This document provides a breakdown of costs for constructing a 15x15 meter mosque. It includes estimated costs for various construction materials, labor, and other expenses. The costs are broken into categories like earthworks, masonry, electrical work, painting and more. Labor is the largest single cost item.

Uploaded by

Rdbb Ridwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
2K views

Rab Masjid

This document provides a breakdown of costs for constructing a 15x15 meter mosque. It includes estimated costs for various construction materials, labor, and other expenses. The costs are broken into categories like earthworks, masonry, electrical work, painting and more. Labor is the largest single cost item.

Uploaded by

Rdbb Ridwan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

RAB MASJID 15X15 METER

Satuan Pekerjaan
No Jenis Pekerjaan
Volume Sat. Harga sat. Jumlah Bobot
A PEKERJAAN PERSIAPAN
1 Pekerjaan persiapan 500 m2 Rp 10.000 Rp 5.000.000 0,29%
2 ember cor 80 bh Rp 10.000 Rp 800.000 0,05%
3 Pekerjaan pengukuran dan bowplank 90 m1 Rp 30.000 Rp 2.700.000 0,16%
Sub Total Rp 8.500.000 0,50%
B PEKERJAAN TANAH
1 Galian pondasi 54 m3 Rp 200.000 Rp 10.800.000 0,64%
2 Urukan tanah peninggi elevasi lantai 50 CM 120 m3 Rp 300.000 Rp 36.000.000 2,12%
Sub Total Rp 46.800.000 2,75%
C MATERIAL
1 BATU GUNUNG 60 M3 Rp 400.000 Rp 24.000.000 1,41%
2 PASIR 150 M3 Rp 400.000 Rp 60.000.000 3,53%
3 batu pecah cor 1/2 35 M3 Rp 350.000 Rp 12.250.000 0,72%
4 SEMEN 40kg 1.300 ZAK Rp 55.000 Rp 71.500.000 4,21%
5 DINDING HEBEL 80 KUBIK Rp 750.000 Rp 60.000.000 3,53%
6 LEM HEBEL 80 ZAK Rp 120.000 Rp 9.600.000 0,56%
7 Besi 8 120 BTG Rp 63.000 Rp 7.560.000 0,44%
8 Besi 10 450 BTG Rp 94.000 Rp 42.300.000 2,49%
9 BESI 12 250 BTG Rp 140.000 Rp 35.000.000 2,06%
10 KAWAT BENDRAT / roll 25kg 3 ROLL Rp 500.000 Rp 1.500.000 0,09%
11 Kayu bekisting balok 5/7 panjang 4 meter 300 BTG Rp 20.000 Rp 6.000.000 0,35%
12 plywood 9mm 80 Lembar Rp 125.000 Rp 10.000.000 0,59%
13 PAKU UKURAN 5/7/10 50 KG Rp 22.000 Rp 1.100.000 0,06%
14 PRALON RUCIKA PVC 1/2" AW 30 BTG Rp 31.500 Rp 945.000 0,06%
15 PRALON RUCIKA PVC 2" D 10 BTG Rp 142.300 Rp 1.423.000 0,08%
16 PRALON RUCIKA PVC 3" D 10 BTG Rp 223.800 Rp 2.238.000 0,13%
17 SAMBUNGAN PRALON DLL 1 LS Rp 1.000.000 Rp 1.000.000 0,06%
18 KLOSET duduk 2 BH Rp 3.000.000 Rp 6.000.000 0,35%
19 KRAN AIR 21 BH Rp 50.000 Rp 1.050.000 0,23%
20 FLOOR DRAIN (AVUR) 4 BH Rp 50.000 Rp 200.000 0,01%
Sub Total Rp 353.666.000 19,56%

D PEKERJAAN GRC DAN KUBAH


1 KUBAH ENAMEL DIAMETER 8 METER 1 SET Rp 300.000.000 Rp 300.000.000 17,65%
2 BATU ALAM 2 WARNA TAMPAK LUAR FULL 400 m2 Rp 180.000 Rp 72.000.000 4,24%
3 LISPLANK GRC SERUT 90 m1 Rp 800.000 Rp 72.000.000 16,00%
4 Krawangan 128 m2 Rp 800.000 Rp 102.400.000 6,02%
5 GRC krawangan buntu / masif tempel 60 m2 Rp 800.000 Rp 48.000.000 2,82%
Sub Total Rp 594.400.000 46,73%
E PEKERJAAN PLAFOND PVC
1 Pekerjaan rangka besi hollow 1x40.40.2mm, modul 60 x 60 cm, plafon 225 m2 Rp 80.000 Rp 18.000.000 1,06%
2 Plafond pvc 225 m2 Rp 120.000 Rp 27.000.000 1,59%
3 Tenaga pasang plafond 225 m2 Rp 60.000 Rp 13.500.000 0,79%
Sub Total Rp 58.500.000 3,44%
F PEKERJAAN KUSEN DAN PINTU
1 PINTU P1 6 bh Rp 5.000.000 Rp 30.000.000 1,76%
2 PINTU P2 pintu ukir motif nabawi 1 set Rp 30.000.000 Rp 30.000.000 1,76%
3 PINTU P3 1 bh Rp 3.500.000 Rp 3.500.000 0,21%
4 PINTU P4 1 bh Rp 3.000.000 Rp 3.000.000 0,18%
5 JENDELA J1 3 bh Rp 3.000.000 Rp 9.000.000 0,53%
Sub Total Rp 75.500.000 4,44%
G PEKERJAAN KERAMIK
1 GRANIT 60X60 225 m2 Rp 150.000 Rp 33.750.000 1,99%
2 KERAMIK gudang & marbot 22 m2 Rp 90.000 Rp 1.980.000 0,12%
3 Kramik Lantai KM / WC 20/20 27 m2 Rp 90.000 Rp 2.430.000 0,14%
4 Kramik dinding KM / WC 20/25 60 m2 Rp 90.000 Rp 5.400.000 0,32%
Sub Total Rp 43.560.000 2,56%
H PEKERJAAN LISTRIK
1 Lampu LED 18 W + assesories 34 BH 200.000 Rp 6.800.000 0,40%
2 Lampu gantung 2 BH 10.000.000 Rp 20.000.000 1,18%
3 Lampu taman 4 BH 2.500.000 Rp 10.000.000 0,59%
4 Saklar Tunggal 5 BH 70.000 Rp 350.000 0,02%
5 Saklar Seri 8 BH 70.000 Rp 560.000 0,03%
6 Stop Kontak 7 BH 70.000 Rp 490.000 0,03%
7 Instalasi kabel 60 titik 80.000 Rp 4.800.000 0,28%
8 MCB 2 250.000 Rp 500.000 0,03%
Sub Total Rp 43.500.000 2,56%

I PEKERJAAN PENECATAN
1 Pekerjaan pengecatan dinding dulux 4 PIL 25K5 Rp 2.500.000 Rp 10.000.000 0,59%
Sub Total Rp 10.000.000 0,59%
J MOBILISASI
1 MOBILISASI DAN LAIN LAIN 1 SET Rp 15.000.000 Rp 15.000.000 0,88%
Sub Total Rp 15.000.000 0,88%
K TENAGA KERJA
1 TENAGA KERJA 225 m2 Rp 2.000.000 Rp 450.000.000 26,47%
Sub Total Rp 450.000.000 26,47%
JUMLAH Rp 1.699.426.000 100%
DIBULATKAN Rp 1.700.000.000 100%