried out excluding field density which is done on the field and not on the laboratory.
Proctor test is usually done first as it gives a deep guideline to the other tests waiting to be done. The whole
sample is first air dried or sun dried to remove all the moisture in it before any test is carried out on them
Proctor test
This is a test done to ascertain the maximum dry density and the optimum moisture content of soil under
investigation, a number of samples are taken for proctor test so as to acquire a certain degree of accuracy with
the average of the test done being taken as the final standards of the soil investigations.
Procedure
i. Collect undisturbed soil sample in a container and add 0.01 cubic meters of water into soil
ii. Subdivide the soil into 3 layers, compacting each layer by 27 blows of a standard rammer.
iii. Insert a third of the soil sample in a mould and a rammer on top of it for each blow.
iv. Lift the rammer head half of its foot high to a length of 300mm for each blow
vi. Take 3-4 samples of the soil and determine their moisture content by placing in an oven.
vii. Add water again into the soil five times hence determination of the moisture content.
maximum dry density and the optimum moisture content to derive the quantity of the soil to be use in
Procedure of CBR
i. Subdivide the soil sample into 3 layers and place the first layer into mould for the compaction ~ first
ii. Remove the collar and trim the edge with an edge, weigh the sample and record the values.
iii. Insert the mould and the specimen, place another filter paper and put in place. Return the collar and the
iv. Soak the specimen in the soaking tank for 4 days to determine the neat materials. After four days place it
on the penetrating machine and record readings from the top to bottom.
days
Atterberg limits
This is the test done to ascertain behavior of soil under certain or specified amount of water.
They include; liquid limits, plastic index, plastic index and linear shrinkage.
Liquid limit
This is the maximum amount of water by and which a soil sample is no longer plastic.
Procedure
i. Sieve the soil sample using a 5.00mm sieve and take the passing test.
ii. Crush the passing using a mortar and a pestle to obtain fine powder which is ideal for the test.
iv. Put the muddy substance in cylinder and penetrate it with a cone, repeat it by adding water or dry soil until
v. Take a sample from the cup and put it in a tin and weigh it before oven drying it
vi. After 24 hours remove the tin from the oven and note the weight.
iv. Add water to it and roll it on the glass surface until it forms 3mm long or roll it by hands until it forms
v. Put the remaining in a tin note the weight and put it In an oven for 24 hours
Procedure
i. Take a sample from the molding that gives a 20mm penetration on a dial gauge by a cone and put it in a
iv. Remove the trough and measure the empty pot due to shrinkage of the initial plastic samples.
Grading
Grading is test done on a sample collected from the site to ascertain the description of soil particles under
consideration
Procedure
iii. Its washed to remove clay and silt, then oven dried
iv. A certain solution is added together with water to remove all humus and living organisms in the sample
for 12 hours
v. Its then oven dried and sieved on sieves on ranging from 5mm-2mm, 1mm-300gm, 425gm
viii. The percentage passing is calculated progressively from the percentage retained.
ix. A graph of percentage passing against the size the is drawn (it should be a smooth curve)
Conclusion
The soil is well graded since it has particles of all particles of almost all sizes as shown above when sieved by a
Electrical distribution
A means of transmitting electricity will be employed. A network of conductors and equipment designed to
distribute and convert electric power safely from a point of delivery to various loads around the building that
Electrical components for this purpose will include; main service panel, electric cables, conduits circuit
breakers.
Ventilation and air-conditioning. - which is the intentional introduction of outside air into the building will be
used due to climatic changes to control indoor air by diluting and displacing indoor pollutants. Both natural and
Plumbing
Systems that will be used to transmit water or fluids for wide range application will be used. The major
Gas detectors to detect combustible gases will be applied to prevent events of fires by gases.
Fire protection
Active and passive fire protection to fight a fire in an eventuality of a fire shall be applied. This includes;
system such as sprinkler system which require manual intervention such as fire extinguishers, hose reals and
hydrant valves.
Passive fire protection will be applied which attempts to contain or slow spread of fire. This also includes
provision of containment of areas and escape routes for evacuation in an even of fire outbreak.
protection where a separation will be created between the building and possible threat. Visual security system
i.e., CCTV camera system and alarm devices such as burglar alarm will be installed.
Other services will include; communication and IT networks e.g., wireless data provision network (Wi-Fi),
ii. Elevations.
ii. Stairs
iii. Beams
Building up unit rate and price all the items for the substructure works.
C/ Backfill with
S/ excavation to approved material.
remove top soil
average 150mm
from ground
level.
CONCRETE
WORKS
C/ Blinding concrete
S/ excavate to in H/C surface.
reduced level
50mm from
stripped level.
C/ VRC 1.2.4 in
foundation.
C/m Excavate
foundation trench
not exceeding
150mm from
stripped level.
THE KABETE NATIONAL POLYTECHNIC
TITLE: ABSTRACTING SHEET FOR SUBSTRUCTURE
EXAMINER: THE KENYA NATIONAL EXAMINATION COUNCIL
COURSE: DIPLOMA IN BUILDING TECHNOLOGY
PROJECT: PROPOSED KNP STUDENT HOTEL COMPLEX
DESIGNER: KANJA SMUEL MUTHAKA SHEET NO.
ADD DITTO ADD DITTO
FORMWORKS
Sawn timber
formwork to sides
of foundation in
stages
THE KABETE NATIONAL POLYTECHNIC
TITLE: BILL OF QUANTITY
EXAMINER: THE KENYA NATIONAL EXAMINATION COUNCIL
COURSE: DIPLOMA IN BUILDING TECHNOLOGY.
PROJECT: PROPOSED KNP STUDENT HOTEL COMPLEX
DESIGNER: FELIX OUMA ODIEMBO SHEET NO.
ITEM DESCRIPTION UNITS QTY RATE Kshs. Cts.
EXCAVATION AND
EARTHWORKS
FOUNDATION WALL
HARDCORE FILL.
CONCRETE WORKS.
25mm thick blinding concrete in
foundation trench.
FORMWORK.
practicality of the of the project plan in order to judge whether or not we are able to move forward with the
project or not by answering whether the team has the required tools and equipment and resources to complete
the project. Feasibility study will also help evaluate if there will be enough return on the investment to make the
Method Statement
Contract Program
ACTIVITY METHOD REMARKS
Site clearance Manually done with spades Cut down the shrub, clear grass, grab of
and jmbes the roots and burn the shrub.
Surface stripping Manually done using Deposit soil away from working area
spades, formjembes etc..
Foundation trench A backhoe will be hired Soil preserved at one corner for later
backfilling
Column base excavation Manual using mallets Deposit at one corner, less backfill
Oversite concrete Tilting drum mixer Transport and place the concrete
Site Layout Plan
Month Jan Feb March April May June July August September October
Preparation
Surveying
Works
Soil
Investigation
Architectural
Drawings
Structural
Drawings
Measurement
Management
and services
Typing and
Printing