Demsie Loundary Project
Demsie Loundary Project
Tigray, the northern part of Ethiopia, pass through an area of 53,638 sqkm
endowed with picturesque land features, the region with altitude that varies
from 600-2700 meters above sea level. Its population is estimates as about
more than 3.6 million.
Although the region was no achieved the expect development which initiated
external and internal factors, Tigray has also fertile agricultural land and
extremely hard workers of people
For example during the period of the Derg Regime, the region was severely
affected by man-made and natural calamites which once made the over all
national economy nearly collapse. For the present government, this being the
fact, rehabilitating the economy of the country as a whole and Tigray in
particular was no any easy task to accomplish after the demise of Derg. This
was seemed like an indigenous problem the Federal Government Ethiopia was
launch and formulated the market Economy to solve and tackle.
Parallel to that the Regional Government of Tigray also implemented the
federal policies by relating and comparing the ground and environment of the
region.
These policies and regulations which the region able to implemented were try
to appreciated the role of the private sector in developing the economy and
spared no effort to meet its equipments. These policies and regulations are like
facilitating infrastructures and providing land for investment with fair lease
base etc were created conducive environment for private sectors.
Due to this reason many private businesses are tried to invest in the region
indifferent business sectors .This also makes an out come to the economy
growth of the country to increases from year to year in general and the region
particular.
Although there are many business sectors tried to invest their capital and
resources in the proposed area and business type, they are not able to observe
the desire and need of the society both in quantity and quality. Particularly at
Alamata town, the project area, there is no even one similar business which
able to serve the consumer. The societies are getting services either in Mekelle
or Desie cities.
Therefore the promoter is planned to observe the excess demand and needs by
establishing modern laundry based on the expected needs and desires of the
society.
2.4 Justification
The promoter has the following justifications established his business in the
area of laundry.
The western zone has a unique culture in wearing what locally it called
Gabi which should be washing by laundry.
Service rendering business by its nature has a good market specifically
the laundry service is un exploited market.
The region is introduced encourage able police which have an advantage
to attract private business and this make a linkage effect to the expected
project.
The conducive and encourage able private business police have an
advantage to attract private business and this make a linkage effect to
the expected project.
The population growth of the country indicates that growing constantly.
Hence, there must a corresponding growth in other social and
economical institution to cop up with the number of population.
To invest his capital and knowledge in his own country to help the
people of Tigray in particular and the people of Ethiopia in general.
To generate revenue and increase the government revenue by issuing
taxes.
2.5 Objective of the project
The primary objective of this sort of project proposal is to give more emphasize
on the participating in laundry business at Alamata town at full capacity by getting
bank loan which enable to play a vital role in social, economic and technical
development of the country and finally to generate profit to him.
III. MARKET STUDY
3.1 project description and application of the project
The proposed laundry service business in which established at a given building
will be expected to give services for gleaming blankets, Gabi, Bofe, sheets complete
cloth and other similar clothes.
Specifically:-
For Hotel and bar services: the promoter will plane to serve for clearing for
hotel blanket, sheets and other clothes
For Societies service: the envisaged project will have to serve for societies
who live in Alamata and its surrounding areas for their cultural clothes like
bofe , Gabi and try to serve for blanket , complete cloth and sheets
3.2 Demand and Supply Analysis
The main factors that are considered in the determination of the demand and
supply of project is the availability of hotels and bars , population growth
rate, the level of economy growth, the purchasing power of the society, service
rendering and location of the project, and culture are exampled
To analysis the market assessment of modern hotel there are certain indicators
to show the gap between the demand and supply.
To give some high light the consultancy tries to explain the gap using the
supply and demand approaches.
3.2.1 Demand analysis
The population growth in Wereda Alamata like the Tigray region, the
population growth rate shows that an increment by more than 3% annually.
The consultancy tries to take the analysis of the demand concept by assessing
the available of consumers in Wereda Alamata.
According the study conduct by the consultancy there are more than 142,000
populations at Wereda Alama-Ata.
Table: 3.2.1.1
Number of population Alama-Ata Wereda
Time Urban Rural Total
Recent 45000 97000 142000
Source: assessment conduct by the consultancy
In addition to that there are 938 and 500 employees in rural and urban
Wereda Alamata respectively.
There are also more than 600 traders available presently at Alamata town.
Assuming also out of the total demanders 50% will be expected to use laundry
services.
Table: 3.2.2.3
Supply and Demand Gap
Types of service Supply Demand Gap/
Excess demand
Bofe / gabi No one 23550 23550
Complete cloth No one 9000 9000
Blanket No one 16305 16305
3.3 Demand Projection
Before try to explain the demand projection of laundry hotel service let see the
main demand projections which are linked with it.
According to central stastics authority the population grew 3 and 4 in rural
and urban respectively. When we see the economic growth of the country
achieved more than 10 % consecutive for four years (Prime Minister Meles).
Thus such opportunity is making comparative advantage to the society to use
the laundry service to keep their health.
The consultancy has assumed in all nature of services will increase by 10 %
annually
Table 3.3.1
The projected demand laundary service for ten years
Year Demand projection
Table 3.6.3.1
Expected revenue for proposed project pension for
consecutive ten years
Table 3.6.3.2
Expected revenue for soft drink and beverage
For consecutive ten years
Sheet one beer
No Year Meas Total beer Unit price Total sales
per year
1 2000 Bottle 43800 4.00 175200.00
2 2001 Bottle 48180 4.00 192720.00
3 2002 Bottle 52998 4.00 211992.00
4 2003 Bottle 58298 4.00 233192.00
5 20004 Bottle 64128 4.00 256512.00
6 2005 Bottle 70540 4.00 282160.00
7 2006 Bottle 77594 4.00 310376.00
8 2007 Bottle 85353 4.00 341412.00
9 2008 Bottle 93888 4.00 375552.00
10 2009 Bottle 102276 4.00 409104.00
Table 3.6.3.3
Expected revenue for recreational activities for consecutive ten years
Year For pool For dart For For table Total
caranbula tennis revenue
2000 18000.00 43200.00 12960.00 10800.00 84960.00
2001 18000.00 43200.00 12960.00 10800.00 84960.00
2002 18000.00 43200.00 12960.00 10800.00 84960.00
2003 18000.00 43200.00 12960.00 10800.00 84960.00
2004 18000.00 43200.00 12960.00 10800.00 84960.00
2005 18000.00 43200.00 12960.00 10800.00 84960.00
2006 18000.00 43200.00 12960.00 10800.00 84960.00
2007 18000.00 43200.00 12960.00 10800.00 84960.00
2008 18000.00 43200.00 12960.00 10800.00 84960.00
2009 18000.00 43200.00 12960.00 10800.00 84960.00
Assumptions to computing the annuals income for meals
1. There Will Be Expect To Sale 30 Dishes Per Day none for feast food
2. There Will Be Expect To Sale 20 Dishes Per Day for feast food
3. There Are 365 Working Days
4. Prices For Feast Dish Will Birr 5.00
5. Prices For None Feast Meal Will Birr 12.00
Table 3.6.3.4
Expected revenue for meals for consecutive ten years
None Feast foods
Year quantity Meas Unit price Total Remark
2000 10950 Dish 12.00 131400.00
2001 12045 Dish 12.00 144540.00
2002 13250 Dish 12.00 159000.00.
2003 14575 Dish 12.00 174900.00
2004 16032 Dish 12.00 192384.00
2005 17636 Dish 12.00 211632.00
2006 19400 Dish 12.00 232800.00
2007 21340 Dish 12.00 256080.00
2008 23474 Dish 12.00 281688.00
2009 25821 Dish 12.00 309852.00
Table 3.6.3.5
Tea
Year quantity Meas Unit price Total Remark
2000 36500 Cup 1.00 36500
2001 43800 Cup 1.00 43800
2002 52560 Cup 1.00 52560
2003 63072 Cup 1.00 63072
2004 75686 Cup 1.00 75686
2005 90823 Cup 1.00 90823
2006 108988 Cup 1.00 108988
2007 130786 Cup 1.00 130786
2008 156943 Cup 1.00 156943
2009 188332 Cup 1.00 188332
There are also other incomes that the expect project to collect revenue
like from laundry service. There fore the consultancy expects to collect
income from laundry service birr 500.00 per day. The laundry expected
to occupied three hundred day per year thus the annual income will be
182500.00
Table 3.6.3.7
Expected revenue for laundry service for consecutive ten years
Year Amount Remark
2000 182500.0
2001 219000.00
2002 262800.00
2003 315360.00
2004 378432.00
2005 454118.00
2006 544942.00
2007 653930.00
2008 784716.00
2009 941659.00
Table 3.6.3.6
Expected revenue for the summary for hotel
For consecutive ten years
Year capacity total
Table 4.1:
the required materials for the pension rooms
Item Description Mes Requir Require Total Unit price Total price
code ed per d rooms require
room d
001 Guests salon Set 1 2 2 20000.00 40000.00
002 TV for guests Pcs 1 2 2 12420 24840.00
003 TV Pcs 1 32 32 4500.00 144000.00
004 Rag Pcs 1 34 34 2000.00 68000.00
005 Bed Pcs 1 32 32 2000.00 64000.00
006 Cupboard Pcs 1 32 32 1500.00 48000.00
007 Tables Pcs 1 32 32 600.00 19200.00
008 Chair Pcs 2 32 64 250.00 16000.00
009 Phone cable Pcs 1 32 32 350.00 11200.00
010 Dish Set 1 1 1 5000.00 5000.00
011 stab Set
012 Pillow Pcs 2 32 64 50.00 1680.00
013 Blanket Pcs 2 32 64 750.00 48000.00
014 Bed sheet Pcs 4 32 168 200.00 33600.00
015 Mattress Pcs 1 32 32 1500.00 48000.00
016 KEBRELETO Plc 2 32 64 250.00 16000.00
017 Panasonic tape Pcs 1 4000.00 4000.00
Table 4.2
the required machinery
396000.00
Table 4.3
the required materials for bar and cafteria
13300.00
Table 4.4
office of equipment and furniture
No description quantity unity price total price
4.9.3 Cost
According the engineering estimation made the total cost of the buildings
and civil works estimated as Birr 2191056.00. Out of the total tasks 40% is
finished and for the remaining cost will be estimated as birr 876422.40.
Finished building
Except the service rooms ,the ground and first floor of the main
building is already finished
Building on process
The second floor of the building is now on process to start. The
promoter will be also to start by step on the coming year.
V. RAW MATERIAL, STATIONARY, UTILITIES OTHER EXPENSES
Table 5.2.1
Utility expense per a year
No Description Monthly expense Yearly
1 Telephone 2000.00 24000.00
2 Eclectic 5000.00 60000.00
3 Internet 600.00 7200.00
4 Postage 48/12 48.00
5 Water 1000.00 12000.00
5.3 Stationary
In fact there is no such row material which uses for this project sine there is
no production or fabrication activities in the processes. While the
consultancy has taken the stationary materials will require for cash receipt,
report writing and other purposes. The estimated stationary materials as
birr—23800 are given in the following tables.
Table 5.3.1
The required materials and its cost of materials
No types of raw materials quantity means unit total cost remark
1. Paper 50 Lasta 40 2000.00
2 .Pen 1200 Pcs 1.50 1800.00
3. Financial pads 1000 pcs 20.00 20000.00
23800.00
5.5 Pre-operation
Pre operation expenditure includes the cost for feasibility training if key
persons and is expected as Birr 10,000.00
Period of operation
When the implantation process has been started, the period required to
complete the activities are assumed to be 6 months and the project will
expect to start its service at full capacity after 6 months.
Financing of the project is to be financed in the following manner.
Equity: 40%
Total equity -------------------------------------------- Birr 1388616.80
Long term loan (60%)
Total long term loan ---------------------------------- Birr 2082925.20
The total initial investment will be birr------------------ 3471542.00
Initial investment cost
The total initial investment cost amounts about Birr 3.47 million including
initial working capital. The foreign currency portions will not such should
be taken in account. The cost of civil works is about Birr 2.19 million, or
63% of total investment cost, this indicates that the balance goes for the
building costs the major components of the per production expenditure are
interest during construction, project study, erection of machinery and
equipment other and implementation costs. The details of the initial
investment are given in the following table.
The total initial investment cost including initial working capital amount to
about Birr 3471542.00
Table 5.1 initial investment cost.
Net income (166898.32) 222581.44 228677.55 255234.63 282761.97 549855.66 558261.83 613514.14 64622.90 669702.32
Dep 367080.80 367080.80 367080.80 367080.80 367080.80 367080.80 109552.80 109552.80 109552.80 109552.80
Net cash flow 200182.48 589662.24 595758.35 622315.43 649842.77 916936.46 667814.63 723066.94 174175.70 779255.12
Cum. cash flow 200182.48 789844.72 1385603.07 2007918.50 2657761.27 3574697.73 4242512.36 4965579.30 5139755.00 5919010.12
Based on the above table the project will cover its initial investments cost at the binning of years two that is
after 6 years and 7 months.
Pay bank period= 6 year + (3471542.00 -2657761.27)
3574697.73
= 6 year + .2 year
= 6.2 year
The net cash flows if the operations of the project can generate enough money to recover the total initial
investment cost within a period of less than 7 years. This can be seen form the cash flow statement in the
annexed financial analysis schedule
Payment of medium term loan
The yearly cash flows of the operations of the project can generate enough term
loan of Birr 2082925.20 and the rate of payment Birr208292.52 for the first
year and 52073.13 quarterly. The loan repayment is not envisaged to strain the
cash strain in cash position of the project after the first period of payment
Break-even capacity
The calculation of the break even capacity of a project must be with reference of
the fixed costs expected in insure when the project is purposed to read the rater
capacity utilization level usually 90% -100% the lower this capacity is the more
the chances are for the project to earn profits are for the project to earn, the
break even capacity during the first year operation is calculated as follows.
Break even capacity = fixed costs
Sales-variable
3303176.00 =3303176.00
1082210.00.-390763.47 691446.53
4.8
Average yearly net return
Average yearly net return which us a variable of the average return allows the
comparison of projects of different life times through computational of the
average percentage return on the initial investment per a year. Under this
technique for a single project to be accepted the average yearly net return must
be at least the rate of interest available in the company and at least the current
interest rate
Sales-initial in. vestment cost =1082210.00-3471542.00 = 2389332.00
Initial investment (year) 3471542.00x5 17357710.00
= 14%
From the above analysis understand that the project is justifiable when the
promoter invests his money on the project of hotel business. Because of the
average yearly net return rate is greater than even the rate of bank interest i.e.
8.50 %.
Other benefits
Other than its commercial viability and profitability to the owner of the project,
there are a number of contributions that can be derived form the
implementation of the project.
The project will contribute several important types of benefits, such as
1. It creates job opportunities for more than 20 citizens.
2. It promotes sustainable and continuous market stability.
3. It makes self confidence for the promoter.
Annex 1
1 2 3 4 5 6 7 8 9 10
Revenue 1082210.00 1639798.00 1739606.00 1890993.00 2067842.00 2274770.60 2484928.52 2801834.42 3136277.51 3525846.41
Less cost 1249108.32 1309595.78 1400025.15 1510555.10 1645054.36 1441069.58 1638294.94 1876274.20 2162934.4 2507765.92
0
Raw maternal 387016.00 464419.20 557303.04 668763.65 802516.38 963019.66 1155623.59 1386748.31 1664097.9 1996917.56
7
Stationary materials 23800.00 26180.00 28798.00 31677.00 34844.00 38328.00 42160.00 46376 51013.00 56114.00
Preoperational 10000.00
Installation of utility 5000.00
Promotion/marketing 12000.00 12000.00 12000.00 12000.00 12000.00 12000.00 12000.00 12000.00 12000.00 12000.00
Salary 104400.00 114840.00 126324 138956.00 152851 168136.00 184949.00 203443.00 223787.00 246165
Utility 103248.00 103248.00 103248.00 103248.00 103248.00 103248.00 103248.00 103248.00 103248.00 103248.00
Other expense 20000.00 20000.00 20000.00 20000.00 20000.00 20000.00 20000.00 20000.00 20000.00 20000.00
Maintenance 30000.00 30000.00 30000.00 30000.00 30000.00 30000.00 30000.00 30000.00 30000.00 30000.00
Provident fund 8259.84 11484.00 12632.40 13895.60 15285.10 16813.60 18494.90 20344.30 22378.70 24616.50
Bank interest 177303.63 159343.78 141638.91 123934.05 106229.18 88524.32 70819.45 53114.59 35409.73 17704.86
Dep. computer 1000.00 1000.00 1000.00 1000.00 1000.00 1000.00 1000.00 1000.00 1000.00 1000.00
Dep building 109552.80 109552.80 109552.80 109552.80 109552.80 109552.80 109552.80 109552.80 109552.80 109552.80
Dep for machines 118304.00 118304.00 118304.00 118304.00 118304.00
Dep in furniture 123224.00 123224.00 123224.00 123224.00 123224.00
Dep generator 16000.00 16000.00 16000.00 16000.00 16000.00 16000.00 16000.00 16000.00 16000.00 16000.00
Grosse income B.Tax (166898.32) 330202.22 339580.85 380437.90 422787.64 833701.02 846633.58 928560.22 973342.91 1018080.49
Profit Tax 35% 107620.78 110903.30 125203.27 140025.67 283845.36 288371.75 315046.08 332720.01 348378.17
Net income (166898.32) 222581.44 228677.55 255234.63 282761.97 549855.66 558261.83 613514.14 640622.90 669702.32
Assumptions to computing this income statement
1. Depreciation rate policy for the other fixed assets are using the pooling system by 20%
2. The salary expenses will be increase by 10% per a year to motivate the employees
3. There is no a any fear of price fluctuating for the material
4. provident fund is 20%
Annex 2
Description y e a r s
1 2 3 4 5
Assets
Cash 206672.56 588442.28 976308.11 1390731.02 1832681.27
Fixed asset 3303176.00 3303176.00 3303176.00 3303176.00 3303176.00
Less Acc Dep 368080.80 736161.60 1104242.40 1472323.20 1840404.
Net fixed asset 2935095.20 2567014.40 2198933.6 1830852.80 1462772.00
Total asset 3141767.76 3155456.68 3175241.71 3221583.82 3295453.27
Bank loan 2082925.20 1874632.68 1666340.16 1458047.64 1249755.12
Capital 1225740.88 1058242.56 1280224.00 1508301.55 1762936.18
Acc. Income (166898.32) 222581.44 228677.55 255234.63 282761.97
Total liable & capital 3141767.76 3155456.68 3175241.71 3221583.82 3295453.27
WOLDAY LEMMA
FEASIBILITY STUDY
FOR
CONSULTANCY:
TEADY BUSINESS PROMOTION AND CONSULTANCY
Title Page
Executive -------------------------------------------------------------------------------------- I.II
Back ground
Applicant profile -------------------------------------------------------------------------------1
Introduction ----------------------------------------------------------------------------------- 2
Justification ------------------------------------------------------------------------------------3
Objectives -------------------------------------------------------------------------------------- 4
Market Study
Project description -------------------------------------------------------------------------- 5
Demand & Supply analysis ---------------------------------------------------------------- 5
Demand Projection --------------------------------------------------------------------------9
Pricing -----------------------------------------------------------------------------------------11
Capacity and revenue ----------------------------------------------------------------------12
Technical study
Furniture, equipment ----------------------------------------------------------------------21
Machines-------------------------------------------------------------------------------------23
Stand by generatore ------------------------------------------------------------------------25
Required land, building and civil work--------------------------------------------------26
Raw material , stationary , utility, other expense
Raw materials --------------------------------------------------------------------------------28
Utility ---------- -------------------------------------------------------------------------------28
Stationary-------------------------------------------------------------------------------------29
Pre operation ---------------------------------------------------------------------------------29
Required humane resource ---------------------------------------------------------- ------30
Financial analysis ----------------------------------------------------------------------------31
Annex
1. income statements ------------------------------------------------------------ 37
2. repayment of bank loan ---------------------------------------------------- --39
3. cash flow of the project ----------------------------------------------------- --40
4. projected balance sheet ------------------------------------------------------41
Executive summary
Tourism is one of the under exploited niche markets that will be focused on the
government on the coming 20 years. The long vision of the government is to
make Ethiopia one of the top ten tourist destination in Africa by the year 2020.
Hotel service is also one of the main components of tourism sector.
Thus Establishing Modern Hotel service is regarded as a very important
business to the promoter and contributes at all levels, local, regional as well as
national. It has also a high degree of contribution to alleviate and solve the
burn issues of food in security problems to the country. It generates and
contributes in the form of different types of taxes to the government from its
revenue. In addition to this it makes employment opportunities. It consumes
high utilities like electric, water and telephones. It also tries to maintain the
excess demand to ward to the tourism expansion desire of the region.
To this effect due attention has been given at all levels for the study and
implementation. The feasibility study made on the modern hotel service has
been investigate in different aspects that could justify viability of the project,
such as the market assessment, demand analysis, capacity and programmed,
financial aspects and profitability of the project, economical aspects and its
opportunities. In addition to the above benefits of the project, is converted in to
reality, it will definitely play its role in promoting the nation’s economy.
This brings quietly therefore the promoter has an intention to invest his
resources in the mentioned sector in this region.
This project is located at the heart of the Adigrat town marketable areas near
the sky rocket building of Ato Gebreslasie .
The proposed project has lied on 335square meters which consists different
rooms and sections for the purpose of pension , restaurant , recreational , and
cafeteria .the total investment of the project is estimated as birr 3471542.
The project is expected to finance 40% and 60% from the owner/promoter and
bank long term loan respectively for ten years.
It is fact that to applied and assessed the market studies of a project can be
employ using different approaches. But here in this project the consultancy
applied the demand and supply approach: - In this approach the number of
available such business activities mainly the competent and the actual plan
toward socio and economical development of the government have considered
in the assessment. In this assessment and study the present effective demand
for domestic and foreign tourist flow is very high.
The selected price has taken to calculate the expected revenue is using
average current local prices for renting per classes and selling different
products and services of the envisage project.
The Consultancy is applied to calculate the Depreciation rate of the fixed asset
a straight line depreciation systems.
The project can certainly expected to return all the initial investment cost in
the six year and two months of the next year of operational periods. And the
project can expected to return the bank loan even in the fourth year of
operational periods.
It is concluding that with above justification this project is justifiable.