Site Visit - April 2024
Site Visit - April 2024
Site Visit
Date : 06/04/2024
Vertical Pipes should be straight
These marks of
cutter should
not be there in
stone chowkhat
There should be
Grove at joint of
Stone chowkhet
and brick wall
Chajja at
Mumty door
should not be
this thick. It is
not according to
Structure
drawing
There should be
hard surface in
front of Ground
floor front yard
for easy and
clean access
Point from previous visit on
Date : 05/09/2023
Top and Bottom
bands should
be of equal
width
L : 41- Beam is
bent
Its due to mivan and ply shuttering joint will be manage with plaster work
L : 41- Gap between bricks shall be
15mm but the gap is more than
30mm at several places
3”
L : 28- There is some unwanted slab
extension in staircase waist slab.
L : 28- Either wall is out of Grid or
beam is out of Grid
its due beam out of grid , shuttering level , plum , grid improved
L : 28- There is some bend in RCC
slab
7.5” 4.5”
In plaster work will be manage
Staircase profile beam is still not resting
on the wall which was marked by
Bijendra in previous site visit
Plinth protection shouldn’t be this
much thick and it should be uniform for
all buildings
Electric room and Bore pipe at front park
should be finished properly as these have
impact on overall appearance of the site.
Conclusion :
4. Brick work should aligned with RCC beams as it required more plaster work in
finishing if beams, columns and walls are not aligned which led to surface cracks
and reduction in carpet areas.