Work Schedule-15.05.24

Uploaded by

Mehadi Hasan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views3 pages

Work Schedule-15.05.24

Uploaded by

Mehadi Hasan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Work schedule for construction of Design and Build Jetty and other Associated works for Mongla port

Authority under the Project of "Establishment of Modern Waste and Spilled Oil Management at Mongla Port" ( Tender Package No. W-1)
ID Task Name Duration Start Finish Predecessors Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25
31 7 14 21 28 4 11 18 25 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
1 Total Contact Period 645 days Thu 1/5/23 Thu 12/26/24
2 Notification of Award 1 day Thu 1/5/23 Thu 1/5/23
3 Date of Contact Sign 1 day Wed 2/1/23 Wed 2/1/23
4 Date of commencement 1 day Wed 2/15/23Wed 2/15/23
5 Design Phase 274 days Thu 2/16/23 Wed 12/27/234
6 Preparation and Submission of
30Layout
days Drawing
Thu 2/16/23 Wed 3/29/23 4
7 Approval of layout drawing by
60Client
days Thu 3/30/23 Tue 6/20/23 6
8 Sub-soil Investigation works 13 days Wed 8/16/23Mon 8/28/23
9 Preparation of Design drawing
15and
dayssubmission
Tue 8/29/23 Tue 9/12/23 8
10 Design checking and comments
30 days
by ClientWed 9/13/23Thu 10/12/23 9
11 Preparation and Submission of
30Modifide
days Fri
drawing
10/13/23 Sat 11/11/23 10
12 Approval of final Drawing by 9client
days Tue 12/19/23Wed 12/27/2311
13 Construction phase 615 days Thu 2/16/23 Thu 12/26/24 4
14 Carryout survey and 45 days Thu 2/16/23 Wed 4/19/23 4
Establishment of
15 Benchmark
Cleaning of site and 45 days Thu 4/20/23 Tue 6/20/23 14
Mobilization of Equipment
16 and
Test Manpower
pile 3 days Thu 10/19/23Sat 10/21/23 7FS+7 days
17 Load test on test pile 7 days Sat 11/18/23 Fri 11/24/23 16FS+21 days
18 Service pile 194 days Thu 12/28/23Thu 8/1/24 17,12
19 Group -1 (Type-2, Pile 32 days Thu Sun 1/28/24 17
No. 11, 12, 13, 14, 15 12/28/23
28 and 16)-2 (Type-2, Pile
Group 9 days Mon Tue 2/6/24 27
No. 9 and 10) 1/29/24
33 Group -3 (Type-2, Pile 22 days Wed 2/7/24 Wed 2/28/24 32
No. 5,6,7 and 8)
40 Group -4 (Type-2, Pile 7 days Thu 2/29/24 Wed 3/6/24 39
No. 3 and 4)
45 Group -4 (Type-2, Pile 6 days Sun 3/10/24 Fri 3/15/24 44
No. 1 and 2)
50 Group -5 (Type-1, Pile 12 days Wed Sun 3/24/24 49
No. 9, 14 and 15) 3/13/24
56 Group -6 (Type-1, Pile 10 days Fri 3/22/24 Sun 3/31/24 55
No. 10, 13 and 16)
62 Group -7 (Type-1, Pile 9 days Sat 5/18/24 Sun 5/26/24 61
No. 11, 12 and 17)
63 Permanent stell casing 2 days Sat 5/18/24 Sun 5/19/24 61
driving
64 Setting of Barge 1 day Mon 5/20/24Mon 5/20/24 63
65 Boring and casting P-112 days Tue 5/21/24 Wed 5/22/24 64
66 Boring and casting P-122 days Thu 5/23/24 Fri 5/24/24 65
67 Boring and casting P-172 days Sat 5/25/24 Sun 5/26/24 66
68 Group -8 (Type-1, Pile 7 days Mon Sun 6/2/24 66
No. 24 and 25) 5/27/24
69 Permanent stell casing 2 days Mon Tue 5/28/24
driving 5/27/24
70 Setting of Barge 1 day Wed 5/29/24Wed 5/29/24 69
71 Boring and casting P-242 days Thu 5/30/24 Fri 5/31/24 70
72 Boring and casting P-252 days Sat 6/1/24 Sun 6/2/24 71
73 Group -9 (Type-1, Pile 7 days Mon 6/3/24 Sun 6/9/24
No. 19 and 20)

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Work schedule-7.03.24
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 5/15/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

DEW-DCL JV.
Page 1
Work schedule for construction of Design and Build Jetty and other Associated works for Mongla port Authority under the Project of "Establishment of Modern Waste and Spilled Oil Management at Mongla Port" ( Tender Package No. W-1)
ID Task Name Duration Start Finish Predecessors Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25
31 7 14 21 28 4 11 18 25 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
74 Permanent stell casing driving
2 days Mon 6/3/24 Tue 6/4/24
75 Setting of Barge 1 day Wed 6/5/24 Wed 6/5/24
76 Boring and casting P-192 days Thu 6/6/24 Fri 6/7/24
77 Boring and casting P-202 days Sat 6/8/24 Sun 6/9/24
78 Group -10 (Type-1, Pile 7 days Fri 6/21/24 Thu 6/27/24 72
No. 8 and 5)
79 Permanent stell casing 2 days Fri 6/21/24 Sat 6/22/24 72
driving
80 Setting of Barge 1 day Sun 6/23/24 Sun 6/23/24 79
81 Boring and casting P-082 days Mon 6/24/24Tue 6/25/24 80
82 Boring and casting P-052 days Wed 6/26/24Thu 6/27/24 81
83 Group -11 (Type-1, Pile 7 days Fri 6/28/24 Thu 7/4/24 82
No. 04 and 01)
84 Permanent stell casing 2 days Fri 6/28/24 Sat 6/29/24 82
driving
85 Setting of Barge 1 day Sun 6/30/24 Sun 6/30/24 84
86 Boring and casting P-042 days Mon 7/1/24 Tue 7/2/24 85
87 Boring and casting P-012 days Wed 7/3/24 Thu 7/4/24 86
88 Group -12 (Type-1, Pile 7 days Fri 7/5/24 Thu 7/11/24 87
No. 02 and 03)
89 Permanent stell casing 2 days Fri 7/5/24 Sat 7/6/24 87
driving
90 Setting of Barge 1 day Sun 7/7/24 Sun 7/7/24 89
91 Boring and casting P-022 days Mon 7/8/24 Tue 7/9/24 90
92 Boring and casting P-032 days Wed 7/10/24Thu 7/11/24 91
93 Group -13 (Type-1, Pile 7 days Fri 7/12/24 Thu 7/18/24 92
No. 06 and 07)
94 Permanent stell casing 2 days Fri 7/12/24 Sat 7/13/24 92
driving
95 Setting of Barge 1 day Sun 7/14/24 Sun 7/14/24 94
96 Boring and casting P-062 days Mon 7/15/24Tue 7/16/24 95
97 Boring and casting P-072 days Wed 7/17/24Thu 7/18/24 96
98 Group -14 (Type-1, Pile 7 days Fri 7/19/24 Thu 7/25/24 97
No. 18 and 21)
99 Permanent stell casing 2 days Fri 7/19/24 Sat 7/20/24 97
driving
100 Setting of Barge 1 day Sun 7/21/24 Sun 7/21/24 99
101 Boring and casting P-182 days Mon 7/22/24Tue 7/23/24 100
102 Boring and casting P-212 days Wed 7/24/24Thu 7/25/24 101
103 Group -15 (Type-1, Pile 7 days Fri 7/26/24 Thu 8/1/24 102
No. 22 and 26)
104 Permanent stell casing 2 days Fri 7/26/24 Sat 7/27/24 102
driving
105 Setting of Barge 1 day Sun 7/28/24 Sun 7/28/24 104
106 Boring and casting P-222 days Mon 7/29/24Tue 7/30/24 105
107 Boring and casting P-262 days Wed 7/31/24Thu 8/1/24 106
108 Beam and Deck slab 153 days Wed 6/5/24 Mon 11/11/24
109 Type-2 Area (Gang way) 45 days Wed 6/5/24 Fri 7/26/24
110 Stagging and Form work20 days Wed 6/5/24 Mon 7/1/24
111 Re-bar Work 7 days Tue 7/2/24 Mon 7/8/24 110

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Work schedule-7.03.24
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 5/15/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

DEW-DCL JV.
Page 2
Work schedule for construction of Design and Build Jetty and other Associated works for Mongla port Authority under the Project of "Establishment of Modern Waste and Spilled Oil Management at Mongla Port" ( Tender Package No. W-1)
ID Task Name Duration Start Finish Predecessors Jan '24 Feb '24 Mar '24 Apr '24 May '24 Jun '24 Jul '24 Aug '24 Sep '24 Oct '24 Nov '24 Dec '24 Jan '25
31 7 14 21 28 4 11 18 25 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29
112 Concreting beam 3 days Tue 7/9/24 Thu 7/11/24 111
113 Form work, re-bar 15 days Fri 7/12/24 Fri 7/26/24 112
work and Concreting
114 of Deck
Jetty Head Area 53 days Tue 7/2/24 Fri 8/23/24 110
115 Stagging and Form work20 days Tue 7/2/24 Sun 7/21/24 110
116 Re-bar Work 10 days Mon 7/22/24Wed 7/31/24 115
117 Concreting beam 3 days Thu 8/1/24 Sat 8/3/24 116
118 Form work, re-bar 20 days Sun 8/4/24 Fri 8/23/24 117
work and Concreting
119 of Deck and 2 area
Dolphin-1 40 days Sat 8/24/24 Wed 10/2/24 118
120 Stagging and Form work15 days Sat 8/24/24 Sat 9/7/24 118
121 Re-bar Work 7 days Sun 9/8/24 Sat 9/14/24 120
122 Concreting beam 3 days Sun 9/15/24 Tue 9/17/24 121
123 Form work, re-bar 15 days Wed Wed 10/2/24 122
work and Concreting 9/18/24
124 of Deck and 4 area
Dolphin-3 40 days Thu 10/3/24 Mon 11/11/24118
125 Stagging and Form work15 days Thu 10/3/24 Thu 10/17/24 118
126 Re-bar Work 7 days Fri 10/18/24 Thu 10/24/24 125
127 Concreting beam 3 days Fri 10/25/24 Sun 10/27/24 126
128 Form work, re-bar 15 days Mon Mon 127
work and Concreting 10/28/24 11/11/24
129 of Deck
RCC Supporting wall 148 days Sun 2/25/24 Wed 8/14/24
130 Manufacturing of 120 days Sun 2/25/24 Wed 7/17/24
Interlocking Pile
131 Driving of Interlocking pile40 days Mon 5/27/24Wed 8/14/24 130FS-45 days
132 River bank Protection works204 days Thu 5/30/24 Thu 12/26/24
133 Manufacturing of CC Block120 days Thu 5/30/24 Thu 10/3/24
134 Bed preparation 15 days Fri 10/4/24 Fri 10/18/24 133
135 1st layer 41 days Sat 10/19/24Thu 11/28/24
136 Laying of Geotextile 2 days Sat 10/19/24 Sun 10/20/24 134
137 Earth filling and compaction
7 days Mon 10/21/24Sun 10/27/24 136
138 2nd layer 9 days Mon 10/28/24
Tue 11/5/24 137
139 Laying of Geotextile 2 days Mon 10/28/24Tue 10/29/24 137
140 Earth filling and compaction
7 days Wed 10/30/24Tue 11/5/24 139
141 3rd layer 26 days Wed 11/6/24Sun 12/1/24
142 Laying of Geotextile 2 days Wed 11/6/24Thu 11/7/24 140
143 Earth filling and compaction
7 days Fri 11/8/24 Thu 11/14/24 142
144 Laying of Permeable layer 10 days Fri 11/15/24 Sun 11/24/24
145 Placing of CC Block 25 days Mon 11/25/24Thu 12/19/24 144
146 Placing of Top and 7 days Fri 12/20/24 Thu 12/26/24 145
Bottom Edge concrete
147 Other works 108 days Sat 8/24/24 Mon 12/9/24
148 Fixing of Bolard 20 days Sat 8/24/24 Thu 9/12/24 114
149 Fixing of fender 60 days Sat 8/24/24 Tue 10/22/24 114
150 Laying of 500 mm dia pipe7 days Tue 8/27/24 Mon 9/2/24 114FS+3 days
151 Lighting and other 30 days Wed Thu 11/21/24 150,149
ormental works 10/23/24
152 Cleanning and demobilization
20 days Wed 11/20/24Mon 12/9/24 151FS-7 days

Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: Work schedule-7.03.24
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Wed 5/15/24
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

DEW-DCL JV.