2nd Case Digests
2nd Case Digests
Facts:
Gregorio Araneta, Inc. and Philippine Sugar Estates Development Co., Ltd. were involved in a contract dispute. The
dispute arose over the construction of a church and streets on a portion of land sold by J.M. Tuason & Co.,
Inc. to Philippine Sugar Estates Development Co., Ltd. The contract stipulated that the buyer would build the
church and the seller would construct the streets. However, the seller was unable to complete the construction
of one of the streets due to a squatter named Manuel Abundo refusing to vacate the area. Philippine Sugar
Estates Development Co., Ltd. filed a complaint against J.M. Tuason & Co., Inc. and Gregorio Araneta, Inc. in the
Court of First Instance of Manila. The complaint sought to compel the defendants to comply with their obligations
or pay damages. The lower court initially dismissed the plaintiff's complaint, upholding the defendant's
defense of prematurity. The plaintiff filed a motion for reconsideration, requesting the court to fix a period
for the defendant to comply with its obligation. The court granted the motion and amended its decision,
giving the defendant two years to comply with the obligation. The defendant appealed to the Court of Appeals,
arguing that the relief granted was not justified by the pleadings and evidence presented at the trial. The Court of
Appeals affirmed the lower court's decision, stating that the fixing of a period was within the pleadings and
there was no change of theory after the submission of the case for decision. The defendant filed a petition for
review by certiorari to the Supreme Court.
Issue:
Whether or not the court has the authority to fix a period for performance under a contract that establishes a
"reasonable time" for completion?
Ruling:
No. The Supreme Court agreed with the defendant's argument that the decision of the Court of Appeals was legally
untenable, and reversed the decision of the CA. The Supreme Court explained that the intervention of the court to fix
the period for performance was not warranted because the contract already provided a "reasonable time" for the
defendant to comply with its obligation. If the contract provided a "reasonable time" for performance, then a period
was already fixed. The court's role should have been to determine if that reasonable time had already elapsed
when the suit was filed. If the reasonable time had passed, the court should have declared that the defendant
had breached the contract and fixed the resulting damages. If the reasonable time had not yet elapsed, the
court should have dismissed the action as premature. It was not logical for the court to intervene and fix the
period for performance when the contract already established a reasonable time. The trial court had arbitrarily set
the two-year period without sufficient explanation. Furthermore, the court's decision was based on Article 1197
of the Civil Code. Article 1197 states that if the obligation does not fix a period but it can be inferred from the
nature and circumstances that a period was intended, the court must determine what period was probably
contemplated by the parties. The period cannot be set arbitrarily and must be based on the intention of the
parties. In this case, the contract did not specify an exact period for performance because the parties were aware that
the land was occupied by squatters and the duration of the eviction process was uncertain. Therefore, t he court held
that the performance of the obligations should be deferred/delayed until the squatters were evicted, and the
date of performance should be set at the time of their eviction. The court reversed the decision of the lower
courts and fixed the performance period accordingly.