Cost Breakdown For Additional Works
Cost Breakdown For Additional Works
A= Materials Unit Cost Birr/m2 B= Manpower Unit Cost 66.67 Birr/m2 C= Equipment Unit Cost 666.67 Birr/m2
Total of (1:02) Total of (1:03) 20,000.00
Daily Output: Daily output: 30
Direct Cost of Work Item = A+B+C = 733.33 Birr/m3
Over head cost : 0.15 110.00 "
Profit Cost: 0.15 110.00 "
Total : 953.33 Birr/m3
VAT:
Total Unit Cost : 953.00 Birr/m3
A=Materials Unit Cost 2,360.00 Birr/m2 B= Manpower Unit Cost 688.89 Birr/m2 C= Equipment Unit Cost 88.89 Birr/m2
UF: UTILIZATION FACTOR Total of (1:02) Total of (1:03)
Daily Output: Daily output: ______________
Direct Cost of Work Item = A+B+C = 3,137.78 Birr/m2
Over head cost : 15% 470.67 "
Profit Cost: 15% 470.67 "
Total : 4,079.11 Birr/m2
Vat
Total unit cost: 4,080.00 Birr/m2
ANALYSIS SHEET FOR DIRECT & INDIRECT COSTS
PROJECT: LABOUR DAILY OUTPUT: 1.00 m2/Dy.
WORK ITEM :- () University name in Amharic & Engish words for gate one and Two & Loga for both gate EQUIPEMENT DAILY OUT PUT: 1.00 m2/Dy.
TOTAL QANTITY OF WORK ITEM: 1.00 LM RESULT: 639,800.00 Birr/m2
A=Materials Unit Cost 556,347.83 Birr/m2 B= Manpower Unit Cost - Birr/m2 C= Equipment Unit Cost - Birr/m2
UF: UTILIZATION FACTOR Total of (1:02) Total of (1:03)
Daily Output: Daily output: ______________
Direct Cost of Work Item = A+B+C = 556,347.83 Birr/m2
Over head cost : 0% - "
Profit Cost: 15% 83,452.17 "
Total : 639,800.00 Birr/m2
Vat
Total unit cost: 639,800.00 Birr/m2
Consultant:- Aspire AECOM Consulting Architects and Engineers
Contractor:- Ganji Construction
Project :- LOT-3 Supplementary Agreement main gate connect with fence
Location:- Gambella, Ethiopia
Item no Description Unit Quantity Rate Amount REMARK
1. Demolishing