Fire - Water Line & Cistern Tanks
Fire - Water Line & Cistern Tanks
Item Activity Description Qty. OUM Unit Cost Material Cost Labor Rate Labor Cost Total Amount
I GENERAL REQUIREMENTS
Mobilization/Demobilization 1 lot 200,000.00 200,000.00 - - 200,000.00
Delivery and Transportation Materials 1 lot 125,000.00 125,000.00 - - 125,000.00
Site Team Supervision 1 lot 200,000.00 200,000.00 - - 200,000.00
Temporary Utilities
Water and Power Consumption by CLIENT
Provision and Maintenance of Latrine utilities by CLIENT
Worker's Transportation and Accomodition 1 lot 100,000.00 100,000.00 - - 100,000.00
Construction occupational Safety & Health 1 lot 100,000.00 100,000.00 - - 100,000.00
Housekeeping 1 lot 50,000.00 50,000.00 - - 50,000.00
Tools and Equipments 1 lot 100,000.00 100,000.00 - - 100,000.00
ITEM I SUB-TOTAL 875,000.00
II FIRE LINE AND WATER LINE (Mainline)
a. FIRE LANE
1. HDPE PIPE, HIGH DENSITY POLYETHYLENE (HDPE),
PE-3408, SDR 7.3 MANUFACTURED AND TESTED
IN ACCORDANCE TO ISO 4427.
8" Φ x 6M. 45 length 16,968.17 763,567.65 6,787.27 305,427.06 1,068,994.71
6" Φ x 6M. 5 length 8,543.04 42,715.20 3,417.22 17,086.08 59,801.28
2. HDPE FITTINGS
8" Φ X 6"Φ tee reducer 10 pcs. 23,700.00 237,000.00 9,480.00 94,800.00 331,800.00
6" Φ X 4"Φ tee reducer 5 pcs. 14,980.00 74,900.00 5,992.00 29,960.00 104,860.00
3. Fire Hydrants, 6" Φ 4 pcs. 71,500.00 286,000.00 28,600.00 114,400.00 400,400.00
4. Hose House 4 pcs. 45,000.00 180,000.00 18,000.00 72,000.00 252,000.00
5. Gate Valves (OS&Y), 6" Φ 4 pcs. 30,500.00 122,000.00 12,200.00 48,800.00 170,800.00
6. Check Valves, 6" Φ (Swing Type), 150 lbs. 4 pcs. 38,625.00 154,500.00 15,450.00 61,800.00 216,300.00
7. Mechanical Coupling, 8" Φ 45 pcs. 14,000.00 630,000.00 5,600.00 252,000.00 882,000.00
8. Mechanical Coupling, 6" Φ 22 pcs. 11,000.00 242,000.00 4,400.00 96,800.00 338,800.00
9. Thrust Blocks 1 lot 75,000.00 75,000.00 30,000.00 30,000.00 105,000.00
10. Stell Post Barricade 26 pcs. 5,000.00 130,000.00 2,000.00 52,000.00 182,000.00
11. Concrete Pipe Encasement 30.25 cu.m 1,780.00 53,845.00 712.00 21,538.00 75,383.00
12. Pipe Sleeves 1 lot 50,000.00 50,000.00 - - 50,000.00
13. Earth Works
Soil excavation of embeded pipes 660.6 cu.m - - 350.00 231,210.00 231,210.00
Soil compaction using plate compactor 440.4 sq.m - - 150.00 66,060.00 66,060.00
Gravel bedding of of Embeded Pipes 264.24 cu.m 1,780.00 470,347.20 712.00 188,138.88 658,486.08
Backfilling from excavated soil 220.2 cu.m - - 250.00 55,050.00 55,050.00
14. Miscellaneous Works 1 lot 100,000.00 100,000.00 - - 100,000.00
15. Testing & Commissioning 1 lot 100,000.00 100,000.00 - - 100,000.00
2.) Completion Period : 144 Working days (To coordinate with civil works and other Engineering discipline.)
3.) Warranty : One (1) year against inherent defect on materials and workmanship.
4.) Delivery lead time for all materials: Two (2) weeks from the start of working permits.
Thank you for giving us the opportunity to quote on your requirements and we look forward to serve you soon. GOD BLESS.
PREPARED BY:
ROLDAN L. TUMANDA
OPERATION MANAGER