Feasibility Study On The Sihanoukville Combined Cycle Power Development Project 180 MW 4
Feasibility Study On The Sihanoukville Combined Cycle Power Development Project 180 MW 4
Fuels for thermal power plants are generally heavy fuel oil, diesel oil, naphtha, natural
gas, liquefied natural gas and coal.
For this project, heavy fuel oil and diesel oil are suitable at present and natural gas
will be added in near future as described below.
Among the imported fuels, diesel and heavy fuel oils can be used as fuels for
power plants. Naphtha, which IPP2 had considered as the main fuel, is available
in Singapore (note : IPP2 contract has been suspended). However, it has no ad-
vantage compared to diesel oil because of higher price and more difficult han-
dling. As of December 1999, the prices of fuels are as follows; Naphtha : 5.0 $/
MMBTU, Diesel oil : 4.6 $/MMBTU, Heavy fuel oil : 3.5 $/MMBTU.
Cambodia imports mainly those fuels from Singapore, Thailand and Vietnam,
and there are several oil companies to deal in petroleum products, such as So-
kimex, SHELL, CALTEX, TELA, CUPL, etc. in Cambodia.
Imported petroleum products are transported by ship, and unloaded at Sokimex Oil
Terminal that is located near the site for the Project, or transported by barge from
3-1
Vietnam to Phnom Penh through the Mekong River and unloaded there. The un-
loaded petroleum products are transported by tank car to each consumer such as
power stations. Most of the tank cars have a capacity of 12 or 16 kl, and Sokimex
has 5 tank cars with a capacity of 38 kl. Transportation of fuel oils by rail is also
available because a siding of the railroad between Sihanoukville and Phnom Penh
is routed through in Sokimex Oil Terminal. However, almost all of the rail cars re-
quired repairing due to superannuation. There are 34 rail cars with a capacity of 72
kl.
Sokimex Oil Terminal handles gasoline, diesel oil and heavy fuel oil, and the
jetty of Sokimex Oil Terminal is used to unload petroleum products not only for
Sokimex but also for SHELL, CALTEX and TELA. Sokimex Oil Terminal has
never handled naphtha but Sokimex has an intention to deal with naphtha if there
is a demand for it. The storage capacity of Sokimex Oil Terminal is 16,200 m3
for heavy fuel oil (tank : 3 × 5,400 m3), 49,500 m3 for diesel oil (tank : 1 × 10,500
m3 and 6 × 6,500 m3) and 6,060m3 for gasoline (tank : 2 × 2,000 m3 and 2 ×
1,030 m3) and total 72,000 m3. Furthermore, Sokimex has a plan to increase the
capacity to 172,000 m3. In addition, a storage tank with capacity of 25,000 m3
was constructed in 2000 and 3 tanks with the same capacity are under planning.
These tanks will be used for diesel oil. The new jetty to accommodate tankers up
to 46,000 DWT was inaugurated in April 2001. Sokimex has a plan that the ex-
isting unloading facilities including under-sea pipe for tankers up to 5,000 DWT
will go out of use after completion of the extension.
Sokimex Oil Terminal has one jetty (4.2 m deep completed in 1979) with the ca-
pacity to accommodate tankers up to 1,500 DWT. The rest is floating buoy asso-
ciated with undersea pipe, build under an agreement between Sokimex and
SHELL for temporary use with the capacity to accommodate tankers to the
maximum of 5,000 DWT. The unloading time of 1,500 DWT tankers and 5,000
DWT tankers are about 6 hours and 12 to 16 hours respectively.
3-2
(2) Natural Gas
So far, oil and gas wells with commercial scale have not been developed
in Cambodia.
In 1998, after poking around for seven-years, the four foreign firms that
had drilled a total of nine wells in potential oil and gas fields offshore
Cambodian territory, however they have walked away from their in-
vestments in Cambodia, because they had not found much oil/gas, and
collapsed world oil prices had made exploration in Cambodia less inter-
esting.
Woodside expects recoverable gas reserves of 2.7 TCF in this area using
the past available data (Refer to Table 3.1-1).
3-3
velopment wells. After signing of the contract, Woodside will start
seismic analysis and well drilling for exploration, appraisal and devel-
opment. As per their latest information, two exploration wells will be
drilled in the first quarter of 2002 initially and after that four wells will
be added and commercial operation is expected in 2006. As shown in
Fig.3.1-2, it takes about 4 to 5 years up to commercial production.
3-4
OVERLAPPING ZONE
6
Ⅱ
7 ■ Sihanoukville
5
● B1-1
● Koah Tang-1 4
● Koah Pring-1
Apsara-1 ● ● Devada-1 3
H-1 ● ● Poulo Wai-1
Bayon-1 ●● Angkor-1
● Preah Kahn-1
Ⅲ DA-1 ● 2
● L-1
Ⅳ 1
New Development Zone
100 km
3-5
PSC Commercial
Sign Operation
1st year 2nd year 3rd year 4th year 5th year
Exploration Appraisal
Seismic
Drilling Development
analysis
(proving)
The history of gas and oil development in Cambodia is not so long and
started from 1950s when natural resource surveys were carried out off-
shore and on land by France, China, Poland, the former Soviet, etc.
However, the survey was not full-scale and was carried out in a small
way only in specified areas.
The activities have been full-scale since 1969. The Cambodian Gov-
ernment of those days gave the right of oil exploration to French com-
pany and this marked a turning point in survey activity.
Geological surveys all over the country restarted from 1988. Gas and
oil reserves were not discovered, but potential possibilities were prom-
ising. At that time a team of Russian geologists carried out investiga-
tions and made the judgment that there is potential possibility of gas and
oil reserves in 6 areas of sedimentary rock. The East West Center esti-
3-6
mated that reserves of crude oil and natural gas are 50 to 100 million
barrels and 1,500 to 3,500 billion ft3 respectively.
3-7
cated onshore.
It withdrew entirely due to nonfulfillment.
3-8
Chairman
Vice Chairman
Direct General
Legal &
Upstream Administration Downstream
Negotiation
Department Department Department
Department
Refinery &
Oil & Gas Negotiation &
Administration Petrochemical
Exploration Contract
Industry
Engineering &
Personnel Distribution
Development
Data
Management &
Mapping
3-9
(b) Development in Overlapping Area
Each government has issued a license to different four foreign joint ventures
for exploration of oil/gas in the early 1970s, but the dispute of the territory
has prevented any exploration.
1) Neither country can allow oil/gas drilling until each agrees on a resolu-
tion to the dispute
2) Split revenue between two countries 50/50
3) Set up a joint committee to continue working toward a solution for the
next six months
This MOU may break the deadlock over the overlapping claims and there
might be much progress, but states only basic standpoint.
This means that Cambodian committee member should take stronger leader-
ship to accelerate the developing schedule which has a tendency to a tremen-
dous delay normally.
3 - 10
(c) Import from Neighboring Countries
The JICA Study Team has contacted with and obtained some informa-
tion from Mitsui Oil Exploration Company (MOECO) who is one of the
main gas suppliers in Thailand. MOECO is producing natural gas in the
Gulf of Thailand and supplying it to PTT (Petroleum Authority of Thai-
land) in the form of joint supplier with Unocal Thailand, Ltd. Unocal-
MOECO co-venture is the largest gas producer in Thailand. They sup-
plied natural gas of around 1,000 MMCFD to PTT in 1999; this amount
corresponded to about 60 % of total demand of Thailand in 1999.
Therefore Unocal-MOECO is considered to be the most possible gas
supplier to Cambodia.
MOECO suggests that they could afford to supply natural gas to Cam-
bodia in future from the viewpoint of their ample production capacity.
However, to import natural gas from Thailand, there some issues to be
concluded as described below:
3 - 11
} At present the supply capability of natural gas in Thailand has an
enough margin over the demand due to the recent economic depres-
sion in Thailand and import of Yadana gas from Myanmar that has
commenced in the late last year. However, due to the recent Thai
government policy to promote utilizing natural gas and gradually
drying up of the existing fields, it is assumed that several new gas
resources with ample capacity will be required to be developed after
the year 2007- 2008. This time of 2007-2008 might correspond to
the time of completion of Sihanoukville Power Plant. Therefore it is
expected that Thai government would be reluctant to supply natural
gas to Cambodia.
~ The demand of natural gas in the Project is rather small for com-
mercialization of gas supply from Thailand. Approx. 300 km length
gas pipeline would be required to be constructed from the existing
gas fields to Sihanoukville. The length of 300 km itself is unlikely
so long, but smaller size of pipeline needs a higher construction cost
per unit volume of transferred gas. Unocal suggested to MIME that
a minimum electric generation capacity to assure economic viability
would be around 300 MW.
To realize the supply of natural gas from Thailand in time, the above is-
sues should be concluded soon.
The natural gas to Vietnam is now supplied solely from the offshore gas
fields located in the South China Sea. Meanwhile, in Vietnamese territo-
ry in the south of the Gulf of Thailand, some developers are working to
develop new gas resources. Joint developer of MOECO/Unocal/
PTTEP/PVE is one of these developers, and they have a plan to supply
natural gas from this area to power stations that are located or to be lo-
cated in future in the Mekong delta area of Vietnam.
In 2000, they have drilled seven test wells in total in the western offsho-
re area of Vietnam, approx. 300 km apart from Sihanoukville. Accord-
ing to their test well results, they estimate that the recoverable gas
3 - 12
volume may be around 1 ~ 5 TCF. They intend to supply this natural
gas to the second stage of O Mon Power Station (300 MW) and IPP
power station(s) from 2007-2008. However, at present, the construction
of the second stage of O Mon Power Station is not yet finalized to con-
struct, furthermore there is no specific plan about IPP at present.
Therefore they are now seeking specific consumers for realizing this
project and consider supplying to Cambodia as one of the feasible op-
tions. But this option may also have a political complexity depending on
the intention of Vietnamese government as the case of Thailand de-
scribed above.
As discussed in the above, regarding the possibility of natural gas, all options, i.e.
the development in Cambodian territory, the development in overlapping zone
and the import from Thailand or Vietnam, have several kinds of issues to be
solved at present. A common key issue that is related to all options is a low
economic viability which is arisen from a relatively small size of gas demand ex-
pected in Cambodia. Therefore, increase of demand requirement, with introduc-
ing a gas-consumed industry as well as a power generation, would be the most
effective factor, which accelerates the realization of development or import of
natural gas.
3 - 13
Fig.3.1-4 Natural Gas Fields and Gas Pipelines of Thailand
3 - 14
(3) Liquefied Natural Gas
Liquefied natural gas (LNG) is also not available in Cambodia at present. Origin
of LNG may be Malaysia, Indonesia and Brunei. Receiving and supply facilities
for LNG consist of unloading jetty, storage reservoir, BOG compressors, vapor-
izer, transfer piping system, etc. Capacity of storage reservoir is approximately
40,000 m3 for 180 MW power plant. Construction cost of these facilities will be
approximately 130 to 170 Million US$, which is almost compatible to the power
plant cost.
Fuel price of LNG is generally higher than that of natural gas. Therefore LNG is
not suitable for this project.
(4) Coal
Possibility of coal utilization is low judging for this project from the economic
point of view, i.e. small scale of power plant, wholly importing of coal, etc.
Cambodia has a indication of existence of coal deposit, but now it is not yet de-
veloped. Therefore, Cambodia has to import coal wholly if coal is used for
power plant. Furthermore, there is no coal unloading facilities in Cambodia, so
that it is necessary to construct a new coal unloading facility in the power station.
The total capacity of new power station will be 270 MW when the 3-stage devel-
opment is completed. Therefore, it might be necessary to construct jetty, un-
loading facility and coal storage facility to meet the requirement of this 270 MW
ultimate capacity. That may results in excessive initial investment, i.e. additional
cost is more than 130 Million US$. The cost of power plant itself is also signifi-
cantly higher than that of gas turbine combined cycle.
(5) Conclusion
In conclusion, only diesel oil and heavy fuel oil could be used as fuels for the
new power station at present in Cambodia, and natural gas will be available in
near future.
3 - 15
3.1.2. Fuel Prices
Contracted fuel price is composed of a standard fuel price at Singapore and an oil
company’s handling cost (premium) including transportation cost. The amount of
premium is fixed during the contract period but the standard fuel price at Singa-
pore varies every hour, so that the fuel price at consumer is not constant.
The example of the price of heavy fuel oil is shown in Table 3.1-2.
The import tax, exceptional tax and social funds are added to the above-
mentioned fuel price. Among these taxes, the exceptional tax is applied to only
gasoline and lubricants. And the social funds are applied to gasoline, diesel oil
and heavy fuel oil.
The import tax rate of diesel oil is 20% and that of heavy fuel oil is 7%. VAT of
10% is applied to all kinds of fuels. Refer to Table 3.1-3.
Base fuel price used for calculation of taxes is not an actual fuel price but a fixed
standard price decided by the custom office. However, if an actual fuel price ex-
ceeds the standard fuel price, the actual fuel price is used for calculation of taxes.
New projects will be exempted from taxes only in the first year of operation.
Fig.3.1-5 shows the trend of heavy fuel oil and diesel oil prices for the last five
years, from Nov. 1996 to Aug. 2001. The average prices of diesel oil and heavy
fuel oil during the last five years, which are of CIF at Phnom Penh and excluding
tax and duties, were 154 and 237 $/ton, respectively.
3 - 16
Table 3.1.-2 Example of Heavy Fuel Oil Price
(Unit : $/MT)
Singapore Market Price
Date Average
Low High
30th Nov., 1999 138.75 139.75 139.250
Average 140.050
Premium 41.000
Exceptional
Custom Import Tax Social VAT Grand Total
Tax Sub
Kind of Fuel Cost Funds *1
Amount Amount Total Amount Amount
($) % % ($) % %
($) ($) ($) ($)
Gasoline 320 50 160.00 20 96.00 1.10 257.10 10 57.71 314.81 98.4
Heavy Fuel Oil 129 7 9.03 - 0.81 9.84 10 13.88 23.72 18.4
3 - 17
CIF Phnom Penh
1996 1997 1998 1999 2000 2001
FuelType Ave
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Heavy Fuel159 158 163 165 163 142 142 142 142 141 142 148 154 147 144 117 103 103 103 103 109 110 105 110 131 126 109 116 106 105 116 129 128 135 152 164 178 181 182 179 184 208 200 202 213 198 183 206 218 216 190 165 180 180 186 193 184 171 154
Diesel Oil 240 274 291 291 253 255 255 255 255 210 210 217 224 224 208 187 180 176 176 176 165 167 155 168 165 161 150 176 160 160 171 176 174 187 187 216 219 231 230 238 253 306 314 314 300 300 300 342 342 342 315 308 298 314 330 322 320 237
400
Heavy Fuel Oil Diesel Oil
350
300
250
3 - 18
200
150
100
Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
Fig. 3.1-5 Fuel Price in Phnom Penh (CIF) Purchased from CUPL
(2) Natural Gas
Natural gas is not used in Cambodia, so there is no price at present. Natural gas
price at site consists of wellhead price and submerged pipe cost. Wellhead gas
prices are less than 2.2 $/MMBTU at Erawan gas filed which is the biggest gas
filed of Unocal who is the biggest gas supplier in the Gulf of Thailand (i.e., Uno-
cal supplies about 1,000 MMCFD out of 1,800 MMCFD of total consumption of
Thailand) and about 2.5 $/MMBTU on an average in the Gulf of Thailand. The
reason of cheaper price at Erawan would be the effect of more than 1,000 wells
drilling. The price of Yadana gas from Myanmar is 2.5 $/ MMBTU at Thai bor-
der and in southern Vietnam about 2.5 ~ 3.0 $/MMBTU.
In case of development in Cambodian gas fields, as each reservoir capacity is
smaller than that of other countries, well drilling cost might run up. Therefore
wellhead price is estimated around 2.5 ~ 3.0 $/MMBTU.
Gas pipeline cost from the fields to Sihanoukville is estimated about 140 Million
US$ by CNPA and Woodside Co. for 24” pipe diameter and 170 km length. This
cost can be considered as reasonable considering adjusted value of 158 Million
US$ from actual value for 24” pipe and 120 km length in Thailand.
Using this estimation, pipe cost for 12 inch which is suitable size for 270 MW is
calculated about 90 Million US$. This cost is equivalent to 1.0 ~ 1.5 $/MMBTU
depending on the operation load in case of discount rate of 15% and payback
period of 20 years.
Therefore, natural gas price at power plant site would be around 3.5 ~ 4.5 $/
MMBTU as a criterion depending on depreciation period and well drilling cost,
etc.
3 - 19
3.1.3. Typical Analysis of Fuels
Tables 3.1-4 and 3.1-5 show the typical specification of diesel oil and heavy fuel oil,
respectively.
Tables 3.1-6 and 3.1-7 show the analyses of samples from diesel oil and heavy fuel oil,
respectively. These data were submitted by Sokimex. According to the result, sulfur
content is 0.03%, which is incredibly low compared to the specified maximum value
of 0.25%.
In general, analysis of fuel is carried out by each tank car. However, at present So-
kimex Oil Terminal has no analyzing devices, therefore, analysis of fuel is carried out
at his laboratory in Phnom Penh.
Table 3.1-8 shows standard specification for Singaporean oil which shows higher
sulfur content.
New environmental law was drafted in 2000 and authorized without any amendment
in 2001. Sub-decree on air and noise pollution control limits sulfur and lead content
in its Chapter 2, Article 10, Annex 8 (Refer to Table 3.1-9). According to the stan-
dard the permitted sulfur content in diesel oil is 0.2%. Diesel oil imported from
Thailand may pass this new regulation because of their lower sulfur content in the
standard oil, but oil from Vietnam or Singapore shall be analyzed carefully.
3 - 20
Table 3.1-4 Distillate Fuel Quality Specification
3 - 21
Table 3.1-6 Analysis Data of High Speed Diesel Fuel
(Source : Sokimex)
*1 This test is performed on a 6-monthly basis. The result was obtained from sample dated 03 Dec., 1999.
3 - 22
Table 3.1-7 Analysis Data of Fuel Oil No.2
(Source : Sokimex)
*1 This test is performed on a 6-monthly basis. The result was obtained from sample dated 09 July, 1999.
*2 This test is performed on a monthly basis. The result was obtained from sample dated 01 Dec., 1999.
3 - 23
Table 3.1-8 Standard Specification for Singapore Oil
Diesel Oil
No. Test Definition Method ASTM Range Type
1 Appearance Visual -
2 Color ASTM D-1500 Max. 1.5
3 Density at 15°C D-1298 Max. 0.8500
4 Copper Corrosion (3h, 50°C) D-130 Max. No.1
5 Distillation D-86
- I.B.P, °C Min. 150
Max. 170
- 10%, °C Max. 230
- 50%, °C Max. 300
- 90%, °C Max. 365
6 Flash Point D-93 Min. 60
7 Pour Point, °C D-97 Max. +10
8 Ash Content, %WT D-482 Max. 0.01
9 Water Andsediment, 5 vol. D-1796 Max. 0.05
10 Sulfur Content, %WT D-1216 Max. 0.70
11 Cetane Inde D-976 Min. 45
12 Water by Distillation D-95 Max. 0.50
13 Acid Number, mgKOH/g D-664 Max. 0.25
14 Carbon Residue, %WT D-189 Max. 0.05
Max. 1.4
15 Kinematic Viscosity at 40°C, cst D-445
Min. 5.0
(Source : EDC)
3 - 24
Table 3.1-9 Sulfur and Lead Standard permitted to Fuel and
Other Combustion Substances
Components Unit
CO2 vol. % 1.65
N2 vol. % 1.92
CH4 vol. % 95.49
C2H6 vol. % 0.72
C3H8 vol. % 0.07
C4H10 vol. % 0.02
C5H12 vol. % 0.10
High Heating Value kJ/Nm3 38,700
Low Heating Value kJ/Nm3 34,920
3 - 25
3.2. Candidate Power Plant Types
Power plant types widely used for utility power stations in the world are as follows:
• Gas Turbine Combined Cycle (GTCC) Power Plant
• Diesel Power Plant
• Conventional Power Plant (boiler/steam turbine system)
• Open-cycle gas turbine power plant
Conventional power plant is the most popular because it can use many kinds of fuel
such as coal, oil and natural gas. GTCC has high thermal efficiency and is used in the
area where clean fuels such as natural gas and diesel oil are available. Diesel generator
is widely used for scattered power sources. Open-cycle gas turbine is mainly used as
standby source for peak load due to its low thermal efficiency.
In this study, three kinds of plant type (GTCC, diesel power plant and conventional
power plant) except open-cycle gas turbine are compared for Sihanoukville Power
Plant which are planned to be operated as base-load power station.
Main equipment of GTCC are gas turbine, heat recovery steam generator (HRSG),
steam turbine, and generator. Fig.3.2-1 shows system diagram of GTCC. Fuel is
burnt in combustor of gas turbine, combustion gas rotates the turbine rotor, that turns
the generator. This is the first stage of generation. Then, exhaust gas flows into
HRSG and heats the boiler water in the heat exchanger tubes of HRSG. The boiler
water is converted to the steam, which is induced into steam turbine and rotates the
steam turbine generator. This is the second stage of generation.
3 - 26
From
No.3
HRSG
From
No.2
H.P. Steam HRSG
From
No.3 HP Turbine Bypass
HRSG
From
No.2
L.P. Steam HRSG
Note :
LP Turbine Bypass
shows the steam line.
shows the water line.
3 - 27
Steam Turbine G
No.1
Deaerator
No.1 HRSG
Condenser
Seawater
LP BFP
Fuel C.P.
(Natural Gas/Diesel Oil)
To
HP BFP No.2
HRSG Condensate
&
G Boiler Feed Water Deaerator
To
No.3
No.1 Gas Turbine HRSG
&
Deaerator
Diesel power plant consists of diesel engine and generator. Diesel engine is used for
prime mover for automobile, ship, and electric generator. Fig.3.2-2 shows the system
diagram of diesel power plant. There are three types of diesel engine, i.e. high-speed,
middle-speed and low-speed. High speed diesel generator is excluded from this study
because of its very small capacity. As for rotation speed, revolution of middle speed
diesel engine is around 400 ~ 700 r.p.m. and that of low speed diesel is around 150
r.p.m. Low speed diesel engine has higher thermal efficiency but it is more expensive.
In Cambodia, middle speed diesel is usually used.
Diesel engine is not suitable for large-scale power station because of its small capac-
ity per unit. If it is applied to large-scale power station, so many units need be in-
stalled and that cannot enjoy a scale merit. Maximum unit capacity of middle speed
diesel is less than about 20 MW and the maximum unit capacity of low speed diesel is
about 50 MW.
Main equipment of conventional power plant are boiler, steam turbine, and generator.
Fig.3.2-3 shows system diagram of conventional power plant. Fuel is burnt in boiler
using burner, and heats the boiler water in the heat exchanger tubes of boiler. The
boiler water is converted to the steam, which is induced into steam turbine and rotates
the steam turbine generator.
3 - 28
Fuel (Heavy Fuel Oil)
Air
Stack
3 - 29
Diesel
Engine G
De-NOx De-SOx
Boiler
Fuel (Heavy Fuel Oil) G
Air
De-SOx
3 - 30
Condenser
Seawater
B.F.P.
Table 3.3-1 shows technical comparison of each power plant type. Details are de-
scribed as follows:
• Construction Cost
• Applicable Fuel
In rare case, heavy fuel oil is used for gas turbine but it is not recommendable be-
cause of some difficulties mentioned below:
Therefore natural gas as main fuel and diesel oil as standby fuel are applied to
GTCC. Diesel generator and conventional power plant can use both heavy fuel oil
and diesel oil, but heavy fuel oil is usually used from economical point of view
even if environmental mitigation cost is considered.
GTCC and low speed diesel have the highest efficiency of about 50% at LHV
(Low Heating Value) base among 4 candidates. Middle speed diesel has the sec-
ond high efficiency of about 43% (LHV), conventional power plant has the lowest
efficiency of about 39% (LHV).
GTCC, middle speed and low speed diesels are low because they have less auxili-
ary apparatuses. Conventional power plant is almost 2 times higher than GTCC.
3 - 31
• Environmental Mitigation Measures
As for prevention of air pollution, maximum emission levels for pollutant matters
are prescribed by Draft Sub-Decree on Control of Air Pollution and Noise in Cam-
bodia. This standard is applied as temporary emission standard of this study.
Standard O2 concentration in the exhaust gas and conditions for gas volume are not
prescribed by Draft Sub-Decree, so we tentatively use actual O2 concentration and
gas volume at 760 mm Hg, 0°C for the calculation of air pollution. Table 3.3-2
shows comparison of Cambodian standard and estimated emission level of air
pollutant from each type of plant under the conditions described above. As for air
pollution, GTCC needs no environmental mitigation measure because emission
level of NOx, SOx, and particulates are less than emission standard. Other types
of plant need some measures to reduce air pollutant because emission level of air
pollutants exceed the standard except NOx level in conventional power plant.
As for hot water discharge, middle and low speed diesel need no cooling seawater
so they need no measure. GTCC and conventional power plant need measures to
reduce influence of hot water discharge. GTCC uses less quantity of seawater than
conventional power plant, so it needs less expensive cost.
• Ease of Operation
Diesel power plant seems easy to operate. GTCC and conventional power plant
are relatively easy to operate except star-up and shut-down operation because, in
normal operation, they are operated with sophisticated automation system.
• Reliability
GTCC, diesel power plant, and conventional power plant are widely used in the
world, all of them show good reliability. Diesel power plant probably has higher
reliability because it consists of simple equipment.
3 - 32
used in Cambodia at present, but it may needs more frequent maintenance and
higher expense.
As shown in Table 3.3-1, GTCC is superior to other candidates at the points of plant
performance and construction cost. The second is middle speed diesel. Convention-
al power plant has no advantage compared to others. However, the final decision of
plant type should be made after considering environmental and economic compari-
sons.
3 - 33
Table 3.3-1 Comparison of Type of Power Plant
Fuel Natural Gas Heavy Fuel Oil Heavy Fuel Oil Heavy Fuel Oil
Efficiency ( LHV ) Approx. 50% Approx. 43% Approx. 49% Approx. 39%
Auxiliary Power
3 - 34
Approx. 2.8% Approx. 4.6% Approx. 4.6% Approx. 6.7%
Consumption Ratio
1,000 mg/m3
NOx < 150 ppm < 1,500 ppm < 1,500 ppm < 300 ppm
(487 ppm)
500 mg/m3
SOx - < 700 ppm < 700 ppm < 2,200 ppm
(175 ppm)
3 - 35
Particulate 100 mg/m3 < 5 mg/m3 < 250 mg/m3 < 250 mg/m3 < 200 mg/m3
Note : Cambodian standard is based on the sub-decree on Control of Air Pollution and Noise.
The maximum concentration of sulfur for diesel oil and heavy fuel oil is 0.2 % and 3.5 % respectively.
Emission levels for Gas Tribune Combined Cycle are based on natural gas, because diesel oil is used as
back-up fuel.
Above concentrations are based on 760 mmHg, 0°C condition, and the emission levels of NOx and
Particulates are referred to typical maximum level given by main manufacturers.
3.3.2. Environmental Comparison
Table 3.3-3 shows annual expected quantities of air pollutant discharged from each 180
MW power plant. Table 3.3-4 shows calculation of discharge quantity. Table 3.3-5 and
Table 3.3-6 show composition of fuels used for calculation. Data of composition of die-
sel oil, heavy fuel oil and natural gas in Cambodia which we have obtained are very lim-
ited, so general data is used for calculation.
Emission level of NOx, SOx from diesel power plant and NOx from conventional
power plant surpass Cambodian draft standard, so De-NOx and De-SOx systems are
supposed to be installed to those power plant to reduce emission level less than Cambo-
dian draft standard (NO2 < 1,000 mg/Nm3 (487 ppm), SO2 < 500 mg/Nm3 (175 ppm)).
Quantity of air pollutant discharged from each power plant is calculated using con-
centration of NOx and SOx after De-NOx and De-SOx system.
Table 3.3-3 Quantity of Air Pollutant Discharged from Each Power Plant
As for emission of CO2, GTCC is the lowest among 4 candidates. GTCC consumes
less fuel for generation compared to others because of high efficiency.
Compared to diesel power plant using heavy fuel oil, GTCC using natural gas can re-
duce emission of air pollutant. CO2 is also reduced, that will contribute to preventing
greenhouse effect in the earth.
3 - 36
Table 3.3-4 Calculation of Air Pollutant Discharged from Each Power Plant
3 - 37
Concentration of SOx Quantity of SO2
PPM ton/year
GTCC 0 0
*
Diesel (middle speed) 175 1,353
*
Diesel (low speed) 175 1,198
*
Oil-fired Conventional 175 506
* : after DeSOx system
Emission of CO2 j k -6
k = e × j × 10
Concentration of CO2 Quantity of CO2
Vol.% ton/year
GTCC 5.55 3.432E+05
Diesel (middle speed) 6.81 5.267E+05
Diesel (low speed) 6.81 4.663E+05
Oil-fired Conventional 20.61 5.963E+05
Table 3.3-5 Composition of Fuel Oil
(Unit : wt.%)
Components Diesel Oil Heavy Fuel Oil
(Unit : vol.%)
Components Natural Gas
CO2 1.65
N2 1.92
CH4 95.49
C2H6 0.72
C3H8 0.07
C4H10 0.02
C5H12 0.10
3 - 38
3.4. Economic Comparison
3.4.1. Purpose
The purpose of the economic comparison is to study the most economic power plant
type among the alternative candidates that will be introduced to Cambodia. The
economic justification for the implementation of a power plant is also carried out in
Chapter 10.
The following economic indicators are used for the economic comparison.
(1) Net Present Value of Total Cost (NPV)
(2) Levelised Production Cost at Sending-out (LPC)
All alternative candidates are assumed to be the same kWh and kW values at the
sending-out (at powerhouse exit).
The net present value of the total cost, consisting of construction cost, mainte-
nance & operation cost during the service period, is derived from the conversion
to the present value with a discount rate. A power plant type with the lowest net
present value (least cost) against the same benefit is regarded as an economic
type. The net present value is derived from the following formula and converted
to the year of commencement of plant operation.
n
Cost( i )
NPV = ∑
i = −1 ( 1 + r )
i
Where i : years
n : Construction period + Service period (= 2 years + 20 years)
r : Discount rate (= 10%)1
Cost (i) : Cost in year i
1
A Discount rate of 10 % ~ 12 % is well applied to Power Sectors in South-east Asia. A discount rate of 10 % is used here.
3 - 39
(2) Levelised Production Cost at Sending-out
The levelised production cost calculated in this section is used as one of the indi-
ces to make the economic priorities among the candidates. Financial levelised
production cost is also calculated in Chapter 10.
Four (4) power plant types as mentioned in the preceding sections are used in the
economic comparison.
(1) GTCC Power Plant
(2) Diesel Power Plant (middle speed)
(3) Diesel Power Plant (low speed)
(4) Conventional Power Plant
Unit construction cost, maintenance & operation cost, fuel type, fuel cost, rate of sta-
tion use, forced outage rate and scheduled maintenance days are shown in Table 3.4-1.
The construction cost concerning the diesel power plant and conventional power plant
includes the equipment cost related to reducing the air pollution because heavy fuel
will be used.
3 - 40
3.4.4. Prices in Economic Comparison
The economic prices are used in the economic comparison because the evaluation of
the project is carried out from the viewpoint of the national economy. The market
prices are determined with the relationship between demands and supply ideally.
However, provided that the market prices are distorted by the government’s interfer-
ences with the market, the market prices removed the above distortion are called as
the economic prices (shadow prices). Tax, duty and subsidy are one of the examples2
of the government’s interferences. In the economic comparison, tax and subsidy are
excluded and the following prices are applied concretely.
The unit construction cost expressed in US$ term is used as the border price.
The fuel prices of CIF (Cost, insurance and freight) are used except natural gas
because the all oil fuels in Cambodia are imported from overseas. Averaged CIF
fuel prices for the period from 1996 to 2001, as mentioned in Section 3.1.2, are
applied.
Other operation and maintenance costs estimated in US$ term are used as the
border prices at the moment.
2
An exchange rate controlled by a government is also one of the examples.
3 - 41
3.4.5. Annual Capacity Factor
Annual capacity factors are referred to the results of optimum power development
program in Section 2.2.
From the year 7th (2012) onwards, the annual capacity factors are set at 50 % based
on the estimated capacity factors from the 7th year (2012) to 13th year (2018).
The results of economic comparison for the four (4) power plant types are summa-
rized in Table 3.4-4. The relative calculation sheets are demonstrated in Table 3.4-2
to Table 3.4-3 and Fig.3.4-1 shows the breakdown of production cost.
A combined cycle power plant presents the lowest net present value of total cost and
accounts for 70%, 59%, and 69% of middle speed diesel, low speed diesel and oil-
fired conventional respectively.
Concerning the levelised production cost at sending-out level, natural gas-fired com-
bined cycle power plant is proven to be far least among the alternative candidates.
According to the above results, combined cycle power plant is the most economic
power plant.
3 - 42
Table 3.4-1 Characteristics of Candidates of Power Plants and Fuel Cost
Installed costs of Diesel and Oil-fired Conventional include the mitigation equipment costs against the air pollution.
3 - 43
Fuel Price* Efficiency Fuel Cost
Plant Type Fule Type
US$/MMBTU BTU/kWh US$/MWh
Combined Cycle NG 4.00 6,829 27.32
Diesel (Middle Speed) HFO 3.99 7,888 31.49
Diesel (Low Speed) HFO 3.99 6,987 27.89
Oil-fired Conventional HFO 3.99 8,729 34.85
Note: *Fuel Price based on L.H.V. (Low Heating Value)
Table 3.4-2 Calculation for Equivalent Installed Capacity and Generation Energy
Year 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Capacity Factor 71% 75% 55% 63% 67% 70% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50% 50%
Stage1 90 MW
Stage 2 90 MW
3 - 44
Forced Outage Rate 20.0%
Station Use 4.6%
kW Adjustment Factor 1.099
kWh Adjustment Factor 1.019
Equivalent Installed Capacity 197.8
Equivalent Generation Energy GWh 570.4 602.5 883.7 1012 1077 1125 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 401.7 401.7
4 Oil-fired Conventional
Scheduled Maintenance Days 53 days
Forced Outage Rate 8.0%
Station Use 6.7%
kW Adjustment Factor 1.055
kWh Adjustment Factor 1.042
Equivalent Installed Capacity 189.9
Equivalent Generation Energy GWh 583.3 616.1 903.6 1035 1101 1150 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 410.8 410.8
Table 3.4-3 Comparison Among the Power Plant Candidates
Year -1 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
Sending-out GWh 544.1 574.7 842.9 965.6 1027 1073 766.3 766.3 766.3 766.3 766.3 766.3 766.3 766.3 766.3 766.3 766.3 766.3 766.3 766.3 383.2 383.2
Discount Rate 10.0%
Conversion Factor 1.2100 1.1000 1.0000 0.9091 0.8264 0.7513 0.6830 0.6209 0.5645 0.5132 0.4665 0.4241 0.3855 0.3505 0.3186 0.2897 0.2633 0.2394 0.2176 0.1978 0.1799 0.1635 0.1486 0.1351 Sum
NPV of Sending-out GWh 0.0 0.0 544.1 522.5 696.6 725.5 701.3 666.2 432.6 393.3 357.5 325.0 295.4 268.6 244.1 222.0 201.8 183.5 166.7 151.6 137.9 125.3 56.9 51.8 7470.2
1 Combined Cycle (Natural Gas-fired) Net Present Value of Cost 412.1 M.US$ Levelised Production Cost 5.52 c/kWh
Generation Energy GWh 559.8 591.3 867.2 993.4 1056 1104 788.4 788.4 788.4 788.4 788.4 788.4 788.4 788.4 788.4 788.4 788.4 788.4 788.4 788.4 394.2 394.2 Sum
Construction Cost M.US$ 31.32 46.98 31.32 46.98 156.60
Fixed O/M Cost M.US$ 1.80 1.80 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 3.60 1.80 1.80 72.00
Variable O/M Cost M.US$ 0.56 0.59 0.87 0.99 1.06 1.1 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.79 0.39 0.39 17.01
Fuel Cost M.US$ 15.29 16.15 23.69 27.14 28.86 30.16 21.54 21.54 21.54 21.54 21.54 21.54 21.54 21.54 21.54 21.54 21.54 21.54 21.54 21.54 10.77 10.77 464.39
Cost Total M.US$ 31.32 46.98 48.97 65.52 28.16 31.73 33.52 34.86 25.93 25.93 25.93 25.93 25.93 25.93 25.93 25.93 25.93 25.93 25.93 25.93 25.93 25.93 12.96 12.96 710.00
NPV as of Year 1 M.US$ 37.9 51.68 48.97 59.56 23.27 23.84 22.89 21.64 14.64 13.31 12.10 11.00 10.00 9.09 8.26 7.51 6.83 6.21 5.64 5.13 4.66 4.24 1.93 1.75 412.05
2 Diesel (Middle Speed) Net Present Value of Cost 591.4 M.US$ Levelised Production Cost 7.92 c/kWh
Generation Energy GWh 570.4 602.5 883.7 1012 1077 1125 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 401.7 401.7 17321.2
Construction Cost M.US$ 67.75 67.75 67.75 67.75 271.0
3 - 45
Fixed O/M Cost M.US$ 2.08 2.08 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 2.08 2.08 83.0
Variable O/M Cost M.US$ 1.71 1.81 2.65 3.04 3.23 3.37 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 1.21 1.21 52.0
Fuel Cost M.US$ 17.96 18.97 27.83 31.88 33.9 35.42 25.3 25.3 25.3 25.3 25.3 25.3 25.3 25.3 25.3 25.3 25.3 25.3 25.3 25.3 12.65 12.65 545.5
Cost Total M.US$ 67.75 67.75 89.5 90.61 34.63 39.07 41.28 42.94 31.86 31.86 31.86 31.86 31.86 31.86 31.86 31.86 31.86 31.86 31.86 31.86 31.86 31.86 15.94 15.94 951.5
NPV as of Year 1 M.US$ 81.98 74.53 89.50 82.37 28.62 29.35 28.19 26.66 17.98 16.35 14.86 13.51 12.28 11.17 10.15 9.23 8.39 7.63 6.93 6.30 5.73 5.21 2.37 2.15 591.4
3 Diesel (Low Speed) Net Present Value of Cost 694.8 M.US$ Levelised Production Cost 9.3 c/kWh
Generation Energy GWh 570.4 602.5 883.7 1012 1077 1125 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 803.4 401.7 401.7 17321.2
Construction Cost M.US$ 99.89 99.89 99.89 99.89 399.6
Fixed O/M Cost M.US$ 2.08 2.08 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 4.15 2.08 2.08 78.9
Variable O/M Cost M.US$ 1.71 1.81 2.65 3.04 3.23 3.37 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 2.41 1.21 1.21 49.6
Fuel Cost M.US$ 15.91 16.8 24.65 28.23 30.02 31.37 22.41 22.41 22.41 22.41 22.41 22.41 22.41 22.41 22.41 22.41 22.41 22.41 22.41 22.41 11.2 11.2 460.7
Cost Total M.US$ 99.89 99.89 119.6 120.6 31.45 35.42 37.4 38.89 28.97 28.97 28.97 28.97 28.97 28.97 28.97 28.97 28.97 28.97 28.97 28.97 28.97 28.97 14.49 14.49 988.7
NPV as of Year 1 M.US$ 120.9 109.88 119.59 109.62 25.99 26.61 25.54 24.15 16.35 14.87 13.51 12.29 11.17 10.15 9.23 8.39 7.63 6.94 6.30 5.73 5.21 4.74 2.15 1.96 694.8
4 Oil-fired Conventional Net Present Value of Cost 601.2 M.US$ Levelised Production Cost 8.05 c/kWh
Generation Energy GWh 583.3 616.1 903.6 1035 1101 1150 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 821.5 410.8 410.8
Construction Cost M.US$ 50.89 76.34 50.89 76.34 254.46
Fixed O/M Cost M.US$ 1.90 1.90 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 3.80 1.90 1.90 72.20
Variable O/M Cost M.US$ 2.10 2.22 3.25 3.73 3.96 4.14 2.96 2.96 2.96 2.96 2.96 2.96 2.96 2.96 2.96 2.96 2.96 2.96 2.96 2.96 1.48 1.48 60.84
Fuel Cost M.US$ 20.33 21.47 31.49 36.07 38.36 40.08 28.63 28.63 28.63 28.63 28.63 28.63 28.63 28.63 28.63 28.63 28.63 28.63 28.63 28.63 14.32 14.32 588.62
Cost Total M.US$ 50.89 76.34 75.22 101.93 38.54 43.60 46.12 48.02 35.39 35.39 35.39 35.39 35.39 35.39 35.39 35.39 35.39 35.39 35.39 35.39 35.39 35.39 17.70 17.70 976.12
NPV as of Year 1 M.US$ 61.58 83.97 75.22 92.66 31.85 32.76 31.50 29.82 19.98 18.16 16.51 15.01 13.64 12.40 11.28 10.25 9.32 8.47 7.70 7.00 6.37 5.79 2.63 2.39 601.24
Fuel : NG HFO HFO HFO
10.0
9.30
3.66
6.0
4.09 4.49
5.52
3 - 46
4.0
3.33
2.0 3.83
3.56
2.19
0.0
Combined Cycle Diesel (Middle Speed) Diesel (Low Speed) Oil-fired Conventional
Fig. 3.4-1 Comparison of Production Cost Components at Plant excluding Taxes imposed on Fuel (10%Discount Rate)
3.5. Conclusion
Combined cycle power plant is superior to the others in plant performance and envi-
ronmental aspect. Compared to oil-fired middle speed diesel usually used in Cambo-
dia, combined cycle power plant can reduce about 75% of NOx and 100% of SOx,
about 35% of CO2 emission. From environmental point of view, such as prevention
of air pollution and greenhouse effect, it is preferable to select combined cycle power
plant as the plant type of Sihanoukville Power Plant.
As for operation and maintenance, combined cycle power plant is some difficult for
Cambodia to operate or maintain compared to diesel generator because gas turbine
needs new technological knowledge for operation and maintenance but they have no
experience. However, gas turbine and gas turbine combined cycle technologies are
very popular throughout the world. And a gas turbine has been used since 1960’s and
combined cycle is used since 1980’s even in neighboring countries in Southeast Asia
such as Indonesia and Bangladesh. Thus introduction of combined cycle power plant
to developing countries seems to bring no serious technical problem. Also in Cambo-
dia, introduction of combined cycle power plant is possible through appropriate tech-
nical training.
It is expected that electrical demand will further increase and large-scale power plant
will be needed in Cambodia from now on. Introduction of combined cycle power
plant, which is suitable for large-scale power plant, will contribute to the development
of large-scale power source in future Cambodia.
A combined cycle power plant has been proved to be the most economic power plant
type in the course of the economic comparative studies, consisting of net present val-
ue of total cost, annual levelised cost under the assumed conditions.
3 - 47
3.5.3. Conclusion of Optimum Type Power Plant
On the other hand, since EDC has no operation experience concerning the gas turbine
combined cycle including a gas turbine itself, the technical training for EDC staffs
will be required based on the technical training schedule, which will incorporate the
timing of the project implementation.
3 - 48