PA SCHOOL: CHAPEL

RENOVATION &
EXPANSION
Emma Willard School
in Troy, NY

PRESENTED BY
INDIGO CONSTRUCTION
TABLE OF CONTENTS
01 OUR APPROACH

02 LOGISTICS

03 ESTIMATED COSTS

04 SCHEDULE

05 LEED AND VALUE ENGINEERING

06 ADDENDA AND CHANGE ORDERS


OUR COMPANY
Indigo is a company founded
by engineers with music
backgrounds. We build with
the intention of innovating
the performing arts center
space and we specialize in
environments that musicians
thrive in.
Company Stats

$440,000,000 Total Portfolio Value

Projects Last 5 Years


14

Total Employees
45
ABOUT THE
PROJECT
14,000 SF of
renovation of the
school’s historic
chapel and an
addition of 16,000 SF
of new construction in
the soon to be art
wing.
OUR APPROACH

01
CONSTRUCTION MANAGEMENT APPROACH

Risk Management Scheduling Estimating

● TrueLook will be implemented as the ● Monthly meetings about ● Our team will conduct a
3rd party to audit on our on site deliverables with the design team Detailed Quantity Takeoff
practice for the safety of construction and client. Progress updates, for materials and labor
workers and the project,. The Anticipated Cost Reports, and 4 required for each phase of
combination of 24/7 HD recording, Week Look Aheads will also be the construction project.
AI-powered motion detection, and provided.. ● Also will present the
real-time notifications provides ● Supply chain management will defined scope of work for
owners with a peace of mind. include frequent updates on our each construction phase
● With seamless integrations with internal Material Delivery Log. and component.
Procore and Autodesk allows for ● Bi-weekly meetings will be
organization to monitor the project. conducted with the design team.
Weekly meetings will be conducted
with all site personnel.
LOGISTICS

02
SITE LAYOUT
Purple Area: Staging Area
Orange Area: Material Storage
Dark Green Area: Field Office
White Area: Portable Toilets
Blue Area: Security Booth
Pink Area: Wing Expansion

Yellow Route: Material Delivery to site


Bright Blue arrows: Trucks exit route
Red Outline: Fence to Barricade Site
Light Green: Main Entrance to Site
Gray X’s: Emergency Evacuation Points
Preview of Chapel
Renovation - BIM

Southwest View Section Cut


ESTIMATED COSTS

03
Guaranteed Maximum Price Estimate

$36,594,888 GMP

CM Fee
2% (included)

Contingency
5% (included)
GMP Breakdown

00 Procurement & Contracting Requirements $1,196,652.85

01 General Requirements $3,052,013.70

02 Existing Conditions $2,367,689.28

03 Concrete $2,279,861.55

04 Masonry $2,115,184.55

05 Metals $1,873,658.29

06 Wood, Plastics, & Composites $1,822,425.44

07 Thermal & Moisture Protection $1,745,576.18

08 Openings $1,906,593.69

09 Finishes $2,074,930.17
GMP Breakdown

10 Specialties $724,578.79

11 Equipment $1,002,699.94

12 Furnishings $845,341.92

14 Conveying Equipment $530,625.88

21 Fire Suppression $362,289.40

22 Plumbing $1,741,916.69

23 HVAC $3,011,759.32

17 Electrical $2,814,146.92

31 Earthwork $3,333,794.34

32 Exterior Improvements $1,793,149.53


Project-Specific Conditions

● Soil conditions at foundation level


● Harsh winter conditions factored
in contingency fee of the GMP
● Additional protection to avoid
damage and preserve the chapel

Change Order
Change Order #1: approx. $110,000
Change Order #2: approx. $8,000
SCHEDULE

04
Schedule
Renovation of the Chapel Expansion of the Arts Wing
Key items Key items

● Demolition of the pool slab ● Chiller plant


● Restoration work ● Interior finishes for all floors
● Underpinning ● Non acoustical deck

Pre-Construction & Procurement Phase Construction Phase


Date: 11/10/2023-6/10/2024 Date: 6/18/2024-1/12/2026
Duration: 7 months, 2 weeks, 3 days Duration: 1 years, 6 months, 3 weeks, 4 days
Work Days: 143 Work Days: 388

Total construction schedule


Date: 11/10/2023- 1/12/2026
Duration: 2 years, 2 month, 1 week, 5 days
Work Days: 537
Project Schedule - Microsoft Project
Schedule
Construction Phase
● Mobilization scheduled to start on 6/18/24.
● Pre-construction meeting might happen early in the
year, potentially enabling site mobilization to start
much earlier, finishing construction up to 5 months
ahead of the original estimate.
● This strategy aims to create flexibility between
activities to accommodate unexpected weather or
delays, avoiding setbacks to critical path activities.
● Mobilization will commence when conditions are
suitable to achieve substantial completion by
1/12/2026 without delays.
Important Milestones

Milestones Duration Start Date Finish Date

Notice to Proceed 1 day Fri 11/10/23 Fri 11/10/23

Assigning the Project 1 day Mon 11/13/23 Mon 11/13/23


Team

Preconstruction 156 days Mon 11/13/23 Mon 6/17/24

Construction 395 days Tue 6/18/24 Mo 12/22/25

Mobilization 20 days Tue 6/18/24 Mon 7/15/24

Excavation for 40 days Tue 7/16/24 Mon 9/9/24


Foundations
Important Milestones
Milestone Duration Start Date Finish Date

Renovation of the 247 dys Tue 7/16/24 Wed 6/25/25


Chapel

Construction of 335 days Tue 9/10/24 Mon 12/22/25


Expansion

Substantial 15 days Tue 12/23/25 Mon 1/12/26


Completion

Closeout 10 days Tue 1/13/26 Mon 1/26/26


Documentation

Final Payments and 20 days Tue 1/27/26 Mon 2/23/26


Warranties

Owner Move in 0 days Mon 1/12/26 Mon 1/12/26


Schedule
Critical Path Activities

● There are 24 critical path activities


● Critical Path Activities marked red
Flow of Work

RENOVATION
OF CHAPEL

7/16/24
NOTICE TO SUBSTANTIAL
PRECONSTRUCTION
PROCEED COMPLETION

11/10/23 11/13/23 1/12/26


CONSTRUCTION OF
EXPANSION

12/22/25
PERMITS
Building Permits Concrete & Steel
-Site plan Approval -Crane and Rigging Permits
-Environmental Impact Assessment -Retaining Wall Permits
-Excavation Permit -Concrete Cutting or Coring Permits
-Land Disturbance or Erosion Control -Crane and Rigging Permits
-Stormwater Management -Highway and Transportation Permits
-Historic Preservation Review -Specialty Inspections
-Site Plan Approval -Welding and Fabrication Permits

MEP Permits Historical


-Mechanical Permit
-Demolition Delay or Review
-Electrical Permit -Site Assessment
-Plumbing Permit: -Specialty Inspections
-Gas Permit -Historic Preservation Approval
-Fire Alarm Permit:
-Fire Sprinkler Permit:
-Backflow Prevention Permit
Key Procurement Items

Glass Storefront Variable frequency Drives

Structural Steel Specially Molded Face Bricks

Boilers Elevators

Air separators
Change Order
● While removing old flooring in the chapel, discovered basketball flooring that needs to
be removed.
● Expected delay of 15 work days in the schedule
● However, due to not being a critical task, no delay for substantial completion date
VALUE ENGINEERING AND LEED

05
OUR LEED SERVICES
Project as it is:
LEED Certification, approx. 45 credits

The Indigo Guarantee:


Platinum LEED Certification, 83
credits.

Improvements on areas of carbon,


energy, water, waste, transportation,
materials, indoor and outdoor
environmental quality.
PRE-CONSTRUCTION

ASSESSMENTS:
● Environmental Site Assessment
(ESA)
○ Soil acidity
○ Possible pollutants
○ Type of soil for foundation
○ Dangerous materials in
paint
■ Asbestos

● Cost:
○ Phase 1 → $2,000 - $5,000
○ the research, site visits,
and required reporting.
○ Contamination issues,
foundation issues, delays.
CONSTRUCTION

POLLUTION
PREVENTION

● Water sprays:

● Protective equipment for workers

WASTE SEPARATION &


RECYCLING

● Separate containers for different materials


○ Maximize profit from recycling
■ Identity, partner, negotiate.
WATER EFFICIENCY OUTDOOR
● Turf alternative:
○ Micro clover
■ Drought resistant
■ No-mow lawn
■ Will spread

INDOOR
● Low flow toilets
○ 1.28 gpf or less
● Automatic faucets
○ 0.5-1.5 gpm
OPEN SPACES
LAWN & GREEN ROOF

● Heat island reduction


● Rainwater management
● Open space
VALUE ENGINEERING
Title Value Engineering Current GMP Value Estimated Value of Proposed GMP
Option VE Value

Grass lawn Micro clover $160 $3,060 in water $315

Diesel Electric 10,000 hours 4,000 hours 6,000 hours


Construction Construction (value measured in
Equipment Equipment operating time)

- 1000F - 1” - - $239
Wheeled Sprinkler

Regular Parking ChargerPoint - - $1,299


CPF50

- Solar Panel - ~$2000 $6,000


PA SCHOOL: CHAPEL
RENOVATION &
EXPANSION
Emma Willard School
in Troy, NY

PRESENTED BY
INDIGO CONSTRUCTION