Johannesburg Development Agency (Jda) Jda Gpe-Fs Cn002: A.8.3.2 AB.3.2 A.8.3.2.2
Johannesburg Development Agency (Jda) Jda Gpe-Fs Cn002: A.8.3.2 AB.3.2 A.8.3.2.2
1.1 8.3.1 Contractual Requirements, Sureties and Insurance Sum 1.0 R - 0.00
1.2 AB.3.2 Offices for Engineer and staff and notice board Sum 1.0 R29,400.00 29,400.00
1.10 A.8.3.3 Other fixed-charge obligations: setting out, security and deviations sum 0.00
1.12 A.8.4.5 Contractor’s obligations in respect of the Occupational Health and sum 1.0 R25,000.00 25,000.00
Safety Act and any other Health & Safety regulations as may be
applicable.
1.14 A.8.4.1 Contractual requirements, sureties & insurance sum 1.0 0.00
1.15 A.8.4.2 Operate & maintain facilities for the duration of the sum 1.0 0.00
contract
1.16 AB.3.2 Offices for Engineer & staff and notice board sum 1.0 0.00
1.26 A.8.4.4 Company & head office overhead costs for the duration of the contract sum 1.0 0.00
1.27 A.8.4.5 Other time-related obligations: setting out, survey for as-built drawings, sum 1.0 0.00
security, deviations and dealing with traffic.
1.30 A 8.5.1 a) Testing of materials by the Engineer Prov 1.0 30,000.00 30,000.00
1.31 b) Overheads, charges and profit on (a) above sum
% 30,000.0 10.00 3,000.00
Quality Control
1.33 c) Quality control testing by the Engineer during installation Prov 1.0 40,000.00 40,000.00
1.34 d) Overheads, charges and profit on (c) above sum
% 40,000.0 10.00 4,000.00
2.2 C.8.2.10 Remove approx. 150mm topsoil & stockpile m2 44775 R 75.00 3,358,125.00
2.3 C 8.2.12 Remove refuse from the active cell edge berms. For liner overlap and m2 230 R 60.00 13,800.00
contaminated stormwater drainage.
2.4 D-8.3.2 a) Excavate in all materials, fill and stockpile and maintain as m3 90000 R 45.00 4,050,000.00
instructed. Inclusive of all benching volumes and haulage.
2.5 D-8.3.2 b) Excavate in all materials in natural ground or from existing m3 4500 R 100.00 450,000.00
stockpiles, fill and compact to 90% Mod AASHTO density or as
instructed. Inclusive of all benching volumes and haulage.
2.6 DB.8.3.2 b) 2) Extra over all item above for hard rock m3 4500 R 150.00 675,000.00
excavation (5% of the area)
2.7 DB.8.3.2 1) Generally for 600-800mm inclusive outside diameter piping & m3 8.97808 R 90.00 808.03
Trapezoidal and V drains. 0 - 1.2m depth.
2.8 2) Generally for 600-800mm inclusive outside diameter piping & drains. m3 0 R 95.00 0.00
>1.2 - 2m depth.
2.9 3) Generally for 600-800mm inclusive outside diameter piping & drains. m3 39.81578 R 145.00 5,773.29
2-3m depth.
2.10 3) Generally for 600-800mm inclusive outside diameter piping & drains. m3 634.1105 R 175.00 110,969.34
> 3m depth.
2.11 b) 2) Extra over item above for hard rock excavation (provisional). m3 0 R 350.00 0.00
2.12 1) Selected fill material (Main leachate pipe) m3 108 R 90.00 9,720.00
2.13 2) Selected granular material (Main leachate pipe) m3 101 R 95.00 9,595.00
2.15 DB.8.3.8 Anchor trench backfill with cement stabilised material inclusive of 6% m3 255 R 95.00 24,225.00
cement by mass, approved material for stabilisation, mixing, placing
and compaction to 95% Mod AASHTO density. Generally in selected
areas for pipe bedding and / or backfilling where specified.
8.2.3 MANHOLES
3.5 Construct a field inlet system with a ROCLA pre HDPE lined manhole No 1 R20,000.00 20,000.00
rings exeeding 5-6m
4.1 DM 8.3.3 Excavate in all materials in natural ground of ring road and pavement , m3 5640 R 100.00 564,000.00
fill and compact to 90% Mod AASHTO density or as instructed.
4.2 DM.8.3.4 a) Cell 2 and Leachate Dam Base Layer. Imported approved granular m3 1395 R 120.00 167,400.00
material, G7 quality generally 150mm thick. Compaction to 93% Mod
AASHTO density. The base sloping as shown in the drawings and the
berms at approximately 1v:3h.
4.3 DM.8.3.4 b) Cell 2 Leachate collection layer - Imported 53mm or 75mm single m3 4403.5 R 421.00 1,853,873.50
sized, hard, durable crushed stone to the Engineer's approval. 150mm
thick. Nominal compaction. Side slopes up to approximately 1v:3h.
4.4 DM.8.3.4 c) Gravel Ring Road and Pavement. G7 selected fill material for road m3 1520 R 120.00 182,400.00
selected layer and where specified. Compaction to 95% Mod AASHTO
density. Provisional.
4.5 DM.8.3.4 d) Gravel Ring Road and Pavement. G5 imported gravel generally m3 1520 R 120.00 182,400.00
150mm thick gravel wearing course to roadways inc supply, placing &
grader shaping where specified. Compaction to 98% Mod AASHTO
4.6 Supply and place 20mm bedding sand on top of the compacted
roadworks
4.7 Supply and lay 80mm interlocking blocks on top of the bedding sand m 1600 R 200.00 320,000.00
4.8 DM.8.3.15 Stormwater. Excavation & filling for catchwater mounds and channels m3 1102 R 125.00 137,750.00
incl. working on 1v:3h landfill slopes, forming and compaction
4.9 LE 8.2.5 Cast insitu concrete, formwork and reinforced steel for Trapeziodal and m3 482.48 R 2,940.83 1,418,893.27
Vee drains
4.11 DK.8.2.4 a) Type 2 Geotextile seperation liner to cover leachate collecton layer. m2 38775 R 50.00 1,938,750.00
Supply onto site only and excluding any overlaps or wastage.
4.13 MK 8.2.1 Supply and Install concrete kerbs around the perimeter of the paved m 260 R 220.00 57,200.00
area
5.1 Supply and Install Geomembrane to GRI GM-13. Supply to the site m2 38775 R 95.00 3,683,625.00
and store safely in accordance with the project and manufacturer's
specifications. Slope area measured net, excluding all wastage, and
overlaps but including anchorage length and overlap with existing liner.
1.5 mm thick HDPE as approved. Completely install geomembrane on
slopes of up to 1v:2.5h (generally 1v:3h max.). Slope area measured
net, excluding all wastage, overlaps and welding requirements but
including anchorage length and overlap with existing liner. Including for
embossed texturing on both faces of the geomembrane.
5.3 Suuply and Install Geosynthetic Clay Liner (GCL). Supply to the m2 38775 R 150.00 5,816,250.00
site and store safely in accordance with the project and manufacturer's
specifications. Slope area measured net, excluding all wastage, and
overlaps but including anchorage length and overlap with existing liner.
Completely install on slopes of up to 1v:3h. Slope area measured net,
excluding all wastage, and overlaps but including anchorage length
and overlap with existing liner.
5.4 Establishment of leak detection equipment, once off for dipole testing. sum 1 0.00
5.5 Leak detection of geomembrane lining by dipole in accordance with sum 1 0.00
ASTM D7007.
5.6 Provisional sum for specialist testing on the liner components as sum 1 ######### 25,000.00
directed by the Engineer.
5.7 Overheads, charges & profit on item above % R 25,000.00 R 15.00 3,750.00
LABOUR
6.1 Unskilled Workers hr 8 R 80.00 640.00
CONSTRUCTIONAL PLANT
6.5 Lowbed (40t capacity)
SUBTOTAL A 29,548,403.69
CONTINGENCIES 2,954,840.37