Yumbe Water Projects Work Program
Yumbe Water Projects Work Program
Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
0 CONSTRUCTION OF WATER SUPPLY SYSTEMS IN YUMBE SCHOOLS 77 days Tue 01/11/22 Wed 15/02/23
5 Fabrication and erection of project signpost 2 days Fri 04/11/22 Mon 07/11/22
10 Installation and removal of temporary casings 1 day Wed 30/11/22 Wed 30/11/22
11 Drilling 7.5" in fractured zone and consolidated formation 6 days Thu 01/12/22 Thu 08/12/22
12 Sampling and storing of drilled samples 1 day Fri 09/12/22 Fri 09/12/22
Page 1
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
13 Supply and installation of uPVC plain casing (5'' ND) 3 days Mon 12/12/22 Wed 14/12/22
14 Supply and installation of uPVC screen casing (5'' ND) 2 days Thu 15/12/22 Fri 16/12/22
15 Supply and installation of bottom cup 2 days Mon 19/12/22 Tue 20/12/22
16 Supply and installation of gravel pack (50 Kg bags) 2 days Wed 21/12/22 Thu 22/12/22
17 Supply and Installation of inert backfill 1 day Fri 23/12/22 Fri 23/12/22
21 TEST PUMPING AND WATER QUALITY ANALYSIS 17 days Wed 28/12/22 Thu 19/01/23
22 Test pump installation and removal 1 day Wed 28/12/22 Wed 28/12/22
23 Test pumping in 4 steps of 90 mins each 4 days Thu 29/12/22 Tue 03/01/23
24 Allowed recovery time before water sampling 1 day Wed 04/01/23 Wed 04/01/23
Page 2
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
26 Water quality analysis (Physio-Chemical) 5 days Fri 06/01/23 Thu 12/01/23
28 Casting of (1X1)m platform with pedestal fixing 2 days Tue 17/01/23 Wed 18/01/23
31 General site clearance for pipe trench 2 days Fri 13/01/23 Mon 16/01/23
33 Laying 90mm HDPE9 transmission pipeline 10 days Thu 26/01/23 Wed 08/02/23
36 Fabrication and installation of pedestrian gate 2 days Tue 31/01/23 Wed 01/02/23
Page 3
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
39 Construction of tank stand foundations 2 days Fri 20/01/23 Mon 23/01/23
40 Fabrication and erection of Tank stand 3 days Tue 24/01/23 Thu 26/01/23
41 Supply and installation of 10m3 storage tanks 2 days Wed 25/01/23 Thu 26/01/23
43 Supply and installation of submersible pumpset 2 days Fri 27/01/23 Mon 30/01/23
44 Installation of solar panels and electrical accessories 3 days Fri 27/01/23 Tue 31/01/23
46 All civil works for public stand post 4 days Fri 27/01/23 Wed 01/02/23
47 Pipework for stand post inclusive of all fittings 4 days Tue 31/01/23 Fri 03/02/23
51
Page 4
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
52 AMBIA 73 days Thu 03/11/22 Mon 13/02/23
56 Fabrication and erection of project signpost 2 days Tue 08/11/22 Wed 09/11/22
61 Installation and removal of temporary casings 1 day Fri 02/12/22 Fri 02/12/22
62 Drilling 7.5" in fractured zone and consolidated formation 6 days Mon 05/12/22 Mon 12/12/22
63 Sampling and storing of drilled samples 1 day Tue 13/12/22 Tue 13/12/22
64 Supply and installation of uPVC plain casing (5'' ND) 3 days Wed 14/12/22 Fri 16/12/22
Page 5
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
65 Supply and installation of uPVC screen casing (5'' ND) 2 days Mon 19/12/22 Tue 20/12/22
66 Supply and installation of bottom cup 2 days Wed 21/12/22 Thu 22/12/22
67 Supply and installation of gravel pack (50 Kg bags) 2 days Fri 23/12/22 Mon 26/12/22
68 Supply and Installation of inert backfill 1 day Tue 27/12/22 Tue 27/12/22
72 TEST PUMPING AND WATER QUALITY ANALYSIS 17 days Fri 30/12/22 Mon 23/01/23
73 Test pump installation and removal 1 day Fri 30/12/22 Fri 30/12/22
74 Test pumping in 4 steps of 90 mins each 4 days Mon 02/01/23 Thu 05/01/23
75 Allowed recovery time before water sampling 1 day Fri 06/01/23 Fri 06/01/23
Page 6
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
78 Well capping 2 days Tue 17/01/23 Wed 18/01/23
79 Casting of (1X1)m platform with pedestal fixing 2 days Thu 19/01/23 Fri 20/01/23
82 General site clearance for pipe trench 2 days Tue 17/01/23 Wed 18/01/23
84 Laying 90mm HDPE9 transmission pipeline 10 days Mon 30/01/23 Fri 10/02/23
87 Fabrication and installation of pedestrian gate 2 days Thu 02/02/23 Fri 03/02/23
Page 7
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
91 Fabrication and erection of Tank stand 3 days Thu 26/01/23 Mon 30/01/23
92 Supply and installation of 10m3 storage tanks 2 days Fri 27/01/23 Mon 30/01/23
94 Supply and installation of submersible pumpset 2 days Tue 31/01/23 Wed 01/02/23
95 Installation of solar panels and electrical accessories 3 days Tue 31/01/23 Thu 02/02/23
97 All civil works for public stand post 4 days Tue 31/01/23 Fri 03/02/23
98 Pipework for stand post inclusive of all fittings 4 days Thu 02/02/23 Tue 07/02/23
100 Commissioning and handing over 1 day Mon 13/02/23 Mon 13/02/23
101 Ambia project complete 0 days Mon 13/02/23 Mon 13/02/23 13/02
102
Page 8
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
104 PRELIMINARIES 17 days Mon 07/11/22 Tue 29/11/22
105 Mobilization and establishment on site 2 days Mon 07/11/22 Tue 08/11/22
107 Fabrication and erection of project signpost 2 days Thu 10/11/22 Fri 11/11/22
112 Installation and removal of temporary casings 1 day Tue 06/12/22 Tue 06/12/22
113 Drilling 7.5" in fractured zone and consolidated formation 6 days Wed 07/12/22 Wed 14/12/22
114 Sampling and storing of drilled samples 1 day Thu 15/12/22 Thu 15/12/22
115 Supply and installation of uPVC plain casing (5'' ND) 3 days Fri 16/12/22 Tue 20/12/22
116 Supply and installation of uPVC screen casing (5'' ND) 2 days Wed 21/12/22 Thu 22/12/22
Page 9
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
117 Supply and installation of bottom cup 2 days Fri 23/12/22 Mon 26/12/22
118 Supply and installation of gravel pack (50 Kg bags) 2 days Tue 27/12/22 Wed 28/12/22
119 Supply and Installation of inert backfill 1 day Thu 29/12/22 Thu 29/12/22
123 TEST PUMPING AND WATER QUALITY ANALYSIS 17 days Tue 03/01/23 Wed 25/01/23
124 Test pump installation and removal 1 day Tue 03/01/23 Tue 03/01/23
125 Test pumping in 4 steps of 90 mins each 4 days Wed 04/01/23 Mon 09/01/23
126 Allowed recovery time before water sampling 1 day Tue 10/01/23 Tue 10/01/23
128 Water quality analysis (Physio-Chemical) 5 days Thu 12/01/23 Wed 18/01/23
Page 10
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
130 Casting of (1X1)m platform with pedestal fixing 2 days Mon 23/01/23 Tue 24/01/23
133 General site clearance for pipe trench 2 days Thu 19/01/23 Fri 20/01/23
135 Laying 90mm HDPE9 transmission pipeline 10 days Wed 01/02/23 Tue 14/02/23
136 PUMP STATION SITE WORKS 9 days Thu 26/01/23 Tue 07/02/23
138 Fabrication and installation of pedestrian gate 2 days Mon 06/02/23 Tue 07/02/23
141 Construction of tank stand foundations 2 days Thu 26/01/23 Fri 27/01/23
142 Fabrication and erection of Tank stand 3 days Mon 30/01/23 Wed 01/02/23
Page 11
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
143 Supply and installation of 10m3 storage tanks 2 days Tue 31/01/23 Wed 01/02/23
145 Supply and installation of submersible pumpset 2 days Thu 02/02/23 Fri 03/02/23
146 Installation of solar panels and electrical accessories 3 days Thu 02/02/23 Mon 06/02/23
148 All civil works for public stand post 4 days Thu 02/02/23 Tue 07/02/23
149 Pipework for stand post inclusive of all fittings 4 days Mon 06/02/23 Thu 09/02/23
151 Commissioning and handing over 1 day Wed 15/02/23 Wed 15/02/23
152 Hilltop project complete 0 days Wed 15/02/23 Wed 15/02/23 15/02
153 All Projects Complete 0 days Wed 15/02/23 Wed 15/02/23 15/02