System Installation Guidelines - Prime
System Installation Guidelines - Prime
1 Introduction
This guideline provides the minimum requirements when installing a Component based Solar home
system where array size ranges from 100 Wp- 2 kWp. All systems to be installed shall be designed in
accordance with the System Design Guidelines.
• d.c. bus systems that consist of solar array(s) connected to the batteries by solar controller(s)
and battery inverter(s);
• a.c. bus systems comprising solar array(s) connected to the a.c. side of grid forming battery
inverter(s) (a.c bus interactive inverter) by PV inverter(s) (grid interactive inverter);
• PV systems comprising both a.c. and d.c. bus configuration.
The array requirements are generally based on the requirements of IEC 62548: Photovoltaic (PV Arrays-
Design Requirements.
Figure 1 shows the configuration of a system that provides d.c. power only. These systems typically
shall have an array range less than 1 kWp. Most solar installations installed on rural and urban town
residences (poor grid) use this basic design.
Systems that include an inverter providing a.c. power to end-user can be configured as either:
1
Figure 2: d.c. bus system powering d.c. and a.c. loads
Some systems can be a combination of a.c. bus and d.c. bus systems where part of the array is
connected by d.c. through a solar controller to the battery and part of the array is connected directly
to the a.c. load side via a PV inverter.
2 PV array installation
2.1 General
• Modules that are electrically in the same string shall all be in the same orientation.
• Even for latitudes less than 10°, a minimum tilt of 10° is recommended to take advantage of
self-cleaning when it rains. Arrays mounted with a tilt less than 10° may require additional
maintenance [cleaning] and this should be included in the recommended maintenance
schedule.
• None of the modules connected in a series string should come under shadow during sunny
hours that is from 90 minutes after sunrise and 90 minutes before sunset.
• on an array frame that is tilted to fix the array at a preferred angle (usually used for flat roofs
or for ground mounting) or
• “flat” on the roof so it is parallel to the slope of the roof but raised off the roof, or
• on a pole mounted system separate from the building, or
• ground mounted if it is a large system.
Though the maximum output would be obtained using an array frame that is tilted to fix the array at
the optimum angle (30-34 degrees for Pakistan), for practical reasons solar arrays are often mounted
parallel to the roof in summers.
2
For best year-round performance, a fixed PV array typically should be mounted facing true south in
Punjab and Sindh. The array should be tilted at a minimum of 30-34 degrees depending upon the
latitude.
3 Batteries installation
Batteries are a dangerous component in a PV system due to weight, explosive gases and potentially
high fault currents. Their performance, life and reliability are affected by their location and climatic
conditions. Correct placement and protection are paramount to minimising risk and maximising
performance.
• The battery/ batteries must be installed in a dedicated enclosure. These enclosures can be
boxes as shown in figures 10 and 11 or a on wall enclosure as shown in figure 12.
• The enclosure selected must ensure that mechanical protection is guaranteed and limits
unauthorised access to the batteries.
• The enclosure shall shelter the battery terminals to limit access and prevent accident short
circuits. As well, appropriate covers on battery terminals are recommended particularly for
open enclosures (as shown in Figure 12)
• Sufficient space should be available within the enclosure to allow for ease of battery
installation and maintenance.
• No uninsulated metal objects --- that could fall across battery terminals and cause a short
circuit --- should be kept nearby.
• Explosive and/or corrosive gas-emitting battery systems: should not be located within 500 mm)
horizontally of any other equipment from 100 mm below the battery terminals (Figure 9),
except where there is a solid separation barrier
• No electrical equipment shall be mounted above explosive and/or corrosive gas emitting
batteries.
3
• No metal devices shall be installed above the batteries or the battery enclosures. These could
fall onto the batteries when the enclosure is open.
• The location where the batteries are installed should be dry.
• Batteries must be raised off the ground or concrete floor.
• The enclosure should not be located in direct sunlight and should be in a location that keeps
the batteries as cool as possible.
• For valve regulated lead acid batteries, if possible, the outlet ventilation should be to the
outside of the building in which the battery system is located. However, if this is not possible
the room in which the battery enclosure is installed should be large enough to allow any
emitted gases to easily disperse.
• Best practice is to provide the input ventilation vents on the enclosure wall below the level of
battery and the output vents on an outside wall on the opposite side of the batteries as high
as possible in the enclosure to prevent hydrogen build up.
• Li-ion battery types (LFP and NMC) are permissible to be included in the system. None other
type of Lithium-ion battery is allowed to be packaged with CB-SHS.
5 PV Inverter Installation
The PV inverter shall be installed as to the manufacturer`s instructions.
• The PV inverter shall be installed in a location that is appropriate for the IP rating of the PV
inverter. Where this is not possible then the PV inverter/s should be in an appropriate
weatherproof enclosure that has adequate ventilation.
• PV inverters are not to be installed in direct sunlight.
• The PV inverter shall be installed with recommended clearances around the PV inverter as
specified by the manufacturer.
• PV inverters should be installed in dust free locations;
• PV inverters can be heavy; it is important that the surface on which the PV inverters will be
mounted is appropriately weight-bearing.
• The PV inverter heat sink shall be clear of any obstacles that may interfere with cooling of the
PV inverter.
• Cables connected to the inverter shall be mechanically secured in such a manner that they
cannot be inadvertently unplugged from the inverter. This can be achieved by:
4
o The use of an inverter which has the cable connection area of inverter covered by a
removable enclosure/cover which protects the supported cables so that there are no
exposed, unsupported cable loops.
o The use of conduit and secure wall fixings:
• Where the inverter requires d.c. connectors to be used, a maximum allowable distance of no
more than 200mm) of unprotected d.c. cable shall be permitted between connectors and
conduit provided the location is not subject to mechanical damage.
• Where the inverter is exposed to the weather there shall be no open ends of conduit. If a cable
is required to exit from a conduit, an appropriate cable gland shall be installed on the end of
the conduit to ensure the IP rating is maintained.
For a.c. bus systems or d.c. bus systems using MPPTs, a dangerous situation is only likely to occur at:
To prevent the possibility of an installer coming in contact with live wires it is recommended practice
that one of the interconnect cables of each string (as shown in Figure 13) is left disconnected until all
the wiring is complete between the array and the inverter. Only after all switch-disconnectors and
other hard wired connections are completed should the interconnecting cable of the array be connected.
The installer shall ensure that all connectors used are waterproof and connected securely to avoid the
possibility of a loose connection. Only connectors of the same type from the same manufacturer are
allowed to be mated at a connection point.
When mounted on a roof, the solar module interconnect cables must be supported clear of the roof
surface to prevent debris build up or damage to insulation.
Note: All national and regional rules and regulations with respect to protection of persons be followed
in particular for installation of AC circuits.
7 PV array wiring
5
• Have a temperature rating appropriate to the application.
• If exposed to salt environments, used tinned copper, multi-stranded conductors to reduce
degradation of the cable over time due to corrosion.
• In all systems operating at voltages above DVC-A, cables shall be selected so as to minimise the
risk of
• earth faults and short-circuits. This is commonly achieved using reinforced or double-insulated
cables,
• particularly for cables that are exposed or laid in a metallic tray or metal conduit.
• Cables shall not lie on roofs or the ground without an enclosure or conduit.
• All external wiring must be protected from UV either by using UV rated cables or installing the
cables in enclosures/conduit.
• All conduits exposed to direct sunlight shall be suitably UV rated.
• The installer shall ensure that all cable connectors used are connected securely to avoid the
possibility of a loose connection.
• Keep bending radius of cables more than 40mm or as recommended by module manufacturer.
• The current carrying capacity of the cable between the controller and battery shall be capable
of carrying the maximum charge current from the array.
• The current-carrying capacity of the cable between the battery and solar controller shall be
based on the d.c. current rating of the associated over-current protection.
• The d.c. cables between the solar controller and the battery bank can be single insulated if
the battery bank is Extra Low Voltage (ELV).
• Cables and conduits shall be installed so that they are adequately supported.
6
9 Installation of Cable Between Battery and Battery Inverter
• For systems using PWM solar controllers, the cable shall have a voltage rating greater than the
battery voltage when being charged.
• For systems using a separated MPPT controller, the cable shall have a voltage rating greater
than the battery voltage when being charged.
• For systems using non-separated MPPT the cable shall have a voltage rating greater than the
maximum voltage of the array.
If the PV array has a rated output voltage greater than 120 V (DVC-C) and the solar controller is a
nonseparated MPPT unit, the d.c. cables between the battery and the battery inverters shall be double.
insulated.
8 Voltage drop
• The voltage drop between the PV array – charge controller and the battery bank should never
exceed 5%
• The voltage drop between the battery bank and any d.c. load should never exceed 5%
• The voltage drop between the PV array and PV inverter should never exceed 3% (a.c. bus)
11 Commissioning
The commissioning sheets provided with these guidelines (Appendix 1) should be completed by the
installer. A completed copy shall be provided to the customer as part of the system documentation and
a copy retained by the installer that has been initialled by the customer showing it to be a true copy of
the commissioning sheets provided to the customer.
7
11 Documentation
All complex systems require a user manual for the customer. The documentation for system installation
that shall be provided includes:
• List of equipment supplied with each item’s model, description and serial number.
• List of action to be taken in the event of any issues.
• Contact details of Focal person to be contacted for aftersales services or any other issues.
• Shutdown and isolation procedures for emergencies and for maintenance
• Maintenance procedures and timetable
• Commissioning sheet and installation checklist
• Warranty information
• System performance estimate including completed load assessment forms.
• Recommended maintenance procedures
• Equipment manufacturer’s documentation and handbooks for all equipment supplied.
8
Appendix 1: Installation and Commissioning Sample
Installer’s name
Installer’s signature
Customer’s name
MFI’s name
Equipment Data
PV module manufacturer
Number of Modules
Battery manufacturer
Battery model:
Battery Voltage V
Battery Capacity Ah
current rating A
9
Solar controller voltage ratings V
Inverter manufacturer
Module No 1: Voc V
Module No 2: Isc A
Module No 2: Voc V
10
Turn System On - including d.c. loads
Array current A
11