Co-Efficient For Raw Material-2
Co-Efficient For Raw Material-2
Thumb rule is an approximate & comparing method. In thumb rules, the units are not the same when we compare to get the
results. So never consider units while performing thumb rule.
Contents [show]
The plan area is 800SFT then the total volume of concrete required = 800 x 0.038m 3 = 30.4m3
For more accurate results you can also use BN Datta recommendations:
As per B N Datta, the Steel quantity used in different members of the building can be calculated easily using the following
recommendations.
Structural Member Percentage of Steel
Example:
How to calculate the steel quantity of slab having the Length, width, and depth of the slab is 5m x 4m x 0.15m
As per the above table, the steel quantity of slab is 1% of the total volume of concrete utilized.
Thumb rule to calculate Steel quantity of above slab = Volume of Concrete x Density of Steel x % of Steel of Member
Suppose the concrete quantity is 0.5m3 then the shuttering area required is 0.5 x 6 = 3m2
Components of Shuttering:-
Shuttering Ply, Battens, Nails are components of Shuttering.
Example :
15m2 is total area of shuttering, then Shuttering oil required = 0.065 x 15 = 0.975 lts
For Accurate Shuttering Area Calculation, you can check here Shuttering area required for slabs, columns, Beams,
Footings
Thumb rule for Cement, Sand, Coarse Aggregate Quantity in Different grades of Concrete :
Concrete Mix Cement Quantity Coarse Aggregate Quantity Fine Aggregate Quantity
For Accurate calculation refer to Concrete Mix design for Different grades of concrete
Thumb rule for Cement quantity in Brickwork, Cement Masonry & Plastering work in construction:
Brickwork Thumb rule:
Cement Masonry Type & Mix Cement Qty in Bags Cement Qty in Kgs
Contents [show]
Concrete Mix design of M5, M7.5, M10, M15, M20, M25, M30 and higher grades of concrete is calculated as below:
The procedure for finding the different grades of concrete mixes are same. The below mentioned method can be applied to
any grade of concrete by changing the values. To make ease in understanding we are finding the Concrete mix design of
M20 grade concrete.
The Concrete mix ratio for M20 grade of concrete is 1:1.5:3 that mean 1 part of cement, 1.5 part of sand (fine aggregate) and
3 parts of aggregate (crushed stone) in volume and then batched for mixing. To know the Concrete Mix Design follow below:-
As per BS 8500-2 British/European standards The grade of concrete is denoted as C10, C15, C20,C25, etc., ‘C’ which
means ‘Concrete Strength class’ and number behind C refers to characteristic Compressive strength of Concrete in
N/mm2 @ 28 days when tested with the 15cm dia & 30cm height cylinder in direct compression test
The grade of concrete is also denoted as C16/20, C20/25, C25/30, etc., which means Concrete Strength Class (C) the
number behind C refers to Compressive strength of Concrete in N/mm2 when tested with Cylinder / Cube.
Characteristic
Compressive strength of
Type of Concrete Concrete Grade Mix Ratio
Concrete
@28Days in N/mm2
We must add all the volume to know the total volume = 1 + 1.5 + 3 = 5.5
As we know that during concreting when we place wet concrete, it gets harden after certain standard time. Considering the
same it had be decided upon by Civil design Engineers to take a factor of safety ranging from 1.54 to 1.57 to counter that
shrinkage.
i.e. volume of dry Concrete = 1.54 to 1.57 times Volume of wet concrete
Volume of Cement
Sand usually consists of moisture content. It increases the volume of sand (bulking of sand).
For accurate calculation use dry sand or include the effect of bulking as mentioned above in calculation.
Hence we require 672kg of sand for 1 cu.m of concrete.
Calculation of Volume of Coarse Aggregate in 1m3 of Concrete:-
The following formula is used to find the quantity of coarse aggregate in 1m3 of concrete.
Volume of Aggregate
Density of aggregate may go higher if void spaces decreases. 5mm aggregate has more density when compared with 20mm
size of aggregate
Summary: –
8 bags of cement required for 1 cu.m of M20 grade concrete.
672 kg of Sand required for 1 cu.m of M20 grade concrete.
1326 kg of 20mm Aggregate is required for 1 cu.m of M20 grade concrete.
200 litres of water is required for 1 cu.m of M20 grade concrete
Table for Quantity of Cement, Sand, Aggregate, Water required for Different grades of concrete