Spring 2024 Pres
Spring 2024 Pres
RENOVATION &
EXPANSION
Emma Willard School
in Troy, NY
PRESENTED BY
INDIGO CONSTRUCTION
TABLE OF CONTENTS
01 OUR APPROACH
02 LOGISTICS
03 ESTIMATED COSTS
04 SCHEDULE
Total Employees
45
ABOUT THE
PROJECT
14,000 SF of
renovation of the
school’s historic
chapel and an
addition of 16,000 SF
of new construction in
the soon to be art
wing.
OUR APPROACH
01
CONSTRUCTION MANAGEMENT APPROACH
● TrueLook will be implemented as the ● Monthly meetings about ● Our team will conduct a
3rd party to audit on our on site deliverables with the design team Detailed Quantity Takeoff
practice for the safety of construction and client. Progress updates, for materials and labor
workers and the project,. The Anticipated Cost Reports, and 4 required for each phase of
combination of 24/7 HD recording, Week Look Aheads will also be the construction project.
AI-powered motion detection, and provided.. ● Also will present the
real-time notifications provides ● Supply chain management will defined scope of work for
owners with a peace of mind. include frequent updates on our each construction phase
● With seamless integrations with internal Material Delivery Log. and component.
Procore and Autodesk allows for ● Bi-weekly meetings will be
organization to monitor the project. conducted with the design team.
Weekly meetings will be conducted
with all site personnel.
LOGISTICS
02
SITE LAYOUT
Purple Area: Staging Area
Orange Area: Material Storage
Dark Green Area: Field Office
White Area: Portable Toilets
Blue Area: Security Booth
Pink Area: Wing Expansion
03
Guaranteed Maximum Price Estimate
$36,594,888 GMP
CM Fee
2% (included)
Contingency
5% (included)
GMP Breakdown
03 Concrete $2,279,861.55
04 Masonry $2,115,184.55
05 Metals $1,873,658.29
08 Openings $1,906,593.69
09 Finishes $2,074,930.17
GMP Breakdown
10 Specialties $724,578.79
11 Equipment $1,002,699.94
12 Furnishings $845,341.92
22 Plumbing $1,741,916.69
23 HVAC $3,011,759.32
17 Electrical $2,814,146.92
31 Earthwork $3,333,794.34
Change Order
Change Order #1: approx. $110,000
Change Order #2: approx. $8,000
SCHEDULE
04
Schedule
Renovation of the Chapel Expansion of the Arts Wing
Key items Key items
RENOVATION
OF CHAPEL
7/16/24
NOTICE TO SUBSTANTIAL
PRECONSTRUCTION
PROCEED COMPLETION
12/22/25
PERMITS
Building Permits Concrete & Steel
-Site plan Approval -Crane and Rigging Permits
-Environmental Impact Assessment -Retaining Wall Permits
-Excavation Permit -Concrete Cutting or Coring Permits
-Land Disturbance or Erosion Control -Crane and Rigging Permits
-Stormwater Management -Highway and Transportation Permits
-Historic Preservation Review -Specialty Inspections
-Site Plan Approval -Welding and Fabrication Permits
Boilers Elevators
Air separators
Change Order
● While removing old flooring in the chapel, discovered basketball flooring that needs to
be removed.
● Expected delay of 15 work days in the schedule
● However, due to not being a critical task, no delay for substantial completion date
VALUE ENGINEERING AND LEED
05
OUR LEED SERVICES
Project as it is:
LEED Certification, approx. 45 credits
ASSESSMENTS:
● Environmental Site Assessment
(ESA)
○ Soil acidity
○ Possible pollutants
○ Type of soil for foundation
○ Dangerous materials in
paint
■ Asbestos
● Cost:
○ Phase 1 → $2,000 - $5,000
○ the research, site visits,
and required reporting.
○ Contamination issues,
foundation issues, delays.
CONSTRUCTION
POLLUTION
PREVENTION
● Water sprays:
INDOOR
● Low flow toilets
○ 1.28 gpf or less
● Automatic faucets
○ 0.5-1.5 gpm
OPEN SPACES
LAWN & GREEN ROOF
- 1000F - 1” - - $239
Wheeled Sprinkler