0% found this document useful (0 votes)
51 views44 pages

Standard BOQ & Specfications

The document provides a bill of quantities for construction projects including a generator house, water point, and public fountains. It lists various construction items, units of measurement, quantities, and costs. The generator house section includes excavation, masonry, concrete, wall, roofing, and door/window work. The water point section lists similar earthwork, concrete, masonry, and pipework items. Public fountains construction is also outlined.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
51 views44 pages

Standard BOQ & Specfications

The document provides a bill of quantities for construction projects including a generator house, water point, and public fountains. It lists various construction items, units of measurement, quantities, and costs. The generator house section includes excavation, masonry, concrete, wall, roofing, and door/window work. The water point section lists similar earthwork, concrete, masonry, and pipework items. Public fountains construction is also outlined.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLS, PDF, TXT or read online on Scribd
You are on page 1/ 44

Bill Of Quantity of Generator & guard house (4.5 x 6.

0 m)

I.No Description of Works Unit Qty Rate Amount


1 Excavation &Earth Works

1.1 Site clearing to anaverageg depth of 20 cm to remove


top soil & Grubbing m2 65

1.2 Excavation for foundation trench to a depth of not


exeeding 100 cm below stripped ground level m3 16

1.3 Back filling around a foundation with good dry filling


material from the site m3 5

1.4 Back filling under a hard core with good and approved
selected material aroundthe site well rammed and
compacted in layers not exeeding 20cm m3 5

1.5
cart away suplus material to a distance of 100m m3 35

1.6 Placing 25cm thick basaltic or equivalent stone hard core


well rolled andconsolidated & blinded with crushed
stone m3 8
2 Masonry work

2.1 Construction of 40 cm thick basaltic or equivalent


masonry foundation wall to adepth of 70 cm blow
stripped level blended & joined in cement mortar of 1:3 m3 7.5

2.2
Construction of 40 cm thick basaltic or equivalent
masonry foundation wall toa height of 35 cm above
ground levelblended & joined in cement mortor1:3 m3 4

2.3 Pointing the external wall surface of the foundation with


cement mortar 1:3 m2 8
3 concrete work

Casting 50 mm thick Lean Concrete Grade C-10, with


3.1
min. cement contentof 150 Kg / m3 of concrete over the
Hard Core m2 25

Casting 50 cm thick reinforced concrete for Generator


3.2
Seat (Basement) withGrade C-20 Concrete with
minimum cement content of 320 kg / m3 cost
includssupply & Installation of Re-bar and approved
Anchor Bolts and Formwork fixing m3 1.5
Sub Total - Carried Forward

Page 1 of 44
Bill Of Quantity of Generator & guard house (4.5 x 6.0 m)

I.No Description of Works Unit Qty Rate Amount


Sub Total - Brought Forward

3.3 Casting 15 cm thick Mass Concrete of Grade C-20, with


minimum cement of 320 Kg / m3 of concrete over Lean
Concrete withTemprature Reinforcement m3 3

3.3 Supply, Cut, Bend & fixing Reinforecment bar DN10


mm spaced @ 200 mm Kg 25

3.4
Supply, cut & fixing in positions sawn wooden
formworks or equavalentproperly erected and struted
with posts & Slings having tight joint not to bleed m2 2.5
4 Wall work

4.1 Construction of corrugated galvanisediron sheets wall


made of G-32 Sheet fixed to horizontal eucalyptus
purlins of DN 80 mm spaced 90 cm with roof nail m2 60

4.2 Supply & fixing stand poles diameter DN150 mm


eucalyptus tree anchoredto masonry foundation wall
with C-15 concrete mix 50 cm deep as design m 80

4.3 Supply and fixing horizontal purlins diameter DN 80


mm round eucalyptus tree nailed to Vertical Posts
spaced @ 90 cm on center m 85
5 Roofing

Supply & fixs G-32 G.I.Sheets with roof nail with


5.1 washer fixed to Purlins ofsmooth DN 60 mm
eucalyptustree fixed on trusses members made of
formworks or equavalent DN 150 mm roundeucalyptus
tree spaced @125 cm . LS 1
6 Doors & windows

6.1 "Tid or Equavalent wooden frame lockable doors made


of G-32 CGI sheets ofDouble Leaf type 2.10 m x 1.50 m Pcs 1

"Tid or Equavalent wooden frame lockable windows


6.2 made of G-32 CGI sheets ofDouble Leaf type 1.20 x
1.50 m Pcs 2

6.3 supply & fix mesh wire for insect netting and
ventilation as design 75 cm high ml 8
Total cost For One Generator House

Page 2 of 44
Bill of Quantity for 4-faucet Water point
S.N Description Unit Qty Unit Rate

1 Earth work
Site clearing and striping of top soil to a minimum
1.1 depth of 200) m2 24.2
Bulk excavation for up to a depth of 50cm below site
1.2 clearing for foundation (working space 25cm) m3 6.85
Excavation for foundation, soak away pit and valve
1.3 chamber m3 5.4
Provide, fill and compact selected material in layers of
1.4 150mm,for foundation. m3 6.85
Provide and fill hard core with hard basaltic or
equivalent stone, well compacted and blinded with
1.5 crushed stone m3 3.5
Cart away and dispose all excavated material to
1.6 approapriate distance not exceeding 1Km m3 11.69
2 Concrete Work
2.1 C-15 lean concrete m3 0.3
2.2 C-20 concrete mass concrete m3 2.16
2.3 Concrete cylinder (Dia,1m and Hight,1m) No 1
2.4 Concrete cylinder (Dia, 30cm and Height, 1m) No 1
3 Masonry Work
Provide and construct 400mm thick trychytic masonry
wall grouted and filled with (1:3) mortar for
3.1 foundation and super structure m3 2.37
Plastering to smooth finish for water point wall and
3.2 surface m2 15
Provide and fix in place pre-cast R. concrete water
3.3 seller seats as per the drawing No 1
Masonry pavement around the water point as per the
3.4 drawing (200 mm thick with 1:3 mortar) m2 7.6
4 Pipe work
4.1 Supplying and installing GS pipes
4.2 DN 40 GS pipe (variable) m 6
4.3 DN20 GS m 6
4.4 Supplying and fixing fittings
4.5 Cross tee DN 40 No 1
4.6 Reducer 40x20 No 4
4.7 Tee DN 40 No 1
4.8 DN 40 Bend (elbow) 90 degree No 5
4.9 Faucet DN 20 No 4
4.1 Socket DN 20 No 4
4.1 Gate valve DN 40 No 2
4.1 Union DN 40(variable) No 1
4.1 Nipple DN 40 No 6
Supply and install DN 40 water meter (approved
4.1 quality) No 1
Construct two valve chambers for water meter and gate
valve, covered with 600*550*6mm sheet metal with
4.2 latch and lock as per the drawing No 2
Supply and place boulders, crashed aggregate and sand
4.2 to form the soak away as per the drawing m3 0.32
Total for one water point

Construction of public fountains


ITEM DESCRIPTION U. PRICE
UNIT QNTY
NO BIRR
1 Earth work
Clearing and striping of top soil to a minimum depth of m2
200 mm inside the fenced compound of each water 66.22
point
1.1
Clearing and grubbing the top soil and unwanted m2
material to a depth of 200 mm and disposal of spoil as
directed by the Engineer 33.80

1.2
Excavation for foundation, soak away pit and valve m3
10.34
1.3 chamber
Provide and compact selected material in layers of m3
13.00
1.4 150mm
Provide and fill hard core with hard basaltic or m3
equivalent stone, well compacted and blinded with
crushed stone 3.00

1.5
Cart away and dispose all excavated material to m3
appropriate distance not exceeding 1 Km. 30.34
1.6
2 Concrete Work
2.1 C-15 lean concrete m3 0.78
2.2 C-25 concrete mass concrete m3 3.78
C-25 R. concrete for tie beam m 3
0.85
2.3 Provide and fix formwork m2 5.00
Provide cut, and fix in position reinforced steel bar all
according to structural drawing, Price shall include
tying wires
2.4
2.5 Diametr 6 mm Kg 21.20
2.6 Diametr 10 mm Kg 42.50
3 Masonery Work
Provide and construct 400mm thick trychytic masonry m3
wall grouted and filled with (1:3) mortar for
foundation and super structure 6.74

3.1
Plastering to smooth finish for waterpoint wall and m2
18.97
3.2 surface
Provide and fix in place precast R.concrete water seller No
seats as per the drawing 1.00
3.3
Masonery pavement around the water point as per the m2
drawing (200 mm thick with 1:3 mortar) 8.90

4 Pipework
Sub-total - Carried forward
Sub-total - Brought forward
4.1 Supplying and installing GS pipes
4.2 DN 40 GS m 12.00
4.3 DN20 GS m 3.00
4.4 Supplying and fixing fittings
4.5 Cross tee DN 40 No 2
4.6 Reducer 40x20 No 6
4.7 Tee DN 40 No 1
4.8 DN 40 Bend (elbow) 90 degree No 5
4.9 Faucet DN 20 No 6
4.10 Socket DN 20 No 6
4.11 Gate valve DN 40 No 1
4.12 Union DN 40 No 1
4.13 Nipples DN 40 No 8
Water meter DN 40 (install only, supplird by
No 1
4.14 employer)
Construct two valve chambers for water meter and gate
valve , covered with 700*700*6mm sheet metal with
latch and lock as per the drawing No 2

4.15
5 Drainage
Reinforced Concrete drainage ditchfrom water point to
soak away pitas per the drawing, Price including
excavation and any other incedental works
m 2.00

5.1
Supply and place boulders, crashed agregate and sand
to form the soak away as per the drawing m3 0.32
5.2
6 Fence
Barbed wires fencing consists of 2.5 mm barbed wire
horizontal and diagonal member fixed to 2500 mm
long concrete posts spaced every 2000mm, including
all necessary material as per the drawing m 30.00

6.1
Supply and fix iron gate 2.1*1.2 m with lock and latch
No 2.00
6.2
6.3 Sub total of - One Public fountain
Amount (birr)
TOTAL
BIRR
Cattle Trough
Item Description Unit Qty Rate
Earth Work

Site clearing up to a depth of 20cm to remove top vegetated


1.1 m2 40
soil

1.2 Excavation for foundation up to 25cm depth m3 5

1.3 Basaltic or equivalent hard core filling 25cm thick m2 10.0

1.4 Cart away excavated material to 100m distance m3 10

2 Masonry work

Construction of Grade C- 20 concrete side wall 10 cm thick


2.1 & 25 cm high wall plastered with cement mortar 1:3 Both m3 12
face with dimention 3.0 m wide & 25 m long

Semi dressed stone pavement pointed with cement mortar


2.2 m2 75
1:3 all round the cattle trough

Back Fill excavated area above the concrete cover over filter
2.3 m3 10.0
media with clay
3 Concrete work

Pouring 5cm thick lean concrete over hard core in with


3.1 m2 10.0
class C-15 Minimum cement content of 150kg/m3,

Casting Grade C-20 with minimum cement content ,of


3.2 320kg/m3 for the Cattletrough Nominal reinforced Base m3 2.0
Slab Filled into formwork

External and internal plastering of the body of the cattle


3.3 m2 70.0
trough

Construction of HCB wall manhole with cover having


3.4 No 1.0
internal Plan area

3.5 Form work wooden or Steel m2 10.0


4 Fineshing work
4.1 3cm thick trawl finish cement screed in 1:3 mix m2 10.4

4.2 Water meter DN 40 mm No 1

4.3 Fittings as per Design Drawing LS 1

Sub total for one cattle troughs

Page 11 of 44
Amount

Page 12 of 44
Bill of Quantity for Spring Development-Standard
Item Description of Works unit Qty. Rate
No
1 Earth work
1.1 Site clearing to an average depth of 20 cm to remove top m2 25
soil
1.2 Excavation for spring box floor area, wing walls' strip m3 10
foundation& retaining walls
1.3 Back fill work around the external faces of the m3 10
foundation wall with approved excavated meterial from
the site

1.4 Spread and Cart awaysurplus excavated material from m3 5


the site to a distance of 50 m to spoil tips

1.5 Filling the spring eye area with clean and graded river m3 2.5
Gravel for filter of approved required size arranged

1.6 Placing 20cm thick hard core for flooring above the m3 2
graded gravel toprotect the spring and for hygene

2 Concrete work
2.1 Construction of reinforced concrete collection box LS 1
adjacent to Spring Eye to collect filtered water and
guide to theOut let, Drainage & Over flow system
including all supply of Pipes, fittings & Control Valves

2.2 Casting 10cm thick mass concrete above the hard core m2 12
to cover andprotect the spring eye

2.3 Construction of 15cm thick reinforced concrete roof m3 0.6


slab with manholeopening of 60 x 60cm left open

2.4 Construction of Man hole cover made of reinforced No 1


concrete having athickness of 20 cm and 75 x 75 cm
dimension & Plastered smooth

2.5 Plastering the internal wall surfaces of the collection m2 35


box & wing wallswith 30 mm thick cement mortar mix
1:3

2.6 Pointing all the external face of exposed masonry wall M2 20

2.7 Provide cut & fix in positions sawn wooden from work M2 10
or equavalentproperly erected and struted with tight
joint not to bleed

2.8 Provide ,cut, bend & fix reinforcement bar Diameter of Kg 30


10 mm placed at 150 mm c/c
3 Masonry Work
Sub total - Carried Forward

Page 13 of 44
Bill of Quantity for Spring Development-Standard
Item Description of Works unit Qty. Rate
No
Sub total - Brought Forward
3.1 Construction of 50 cm thick stone masonry wall for

elevation wall of25 cm above ground & for 50 cm thick m3 12


retaining wall comment mortar of 1:3 as per the Design
Drawing

3.2 Construction of 25cm thick stone pavement and foot m3 3


Steps around the spring collection Box

4 Pipe work
4.1 Supply & install all necessary class "B" pipes and LS 1
fittings ( for out let ,drainage and over flow system)
with all necessarygate valves &control

Sub Total for one spring

Page 14 of 44
Amount

Page 15 of 44
Amount

Page 16 of 44
10M3 ROTO TANKER & STAND
Item Description Unit Qty Rate
1 Excavation & Earth Work

1.1 Site clearing to remove vegetable soil to a depth of 20 cm M2 26.30

1.2 Excavation for footing depth not exceeding 1500cm M3 31.20

1.3 Cart a way excavated material from site M3 36.50


1.4 Back fill selected Borrowed material M3 18.60
2 Concrete work

2.1 10 cm thick lean concrete under footing pad M3 1.10

2.2 25 cm think C20 R.C.C pad to middle part M3 1.10


2.3 Ditto but corner part M3 1.03

2.4 C20 R.C concrete to 35x35cm middle columns M3 1.10

2.5 Ditto but 25x25cm corner columns M3 1.10

2.6 16cm thick R.c concrete to inter me diet slabe M3 2.60

2.7 ditto but 16cm thick to top slab M3 2.60


2.8 R.c steel bar ø 20 Kg 520.00
2.9 R.c steel bar ø 16 Kg 275.00
2.10 R.c steel bar ø12 Kg 133
2.11 R.c Steel bar ø10 Kg 400
2.12 R.c Steel bar ø 6 kg 50
Sawen Zigba wooden formwork for footing pad corner
2.13 M2 4
part
2.14 Ditto but middle part M2 4
2.15 Ditto but column & slabs M2 5
3 Finishing work
3.1 Supply 7 fixing 10m3 roto tanker with fittings Pcs 1

3.2 5cm thick cement sand mortar plastering to slabs M2 33

3.3 Three coast of cement sand plastering to columns M2 30

1" Gib for Shelter of roto tank post hight 3.50 & truss
3.4 M2 57
lengh 2.90
3.5 2.5mm thick sheet metal roof cover M2 16
3.6 Welding truss & post at G2 pipes sheet metal Ls 1
3.7 Painting to Sheet metal roof cover M2 16
Total for one Roto Tank and Stand

Page 17 of 44
Amount

Page 18 of 44
Standard Service Reservoir 50 m3

Description Unit Qty Rate Amount


1 Earth Work

Site clearing & grubbing up to a average depth of 20 cm to


1.1 remove top vegetated soil m2 85

Foundation excavetion to a depth of 75 cm below ground


1.2 level m3 30.5

Filling and compacting foundation base with selected


1.3 materials for 20 cms m3 8.1

Placing 40 cm thick basalic stone or equivalent hard core


1.4 well-rolled consolidated and blinded with gravel m3 16.2

Back filling around a foundation with approved selected


1.5 materials from site well rammed in layer of 20 cm m3 22.1

Cartaway surplus excavated materials from the site to a


1.6 distance of 100 m m3 25
2 concrete work

Casting 50 mm thick Lean concrete over hard-core with


2.1 Grade C-15 concrete with minimum cement 150kg/m3 m2 30.2

Casting 25 cm thick Base slab in Grade C-25 reinforced


2.2 concrete with minimum cement 360kg/m3 mix 1:2:4 m3 70.6

Casting 20 cm thick Roof cover slab with Grade C-25


2.3 reinforced concrete of minimum cement 360kg/m3 m3 6.8

Construction of friction key with Grade C-25 reinforced


2.4 concrete simultaneously with base slab m3 0.83

Construction of 10 cm thick reinforced concrete Grade C-25


filled between masonry wall reinforced with Hexagonal
2.5 Mesh-Wire of size 3/4 m3 5.2

Casting 20cm thick concrete Ring beam of Grade C-25 with


2.6 minimum cement 360kg/m3 m3 1.7

2.7 supply, cut, bend and fix in position reinforcement bars


a/ ø 6mm kg 73
b/ ø 8mm kg 55
c/ ø10mm kg 1012
d/ ø 12mm kg 135

2.8 Supply and fix 3/4 Hexagonal Mesh Wire for hoop stress m2 55
Sub total - Carried Forward

Page 19 of 44
Standard Service Reservoir 50 m3

Description Unit Qty Rate Amount


Sub total - Brought Forward

Fixing of good quality wooden or metal form work firmly


2.9 with strong struting & tight to avoid Bleeding & Bulgingout m2 54
3 Massonry work

Construction of 2 x 20 cm thick Masonry Wall on both side


of the Concrete - Core embeded with cement Sand mortar
3.1 of mix 1 : 3 m3 20.6

Floor finish 30 mm thick trawl and smooth finish with 1:3


3.2 cement Sand mortar screed m2 18.1

Semi Dressed Stone Pavement around the Reservoir 1.0 m


3.3 wide cemented with in 1:3 mix cement mortar m2 36

Construction of Semi-Circular 30 cm diameter Drainage


3.4 Ditch as per drawing m 38

Construction of 100 x 100 x 100 cm Valve chamber with


3.5 Hollow Concrete Block as per Design Drawing LS 1
4 Mislaneous & Finishing

Install & Fix all necessary pipes & fittings with all necessary
accessories, gate valves, Float Valves asper the Design
Drawings for In-let, Out-let, Vent pipe Drain,& Over-flow
4.1 system of the reservoir LS 1

Supply & Install lockabl Steel Man-Hole cover with all


4.2 fixing hings & Accessories with lock gate (Design) No 1

Supply and install both External & Internal Ladder made of


Class B, G S Pipe of DN 25 mm Length 3.0 m having extra
4.3 1.0 m high handle at the top for External Ladder No 2

Install and fix quality water meter DN 80 mm at the outlet of


4.4 the reservoir with approperiate fittngs and Gate Valve No 1

Supply and fix 25 mm thick quality expansion Joint made of


4.5 Biutmen asphalt applied when necessary m2 3

Plastering the whole inner wall face and exposed faces of


concrete works with three coates of cement sand mortar of
4.6 mix 1 : 2 m2 94

Pointing the whole External face of the masonry wall with


4.7 cement mortar mix 1 : 2 m2 56.5
Total for one reservoir

Page 20 of 44
Standard Service Reservoir 25 m 3

Description Unit Qty Rate Amount


1 Earth Work

1.2 Foundation excavetion to a depth of 75 cm below ground level m3 22.6

Filling and compacting foundation base with selected materials for 20


1.3 cms m3 4.3

Placing 40 cm thick basalic stone or equivalent hard core well-rolled


1.4 consolidated and blinded with gravel m3 8.6

Back filling around a foundation with approved selected materials


1.5 from site well rammed in layer of 20 cm m3 1.8

Cartaway surplus excavated materials from the site to a distance of


1.6 100 m m3 25
2 concrete work

Casting 50 mm thick Lean concrete over hard-core with Grade C-15


2.1 concrete with minimum cement 150kg/m3 m2 21.2

Casting 25 cm thick Base slab in Grade C-25 reinforced concrete with


2.2 minimum cement 360kg/m3 mix 1:2:4 m3 5.3

Casting 20 cm thick Roof cover slab with Grade C-25 reinforced


2.3 concrete of minimum cement 360kg/m3 m3 4.2

Construction of friction key with Grade C-25 reinforced concrete


2.4 simultaneously with base slab m3 0.7

Construction of 10 cm thick reinforced concrete Grade C-25 filled


between masonry wall reinforced with Hexagonal Mesh-Wire of size
2.5 3/4 m3 3.1

Casting 20cm thick concrete Ring beam of Grade C-25 with


2.6 minimum cement 360kg/m3 m3 1.3
2.7 supply, cut, bend and fix in position reinforcement bars
a/ ø 6mm kg 53
b/ ø 8mm kg 42
c/ ø10mm kg 716
d/ ø 12mm kg 108

2.8 Supply and fix 3/4 Hexagonal Mesh Wire for hoop stress m2 35.5
Sub total - Carried Forward

Page 21 of 44
Standard Service Reservoir 25 m 3

Description Unit Qty Rate Amount


Sub total - Brought Forward

Fixing of good quality wooden or metal form work firmly with


2.9 strong struting & tight to avoid Bleeding & Bulgingout m2 35
3 Massonry work

Construction of 2 x 20 cm thick Masonry Wall on both side of the


3.1 Concrete - Core embeded with cement Sand mortar of mix 1 : 3 m3 13.1

Floor finish 30 mm thick trawl and smooth finish with 1:3 cement
3.2 Sand mortar screed m2 11

Semi Dressed Stone Pavement around the Reservoir 1.0 m wide


3.3 cemented with in 1:3 mix cement mortar m2 32

Construction of Semi-Circular 30 cm diameter Drainage Ditch as per


3.4 drawing m 35
Construction of 100 x 100 x 100 cm Valve chamber with Hollow
3.5 Concrete Block as per Design Drawing LS 1
4 Mislaneous & Finishing

Install & Fix all necessary pipes & fittings with all necessary
accessories, gate valves, Float Valves asper the Design Drawings for
4.1 In-let, Out-let, Vent pipe Drain,& Over-flow system of the reservoir LS 1

Supply & Install lockabl Steel Man-Hole cover with all fixing hings
4.2 & Accessories with lock gate (Design) No 1

Supply and install both External & Internal Ladder made of Class B,
G S Pipe of DN 25 mm Length 3.0 m having extra 1.0 m high handle
4.3 at the top for External Ladder No 2

Install and fix quality water meter DN 80 mm at the outlet of the


4.4 reservoir with approperiate fittngs and Gate Valve No 1

Supply and fix 25 mm thick quality expansion Joint made of Biutmen


4.5 asphalt applied when necessary m2 3

Plastering the whole inner wall face and exposed faces of concrete
4.6 works with three coates of cement sand mortar of mix 1 : 2 m2 68

Pointing the whole External face of the masonry wall with cement
4.7 mortar mix 1 : 2 m2 38.5
Total for one reservoir

Page 22 of 44
Under Ground Collection Chamber Capacity 25 m3
I No Description of Works unit Qty. Rate Amount
1 Earth Works

1.1 Site clearing to an average depth of 20cm m2 55

Excavation for Foundation to a depth of not exceeding


1.2 m3 33
100 cm

Excavation for foundation to a depth greater than 100cm


1.3 m3 60
& not exceeding 250 cm

Back fill work with selected material below hard core


1.4 m3 37
and around the masonry foundation wall

Placing 25 cm thick Basaltic (Equavalent) Stone for


1.5 m2 30
Hard-core
Cart away surplus material from the site to a distance of
1.6 m3 70
100 m
2 Concrete & Masonry Work

Casting 5 cm thick Lean Concrete above the Hard-Core


2.1 m2 30
with Grade C - 15 mix 1: 3 : 6 min Cement 150 Kg / m3

Casting 25 cm thick Base Slab with Grade C - 25


Concrete of minimum cement content of 360 Kg / m3
2.2 m3 7.4
filled into approperiate form work and properly Vibrated
around the re-bars.

Casting 20 cm thick Ring-Beam with Grade C - 20


Concrete of minimum cement content of 320 Kg / m3
2.3 m3 2
filled into approperiate form work and properly Vibrated
around the re-bars.

Construction of Masonry wall embeded with cement


2.4 mortar of mix 1:3 friction key in the middle for 25 cm at m3 25
the base

Casting 20 cm thick chamber Cover Slab with Grade C -


25 Concrete of minimum cement content of 360 kg / m3
2.5 m3 4.7
filled in to form work and properly Vibrated around the
re-bars.

Construction of 30 cm thick concrete friction key at the


2.6 base Concrete Inner Core all around the side wall center m3 1.2

Sub total - Carried Forward

Page 23 of 44
Under Ground Collection Chamber Capacity 25 m3
I No Description of Works unit Qty. Rate Amount
Sub total - Brought Forward

Supply, Cut, Bend into Shape and fixing in position mild


2.7
steel Reinforcement Bars as Per Design Drawings

a. Diameter 6mm Kg 26
b. Diameter 10mm Kg 256
c Diameter 12mm Kg 674
Supply and fixing an approperiate type Formwork for all
2.8 types of concrete work with proper struting and m2 32
anchoring
3 Finishing and Miscllaneous Works
Finishing with 30 mm thick cement screed mix 1:3 for
3.1 floor base slab Base Slab with 2 % sloping towards the m2 15
drainage

Apply 3 coats of plastering with mortar of 1 : 3 mix to


3.2 inner wall and external faces of the ring beam , roof and m2 64
base slab side

Pointing with cement sand mortar of 1 : 3 mix the


3.3 m2 40
external wall surfaces of the chamber

Install all necessary pipes and fittings with all


accessories, gate valves, float valves, as per the drawing
3.4 Ls 1
for inlet, out let, vent pipes, drainage and overflow
system

Supply and fixing lockable steel Man-hole cover with


3.5 No 1
hinges and accessories for lock

Supply and install both external and internal ladder


3.6 made of 25mm GI pipe, length 3m having extra 1m high No 2
handle at top for the external ladder

Fixing quality water meter at the out let of the chamber


3.7 No 1
with appropriate fitting as per the drawing

Supply and fix 25mm thick quality expansion joint made


3.8 m2 2.5
of buitmen asphalt applied when necessary

Total

Page 24 of 44
Under Ground Collection Chamber Capacity 50m3
No Description of Works unit Qty. Rate Amount
1 Earth Works
1.1 Site clearing to an average depth of 20cm m2 70
1.2 Excavation for Foundation to a depth of not exceeding 100 cm m3 45

1.3 Excavation for foundation to a depth greater than 100cm & not exceeding 250 cm m3 78

Back fill work with selected material below hard core and around the masonry
1.4 m3 50.7
foundation wall
1.5 Placing 25 cm thick Basaltic (Equavalent) Stone for Hard-core m2 38.4
1.6 Cart away surplus material from the site to a distance of 100 m m3 110
2 Concrete & Masonry Work
Casting 5 cm thick Lean Concrete above the Hard-Core with Grade C - 15 mix 1: 3 :
2.1 m2 38.4
6 min Cement 150 Kg / m3
Casting 25 cm thick Base Slab with Grade C - 25 Concrete of minimum cement
2.2 content of 360 Kg / m3 filled into approperiate form work and properly Vibrated m3 9.6
around the re-bars.

Casting 20 cm thick Ring-Beam with Grade C - 20 Concrete of minimum cement


2.3 content of 320 Kg / m3 filled into approperiate form work and properly Vibrated m3 2.5
around the re-bars.

Construction of Masonry wall embeded with cement mortar of mix 1:3 friction key
2.4 m3 34
in the middle for 25 cm at the base

Casting 20 cm thick chamber Cover Slab with Grade C - 25 Concrete of minimum


2.5 cement content of 360 kg / m3 filled in to form work and properly Vibrated around m3 6.3
the re-bars.

Construction of 30 cm thick concrete friction key at the base Concrete Inner Core all
2.6 m3 1.5
around the side wall center
Supply, Cut, Bend into Shape and fixing in position mild steel Reinforcement Bars
2.7
as Per Design Drawings
Sub total - Carried Forward
Sub total - Brought Forward
a. Diameter 6mm Kg 35
b. Diameter 10mm Kg 308
c Diameter 12mm Kg 835
Supply and fixing an approperiate type Formwork for all types of concrete work with
2.8 m2 41
proper struting and anchoring
3 Finishing and Miscllaneous Works
Finishing with 30 mm thick cement screed mix 1:3 for floor base slab Base Slab
3.1 m2 25
with 2 % sloping towards the drainage
Apply 3 coats of plastering with mortar of 1 : 3 mix to inner wall and external faces
3.2 m2 91
of the ring beam , roof and base slab side
Pointing with cement sand mortar of 1 : 3 mix the external wall surfaces of the
3.3 m2 67
chamber

Install all necessary pipes and fittings with all accessories, gate valves, float valves,
3.4 Ls 1
as per the drawing for inlet, out let, vent pipes, drainage and overflow system

3.5 Supply and fixing lockable steel Man-hole cover with hinges and accessories for lock No 1

Supply and install both external and internal ladder made of 25mm GI pipe, length
3.6 No 2
3m having extra 1m high handle at top for the external ladder

Fixing quality water meter at the out let of the chamber with appropriate fitting as
3.7 No 1
per the drawing
Supply and fix 25mm thick quality expansion joint made of buitmen asphalt applied
3.8 m2 3
when necessary
Total

Page 25 of 44
Standard Masonry Reservoir 75 m3
Description
1 Earth Work Unit Quantity Unit Rate Total Amount
Site clearing & grubbing up to a
average depth of 20 cm to remove top
1.1 vegetated soil m2 120
Foundation excavetion to a depth of 75
1.2 cm below ground level m3 49.6

Filling and compacting foundation base


1.3 with selected materials for 20 cms m3 10.6
Placing 40 cm thick basalic stone or
equivalent hard core well-rolled
1.4 consolidated and blinded with gravel m3 21.2
Back filling around a foundation with
approved selected materials from site
1.5 well rammed in layer of 20 cm m3 2.4

Cartaway surplus excavated materials


1.6 from the site to a distance of 100 m m3 31
2 concrete work

Casting 50 mm thick Lean concrete


over hard-core with Grade C-15
concrete with minimum cement
2.1 150kg/m3 m2 40.7
Casting 25 cm thick Base slab in Grade
C-25 reinforced concrete with
2.2 minimum cement 360kg/m3 mix 1:2:4 m3 10.2
Casting 20 cm thick Roof cover slab
with Grade C-25 reinforced concrete of
2.3 minimum cement 360kg/m3 m3 9
Construction of friction key with Grade
C-25 reinforced concrete
2.4 simultaneously with base slab m3 1
Construction of 10 cm thick reinforced
concrete Grade C-25 filled between
masonry wall reinforced with
2.5 Hexagonal Mesh-Wire of size 3/4 m3 5.75
Casting 20cm thick concrete Ring beam
of Grade C-25 with minimum cement
2.6 360kg/m3 m3 2
supply, cut, bend and fix in position
2.7 reinforcement bars
a/ ø 6mm kg 82
b/ ø 8mm kg 61
c/ ø10mm kg 1338
d/ ø 12mm kg 160
Supply and fix 3/4 Hexagonal Mesh
2.8 Wire for hoop stress m2 60
Sub total - Carried Forward
Sub total - Brought Forward

Fixing of good quality wooden or


metal form work firmly with strong
struting & tight to avoid Bleeding &
2.9 Bulgingout m2 59
3 Massonry work

Construction of 2 x 20 cm thick
Masonry Wall on both side of the
Concrete - Core embeded with cement
3.1 Sand mortar of mix 1 : 3 m3 23
Floor finish 30 mm thick trawl and
smooth finish with 1:3 cement Sand
3.2 mortar screed m2 26

Semi Dressed Stone Pavement around


the Reservoir 1.0 m wide cemented
3.3 with in 1:3 mix cement mortar m2 41

Construction of Semi-Circular 30 cm
3.4 diameter Drainage Ditch as per drawing m 42

Construction of 100 x 100 x 100 cm


Valve chamber with Hollow Concrete
3.5 Block as per Design Drawing LS 1
4 Mislaneous & Finishing

Install & Fix all necessary pipes &


fittings with all necessary accessories,
gate valves, Float Valves asper the
Design Drawings for In-let, Out-let,
Vent pipe Drain,& Over-flow system of
4.1 the reservoir LS 1
Supply & Install lockabl Steel Man-
Hole cover with all fixing hings &
4.2 Accessories with lock gate (Design) No 1

Supply and install both External &


Internal Ladder made of Class B, G S
Pipe of DN 25 mm Length 3.0 m
having extra 1.0 m high handle at the
4.3 top for External Ladder No 2
Install and fix quality water meter DN
80 mm at the outlet of the reservoir
with approperiate fittngs and Gate
4.4 Valve No 1
Supply and fix 25 mm thick quality
expansion Joint made of Biutmen
4.5 asphalt applied when necessary m2 3

Plastering the whole inner wall face and


exposed faces of concrete works with
three coates of cement sand mortar of
4.6 mix 1 : 2 m2 118
Pointing the whole External face of the
masonry wall with cement mortar mix 1
4.7 : 2 m2 120
Total for one reservoir 0.00
Standard Service Reservoir Capacity 100 m 3
Item
No Description
1 Earth Work Unit Quantity unit Rate Total Amount

Site clearing & grubbing up to a average


1.1 depth of 20 cm to remove top vegetated soil m2 190

Foundation excavation to a depth of 75 cm


1.2 below ground level m3 45

Filling and compacting foundation base


1.3 with selected materials for 20 cms m3 12.5

Placing 40 cm thick basaltic stone or


equivalent hard core well-rolled
1.4 consolidated and blinded with gravel m3 25

Back filling around a foundation with


approved selected materials from site well
1.5 rammed in layer of 15 cm m3 12

Cart away surplus excavated materials from


1.6 the site to a distance of 100 m m3 35
2 Concrete work

Casting 50 mm thick Lean concrete over


hard-core with Grade C-15 concrete with
2.1 minimum cement 150kg/m3 m2 60

Casting 25 cm thick Base slab in Grade C-


25 reinforced concrete with minimum
2.2 cement 360kg/m3 mix 1:2:4 m3 10.5

Casting 20 cm thick Roof cover slab with


Grade C-25 reinforced concrete of
2.3 minimum cement 360kg/m3 m3 9.5

Construction of friction key with Grade C-


25 reinforced concrete simultaneously with
2.4 base slab m3 3
Construction of 10 cm thick reinforced
concrete Grade C-25 filled between
masonry wall reinforced with Hexagonal
2.5 Mesh-Wire of size 3/4 m3 3.5

Casting 20cm thick concrete Ring beam of


Grade C-25 with minimum cement
2.6 360kg/m3 m3 2
supply, cut, bend and fix in position
2.7 reinforcement bars
dia 6mm kg 100
dia 8mm kg 150
dia 10 mm kg 1720
dia 12 mm kg 184
Supply and fix 3/4 Hexagonal Mesh Wire
2.8 for hoop stress m2 75

Fixing of good quality wooden or metal


form work firmly with strong strutting &
2.9 tight to avoid Bleeding & Bulging out m2 100
Sub total - Carried Forward
Sub total - Brought Forward
3 Masonry work

Construction of 2 x 20 cm thick Masonry


Wall on both side of the Concrete - Core
embedded with cement Sand mortar of mix
3.1 1 : 3 m3 30

Floor finish 30 mm thick trawl and smooth


3.2 finish with 1:3 cement Sand mortar screed m2 99

Semi Dressed Stone Pavement around the


Reservoir1.0 m wide cemented with in 1:3
3.3 mix cement mortar m2 27

Construction of Semi-Circular 30 cm
3.4 diameter Drainage Ditch as per drawing m 32
Construction of 20 x 20 x 40 cm hollow
concrete block Valve- Chamber with supply
and fixing of all necessary pipes, valves and
3.5 fittings (as per Design Drawing) LS 1
4 Miscellaneous & Finishing

Supply & Install all necessary pipes &


fittings with all necessary accessories, gate
valves, Float Valves as per the Design
Drawings for In-let, Out-let, Vent pipe
4.1 Drain,& Over-flow system of the reservoir LS 1

Supply & Install lockable Steel Man-Hole


cover with all fixing hinges & Accessories
4.2 with lock gate (Design) No 1

Supply and install both External & Internal


Ladder made of Class B, G S Pipe of DN 25
mm Length 3.0 m having extra 1.0 m high
4.3 handle at the top for External Ladder No 2

Supply and fix quality water meter DN 80


mm at the outlet of the reservoir with
4.4 appropriate fittings and Gate Valve No 1

Supply and fix 25 mm thick quality


expansion Joint made of Biumen asphalt
4.5 applied when necessary m2 4

Plastering the whole inner wall face and


exposed faces of concrete works with three
4.6 coates of cement sand mortar of mix 1 : 3 m2 125

Pointing the whole External face of the


4.7 masonry wall with cement mortar mix 1 : 3 m2 75
Grand Total 0.00
10 m3 water reservoir(Break Pressure Tank)

No Description of Works Unit Qty. Rate


1 Excavation and earth work
1.1 Clearing of site to remove the top soil to an average depth of M2 12.3
200mm

1.2 Bulk excavation in ordinary soil to an average depth of 600mm M3 9.6

1.3 Back fill under hardcore with non expansive selected material M3 1.2
and well rammed in layers not exceeding 100mm

1.4 Cart away surplus excavated material at a distance not less than M3 9.4
50m from the site
1.5 Basaltic or equivalent stone hard core well rammed consolidated M3 4.6
and blinded with crushed stone to finished thickness of 400

2 Concrete Work
2.1 50mm thick lean concrete in class C-5 with minimum cement M2 11.6
content of 150kg/m3 above hardcore

2.2 Class C-25 concrete with minimum cement content of 360kg/m3 M3 2.3
filled into formwork and vibrated around steel reinforcement in
200m thick cover slab

2.3 Class C-25 concrete with minimum cement content of 360kg/m3 M3 1.7
filled into formwork and vibrated around steel reinforcement in
150mm thick cover slab

2.4 Provide, cut and fix in position sawn zigba wood form work to M2 2.7
foundation base slab
2.5 Provide, cut and fix in position sawn zigba wood form work to M2 8.8
cover slab
2.6 Steel reinforcement according to structural drawing, price
includes cutting, bending, placing in position & tying wires

2.7 12mm diameter plane bars kg 240.47


2.8 10mm diameter plane bars kg 58.42
3 Masonry Work
3.1 400mm thick stone masonry wall bedded in cement sand mortar M3 9.12
mix (1:3)
4 Finishing work
4.1 Apply three coats of plastering in cement sand mortar mix (1:3) M2 19.8
to internal masonry wall
4.2 Pointing in cement sand mix of 1:3 the external surface of M2 25.84
masonry wall
4.3 50mm thick smooth trowel finished cement sand mix of 1:3 M2 26.52
screed to internal wall and bottom slab

Page 32 of 44
10 m3 water reservoir(Break Pressure Tank)

No Description of Works Unit Qty. Rate


4.4 Construct 60x60cm pre cast reinforced concrete man hole cover No 1
for the reservoir

5 Pipe and fitting


5.1 Install all necessary inlet, outlet,float valve, overflow and No 1
drainage pipes and fittings as per the drawing and specification

5.2 2”elbow No 3
5.3 2”Union No 1
5.4 2”Nipples No 2
5.5 2”Tap No 1
5.6 2”Gate valve No 1
5.7 1 1/2”union No 1
5.8 1 1/2”elbow No 2
5.9 Construct reinforced concrete C-20 valve chamber of 75x75cm No 1
as per the drawing
5.10 2m long 40cm width at interval of 40cm mobile welded ladder No 1
with 11/2” GI pipes

Total for 10 m3 Reservoir (Break Pressure Tank) Carried for Summery

Page 33 of 44
Amount

Page 34 of 44
Amount

Page 35 of 44
Bill Of Quantity of Shower Room (3x4m)
Item Description of Works unit Qty Rate Amount
1 Earth Works
Site clearing to anaverageg depth of 20 cm to remove top soil &
1.1 m2 20
Grubbing

Excavation for foundation trench to a depth of not exeeding 100


1.2
cm below

stripped ground level including for drainage of wastes m3 9.3

Back filling around a foundation with good dry filling material


1.3 m3 3.8
from the site

Back filling under a hard core with good and approved selected
1.4
material

around the site well rammed and compacted in layers not


m3 5.2
exeeding 20cm

1.5 cart away suplus material to a distance of 100m m3 8

2 Masonry work

Placing 25cm thick basaltic or equivalent stone hard core well


2.1
rolled and

consolidated & blinded with crushed stone m3 3

Construction of 40 cm thick basaltic or equivalent masonry


2.2
foundation wall to a

depth of 50 cm blow ground level blended & joined in cement


m3 2.9
mortar of 1:3

Construction of 40 cm thick basaltic or equivalent masonry


2.3
foundation wall to

a height of 30 cm above ground level blended & joined in


m3 1.7
cement mortor1:3

Pointing the exposed external wall surface of the foundation


2.4
with cement

mortar of 1:3 mix m2 4.4

20cm stone pavement around the house price including the


2.5 m2 14.6
drainage ditch

3 concrete work

Casting 50 mm thick Lean Concrete Grade C-10, with min.


3.1
cement content

of 150 Kg / m3 of concrete over the Hard Core m2 12

Casting 10 cm thick Mass Concrete of Grade C-20, with


3.2
minimum cement of

320 Kg / m3 of concrete for floor slab sloping to drain pipe m3 1.2

Supply, Cut, Bend & fixing in Reinforecment bar DN10 mm


3.3 Kg 20
spaced @ 250 mm

4 Wall and Roofing

Page 36 of 44
Bill Of Quantity of Shower Room (3x4m)
Item Description of Works unit Qty Rate Amount
supply and fix corrugated galvanised iron sheets of G-32 for
4.1
wall, fixed to 5x4 cm

horizontal zigba purlins spaced 90 cm with roof nail m2 42

Supply and fixing stand poles diameter DN150 mm round


4.2
eucalyptus tree anchored

to masonry foundation wall with C-15 concrete mix 50 cm


m 62
deep as design

Supply and fixing horizontal 5x4cm zigba purlins spaced


4.3 m 30
@90cm& nailed to upper truss

Supply, assemble and fix roof truss @1.25m interval as per the
4.4 No. 4
drawing

Supply & fixs G-32 G.I.Sheets with roof nail having washer
4.5 m2 22
fixed to 5x4 zigba Purlins

5 Doors

"Tid or Equavalent wooden frame lockable doors made of G-32


5.1 No. 4
CGI sheets of 2.10 m x 0.8 m

6 Pipe Works

Supply and installation of all necessary pipes and fittings for


6.1
four showerin units

price incuding shower heads LS 1

Total for the Shower Room

Page 37 of 44
Bill of Quantities Public Washing Basin Construction
S.N Description of Work Unit Qty Rate Amount

1 Earth work
1.1 Site clearing & grubbing up to a average depth of 20cm to M2 9.6
remove top vegetated soil
1.2 Foundation excavation to a depth of 50cm below ground level M3 4.8

1.3 Filling and compacting foundation base with selected materials M3 0.9
for20cm
1.4 Cart away surplus excavated materials from the site to a M3 1.65
distance not less 100m
2 Masonry Work
2.1 Placing 25cm thick basaltic or equivalent hardcore well rolled,
consolidated and blinded with crushed stone M2 4.4

2.2 Construction of stone masonry wall joined with a 1:3 cement-


sand mix mortar as per the drawing M3 1.7
3 Concrete work
3.1 Pouring 50mm thick lean concrete (1:2:6 mix) over the hardcore M2 4.4

3.2 Casting 150mm thick nominally reinforced C-20 concrete with


10mm dia reinforcement bar spaced @250mm c/c on both ways
over the lean concrete and provide drainage ditch as shown on
the drawing.
M3 0.44

3.3 Casting mass concrete for the edges of the washing escarpments M3 0.68

3.4 Supply, cut, bend and fix in position reinforcement bars Of


Ф10mm Kg 21
3.5 Fixing of good quality wooden or metal form work firmly with
strong strutting & tight to avoid bleeding & bulking out M2 7

4 Finishing and miscellaneous works


4.1 Supply & Install all necessary pipes & fittings for drainage with
all necessary accessories as per the Design Drawings Ls 1

4.2 Apply 25mm thick cement screed mix 1:3 for floor base of
washing basin with 1% sloping towards the drainage. M2 2.2

4.3 Plastering the exposed faces of concrete works with three coats
of cement sand mortar of mix 1:3 M2 2.2

4.4 Pointing the whole external face of the masonry wall with
cement mortar mix 1:4

Page 38 of 44
Bill of Quantities Public Washing Basin Construction
S.N Description of Work Unit Qty Rate Amount
4.4 Pointing the whole external face of the masonry wall with
cement mortar mix 1:4 M2 4
4.5 Construction of gravel packed soak away pit to downstream of
the washing basin having 700mm dia. and 600mm depth with
proper drainage canal connection work

No 1
5 Construction of 1.75m high fence of barbed wire fixed to
eucalyptus posts diameter 120mm placed 125cm c/c buried in
concrete C-15 to a depth of 30cm in 50cm dug holes with
corrugated galvanized iron sheet single leaf gate

m 20
Total for one Washing Basin Birr

Page 39 of 44
Bill of Quantities for Public Latrine
I.N Unit
Description of work Unit Qty Rate
1 Earth Work
1.1 Site clearing & grubbing up to a average depth of 20cm to M2
remove top vegetated soil 15
1.2 Excavation for well of latrine to a depth of 2m below ground M3 13.4
level
1.3 Cart away surplus material to a distance not less than 100m M3 13.4

2 Masonry Work
2.1 Construction of basaltic or equivalent cement pointed
masonry to exposed face of excavated latrine well blended &
joined in cement mortar 1:4
M3 7.7

2.2 Construction of 40 cm thick and 50cm high basaltic or


equivalent masonry wall foundation well blended & joined
in cement mortar 1:4
M3 1.1

2.3 Pointing the exposed wall surface with cement mortar1:4 M2 1.1

3 Concrete work
3.1 Pouring 50mm thick lean concrete (1:2:6 mix) over the M2 7.8
hardcore
3.2 Casting 15cm thick Grade C-20 singly reinforced cover slab M3 1.2

3.3 Supply, cut, Bend & fixing Reinforcement bar DN 10 mm Kg 19


space @200mm
3.4 Supply, cut & fixing in positions sawn wooden form works
or equivalent properly erected in strutted with posts & slings M2 2
having tight joint not to bleed

4 Wall Work
4.1 Construction of corrugated galvanized iron sheets wall made
of G-32 CGI Sheet fixed to horizontal eucalyptus purlins of
DN 80mm spaced 90 cm with roof nail
M2 26

4.2 Supply and fixing stand poles diameter DN150mm round


eucalyptus tree anchored to masonry foundation wall with C-
15 concrete mix 50cm deep as design
M 27

4.3 Supply and fixing horizontal purlins diameter DN 80mm


round eucalyptus tree nailed to vertical posts spaced (a) 90 M 30
cm on centre

Page 40 of 44
Bill of Quantities for Public Latrine
I.N Unit
Description of work Unit Qty Rate
5 Roofing
5.1 Supply, assemble & fix roof truss spaced @ 1.25m as shown no 4
on the drawing

5.2 Supply and fix horizontal 5x4 cm zigba purlin spaced at


90cm and nailed to the upper truss m 12

5.3 Supply & fix G-32 G.I. Sheets with roof nail having washer
fixed to 5x4 cm zigba purlins spaced at 90 cm.
M2 15
6 Doors
6.1 “Tid or Equivalent wooden frame lockable doors made of G-
32 CGI sheets of single Leaf type 2.10m x 0.80m Pcs 2

7 Provide DN 65mm PVC pipe for ventilation m 3.5

Total Birr

Page 41 of 44
Amount
(Birr)

Page 42 of 44
Amount
(Birr)

Page 43 of 44
Bill of Quantity for 4-faucet Water point
S.N Description Unit Qty Unit Rate Amount (birr)

1 Earth work
1.1 Site clearing and striping of top soil to a minimum depth of 200) m2 24.2
Bulk excavation for up to a depth of 50cm below site clearing for
1.2 foundation (working space 25cm) m3 6.85
1.3 Excavation for foundation, soak away pit and valve chamber m3 5.4
Provide, fill and compact selected material in layers of 150mm,for
1.4 foundation. m3 6.85
Provide and fill hard core with hard basaltic or equivalent stone,
1.5 well compacted and blinded with crushed stone m3 3.5
Cart away and dispose all excavated material to approapriate
1.6 distance not exceeding 1Km m3 11.69
2 Concrete Work
2.1 C-15 lean concrete m3 0.3
2.2 C-20 concrete mass concrete m3 2.16
2.3 Concrete cylinder (Dia,1m and Hight,1m) No 1
2.4 Concrete cylinder (Dia, 30cm and Height, 1m) No 1
3 Masonry Work

Provide and construct 400mm thick trychytic masonry wall grouted


3.1 and filled with (1:3) mortar for foundation and super structure m3 2.37
3.2 Plastering to smooth finish for water point wall and surface m2 15
Provide and fix in place pre-cast R. concrete water seller seats as per
3.3 the drawing No 1
Masonry pavement around the water point as per the drawing (200
3.4 mm thick with 1:3 mortar) m2 7.6
4 Pipe work
4.1 Supplying and installing GS pipes
4.2 DN 40 GS pipe (variable) m 6
4.3 DN20 GS m 6
4.4 Supplying and fixing fittings
4.5 Cross tee DN 40 No 1
4.6 Reducer 40x20 No 4
4.7 Tee DN 40 No 1
4.8 DN 40 Bend (elbow) 90 degree No 5
4.9 Faucet DN 20 No 4
4.1 Socket DN 20 No 4
4.1 Gate valve DN 40 No 2
4.1 Union DN 40(variable) No 1
4.1 Nipple DN 40 No 6
4.1 Supply and install DN 40 water meter (approved quality) No 1
Construct two valve chambers for water meter and gate valve,
covered with 600*550*6mm sheet metal with latch and lock as per
4.2 the drawing No 2
Supply and place boulders, crashed aggregate and sand to form the
4.2 soak away as per the drawing m3 0.32
Total for one water point

You might also like