Building Attachment Report
Building Attachment Report
“INDUSTRIAL ATTACHMENT REPORT DONE FROM 11TH JUNE TO 24TH AUGUST 2019
IN MULOT SOGOO PROPOSED ROAD CONSTRUCTION”
I,NGENO KKIPNGENO CHARLES hereby declare that the present industrial attachment
report held at Expand Engineering Services Ltd during Mulot Road construction in Narok
county .It is my own work which has neither been submitted nor presented anywhere for the
same purpose. I also declare that this Industrial Attachment Report submitted to Sot Technical
Training in BULDING AND CONSTRUCTION TECHNOLOGY is my own work and has
never been presented or submitted for a similar Award to neither any University nor College
nor other Institute of higher learning.
Signature: …………………...
i
DEDICATION
This Report is dedicated to the following persons who without them the training could not be
successfully completed. Materially, intellectually, physically and financially contributed to
make the training a success:
Almighty God who enables in my studies
My dearest parents who encourage and support me in all my studies
My beloved Sister and my brothers
My Wife
My fellow colleagues and classmates
The technical manager and all staff of EES Ltd
ACKNOWLEDGEMENTS
First of all, I am thankful the Almighty God for the opportunity of a memorable fruitful period in
EES Ltd and the endless kindness that makes my studies success fully.
I would like to thank SOIN BULDERS LTD Staff particularly my Department of CIVIL AND
BULDING TECHNOLOGY for providing and equipping me with the practical and theoretical
experiences that are leading me in BULDING AND CONSTRUCTION
TECHNOLOGYprofession, I specially thank Mr. Sonyo, the industrial attachment coordinator.
I am also grateful to the Kenya Government who sponsored my undergraduate studies through
REB and BRD Ltd.
It is my pleasure to thank and express our appreciations and gratefulness to my site supervisor
the technical manager of EES Ltd Eng. It was my pleasure to work under their
guidance.
My thanks are extended to technicians, masons, carpenters, steel benders for their collaboration
and cooperation to equip me with practical skills.
With greatest pleasure, I would like to extend my thanks to the authors of the books and
e-documents I used to write this report are highly acknowledged.
ABSTRACT
Industrial attachment is one of the main courses in BULDING AND CONSTRUCTION
TECHNOLOGYprogramme. The period of the training was ten weeks started at 11th
June to the 24th August 2018.
The purpose of this course is to apply the class theoretical knowledge into real practical work.
There was two main parts in my training the first part was practical part and the second part
was office work. The student can be trained as site engineer; it gives opportunity to
supervise the construction work closely, or as design engineer using software programs such
as AutoCAD, ArchiCAD, and Microsoft Excel in BULDING AND CONSTRUCTION
TECHNOLOGYproject.
In order to comply the industrial attachment objectives, I gained and learnt more from my
summer internship.
I participated in all technical works done at construction site include site preparation;
interpretation of technical drawings; building setting out; rebar reinforcement works such as
cutting, bending, reinforcement binding of structural members; footing and foundation
excavations; carpentry works such as formwork preparation, scaffolding; quality assurance
and quality control of concreting operations such as volumetric batching, concrete
ingredients mixing, transportations, placing into well prepared formworks, compactions
with the aim of consolidating fresh concrete to remove void and avoiding bleeding and
segregation, curing with aim of achieving cement hydration which leads to the strength of
concrete, removal formwork and finishes; stone and brick masonry works; checking quality
of construction materials; human resources management; site management; practical skills
of using tools and equipment at construction site.
During my internship, I also increased knowledge about team work skills, time management
skills, working under pressure, meeting with deadline, multitask management.
Industrial attachment played great role in my studies where I practiced the class theoretical
knowledge. So, I am hopeful and confident that the future will be bright in my career of
BULDING AND CONSTRUCTION TECHNOLOGYprofession.
TABLES OF CONTENTS
DECLARATION.........................................................................................................................................i
DEDICATION............................................................................................................................................ii
ACKNOWLEDGEMENTS......................................................................................................................iii
ABSTRACT..............................................................................................................................................iv
TABLES OF CONTENTS.........................................................................................................................v
LIST OF TABLES...................................................................................................................................vii
LIST OF FIGURES................................................................................................................................viii
LIST OF APPENDICES...........................................................................................................................xi
2.1.2.2 Bricks...............................................................................................................................18
2.1.2.3 Cement.............................................................................................................................20
2.1.2.4 Aggregates........................................................................................................................21
2.1.2.5 Water................................................................................................................................22
2.1.2.7 Paints................................................................................................................................23
2.1.2.7 Timber..............................................................................................................................23
Trusses fabrication...........................................................................................................................49
5.1 Conclusion......................................................................................................................................52
5.2 Recommendations..........................................................................................................................52
REFERENCES.........................................................................................................................................53
APPENDICES..........................................................................................................................................54
LIST OF FIGURES
FIGURE 1: ORGANIZATION STRUCTURE OF BUILDING TEAM (DORAN, 2009)...........................................................4
FIGURE 2: SOME OF BUILDING COMPONENTS..................................................................................................................7
FIGURE 3: VENTILATION STRUCTURE................................................................................................................................7
FIGURE 4: BRICK MASONRY WORKS FOR WALLS...............................................................................................................9
FIGURE 5: RAT STRAP BOND (MULLER, 2004)..................................................................................................................10
FIGURE 6: BRICK MASONRY BONDS (DORAN, 2009)....................................................................................................11
FIGURE 7: FOUNDATION STONE MASONRY.....................................................................................................................11
FIGURE 8: REMOVAL OF FORMWORKS............................................................................................................................14
FIGURE 9: TYPICAL PROFILE BOARDS FOR SETTING OUT (GREENO R. C., 2007) (MULLER, 2004)...........................15
FIGURE 10: BRICK JOINTS (GREENO R. C., 2007).............................................................................................................16
FIGURE 11: BUILDING STONES........................................................................................................................................17
FIGURE 12: BRICK MATERIALS......................................................................................................................................... 19
FIGURE 13: THE AVERAGE REDUCTION OF STRENGTH IN MIX AS A RESULT OF STORAGE (MULLER, 2004)....................21
FIGURE 14: TIMBER USED TO MAKE FORMWORKS.........................................................................................................23
FIGURE 15: THE BOX AND WHEEL BARROW OF VOLUME BATCHING (DUGGAL, 2008)................................................26
FIGURE 16: CORRECT AND INCORRECT OF CONCRETE PLACING (GAMBHIR, 2006)........................................................27
FIGURE 17: PLACING OF CONCRETE IN FORMWORK.......................................................................................................28
FIGURE 18: SKETCH SHOWING BINDING TOGETHER OF BARS WITH 1.25MM SOFT IRON WIRE (COBB, 2004)..............30
FIGURE 19: STIRRUPS...................................................................................................................................................... 32
FIGURE 20: STEEL TRUSSES STRUCTURES (COBB, 2004)................................................................................................33
FIGURE 21: PAD FOUNDATION-ISOLATED FOOTING (GREENO R. C., 2004).....................................................................34
FIGURE 22: STATER BARS (ARYA, 2009)...........................................................................................................................35
FIGURE 23: COMBINED FOOTING (GREENO R. C., 2004)...............................................................................................35
FIGURE 24: STRAP FOOTING (ULLAH, 2018)....................................................................................................................36
FIGURE 25: RETAINING WALLS (GREENO R. C., P. 81)................................................................................................36
FIGURE 26: HATCHING SYMBOLS ON STRUCTURAL DRAWINGS (COBB, 2004)............................................................39
FIGURE 27: TYPICAL DETAILING SECTION OF CLASS ROOM......................................................................................40
FIGURE 28: TYPICAL SECTION................................................................................................................................. 40
FIGURE 29: SITE TOOLS AND EQUIPMENT (SOURCE: INTERNET)...................................................................................42
FIGURE 30: CAD DRAFTING.............................................................................................................................................43
FIGURE 31 WHEEL BARROW................................................................................................................................... 43
FIGURE 32: SITE WORKS..................................................................................................................................................46
FIGURE 33: SITE WORKS......................................................................................................................................... 47
FIGURE 34: SURVEY MAP................................................................................................................................................ 48
FIGURE 35: STEEL REINFORCEMENT WORKS...................................................................................................................49
FIGURE 36: TRUSS........................................................................................................................................................... 49
FIGURE 37: CARPENTRY WORKS......................................................................................................................................50
FIGURE 38: MASONRY WORKS........................................................................................................................................50
LIST OF SYMBOLS AND ABBREVIATIONS
As max: maximum reinforced area
As min: minimum reinforced area
ASTM: American Society for Testing and Materials
BRD: Banque ise pour la Development/ Development Bank of
BS: British Standard
C.G: Centre of Gravity
c/c: centre to centre
CA: Coarse Aggregate
CAD: Computer Aided Design
CE: Civil Engineering
CIVIL AND BULDING TECHNOLOGY: Civil, Environmental and Geomatics Engineering
CHAP.: Chapter
CST: College of Science and Technology
cum: cubic meter
EAR: Eglise Anglican au / Anglican Church of
EES Ltd: Expand Engineering Services Ltd
Eng.: Engineer
EP: Ecole Primaire
FA: Fine Aggregate
FM: Fineness Modulus
fy: yield strength of steel
IA: Industrial Attachment
IS: Indian Standard
Ltd: Limited
QA: Quality Assurance
QC: Quality Control
RCC: Reinforced Concrete Cement
RCD: Reinforced Concrete Design
KEB: Kenya Education Board
Reg.No. Registration Number
UR: University of
LIST OF APPENDICES
1
To provide recommendation on how problems met in organization can be solved.
2
Finally, to prepare the practical training report showing how the student understands
activities are accomplished in an organization.
1.3 Industrial pre-requisites
Usually, participating in any kind of training requires some important basic knowledge. In
department of CIVIL AND BULDING TECHNOLOGY, students should have
completed the third year and have a theory knowledge from class related to training
course that will help them to easily understand what are going on to the site. The
students should have communication skills, time management skills, teamwork skills
and to meet with deadline. The following are BULDING AND CONSTRUCTION
TECHNOLOGYcourses that are pre-requisite to my industrial attachment:
Basic construction technology
Construction materials
Engineering surveying
Concrete technology
Foundation engineering
Design of reinforced concrete structures I&II
Design of steel and timber structures
CAD design and analysis (AutoCAD and ArchiCAD)
Elements of quantity surveying
Strength of materials
Structural analysis I&II
Soil mechanics
These modules are based on the principles that are used during training period. The training site
where I had conducted my internship had the most of requirements for me to achieve the
objectives and goals of the training. The knowledge of languages is also play great role in
the industrial attachment, during the works, I have met with difference people to be
communicated in the French language.
1.4 Site selection
My site selection was firstly based on my desire and curiosity about building construction.
Building construction combines many class modules which are fundamental theoretical
knowledge required to be applied into practical experience of the BULDING AND
CONSTRUCTION TECHNOLOGYas a career. From this perspective I chose to apply to
the local BULDING AND CONSTRUCTION TECHNOLOGY Company that shares
nearly all its practice with the majority of other firms in the country. This influenced
My decision of working on a construction site under the supervision of a site engineer of
EES Ltd. I also wished to use that opportunity to gain more knowledge in construction
works. Hence, I chose to work with EES Ltd which is a construction company and was
executing construction of road construction at bigger sector. It has always been my dream
to be involved on site works where I have to take some responsibilities. I had already
studied some subjects related to building constructions. Hence, I wanted to match the
theory learnt in class and how applied on the site.
1.5 Training benefits and motivation
It is commonly planned for qualified graduates to be competitive and motivated when they are
looking for job opportunities, training helps them to open their mind and relate theoretical
knowledge in practical skills, on my side I chose to work with construction of building
due to the following motivation:
➢ To get the opportunity of improving professional knowledge
➢ To develop skills about the application of theory to practical work,
➢ To get skills and techniques which allow me to develop my career, served as a key to
develop professional behaviours and social skills;
➢ To be familiar in adjusting from university lifestyle to full-time employment, and
to participate actively in accomplishing goals and objectives of an organization
while conducting the practical training and to acquire basic knowledge and new
skills.
CHAP 2. LITERATURE REVIEW
2.1. Class theories related to the site training
2.1.1 Construction Technology
It is specifically focusing on the practical implementation level and provides a wide range of
essential information to communicate to masons and supervisors during theoretical and on
the job trainings.
2.1.1.1 Building team and their duties and responsibilities
Building Team is a team of efforts in which each of them has an important role to play.
Organizational structure of a building team
Building owner: The employer is the organization or person who commissions the works
and pays the bills. The employer usually appoints a representative to organize the works
on his behalf.
Architect: Engaged by the building owner as his agent to design, advice and ensure that
the project is kept within cost and complies with the design.
Engineer: On any one contract there may be a number of engineers with varying amounts
and types of experience. The duties and responsibilities of a senior engineer are
Typically, as follows:
➢ Ensure accurate setting out and levelling of the works in accordance with the drawings
and specification;
➢ Inspects construction materials to see that they conform to specifications;
➢ Ensure quality control and testing of work and materials is carried out in accordance
with the specification requirements;
➢ Acting as the main technical advisor, direct and supervise day to day operations of
sub- contractors when required, resolving any technical issues that may arise;
➢ Produce Site Diaries and Allocation Sheets;
➢ Deliver the works safely and to deadline;
➢ Maintain compliance with the safety-assurance plan so that work is accomplished in an
environmentally sound manner using safe work practices;
➢ Ensure equipment and manpower resources are being used efficiently;
➢ Provide input into the scheduling of projects to meet the client’s required deadline
and maintain construction resources to acceptable levels;
➢ Responsible for progress and monitoring of all civil works including
substructure, superstructure and foundations;
➢ Oversee construction of the site village;
➢ Utility Authority liaison;
Hence, it is on site engineer to inspect the activities/work on construction site and
ensure that everything is going as per the schedule, plan & design.
Quantity Surveyor: Typical tasks are:
➢ Commercial oversight of site;
➢ Preparation of financial reports, budgets and forecasts;
➢ Application of health and safety requirements;
➢ Insurance cover (quotations and implications);
➢ Fixing new rates for additional works;
➢ Measurement of work done and verification of compliance with specified requirements.
Site Agent: Employed on large contracts and he represents the engineer on site, and controls the
supply of materials.
Contractor: Employed by the building owner on the architect's advice to carry out the
construction
Works and he takes his instructions from the architect.
Doors and windows: The main function of doors in a building is to serve us a connecting
link between internal parts and also to allow the free movement outside the building.
Windows are generally provided for the proper ventilation and lighting of a building.
Lintels: Actual frame of door or window is not strong enough to support the weight of the wall
above the strong enough to support the weight of the wall above the openings and a separate
structural element has, therefore to be introduced. This is known as lintel and is similar to a
beam.
Roofs: A roof is the uppermost part of the building whose main function is to enclose the
space and to protect the same from the effects of weather elements such as rain, sun, wind, heat,
snow etc.
DPC: damp proof course is a layer of waterproofing materials like asphalt, bitumen, waterproof
cement etc. on which the walls are constructed.
Walls: Walls are the vertical members on which the roof finally rests. Walls are provided to
divide the floor space in the desired pattern. Walls provide privacy, security, and protects
from the sun, rain wind, cold etc.
Column: Columns are the isolated load bearing member which carry the axial compressive
load of a structure.
Plinth: The Portion of a building between the ground surrounding the building and the top floor
just above the ground is termed as plinth. Plinth is provided to prevent the surface water
from entering the building.
Building finishes: Building finishes include items like plastering, pointing, washing,
varnishing, painting, distempering etc.
Building services: Building services include services like water supply, drainage, lighting,
sanitation, electricity, acoustics, ventilation, heating, air conditioning, fire detection, and
control etc.
Stretcher bond (also known as running bond or monotonous stretcher bond) is the most
common
Bond in modern times, as it is easy to lay, with little waste.
Header bond: Consists of headers in every course.
English bond (Block Bond): This bond is made up of alternating courses of stretchers and
headers. This produces a solid wall that is a full brick in depth.
Flemish Bond (Mix Bond :) It is created by alternately laying headers and stretchers in a
single course. The next course is laid so that a header lies in the middle of the stretcher in
the course below. Again, this bond is one brick thick.
Monk Bond: A variant of Flemish (block) Bond with two stretchers between the headers in
each row, and the headers centered over the joint between the two stretchers in the row
below.
Cross Bond: Bond consisting of alternate courses of headers and stretchers with an
interceptive header on every second stretcher course.
Figure 9: typical profile boards for setting out (GREENO R. C., 2007) (Muller, 2004)
Methods of setting out a right angle building
➢ Typical builders square or steel square method
➢ 3 – 4 – 5 method or Pythagoras theorem
➢ Levelling instruments.
➢ Prismatic square method
2.1.1.10 Jointing and pointing
According to (GREENO R. C., 2007). These terms are used for the finish given to both the
vertical and the horizontal joints in brickwork irrespective of whether the wall is of brick,
block, solid or cavity construction.
Jointing: is the finish given to the joints when carried out as the work proceeds?
Pointing: is the finish given to the joints by raking out to a depth of approximately 20 mm and
filling in on the face with a hard-setting cement mortar, which could have a color additive?
2.1.2.3 Cement
Cement is a pulverized material that develops binding forces due to a reaction with water.
Density of cement is 1440kg/m3, 1bag of cement=50kg.
Physical Properties of Portland Cement according to (GAMBHIR, 2006)
Fineness: the fineness of a cement is a measure of the size of the particles of the cement.
Fineness of cement is also important; it affects: rate of hydration, rate of setting, rate of
hardening, durability (ASR). As per IS specifications the residue of cement should not
exceed 10%when sieved on 90micron IS sieve.
Setting time:
The setting time of cement when tested shall be as follows:
Initial setting time: the time at which cement pastes loses plasticity. It is not less than 30 min.
Final setting time: the time at which paste becomes hard mass. It is not more than 10 hours.
Soundness
The cement when tested for soundness shall not have an expansion of more than 10mm.
Field test according to (SHETTY, 2005)
It is important that you carry out field tests of your cement sample before use on your sites
to know if the cement is good or bad. You can carry out these field tests as follows:
When you put your hand into a bag of cement, you will receive a cool feeling;
To check manufactured and expired dates to comply cement age;
When you open a bag of cement, take a careful look at the cement powder;
The cement powder should not have any visible lumps;
The color of Ordinary Portland Cement powder is greenish-grey;
When you take a pinch of cement powder and feel it between your fingers, the
cement should give a smooth feeling;
When you take a sample of cement powder and throw it inside a bucket full of water, the
cement particles should first float for some time before they sink into the bucket.
The above tests should satisfy the engineer to agree that the cement sample is good.
Cement storage
Cement can be safely stored in bags for a few months if kept in a dry room. Paper bags are
better for storing than jute bags because paper bags perform better in regard to quality
deterioration due to moisture. Cement bags should be stored on a raised wooden platform
(e.g. timber pallets) about 15 to 20 cm above the floor level and about 30 to 50 cm away
from walls. The cement stack should not be more than 10 bags high. The bags should be
placed close together to reduce circulation of air. A cement bag should never be opened
until its immediate use for mixing. Ordinary Portland cement, which has been stored for
over six months, should not be used for masonry work. Ordinary Portland cement, which
has been stored for over six months, should not be used for masonry work.
The average reduction of strength in mixes a result of storage
1 Fresh cement strength 100%
2 Cement after 3 months Strength reduced by 20%
3 Cement after 6 months Strength reduced by 30%
4 Cement after 12 months Strength reduced by 40%
5 Cement after 24 months Strength reduced by 50%
Figure 13: The average reduction of strength in mix as a result of storage (Muller, 2004)
2.1.2.4 Aggregates
Sand/fine aggregates (FA)
Sand is an important building material used in the preparation of mortar, concrete, etc.
Aggregate passing through 4.75 mm sieve are defined as fine. They may be natural sand
deposited by rivers, crushed stone sand obtained by crushing stones and crushed gravel
sand. The smallest size of fine aggregate (sand) is 0.06 mm.
Coarse aggregates (CA)
Aggregate retained on 4.75 mm IS sieve are identified as course. They are obtained by natural
disintegration or by artificial crushing of rocks. The maximum size of aggregate can be 80
mm. The size is governed by the thickness of section, spacing of reinforcement, clear cover,
mixing, handling and placing methods. For economy the maximum size should be as large
as possible but not more than one-fourth of the minimum thickness of the member. For
reinforced sections the maximum size should be at least 5 mm less than the clear spacing
between the reinforcement and also at least 5 mm less than the clear cover.
Fineness Modulus (FM)
According to (Duggal, 2008) Fineness modulus is a numerical index of fineness, giving some
idea on the mean size of the particles present in the entire body of the aggregates. The sum
of cumulative percentages retained on the sieves divided by 100 give the fineness modulus.
The sieves that are used in sieve analysis are conformed as per IS 2386 (Part-I)1963, are
80mm, 40mm, 20mm, 10mm, 4.75mm, 2.36mm, 1.18mm, 600µm, 300µm, 150µm.
FM for FA varies between 2.0 to 3.5
FM for CA varies between 5.5 to 8.0
FM for all in aggregates varies between 3.5 to 5.5
Figure 15: The box and wheel barrow of volume batching (Duggal, 2008)
Mixing: The object of mixing is to make the concrete mass homogeneous and uniform in color
and consistency. All the aggregate particles should have a coat of cement paste and all the
Ingredients of the concrete should blend into a uniform mass. The mixing is done either by hand or
by machine called mixer.
Hand mixing: It is used for small jobs. Hand mixing is done over an impervious floor.
Machine mixing: For quality works mixing is carried out by mixer. Mixers can be broadly
classified as batch mixer and continuous mixers.
Transportating: Concrete should be transported to the place of deposition at the earliest without
the loss of homogeneity obtained at the time of mixing.
Placing: To achieve quality concrete it should be placed with utmost care securing the homogeneity
Achieved during mixing and the avoidance of segregation in transporting. The concrete
should be place and compacted before its setting starts. Before concrete is placed in
position, formwork should thoroughly be checked for its stiffness and trueness. The
method of placing concrete should be such as to prevent segregation. It should not be
dropped from a height more than one meter.
Figure 17: placing of concrete in formwork © photo taken by phone camera at site
Compaction: The object of this is to remove air holes and to achieve maximum density.
Compaction also ensures intimate contact between concrete and reinforcement and other embedded
parts. To obtain maximum density, the mix design should produce a mix of adequate workability
(consistence) to suit the dimensions of the section
Hand compaction: Hand compaction is done with the help of steel tamping rods, or timber
screeds. Narrow and deep members are compacted with tamping rods. This method of compaction
is used for small and unimportant jobs. However, this method is extremely useful for thin elements
such as slabs, and for members with congested reinforcements.
Compaction by vibrator: This is the most common and widely used method of compacting
concrete for any structural
Element. The vibrations imparted to the fresh concrete reduce the internal friction between the
particles of concrete by setting the particles in motion and thus produce a dense and compact
mass. Formwork vibrators are used for concreting columns, thin walls and precast units.
These are
Rigidly clamped to the formwork, causing it to vibrate and consequently transfer the
vibrations to concrete.
Curing of concrete: When the water added to the cement chemical reactions take place
(hydration of cement) which result the setting and hardening of cement.
Setting time of concrete according to (SHETTY, 2005)
Setting time of concrete differs widely from setting time of cement. Setting time of
concrete does not coincide with the setting time of cement with which the concrete is
made. The setting time of concrete depends upon the w/c ratio, temperature conditions,
type of cement, use of mineral admixture, use of plasticizers–in particular retarding
plasticizer.
2.1.4 R.C Structures
R.C elements are as follows:
Beams
Horizontal members carrying lateral loads.
Slabs: horizontal plate elements carrying lateral loads, the minimum thickness of slab is 125mm.
Columns
The minimum number of steel bars in square or rectangular column is 4.
The minimum number of steel bars in circular column is 6.
Lapping length for compression member is times fifty diameter of steel bar.
Lapping length for tension member is forty times diameter of steel bar.
Lap length considering M20 grade of concrete. D is diameter of bars to be slapped
together, Columns (45D); beams (60D) and slabs (60D).
Figure 18: Sketch showing binding together of bars with 1.25mm soft iron wire (Cobb, 2004)
Clear cover to the main reinforcement
S/N R.C Elements Clear cover in mm
1 footings 50
2 beams 25
3 Raft foundation on top 50
4 Raft foundation on bottom/sides 75
5 columns 40
6 slabs 15
7 Flat slab 20
8 Stair case 15
9 Retaining wall 20/25 on earth
10 Water retaining structures 20/30
11 Shear wall 25
Table 8: Clear cover to the main reinforcement (Ullah, 2018)
Why Stirrups are used in Beam & Column Construction? purpose of Stirrups
Stirrups are provided to hold the main reinforcement rebars together in an RCC structure.
Stirrups are placed at proper intervals to beams and columns to prevent them from buckling.
Also, they protect RCC structures from collapsing during seismic activities (earthquakes).
Combined footing: When two or more columns are supported by a footing it is called
combined footing. This footing may be of rectangular or trapezoidal in plan. Combined
footing is provided under following situations.
When columns are close to each other and their individual footings overlap.
Soil having low bearing capacity and requires more area under individual footing.
The column end is situated near the property line and the footing can not be extended.
Strap Footing: In such footing, the outer and inner column is connected by a strap beam, does
not transfer any load to the soil. The individual footing areas of the columns are so arranged
that the C.G of the combined loads of the two columns pass through the C.G of the two
footing areas. Once this criterion is achieved, the pressure distribution below each individual
footing will be uniform.
Figure 24: Strap Footing (Ullah, 2018)
Mat Foundation: This foundation covers the entire area under the structure. This foundation
has only RCC slab covering the whole area or slab and beam together. Mat foundation is
adopted when heavy structures are to be constructed on soft made-up ground or marshy sites
with uncertain behavior. Mat foundation is also known as raft foundation.
Retaining walls
All retaining walls must be properly designed and construction details provided by
the engineer. Construction must be in accordance with the specified requirements.
Take particular care with backfilling and back drainage which can cause severe
instability if not carried out properly.
Table 10: The quantities of concrete materials per cum (Haroo, 2015)
The weight of steel bars
1.54*1 3
Cement= 0.385m
11
2
Since, density of cement=1440kg/m3, cement weight=0.385*1440=)554.4kg
The number of cement bags=554.4/50=11.088bags (approx. 11bags)
The number of bricks in brick masonry work
The dimension of modular brick is 19x9x9cm (LengthxBreadthxHeight).
The thichness of the mortar in brickwork is 10mm=1cm.
Once the mortar is applied tobrickwork, the dimension of the brick will be chaged to
20x10x10cm. the mortor is formed with cement and sand their ratio.
Initialy, it is required to determine the volume of brick as follow.
Volume of brick =20*10*10cm=0.002m3. now, determine the number of bricks in 1m 3 as
follow: 1/0.002m3=500 bricks.
Now, work out the volume of 1brick devoided of mortar as follow:
Volume of 1 brick without mortar=19x9x9cm=0.001539m 3. now, it is required to volume for
500 bricks in 1m3 as follow. Volume of brick=0.001539m3 so, for 500bricks, the volume
will be =500*0.001539=0.7695m3 so, volume of mortar in 1m3=1-0.7695=0.2305m3
When the mortar is wet at that time,so, the output is in wet volume. It is required to comvert to
the dry volume 33% is increased when comverted to the dry volume. So,
0.2305x1.33=0.306m3.
2.1.7 CAD and analysis
Hatching symbols on structural drawings
Typical section
Computer: it is used for collecting data and daily recording of labours, reporting the daily work
done, I also used to draft assignment given in CAD during my free time.
© photo taken by
screenshot
Figure 30: CAD drafting
Pliers: used for cutting steel wire and fixing it on the steel bars and stirrups
Plumb bob: it is used to verify the wall verticality for high walls by maintaining the distance
from the wall to its suspending cable.
Welding machine: this machine was used to weld different metal for temporally or permanent
works
Wood saws: used for cutting the timbers.
Steel saws: used for cutting steel bars.
Wheelbarrow: It is used for transporting materials such as flesh concrete Sand, aggregate,
cement, water: used for making concrete and mortar
. Photo at site
Figure 31 Wheel barrow
3.3 Exposure of the used methodology
3.3.1 Site visit
After my industrial attachment, I visited Reserve Force at Rulindo District, Base Sector where
it was executing feeder road construction works. I got more practical skills how to
construction feeder road (Lateritic road Base-Cyondo road) include excavation works with
excavators, road surveying works, levelling and grading with graders, compaction, drainage
diches construction, bridge, gabions and culverts construction. I also visited site of 7 road
construction construction works at EP Nyenyeri, Gisenyi sector, Gakenke District.
3.3.2 Required training information and data collection
During training, the purpose of my Industrial Attachment was to match the class theories with
practical skills and social information on the site. This was achieved through many ways and
processes including observations, studying, Documentations and self-orientation guided by the
supervisor.
3.3.2.1 Observation method
The field conditions, complexity, schedule, communications and quality of construction were
determined by the frequency and duration of construction observations.
©Photo at site
©Photo at
site
©Photo at
site
©Photo at site