Yumbe Water Projects Work Program

Uploaded by

mosempt69
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views12 pages

Yumbe Water Projects Work Program

Uploaded by

mosempt69
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23

Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
0 CONSTRUCTION OF WATER SUPPLY SYSTEMS IN YUMBE SCHOOLS 77 days Tue 01/11/22 Wed 15/02/23

1 ABIRIAMAJO 72 days Tue 01/11/22 Wed 08/02/23

2 PRELIMINARIES 17 days Tue 01/11/22 Wed 23/11/22

3 Mobilization and establishment on site 2 days Tue 01/11/22 Wed 02/11/22

4 Construction of temporary facilities 2 days Thu 03/11/22 Fri 04/11/22

5 Fabrication and erection of project signpost 2 days Fri 04/11/22 Mon 07/11/22

6 Hydrogeological survey 14 days Fri 04/11/22 Wed 23/11/22

7 BOREHOLE CONSTRUCTION 25 days Thu 24/11/22 Wed 28/12/22

8 Setting up at every site 2 days Thu 24/11/22 Fri 25/11/22

9 Drilling 10" in overburden 2 days Mon 28/11/22 Tue 29/11/22

10 Installation and removal of temporary casings 1 day Wed 30/11/22 Wed 30/11/22

11 Drilling 7.5" in fractured zone and consolidated formation 6 days Thu 01/12/22 Thu 08/12/22

12 Sampling and storing of drilled samples 1 day Fri 09/12/22 Fri 09/12/22

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 1
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
13 Supply and installation of uPVC plain casing (5'' ND) 3 days Mon 12/12/22 Wed 14/12/22

14 Supply and installation of uPVC screen casing (5'' ND) 2 days Thu 15/12/22 Fri 16/12/22

15 Supply and installation of bottom cup 2 days Mon 19/12/22 Tue 20/12/22

16 Supply and installation of gravel pack (50 Kg bags) 2 days Wed 21/12/22 Thu 22/12/22

17 Supply and Installation of inert backfill 1 day Fri 23/12/22 Fri 23/12/22

18 Casting of sanitary seal 1 day Mon 26/12/22 Mon 26/12/22

19 Well development 1 day Tue 27/12/22 Tue 27/12/22

20 Dismantling at every site 1 day Wed 28/12/22 Wed 28/12/22

21 TEST PUMPING AND WATER QUALITY ANALYSIS 17 days Wed 28/12/22 Thu 19/01/23

22 Test pump installation and removal 1 day Wed 28/12/22 Wed 28/12/22

23 Test pumping in 4 steps of 90 mins each 4 days Thu 29/12/22 Tue 03/01/23

24 Allowed recovery time before water sampling 1 day Wed 04/01/23 Wed 04/01/23

25 Water sampling 1 day Thu 05/01/23 Thu 05/01/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 2
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
26 Water quality analysis (Physio-Chemical) 5 days Fri 06/01/23 Thu 12/01/23

27 Well capping 2 days Fri 13/01/23 Mon 16/01/23

28 Casting of (1X1)m platform with pedestal fixing 2 days Tue 17/01/23 Wed 18/01/23

29 Clearing site 1 day Thu 19/01/23 Thu 19/01/23

30 TRANSMISSION PUMPING MAINS 19 days Fri 13/01/23 Wed 08/02/23

31 General site clearance for pipe trench 2 days Fri 13/01/23 Mon 16/01/23

32 Excavation in pipe trenches 14 days Tue 17/01/23 Fri 03/02/23

33 Laying 90mm HDPE9 transmission pipeline 10 days Thu 26/01/23 Wed 08/02/23

34 PUMP STATION SITE WORKS 9 days Fri 20/01/23 Wed 01/02/23

35 Chain link fencing 7 days Fri 20/01/23 Mon 30/01/23

36 Fabrication and installation of pedestrian gate 2 days Tue 31/01/23 Wed 01/02/23

37 Construction of well head 2 days Tue 31/01/23 Wed 01/02/23

38 STORAGE OVERHEAD RESERVOIR 5 days Fri 20/01/23 Thu 26/01/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 3
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
39 Construction of tank stand foundations 2 days Fri 20/01/23 Mon 23/01/23

40 Fabrication and erection of Tank stand 3 days Tue 24/01/23 Thu 26/01/23

41 Supply and installation of 10m3 storage tanks 2 days Wed 25/01/23 Thu 26/01/23

42 BOREHOLE PUMPS 3 days Fri 27/01/23 Tue 31/01/23

43 Supply and installation of submersible pumpset 2 days Fri 27/01/23 Mon 30/01/23

44 Installation of solar panels and electrical accessories 3 days Fri 27/01/23 Tue 31/01/23

45 PUBLIC STAND POSTS 9 days Fri 27/01/23 Wed 08/02/23

46 All civil works for public stand post 4 days Fri 27/01/23 Wed 01/02/23

47 Pipework for stand post inclusive of all fittings 4 days Tue 31/01/23 Fri 03/02/23

48 Construction of soakway pit 2 days Mon 06/02/23 Tue 07/02/23

49 Commissioning and handing over 1 day Wed 08/02/23 Wed 08/02/23

50 Abiriamajo project complete 0 days Wed 08/02/23 Wed 08/02/23 08/02

51

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 4
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
52 AMBIA 73 days Thu 03/11/22 Mon 13/02/23

53 PRELIMINARIES 17 days Thu 03/11/22 Fri 25/11/22

54 Mobilization and establishment on site 2 days Thu 03/11/22 Fri 04/11/22

55 Construction of temporary facilities 2 days Mon 07/11/22 Tue 08/11/22

56 Fabrication and erection of project signpost 2 days Tue 08/11/22 Wed 09/11/22

57 Hydrogeological survey 14 days Tue 08/11/22 Fri 25/11/22

58 BOREHOLE CONSTRUCTION 25 days Mon 28/11/22 Fri 30/12/22

59 Setting up at every site 2 days Mon 28/11/22 Tue 29/11/22

60 Drilling 10" in overburden 2 days Wed 30/11/22 Thu 01/12/22

61 Installation and removal of temporary casings 1 day Fri 02/12/22 Fri 02/12/22

62 Drilling 7.5" in fractured zone and consolidated formation 6 days Mon 05/12/22 Mon 12/12/22

63 Sampling and storing of drilled samples 1 day Tue 13/12/22 Tue 13/12/22

64 Supply and installation of uPVC plain casing (5'' ND) 3 days Wed 14/12/22 Fri 16/12/22

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 5
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
65 Supply and installation of uPVC screen casing (5'' ND) 2 days Mon 19/12/22 Tue 20/12/22

66 Supply and installation of bottom cup 2 days Wed 21/12/22 Thu 22/12/22

67 Supply and installation of gravel pack (50 Kg bags) 2 days Fri 23/12/22 Mon 26/12/22

68 Supply and Installation of inert backfill 1 day Tue 27/12/22 Tue 27/12/22

69 Casting of sanitary seal 1 day Wed 28/12/22 Wed 28/12/22

70 Well development 1 day Thu 29/12/22 Thu 29/12/22

71 Dismantling at every site 1 day Fri 30/12/22 Fri 30/12/22

72 TEST PUMPING AND WATER QUALITY ANALYSIS 17 days Fri 30/12/22 Mon 23/01/23

73 Test pump installation and removal 1 day Fri 30/12/22 Fri 30/12/22

74 Test pumping in 4 steps of 90 mins each 4 days Mon 02/01/23 Thu 05/01/23

75 Allowed recovery time before water sampling 1 day Fri 06/01/23 Fri 06/01/23

76 Water sampling 1 day Mon 09/01/23 Mon 09/01/23

77 Water quality analysis (Physio-Chemical) 5 days Tue 10/01/23 Mon 16/01/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 6
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
78 Well capping 2 days Tue 17/01/23 Wed 18/01/23

79 Casting of (1X1)m platform with pedestal fixing 2 days Thu 19/01/23 Fri 20/01/23

80 Clearing site 1 day Mon 23/01/23 Mon 23/01/23

81 TRANSMISSION PUMPING MAINS 19 days Tue 17/01/23 Fri 10/02/23

82 General site clearance for pipe trench 2 days Tue 17/01/23 Wed 18/01/23

83 Excavation in pipe trenches 14 days Thu 19/01/23 Tue 07/02/23

84 Laying 90mm HDPE9 transmission pipeline 10 days Mon 30/01/23 Fri 10/02/23

85 PUMP STATION SITE WORKS 9 days Tue 24/01/23 Fri 03/02/23

86 Chain link fencing 7 days Tue 24/01/23 Wed 01/02/23

87 Fabrication and installation of pedestrian gate 2 days Thu 02/02/23 Fri 03/02/23

88 Construction of well head 2 days Thu 02/02/23 Fri 03/02/23

89 STORAGE OVERHEAD RESERVOIR 5 days Tue 24/01/23 Mon 30/01/23

90 Construction of tank stand foundations 2 days Tue 24/01/23 Wed 25/01/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 7
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
91 Fabrication and erection of Tank stand 3 days Thu 26/01/23 Mon 30/01/23

92 Supply and installation of 10m3 storage tanks 2 days Fri 27/01/23 Mon 30/01/23

93 BOREHOLE PUMPS 3 days Tue 31/01/23 Thu 02/02/23

94 Supply and installation of submersible pumpset 2 days Tue 31/01/23 Wed 01/02/23

95 Installation of solar panels and electrical accessories 3 days Tue 31/01/23 Thu 02/02/23

96 PUBLIC STAND POSTS 10 days Tue 31/01/23 Mon 13/02/23

97 All civil works for public stand post 4 days Tue 31/01/23 Fri 03/02/23

98 Pipework for stand post inclusive of all fittings 4 days Thu 02/02/23 Tue 07/02/23

99 Construction of soakway pit 2 days Wed 08/02/23 Thu 09/02/23

100 Commissioning and handing over 1 day Mon 13/02/23 Mon 13/02/23

101 Ambia project complete 0 days Mon 13/02/23 Mon 13/02/23 13/02

102

103 HILLTOP 73 days Mon 07/11/22 Wed 15/02/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 8
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
104 PRELIMINARIES 17 days Mon 07/11/22 Tue 29/11/22

105 Mobilization and establishment on site 2 days Mon 07/11/22 Tue 08/11/22

106 Construction of temporary facilities 2 days Wed 09/11/22 Thu 10/11/22

107 Fabrication and erection of project signpost 2 days Thu 10/11/22 Fri 11/11/22

108 Hydrogeological survey 14 days Thu 10/11/22 Tue 29/11/22

109 BOREHOLE CONSTRUCTION 25 days Wed 30/11/22 Tue 03/01/23

110 Setting up at every site 2 days Wed 30/11/22 Thu 01/12/22

111 Drilling 10" in overburden 2 days Fri 02/12/22 Mon 05/12/22

112 Installation and removal of temporary casings 1 day Tue 06/12/22 Tue 06/12/22

113 Drilling 7.5" in fractured zone and consolidated formation 6 days Wed 07/12/22 Wed 14/12/22

114 Sampling and storing of drilled samples 1 day Thu 15/12/22 Thu 15/12/22

115 Supply and installation of uPVC plain casing (5'' ND) 3 days Fri 16/12/22 Tue 20/12/22

116 Supply and installation of uPVC screen casing (5'' ND) 2 days Wed 21/12/22 Thu 22/12/22

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 9
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
117 Supply and installation of bottom cup 2 days Fri 23/12/22 Mon 26/12/22

118 Supply and installation of gravel pack (50 Kg bags) 2 days Tue 27/12/22 Wed 28/12/22

119 Supply and Installation of inert backfill 1 day Thu 29/12/22 Thu 29/12/22

120 Casting of sanitary seal 1 day Fri 30/12/22 Fri 30/12/22

121 Well development 1 day Mon 02/01/23 Mon 02/01/23

122 Dismantling at every site 1 day Tue 03/01/23 Tue 03/01/23

123 TEST PUMPING AND WATER QUALITY ANALYSIS 17 days Tue 03/01/23 Wed 25/01/23

124 Test pump installation and removal 1 day Tue 03/01/23 Tue 03/01/23

125 Test pumping in 4 steps of 90 mins each 4 days Wed 04/01/23 Mon 09/01/23

126 Allowed recovery time before water sampling 1 day Tue 10/01/23 Tue 10/01/23

127 Water sampling 1 day Wed 11/01/23 Wed 11/01/23

128 Water quality analysis (Physio-Chemical) 5 days Thu 12/01/23 Wed 18/01/23

129 Well capping 2 days Thu 19/01/23 Fri 20/01/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 10
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
130 Casting of (1X1)m platform with pedestal fixing 2 days Mon 23/01/23 Tue 24/01/23

131 Clearing site 1 day Wed 25/01/23 Wed 25/01/23

132 TRANSMISSION PUMPING MAINS 19 days Thu 19/01/23 Tue 14/02/23

133 General site clearance for pipe trench 2 days Thu 19/01/23 Fri 20/01/23

134 Excavation in pipe trenches 14 days Mon 23/01/23 Thu 09/02/23

135 Laying 90mm HDPE9 transmission pipeline 10 days Wed 01/02/23 Tue 14/02/23

136 PUMP STATION SITE WORKS 9 days Thu 26/01/23 Tue 07/02/23

137 Chain link fencing 7 days Thu 26/01/23 Fri 03/02/23

138 Fabrication and installation of pedestrian gate 2 days Mon 06/02/23 Tue 07/02/23

139 Construction of well head 2 days Mon 06/02/23 Tue 07/02/23

140 STORAGE OVERHEAD RESERVOIR 5 days Thu 26/01/23 Wed 01/02/23

141 Construction of tank stand foundations 2 days Thu 26/01/23 Fri 27/01/23

142 Fabrication and erection of Tank stand 3 days Mon 30/01/23 Wed 01/02/23

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 11
ID Task Name Duration Start Finish Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 06 13 20 27 06
143 Supply and installation of 10m3 storage tanks 2 days Tue 31/01/23 Wed 01/02/23

144 BOREHOLE PUMPS 3 days Thu 02/02/23 Mon 06/02/23

145 Supply and installation of submersible pumpset 2 days Thu 02/02/23 Fri 03/02/23

146 Installation of solar panels and electrical accessories 3 days Thu 02/02/23 Mon 06/02/23

147 PUBLIC STAND POSTS 10 days Thu 02/02/23 Wed 15/02/23

148 All civil works for public stand post 4 days Thu 02/02/23 Tue 07/02/23

149 Pipework for stand post inclusive of all fittings 4 days Mon 06/02/23 Thu 09/02/23

150 Construction of soakway pit 2 days Fri 10/02/23 Mon 13/02/23

151 Commissioning and handing over 1 day Wed 15/02/23 Wed 15/02/23

152 Hilltop project complete 0 days Wed 15/02/23 Wed 15/02/23 15/02

153 All Projects Complete 0 days Wed 15/02/23 Wed 15/02/23 15/02

Task Inactive Task Manual Summary Rollup External Milestone

Split Inactive Milestone Manual Summary Deadline


Project: CONSTRUCTION OF W
Milestone Inactive Summary Start-only Progress
Date: Mon 03/10/22
Summary Manual Task Finish-only Manual Progress

Project Summary Duration-only External Tasks

Page 12