Use of Project Schedules and The Critical Path Method in Claims
Use of Project Schedules and The Critical Path Method in Claims
CHAPTER 7
7-1. INTRODUCTION
It is customary for a contractor to create, whether contractually required
or not, some type of progress schedule that defines how the job will be
performed, as well as submit regular updates to measure actual progress and
reaffirm established completion dates. Schedules can be in the form of bar
charts, flowcharts or critical path method (CPM) network diagrams. During
actual performance of the job, other schedules can come into play, such as
short-interval or look-ahead schedules, which break larger, overall project
schedules into more detailed tasks for immediately upcoming phases of
work. In all these cases, schedules are used to plan the work, and later on,
are analyzed to determine responsibility for delays encountered on the proj-
ect. Since CPM analysis is frequently used, and often specified as a means,
to substantiate delay and acceleration claims, this chapter discusses consid-
erations regarding use of CPM schedules to analyze time-related claims and
changes.
Prior to 1980, the use of critical path scheduling was by either contract-
ing with a service bureau or through use of in-house data processing capabil-
ities of companies large enough to retain the computer hardware, software,
and support knowledge required to run the programs. This created a situa-
tion whereby jobsite personnel worked, or attempted to work, with sched-
ules that had been updated once a month at best, and, more often than not,
updated only to satisfy contract requirements.
With the advent of the personal computer, desktop critical path schedul-
ing programs became available at reasonable cost and slowly became uti-
lized by more contractors as an interactive scheduling tool. Today, there are
a number of easy-to-use scheduling programs available. Many more con-
tracts today require the use of a critical path schedule, and some contracts
require them for calculating the contractor's monthly progress payments.
Using the CPM software's capability for cost loading activities, the earned
value of the work complete is computed based on the percentage comple-
tion of activities performed in the period.
'Richard H. Clough, Construction Project Management (New York, John Wiley & Sons,
Inc., 1972), pp. 7-8.
forces the contractor to study operations in detail, with careful planning and
Downloaded from ascelibrary.org by University of Texas at San Antonio on 09/18/15. Copyright ASCE. For personal use only; all rights reserved.
While these apparent concerns may be valid, the benefits of CPM sched-
uling most often far outweigh these obstacles. In some cases, these issues
can be addressed with such actions as additional resources, training, and/or
the use of a simplified or alternative schedules made specifically for the use
of field personnel.
2
Chaney & lames Co. v. U.S., 190 Ct. Cl. 699 (1970); also see Titan Pacific Construction
Corp. v. U.S., 17 Cl. Ct. 630 (1989). (An as-planned CPM schedule was not conclusive regard-
ing delay impact because the contractor failed to follow the schedule during construction.)
the CPM presentation to the job is "the single most important factor in
determining the acceptability of the contractor's CPM-based claim/'3 To
Downloaded from ascelibrary.org by University of Texas at San Antonio on 09/18/15. Copyright ASCE. For personal use only; all rights reserved.
1. The network was not used either in the preparation of the bid
or in the management of the project. Failure to use the CPM in
executing the work pursuant to contract requirements may give
rise to a claim for breach of express or implied warranties. The
fact that the system was not used or implemented will not
prevent the claimant from using a CPM analysis to compare the
originally approved schedule with an 'as built' chart to support
his breach claim or to support a delay or disruption claim. This
assumes, of course, that documentation is available to support
the analysis. Frequently, such data is not available when the
system was ignored during performance.
2. The diagram and network analysis were prepared specifically
for use in the presentation of the claim before the board or
court and had no real relevance to the actual scheduling em-
ployed.
3. The contractor's expert witness could only testify that the pre-
sentation 'appeared logical' and looked right,' since he had
not made a detailed analysis of all relevant job records or other
documentation, nor had he made a site inspection before or
after the project was complete. It is absolutely necessary to
have a fully competent expert witness who will not only review
all of the relevant records and make a detailed and independent
analysis, but who also can make a convincing presentation at
trial.
4. The contractor offered no evidence to support his claim that
the key activity was critical to job progress or on the critical
path.
5. The original network contained numerous mathematical errors,
or failed to consider foreseeable weather or labor conditions,
for this proper adjustment was not made in the analysis.4
3
Wickwire and Smith, 1974, p. 13. [Also see Appeal of Titan Mountain States Construction
Corp., ASBCA No. 2-3095 (Feb. 21, 1985). (CPM consultant's work product was not persuasive
because it did not address the cause and effect of delay in the field.)]
4
A. James Waldron, Publisher, The Legal Implications of a Project Schedule, (Haddonfield,
N.J., Waldron Enterprises, 1974), pp. XIII-3 and XIII-4.
relies on CPM scheduling. The contractor should also submit to the owner,
along with the CPM schedule, a transmittal letter that very specifically notes
the flexibility and limited responsibility provisions of the schedule. Appen-
dix 11 contains an example of a cover letter that illustrates this approach.
5
Note, concerning this last item, pay quantities may be useful in that they represent an
agreement between the owner and the contractor on work completed. Thus, when it comes
time to discuss progress of work at any given date on the CPM, agreed quantities would reduce
disagreements on measuring progress. Some contracts require progress payments to be based
on CPM updates. However, some contractors may find use of pay quantities distracts from the
CPM's intended purpose as a planning and scheduling tool.
critical path (in terms of float time) since these activities closely
precede or follow the activities on the critical path.
7-5. FLOAT
Float, in simple terms, is the time period between scheduled early finish
and late finish of an activity in the CPM schedule. Allocation of float time
has often been a source of controversy in disputes involving delays, suspen-
sions, and change orders. At issue is the right to use available float time-
does it belong to the contractor or to the owner? If the contractor is able to
finish early, is he still obligated to be available through the contract comple-
tion date to perform change orders affecting activities that have float (either
during performance or after completion of the original contract work)? If the
contractor has a 15-day float period, for example, and experiences two
sequential 10-day delays (one 10-day delay his own fault and the other due
to the owner) is the contractor entitled to a five-day contract extension?
Those questions are often answered by determining which party used
the float first. In other words, the float belongs to neither party but is for the
use of both parties7. If the owner orders a 10-day suspension of an activity,
the contractor is still on schedule and has five days float left on that activity.
Subsequently, the contractor falls behind in his work by 10 days, finishes the
contract five days late but is not granted a contract extension. Why? Because
at the time the suspension occurred, the overall contract completion date
was not affected. If the contractor, however, was 10 days late on the item
before the suspension occurred (and had only five days float on the item), he
would then be entitled to a five-day contract extension.
6
Jon M. Wickwire and Richard F. Smith, "The Use of Critical Path Method Techniques in
Contract Claims/' Public Contract Law Journal I (October, 1974): pp. 5-7.
7
The nonexclusive use of float time is explicitly stated in various scheduling specifications,
such as the Corp of Engineers' NAS Section, ER 1-1-11 and the Washington Metropolitan Area
Transit Authority's Appendix F. The most recent version of the NAS specification has omitted
this clause.
date. The owner feels that since the contract gives him the right to issue change
Downloaded from ascelibrary.org by University of Texas at San Antonio on 09/18/15. Copyright ASCE. For personal use only; all rights reserved.
orders, it allows him to use any available time (float) during the contract perfor-
mance period, and thus requires the contractor to perform changes right up to
the contract completion date. While the boards and courts have not been
uniform in their treatment of this issue, the trend now leans toward the contrac-
tor's right to finish early. The following comments supporting this position are
taken from the Construction Contract Negotiating Guide
would have been able to finish early but for the government-caused delay,
Downloaded from ascelibrary.org by University of Texas at San Antonio on 09/18/15. Copyright ASCE. For personal use only; all rights reserved.
and therefore awarded it compensation for delay, despite the fact that the
contractor's original schedule did not show early completion. In other
words, the Board ruled that the owner did not have the right to use available
float if the owner's action delayed performance of the contractor's work. It is
instructive to take a closer look at why the contractor did not show early
completion on its progress chart
10
lbid.
example, it would be best to notify the other party as soon as possible of its
Downloaded from ascelibrary.org by University of Texas at San Antonio on 09/18/15. Copyright ASCE. For personal use only; all rights reserved.
intentions. Such notification would eliminate ambiguities and give the other
party an opportunity to react or adjust its own schedules and intentions. As
is discussed in the next section, there are a variety of approaches to schedule
analysis in an area that continues to evolve.
The contractor can choose to make up for delays on his own by accelera-
tion or by performing critical items of work concurrently. In so doing, he is
entitled to the time saved by his efforts. If the contractor expedites his work
without a directive or condition of constructive acceleration the work will
be considered voluntary.
As discussed in chapter 5, the contractor is not required to accelerate
unless directed to do so by the owner, or so as to adhere to original schedule
requirements when excusable delays have been encountered, but time ex-
tensions not granted (constructive acceleration). The contractor should be
careful to show on his schedule where activities and logic changes are for
constructive acceleration efforts as opposed to those that are for its own
acceleration purposes (make up for contractor delays; attempts at early com-
pletion).
1. Impacted as-planned
2. Fragnet ("windows, chronological impact")
3. Time impact analysis
4. Collapsed as-built ("but for")
1. Has any activity been moved from where the contractor had it
scheduled into a season where normal weather is more unfa-
vorable or makes it impractical to do this type of work?
2. Are there now more activities in progress at a given time than
indicated by the schedule before revision?
3. Have any activities slipped to the extent that significant phases
of the work, such as closing in a building for winter, providing
necessary utilities, completing an access road, building a coffer
dam, etc., will not be accomplished before some overriding
factor (winter, high water stages, unavailability of site) prevent
it, thus making it necessary to defer a portion of the work until
the next favorable season?
are made to the remaining schedule, such as logic changes to mitigate the
impacts, and a new adjusted schedule is computed. The difference between
the completion date of the new adjusted as-built schedule and the prior
baseline becomes the amount of time the project is delayed.
The new adjusted schedule also becomes the baseline for the next pe-
riod to be analyzed. As each window is analyzed, the various category of
delays are tallied, that is, contractor-caused, owner-caused, and excusable
noncompensable. After stepping through the complete series, the final ex-
tended completion date is determined along with the various categories of
delay, which can be used for calculating impact costs. Typically, impact
costs would be calculated at the time of the impact, as the level of delay
costs will vary from period to period.
Depending on how the method is applied, it may or may not take into
account concurrent or "near-critical" delays. Some scheduling experts only
look at the longest delaying activity (controlling impact) in a given window.
Schedule A)
Type of
Schedule Point of
Analysis Reference Schedule A Schedule B
Impacted "Day 1" Original Impacted
As-Planned As-Planned As-Planned
Schedule Schedule
Fragnet Start of Impact Contemporane- Schedule A
Approach ous Schedule at with firagnet
start of impact inserted
Time Impact Conclusion of Schedule Schedule
Analysis Impact update at update through
conclusion of conclusion of
prior impact impact
Collapsed Conclusion of Collapsed As- As-Built
As-Built Project Built Schedule Schedule
7-11. CONCLUSION
The contractor should consider the compilation and use of CPM sched-
uling techniques as a valuable tool and not just a nuisance contract require-
ment. The as-planned CPM should be constructed realistically and accu-
rately, and the schedule should be updated on a regular basis to reflect
actual events, durations, and start and stop times. The schedule clauses
should also be read carefully because each contract may demand different
scheduling and update requirements of the contractor. Finally, the boards
and courts have become sophisticated in the understanding of CPM schedul-
ing theory and will look for the underlying proof of cause and effect relation-
ships before relying on the schedule analysis presentations provided by the
parties.