Types of Form Works
Types of Form Works
Introduction to
Formwork
4
1. Introduction:
• They mould the concrete to the desired size & shape & control its alignment &
position.
• Formwork also carries the weight of freshly placed concrete and itself besides live
load due to materials, equipment and workmen
5
1.3 Importance of Formwork:
•In the Construction of any building concreting and reinforcement binding is the main
activity after that to hold them in their position Formwork is most important
• Formwork constitutes 20% of the standard cost and 60% of the time in concrete
construction.
• Thus a good formwork system helps in achieving speed, quality, economy and safety
in reinforced concrete construction
6
1.4 Requirement of Formwork:
• To obtain the required shape, size, finish, position and alignment of concrete
members.
Plywood (Fig-1.1)
Bamboo (Fig-1.2)
Steel (Fig-1.3)
Aluminium (Fig-1.4)
Plastic (Fig-1.5)
8
Plywood :
Mivan Formwork
System
14
15
The technology has been used extensively in other countries such as Europe, Gulf
Countries, Asia and all other parts of the world.
MIVAN technology is suitable for constructing large number of houses within short
time using room size forms to construct walls and slabs in one continuous pour on
concrete.
Early removal of forms can be achieved by hot air curing / curing compounds.
All the activities are planned in assembly line manner and hence result into more
accurate, well – controlled and high quality production at optimum cost and in shortest
possible time.
16
2.3 Mivan Formwork Assembly:
MIVAN aims in using modern construction techniques and equipment in all its projects.
On leaving the MIVAN factory all panels are clearly labeled to ensure that they are
easily identifiable on site and can be smoothly fitted together using the formwork
modulation drawings. All formwork begins at a corner and proceeds from there.
b) Level Surveys – Level checking are made to maintain horizontal level check.
20
3.3 POST – CONCRETE ACTIVITIES:
A) CLEANING:
• All components should be cleaned with scrapers and wire brushes as soon as they are
struck. Wire brush is to be used on side rails only.
B) TRANSPORTING:
• The heaviest and the longest, which is a full height of wall panel, can be carried up
the nearest stairway. Passes through void areas.
C) STRIKING:
• Once cleaned and transported to the next point of erection, panels should be stacked at
right place and in right order.
Comparison of Mivan
Formwork
Components with
Actual Sight Photos
25
4.0 Comparison of Mivan Formwork Components with Actual Sight
Photos:
1) Beam Side Panel:- It forms the side of the beams. It is a rectangular structure and is
cut according to the size of the beam
29
4.2 Deck Component:
1) Deck Panel:- It forms the horizontal surface for casting of slabs. It is built for proper
safety of workers.
1) Internal Soffit Corner:- It forms the vertical internal corner between the walls and
the beams, slabs, and the horizontal internal cornice between the walls and the beam
slabs and the beam soffit.
36
2) External Soffit Corner:- It forms the external corner between the components
38
FIG- 4.3.3: EXTENAL CORNER
4) Internal Corner: - It connects two pieces of vertical formwork pieces at
their exterior
39
FIG-4.3.4: INTERNAL CORNERS
4.4 Wall Components:
1) Wall Panel: It forms the face of the wall. It is an Aluminium sheet properly cut to fit
the exact size of the wall
Fig-4.4.3: KICKER 42
4) Stub Pin: It helps in joining two wall panels. It helps in joining two joints
Design,
Specification, &
Work Cycle
44
5.0 Design, Specification, and Speed of Construction (Work Cycle):
i) Conventional RC columns, beams, and slab construction (RC moment resisting framed
structure)
5.2 Specifications:
1) Aluminium thickness: 0.06 0.08 0.10 0.12 0.15 0.18 0.21 0.25 0.30 0.35 0.40 0.45
0.50mm
3) Standard size:-1220x2440x3mm
-1220x2440x4mm
-1220x2440x5mm
45
5.3 Work cycle:
Day 1: The first activity consists of erection of vertical reinforcement bars and one side
of the vertical formwork for the entire floor or a part of one floor.
Day 2: The second activity involves erection of the second side of the vertical
formwork and formwork for the floor
Day 3: Fixing reinforcement bars for floor slabs and casting of walls and slabs.
Day 4: Removal of vertical form work panels after 24hours, leaving the props in place
for 7 days.
46
5.4 Quality Advantage of Mivan:
The high tolerance of the finish means that no further plastering is required.
The MIVAN formwork is specifically designed to allow rapid construction of all types
of architectural layouts.
1) Cost effective.
48
5.6 Limitation of Mivan Formwork:
1) Because of small sizes finishing lines are seen on the concrete surfaces.
49
Chapter – 6
Conventional
( Traditional )
Formwork system
50
6.0 Conventional ( Traditional ) Formwork system:
• Foundations
• Wall
• Column
• Stairs
51
6.1.1 Formwork for
foundation
Wall foundations
It consists of
- Plywood Sheeting
- Struts
Column Foundations
It consists of
- Side Supports
- Side Planks Side Planks
Cleat
- Cleats Side Support 52
6.1.2 Formwork for Wall:
It consists of
•Timber sheeting
•Vertical posts
•Horizontal members
•Wedges
•Two end & two side planks are joined by the yokes and bolts.
• Yokes are the horizontal member which gives support to the side & end planks.
• Yokes are connected to each other by the help of nut & bolts.
54
Fig-6.1.6 Formwork for Column
6.1.4 Formwork for Slabs & beams
It consists of
• Sole plates
• Wedges
• Props
• Head tree
• Planks
• Batten
• Ledgers
55
Fig-6.1.10 Formwork for Slab & Beam 56
6.1.5 Formwork for Stairs
It consists of
•Vertical & inclined posts
•Inclined members
•Wooden Planks or sheeting
•Stringer
•Riser Planks
57
6.2 Removal of formwork
1.Type of Cement
1.Rich ratio concrete gain strength earlier as compared to weak ratio concrete.
3.Weather condition
58
Fig- 6.2.1 Removal of Formwork 59
6.3 Time of Removal of formwork
60
Work on which would be carried out in next semester :
Applications and comparison among different types of formwork system with its merits
and demerits of one or two of following formwork system….
61
COFFOR INNOVATIVE
STAY-IN-PLACE
FORMWORK
COFFOR Construction
Technology Pvt. Ltd 62
About COFFOR Technology
COFFOR is a patented structural stay in place formwork
system to build load bearing monolithic structures.
About COFFOR Technology
It is composed of 2 filtering grids made of rib lathe
reinforced by vertical stiffeners.
COFFOR Construction
Technology Pvt. Ltd 67
Part – 3: Connector
– They connects C profile & Rebar.
– They are made up of 1.6 thick CRCA plate.
COFFOR Construction
Technology Pvt. Ltd 68
Part – 4: Rib Mesh
– Rib meshes are filtering grids.
– They are made up of 0.42 mm thick GP
sheets
COFFOR Construction
Technology Pvt. Ltd 69
T Pane T A B W H
l (m (m (m (m (mm
T Type m) m) m) m) )
A
C 10 100 200 100,
200 300,
500, 0.5 m
C 16 160 200 100, 700, To
H 200 900 5 m
,
C 20 200 200 100,
1100
200
B C 25 250 200 100,
200
COFFOR Construction
Technology Pvt. Ltd
COFFOR Construction
Technology Pvt. Ltd 71
Installation of COFFOR Panels
Individual Bungalow
Strip Footing for Coffor Panel
Installation
COFFOR Construction
Technology Pvt. Ltd 73
Individual Bungalow
Support provided to the panels
Structure Post-Concreting
COFFOR Construction
Technology Pvt. Ltd 74
Individual Bungalow
Installation of wall panels up to
slab level
COFFOR Construction
Technology Pvt. Ltd 75
Individual Bungalow
Support & Concrete pouring of
walls & slab at one go
Monolithic Structure
COFFOR Construction
Technology Pvt. Ltd 76
Applications of COFFOR
Individual Bungalow
Plastering is required
COFFOR Construction
Technology Pvt. Ltd 78
P+4 Residential Apartment
COFFOR Construction
Technology Pvt. Ltd 79
P+4 Residential Apartment
COFFOR Construction
Technology Pvt. Ltd 80
P + 4 Apartment
www.cofforindia.com 81
Storm Water Drainage
www.cofforindia.com 82
Radius Architectural Designs
Various architectural designs can
be easily done with Coffor
COFFOR Construction
Technology Pvt. Ltd 83
Radius Architectural Designs
Post concrete pouring
COFFOR Construction
Technology Pvt. Ltd 84
Utility Chambers
COFFOR Construction
Technology Pvt. Ltd 85
Utility Chambers
86
Shaped Wall
Various shapes/designs are
possible with Coffor for
door/windows openings
COFFOR Construction
Technology Pvt. Ltd 87
Compound Wall
Panel Installation in Nasik,
Maharashtra
COFFOR Construction
Technology Pvt. Ltd 88
Inclined Roof
COFFOR Construction
Technology Pvt. Ltd 89
Slabs & Lintels
COFFOR Construction
Technology Pvt. Ltd 90
Swimming Pool
COFFOR Construction
Technology Pvt. Ltd 91
Water Purification Tank
COFFOR Construction
Technology Pvt. Ltd 92
Water Purification Tank
COFFOR Construction
Technology Pvt. Ltd 93
Water Tanks
COFFOR Construction
Technology Pvt. Ltd 94
•Less Volume Required
•No Shuttering Required
•No Crane Required
•Minimum Reinforcement
•Less allied accessories required
•Multiple Creative possibilities
•Semi-skilled labour’s required
•Less no of labour’s required
•No honey comb in concrete
•Easy installation of Electric and plumbing lines
•Rapid Concrete Shrinkage
•Over all reduction in construction time
•Higher Seismic Resistance
•All types of Finishing Possible
L & T DOKA FORMWORK
STUB COLUMN
SIDE SUPPORT,
PROP
FOUNDATION FORMWORK
1. FLOOR FORM 2. FORM CLIP
LAPPING PLATE 5
SIZES
1200,900,600
6. STEEL WALER 7. WALER CONNECTOR
6
9. HEAD ADOPTER ASSEMBLY
9
8. CT PROP
TYPES
CT 250, CT 300, CT 340, CT 410
10
COLUMN / WALL FORMWORK
3. TOP SCAFFOLD 4. CT PROP
1. H BEAM (H-16 / H – 20) 2. STEEL WALER BRACKET 60 Types
CT 250, CT 300, CT 340, CT 410,
3
3
1 1 6
4 5
5. FLANGE CLAW
ASSEMBLY
2 6. LIFTING BRACKET
9
7
10
7.SPLICE PLATE 8.ANGLE PLATE
U
COLUMN
11
ANCHOR PLATE
WING NUT
12
TIE ROD TUBE (PVC)
CT PROP 300
ALIGNMENT
PROP
SLAB FORMWORK
SECONDARY
BEAM
PRIMARY BEAM
BEAM FORMING
HEAD
CT PROP
FLEX SYSTEM FOR RCC SLAB (Upto 4.5m Height)
FOUR WAY
HEAD
FLEX SYSTEM
3
1
AVAILABILITY
600,800, 1000,1200
BEAM SIDE SUPPORTS
FLEX TABLE SYSTEM
18 MM PLY
WOOD
STAIRCASE FORMWORK
WORKING PLATFORM AT HEIGHT
HEAVY DUTY
TOWERS
4
2 3
4. U-HEAD
3. FOOT PLATE
7.SHORT PROP
8.LTS-WHEEL B
IT IS USED IN SLAB AND BEAM
FORMWORK FOR TRANSFERRING TO BE FIXED WITH 8
THE SLAB LOAD TO THE BEARING
BOTTOM FRAME OF STAIR
TOWERS THROUGH STANDARD
TOWER / HDT TO SHIFT ONE
WALERS
PLACE TO ANOTHER PLACE
STAIR TOWER / ACCESS SCAFFOLD
STAIR TOWER /
ACCESS
SCAFFOLD
ADVANTAGES
● HIGH LABOR PRODUCTIVITY (APPROX 8 TO 10 SQ.M
PER MAN-DAY)
1.Plywood as well as in
2. Steel
Basic Components of Peri
Formwork
Cup-lock
Steel
Tension
Rod
Tripod
Tripod is the main
basic component of
the system.
Secondary
Girder
Main
Girder
Plywood
Sheet
supported on
Secondary
Beam which
is supported
on Primary
Beam which
rests on Four-
head CT
Props
VT-20
Girder
Plates
supported
on CT
Props
Two VT-
20 Girders
are joined
through
the Steel
Rod and
Threaded
anchor
plate
GT-24 Girder
Main Props
Intermediate Props
Photo of
VT-20
Girders
from the
Top Slab
Level
Peri Sky Deck
Alluminium Forms
Cover strip
(Required when
Drop head is
used)
Wall Formwork
Wall
Panel
Arrangement
of Wall
Panels Before
Concreting
Two
Adjacent
Wall
Panel
Two
Panels
are
joined
through
Cup-lock
Two
Parallel
wall
panels are
joined
through
the Steel
Tension
Rod
Steel
Waller to
Join Two
Column
Panels
Joining of
four panels
through
Cup - lock,
Steel Rod,
and Steel
Waller
Column Formwork
Column
Panel
Supports
Beam Formwork
Beam Head
Cross Head
CT Prop
Locker
Tripod
Stacking of different
types of forms
on Site
Finishing Work
Some Site
Photographs
Comparison of different kinds
of Formworks used with in
Indian Construction Industry
207
In comparison we have given the
score as per below colour code
BEST
GOOD
MEDIUM
Factors Affecting Conventional Mivan Coffor Peri Doka
Initial Cost
Weight
Re-use
Maintenance cost
Scrap Value
Construction speed
Volume of Required
material
Seismic Resistance
Formwork Material
Pilferage
Formwork Material
Shrinkage
Possibility of Damage
Finishing
Reinforcement
Requirement
Monolithic Structure
Allied Accessories
No of post concrete
procedures