CMA - Labour Answer Key
CMA - Labour Answer Key
It tends to vary with volume of It may not vary with the level of
3. Relation to
production, and has a positive output/ production.
Output
relationship with level of output.
Page 1 of 10
(g) Overhead Distribution: Production OH is absorbed over jobs or products using
Labour Hour Rate as the basis.
(a) Time taken by workers to reach the Production (a) Machine break-downs, power
Department from the Factory Main Gate. failure, equipment non-availability,
etc.
(b) Time lost between the finish of one job and starting (b) Non-availability of raw materials
of next job. and tools.
(c) Time spent to overcome fatigue and tiredness. (c) Waiting time for jobs due to
defective planning.
(d) Time spent on workers' personal needs like taking
lunch, tea, etc.
(e) Time required to set up machinery, receipt of (d) Strikes, Lock-outs, poor
materials, initial processing of materials, etc. supervision, fire, floods, accidents,
etc.
It refers to the idle time inherent in every It refers to the idle time over and
1. Meaning work situation. It is estimated in advance. above normal idle time. Abnormal =
Actual Less Normal.
4. Focus In the long run, normal idle time may be Controllable Idle time should be
Page 2 of 10
reduced through improved technologies, eliminated through proper
methods & procedures. managerial action.
2. At Customer's desire, e.g. immediate Charged to the Job directly. Such amount will
delivery, etc. be suitably recovered from the customer by
charging at a higher rate.
4. Due to fault of a particular department, e.g. Charged to the department in default, in order
non-availability of materials during normal to fix responsibility and prevent recurrence.
time.
5. Due to abnormal conditions, e.g. strike, etc. Charged to Costing Profit and Loss Account as
Loss.
6.
8000 + 9600
1. Average Labour Force= L = = Separation S 600
2 = L = 8800 = 6.82%
8,800 workers.
Page 3 of 10
7.
S 40 40
1. Separation Method Rate = L . = L
- = 5% (given). So, L = 5% = 800.
R 𝑅
2. Replacement Method Rate = = = 8%. So, R = 800 × 8% = 64.
L 800
S+ R + N 40+ 64 + N
3. Flux Method Rate = = = 13%. On solving, N = 0.
L 800
Let the Number of Workers at the beginning be X and at the end be Y. So, Average
X+Y
Labour Force (L) = = 800.
2
8.
1. Computation of Time Saved
Time Saved 32 44
2. Loss due to incorrect rate selection i.e. Excess of Rs.55 - 50 = Rs. 5 per hour
(b) Bonus" (Halsey Scheme) (50% × Time (50% × 32 Hrs. × (50 % × 44 Hrs. × 190.00
saved × 5) 5) =
Page 4 of 10
TimeTaken 28 40
(d) Bonus (Rowan Scheme) ( × 60
(×32×5) = 84
(× 44 × 5) =
Time Allowed
Time Saved × Excess Rate) 74.67 104.76 179.43
Halsey = (Hours worked × Rate p.h) + (50% × Time Saved × Rate p.h.) = Rs. 1,100
= (40 hrs × Rs. 25) + (40% × 10 hrs × Rs. 25) = Rs. 1,000 + Rs.
100
Actual Hours
= (Hours worked × Rate p.h) + ( × Time Saved ×
Standard Hours
Rate p.h.)
Note:
• Alternatively, the actual time can be taken as 5 day’s × 9 hours = 45 hours assuming
the worker is paid for the whole day although the work is finished at 12 Noon.
• In this question, Halsey Bonus is taken at 40% as per the question, and not 50% as
per the general formula.
10. Since Standard Time = 20 Hours and Time Taken = 13 hours, Time saved = 7 hours.
Page 5 of 10
3. Total Wages = (1 + 2) 825.00 877.50
(a) Present Standard Hours required to produce 19,200 units (19,200 units - 3,200 hours
r 6 units per hour)
(b) Normal Available Hours per week (60 employees × 40 hours) 2,400 hours
(c) Present Overtime work (paid at normal + 50% rate) [a - b] 800 hours
(d) Standard Hours required after introduction of Bonus Scheme (19,200 2,400 hours
units ÷ 8 units per hour)
Hours worked × Rate 50% × Time Saved × Rate p.h = 50% × 800 × 10 Rs.
Halsey p.h. = 2,400 × 10 = Rs. = Rs. 4,000 28,000
24,000
Note: Wage Rate per hour = Rs. 400 for 40 hours per week = Rs. 10 per hour.
Present Total Wages = (2,400 hours × Rs. 10 ph) + (Overtime 800 hours × Rs. 15 ph) =
Rs. 36,000
3. Computation of Profit under present and proposed Halsey & Rowan Schemes
Page 6 of 10
Particulars Present Halsey Rowan
(d) Variable OH (Actual Hrs × 3,200 × 0.5 = 2,400 × 0.5 = 2,400 × 0.5 =
Rs. 0.50 ph) 1,600 1,200 1,200
13. 1. let the Wage Rates be Rs. R per hour for both workers. The wages can be determined
as under -
Worker Plan Std hrs Actual hrs Time Basic Bonus Wages
Saved
Page 7 of 10
Particulars A B Particulars A B
Add: POH at 5×30 = 150 5×40 = 200 Add: POH at Rs. 5 150 200
Rs. 5 ph
From the above, we have 2 equations Alternative Method: It is given that Materials Cost
as under - is the same. Hence, difference in Prime Cost is due
to difference in wages only. So, difference in Prime
Equation 1 M + 42 R = 3,340 Cost (Factory Cost less Factory OH) = Rs. 3,400 -
Rs. 3,340 = Rs. 60 is due to difference in wages of
Equation 2 M + 45 R = 3.400 45R - 42R = 3R. Solving the equation 3R = 60, we
get, R = 20 per hour)
On subtraction, we αet - 3 R = - 60
14.
1. Computation of Time Saved under Rowan Scheme
Worker A B C
(21 units × 12 min) + (36 units × (25 units × 30 min) = (60 units × 12 min) +
(a) 18 min) + (46 units × 30 min) = 750 min = 12.5 (135 units × 18 min) =
Standard 2,280 min hours 3,150 min = 52.50
Time hours
= 38 hours
System Computation A B C
1. Time Rate = Hours worked × Rate 38×60= Rs. 40x50= Rs. 34x72= Rs.
Wages p.h. 2,280 2,000 2,448
Page 8 of 10
2. Piece Rate
Wages
(a) Total Total of (i) to (iii) above Rs. 2,280 Rs. 750 Rs. 3,150
Piece Wages
(b) 50% of = 50% of Time basis Rs. 1,140 Rs. 1,000 Rs. 1,224
Basic (1) Wages
(c) 75% of = 75% of Time basis Rs. 1,710 Rs. 1,500 Rs. 1,836
Basic (1) Wages
(d) Payment Either (a), or (c) if a < b Rs. 2,280 Rs. 1,500 Rs. 3,150
3. Rowan
System
(i) Basic = Hours worked × Rate p.h. 38x60= Rs. 40x50= Rs. 34x72= Rs.
Wages 2,280 2,000 2,448
(a) Total = Basic + Bonus Rs. 2,280 Rs. 2,000 Rs. 3,311
Wages
15.
1. Computation of Wage Rate per hour
Daily Wages 120
(a) Payment Rate per hour = Total Hours per day = 8
= Rs. 15.00 per hour.
Daily Wages 120
(b) Costing Rate per hour = Effective Hours per day = 7
= Rs. 17.14 per hour.
Note: Effective Working Hours per day = 8 hours less 1 hour (Normal Idle Time) = 7 hours.
2. Treatment of Wages Cost and Normal Idle Time
(a) Wages paid to Ram
Page 9 of 10
Alternative 1: Treated as Direct Alternative 2: Treated as POH
Wages
Total Daily Wages = Rs. 15 × 8 Total Daily Wages = Rs. 15 × 8 hours = Rs.
hours = Rs. 120 120
(b) Wages paid to Raju: Since Raju is not directly engaged in production, Cost of
Indirect Labour is treated as Production OH. It is not generally classified into Normal Idle
Time and Abnormal Idle Time, since these performance standards cannot be laid down
for Indirect Workers.
(c) Wages paid to Dev:
Total Daily Wages = Rs. 15 × 8 Total Daily Wages = Rs. 15 × 8 hours = Rs.
hours = Rs. 120 120
Productive Time Idle Time 2 hours (b/f) Productive Time = 6 Idle Time 2 hours (b/f)
= 6 hours (given) hours (given) Cost =
Cost = 6 hours × 6 hours × Rs. 15 =
Rs. 17.14 = Rs. Rs.90
102.84
Treated as Direct
Treated as Direct Norma Abnormal 1 Labour Cost Normal 1 f Abnormal 1
Labour Cost hr×Rs. 17.14 hr×Rs. 15 hr×Rs. 15
Nil
Taken to P&L Treated as Taken to
A/c POH P&L A/c
Note: Cost of Abnormal Idle Time is charged to Costing P & L Account.
************************************************************************************************
Page 10 of 10