Quality Checklist For Site Works: 20 Ceiling Task
Quality Checklist For Site Works: 20 Ceiling Task
20 CEILING TASK
1ST & 2ND FLOOR
EXTRIOR
CL : 20-A
Sl.No. Description YES NO NA
x Is format CL:15-A & CL:19 for Plastering & MEP works complied with?
1.0 INITIAL CHECKS:
1.1 Drawings & Spec. Details Finalised
1.2 Engineer Approval
1.3 Material Approvals as per Sample
1.4 Method Statement Approved
1.5 Area Clearance from Civil & Services
1.6 Underdeck Insulation complete
1.7 Availability of Materials [Daily Req.]
1.8 All Service lines laid and approved
2.0 GRID ALIGNMENT APPROVALS:
2.1 IS CLEARANCE FOR SERVICES FIXTURE FIXING ALL APPROVED ?
2.2 Line, level & Alignment of Spaces Grids
2.3 Pressure test for Service plumbing lines Complete
2.4 Cleaning/Dusting of Flooring is done
2.5 Fixing of All Service Fixtures Complete
3.0 INSTALLATION CHECKS:
3.1 Check the Frame & Boards Brand Name, Thickness Details ?
3.2 Check the Frame can be Fixed over Plastered / RCC Surface ?
3.3 Check the Lintel level of Door & Plaster Soffit level of Window lintel ?
3.4 Check the Ceiling / Shaft is Clean & Pipes are Painted ?
3.5 Check the Clearance from Sanitary Department ?
3.6 Check the Clearance from Electrical Department ?
3.7 Check the Clearance from Fire Fighting Department ?
3.8 Check the Clearance from Waterproofing Department ?
3.9 Check the Hangers and Horizontal Members are Placed as per Drawing and Specifications ?
3.10 Check the Boards used are of approved Brand & as per Specification ?
3.11 Check the Position of the Trap Door / Openings ?
3.12 Check the Screws to be Embedded inside the Board Thickness ?
3.13 Check the Line, Level and the Right Angles of the Boards Fixed ?
3.14 Check the Jointing of the Gypsum Board Junctions ?
3.15 Check the type of falseceiling as per specification.
3.16 If it is Grid type, Check whether grids are marked as per drawing so as to locate the service points.
3.17 Check whether the frame work and hanger rods are as per specification.
3.18 Before fixing/ laying of boards check all service works such as electrical, AC ducting, fire alarm, sprinkler, speakers, smoke
detector,
Check forheat
any detector,
cornices, etc,
trapWhether cutout/as
door provision opening
per theprovided.
drawing.
3.19
3.20 Check for painting of ceiling ( If it is board) - is it as per specification.
Comments: