Daily Instructions

Uploaded by

atiatimk84
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

1.

General recommendation and procedure


a. M/U & RIH ESP
i. ESP Installation (Max acceptable OD 5.9")
ii. HPJM with all personnel involved. Discuss well control procedure while ESP M/U and ESP Tripping
iii. Measure all ESP dimensions
iv. Don’t
v. touch the power tong (Only TRS Team).
vi. ESP team representative to be on the rig floor all time to observe RIH ESP operation.
vii. Use Tbg Protector Pin & Box while P/U Tbg
viii. ** TIW to be installed above PKR & TRSV while M/U time
ix. ** Don’t move the string till ESP
x. Prepare final well schematic and check all OD, ID & length for all string assemblies
xi. Prepare final tally and confirm only required tubing on racks, mark Tbg at ESP PKR & TRSV
xii. Check and confirm availability of all required fitting
xiii. Provide all tool data and certification
xiv. Confirm all tools has been drifted
xv. Apply pressure in ALL CLs as integrity while RIH
xvi. All required fitting to be on location otherwise ask Zfod to provide fitting
xvii. Comp. to provide list of all required handling tools, slips, pup joint , XO…..
xviii. Confirm PKR Shear Value
xix. Check PKR range and compatibility with casing Wt.
xx. Check the availability ESP packer splice with all accessories
xxi. TIW to be installed above PKR & TRSV while M/U time
xxii. Function test and pressure test for AGV and TRSV with measuring of return are required
xxiii. Confirm availability of CL bands in case no cable use
xxiv. Completion engineer to check return from TRSV & AGV before and after landing (Vol should be same)
xxv. All joint that M/U directly to completion assembles, should be M/U pipe wrench and use JAM, never start directly with Power tong`
b. TRS to follow global procedure while RIH
i. Whenever complete R/U perform function test for JAM unit with Pup joint (Never start directly with the string joint)
ii. Check elevator load capacity / Whenever String Wt reach to 60 ton call WSL (Elevator capacity is 75 ton)
iii. Use Safety clamp till get sufficient wait ( at least first 20 Jts)
iv. All joint that M/U directly to completion assembles, should be M/U pipe wrench and use JAM, never start directly with Power tong
v. TRS Supv. to provide Min, Max & Opt torq for Tbg 3 ½” TSH-Blue 9.2# L-80 tubing and confirm value with FIC/Zfod
vi. Drift all Joint, & P.Jt X.Os & Assy before RIH // T.Hgr with X-O below
vii. TRS Supv. to monitor Tbg cleaning and check before P/U to the floor.
viii. Use API Dope on Pin side of Tbg
ix. Use Stabbing Guide during M/U
x. No Low or Hi shoulder chart are acceptable
xi. TRS team in completely responsible about the tally and count Tbg that RIH or POOH.
xii. Prepare and clean Tbg. Protector pin side to use when R/B Tbg to the derrick
xiii. Dope only the pin ends of tool joints sparingly with a paint brush. Wipe away any excess dope.
xiv. TRS Spv. To check all string components and provide all necessary accessories
xv. All tools and Equip should be suitable for ESP completion
xvi. No one from rig team touch the power tong (Only TRS Team).
xvii. Use tubing protector Pin and box while P/U the joint on V-Door
xviii. All make up tq should be as per attached manufacture paper

WSL Day WSL N TRS ESP WT Eng. CTU Spv. DST Spv. Tool Pusher RM Driller Client Rep