SIMOPs of Precom Activities Rev. A1
SIMOPs of Precom Activities Rev. A1
A1
Document Title:
Highlights of Rev. A1
ARCC Page 1 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
TABLE OF CONTENTS
1.0 PURPOSE 3
2.0 SCOPE 3
3.0 REFERENCES 3
4.0 DEFINITIONS 3
5.0 RESPONSIBILITIES 4
5.1 Project Manager / In-Charge 4
5.2 Pre-commissioning / Commissioning Manager 4
5.3 Project HSSE Manager / Representative 5
6.0 REQUIREMENTS 5
6.1 Planning of Resources 5
6.2 Simultaneous Operation of Pre-commissioning Activities 7
6.3 General Guidelines for Pre-commission Activities 12
7.0 FORM 13
ARCC Page 2 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
1.0 PURPOSE
This procedure was developed to provide Health, Safety & Environmental (HSE)
instruction for controlling simultaneous pre-commissioning / commissioning activities
during the final stage of construction work on ARCC projects to protect persons working
at site against potential hazards of these activities as well as protecting the environment.
2.0 SCOPE
This procedure covers all preparatory, routine and non-routine commissioning activities
of ARCC without interfering construction work at projects. The main pre-
commissioning activities are divided into different categories depending upon sequential
preparatory activities of various systems and subsystems of a unit. The principle
activities include;
Inspection of equipments
Water flushing and cleaning
Blowing Operations
Pressure testing
Tightness testing
Purge and gas blanketing
Functional Test of Rotating Equipments
Instruments checking
Safety device checking
3.0 REFERENCES
4.0 DEFINITIONS
4.1.1 Air Blowing - passing pressurized air through pipeline with full flow.
4.1.3 Battery limit – entry / exit point and isolation valve on any pipeline of a unit
in a process plant.
4.1.4 Hydro test - pressure test carried out using water as pressurizing medium.
4.1.5 Pneumatic test - pressure test conducted using air / nitrogen as pressurizing
medium.
ARCC Page 3 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
4.1.7 Punch point list - Punch list contains all mechanical outstanding items at
Pre-commissioning stage to be carried out as per P&IDs and engineering
Drawings.
5.0 RESPONSIBILITIES
The main responsibility for the pre-commissioning / commissioning activities lies with
the plant operation group. However, the detailed responsibilities are described as;
ARCC Page 4 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
5.3 Project HSSE Manager / Representative – shall ensure that all pre-
commissioning / commissioning personnel are properly trained to adhere work
permit system, use personnel protective equipments as per plant pre-commissioning
/ commissioning, operation and chemicals hazard.
6.0 REQUIREMENTS
The Commissioning Manager is the sole responsible for all the pre-
commissioning activities in the area including providing blinds and tie-in as
per the requirement for these activities.
ARCC Page 5 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
ARCC Page 6 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
Aspects and impacts that will have a significant effect on the environment
based on the analysis shall be given control measures prior to the execution
of work. The commissioning team shall develop this control measures,
implement, monitor and recommend improvement plans to mitigate impacts
the environment.
For pre-commissioning activities, the unit is divided into systems and subsystems
according to equipment like vessels, columns, heaters, Exchangers, pumps,
compressors, piping etc. and associated lines. These activities performed as per the
following:
2) For vessel entry - work permit for Vessel entry / Confined space to be
strictly followed for this activity with proper access and egress, rescue
team, continuous air purging, proper illumination and emergency
evacuation to be provided.
The water flushing and cleaning activities using high pressure water is
carried out to clean and flushing of the equipments and associated lines to
remove dirt, scale, welding bits and left out material.
All piping & equipments are isolated and blinded at each opening of the
flanged joints with a thin metallic sheet / blind to prevent dirty water from
entering to connected equipment or piping. Tube lancing, rotating nozzle jet
assemblies are used for inside tube cleaning of exchangers. Shotgun single
jet blasting is also used for surface cleaning of equipments.
ARCC Page 7 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
Proper and correct size of tools should be used for blinding and hose
connection purpose and no adjustable tools having serrated jaws like
slide wrench permitted.
The personnel engaged in this activity must work in crew system with
minimum numbers of two persons in a crew and must follow the
checklist given as Table-II (see Attachment A: Table II Checklist
minimum safety precautions during water flushing and cleaning).
The safety precautions for blowing operations of air and steam blowing are
described here.
1) Air blowing
All air, gas and vapor lines of the unit are air blown completely from
battery limit with strong flow of pressurized air to clean and dry the
lines including associated drains and vents connections.
2) Steam Blowing
All steam lines (Low, Medium or High pressure) of the unit are steam
blown completely from battery limit to clean the steam network
including associated drains and vents connection with the steam. The
effectiveness of the steam blowing is gauged by providing target plates.
The lines should be repeatedly blown down until virtually unmarked
target plates are obtained.
3) Safety measures for these activities are tabulated in Table – III (see
Attachment A: Table III Checklist minimum safety precautions during
blowing operations).
All the equipments and piping are pressure tested as per service and pressure
profile. The pressure rise to be checked on several pressure gauges and at
least one calibrated pressure gauge must be used in the system coupled with
pressure recorder. For pressure testing of a vessel, the test gauge should be
placed at the bottom of the vessel to account liquid head. Highest vent
must be opened while hydro test to remove any trapped air.
ARCC Page 8 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
At the completion of the hydrostatic test, all water must be removed from
the equipment and if required, flanges may be opened to drain low points
and the equipment air blown to remove as much water as possible before
boxed up.
The initial leak tests can be performed using air to check tightness of
flanges, joints, manholes etc. (except pumps and control instruments) in the
unit. The test pressure will be the air pressure or the design pressure and
leaks must be carefully located using soap solution and tightened.
The inerting of unit equipments and pipelines is carried out using Nitrogen
under pressure to prevent rusting of the internals from corrosion due to
oxygen in the air which can develop any flammable mixture at initial
charging of hydrocarbons.
ARCC Page 9 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
1) General guidelines
All instrument tapings for pressure, level and flow should be clear and
thermowells should not foul with the internals. These should be checked
prior to box up of the equipment with respect to P&IDs.
Alarms, field gas detectors and support system relevant set points to be
provided as per safety analysis function evaluation charts to completely
safeguard the unit.
ARCC Page 10 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
All passive and active fire fighting system shall be arranged considering
safety of life, environment and predominant combustible / flammable
materials present, as per NFPA and other international codes &
standards and confirm the design by risk assessment.
Fire protection systems may be checked as per system selected at site. The
general facilities include;
ARCC Page 11 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
ARCC Page 12 of 13
Originator: Approved By:
SIMULTANEOUS OPERATIONS OF PRE-
COMMISSIONING ACTIVITIES
JRC Atienza RVE / MTM
Doc. No. ARP-HSSE-SWP-037 Rev. No. A1 Date: Date:
c) Ball valve must be used in the pipelines which do not cause any
problem of reduction of diameter of the pipeline.
d) Apron, rubber hand gloves, safety shoes with steel toe, respirators
and helmet are the main personnel protective equipments to be worm
whiling handling solid waste disposal.
e) General arrangement for disposal and control of hazardous substance
and waste management to be strictly followed as per policy
requirements and work culture.
6.3.1 Oil, testing water or chemical spills shall be cleaned up. Spill kit shall be
provided at the worksite.
6.3.2 Ensure proper housekeeping on all waste materials, debris lying around and
other potential cause of incidents.
6.3.3 All equipment / piping / rotary machines are grounded and continuity to be
checked and comply with electrical safety requirements.
6.3.7 Road / access closure permit shall be applied on areas greatly affected by
simultaneous operations of pre-commissioning activities.
7.0 FORM
ARCC Page 13 of 13