Project Review N Closure Report - Template N Guide - Project 2
Project Review N Closure Report - Template N Guide - Project 2
Report
(Small Projects)
Template and Guide
Version 2.1 April 2008
This guide is intended to be read in conjunction with the following template for the development of a Project
Review & Closure Report for small projects. As such the Guide should be removed from the front of the final
document.
Additional templates for the review of a project phase (PM 037 Project Phase Review Report), the review
of a large complex project (PM 036 Project Review & Evaluation Report) and the closure of a large
complex project (PM 035 Project Closure Report) have also been developed. These are available at
www.egovernment.tas.gov.au.
The project management templates are being continuously improved. Feedback on suggested improvements
to this Template would be appreciated, and may be made to IAPPU by emailing
[email protected].
DISCLAIMER
This material has been prepared for use by Tasmanian Government agencies and Instrumentalities. It
follows that this material should not be relied upon by any other person. Furthermore, to the extent that ‘this
material is relied upon’, the Crown in Right of the State of Tasmania gives no warranty as to the accuracy or
correctness of the material or for any advice given or for omissions from the material. Users rely on the
material at their own risk.
A Project Review and Closure Report is How to determine the lessons learned
developed to: from the Project?
Review the outputs and success of the There are a number of mechanisms that can
project; be used to determine the lessons learned
Outline outstanding issues and from a project. The following list is not fully
recommendations; and comprehensive, but provides a few
Detail activities undertaken to close the suggestions, a combination of which may
project; and best suit your individual needs:
Inform future projects.
examination of project records and
The document enables those who approved documentation;
the resources to analyse how well the project questionnaire or survey of a
met the objectives by assessing the representative stakeholder sample;
economics and impact of the project and face to face interviews – either one-on-
comparing these against what was originally one or groups; and/or
planned. facilitated feedback sessions with a large
group of stakeholders.
Where an Agency, Division or Business Unit
has a number of projects, the Project Review It is important that stakeholder perceptions of
and Closure Report can be used as a tool to the project are captured. Although different
measure success and inform other future stakeholder groups will have different
projects. perceptions of the project, for future projects
it is important to learn from their perspective
what worked well or could be improved.
Checklist
PM 036 Project Review & Large or complex projects A useful tool to assist a Project
Evaluation Report Sponsor and/or Steering
Committee to:
determine if the appropriate
project management
framework has been selected
and appropriately applied
enabling any deficiencies to be
remedied
provide validation of a decision
to ‘stop’ the project
make an informed decision
about closing the project and
capturing the lessons learnt
PM 936 Project Review & Small projects Excellent tool for capturing
Closure Report lessons from small projects
and formally closing the
project.
PM 037 Project Phase Review Large or complex projects A useful tool to assist the Project
Report (phases) Sponsor and/or Steering
Committee to:
determine if the appropriate
project management
framework has been selected
and appropriately applied
enabling any deficiencies to be
remedied
provide validation of a decision
to proceed to the next phase of
the project
provide validation of a decision
to ‘stop’ the project
PM 035 Project Closure Report Large or complex projects A tool to assist a Project Sponsor
and/or Steering Committee to ‘tidy
up’ any loose ends and formally
close the project.
It may follow on from a Project
Phase Review Report or a Project
Review & Evaluation Report.
Copy: Uncontrolled
The version number starts at one and increases by one for each release. It shows the release number and a
revision letter if in draft. The original draft is 0.A and subsequent drafts are 0.B, 0.C etc. The first accepted
and issued document is 1.0. Subsequent changes in draft form are 1.0A, 1.0B etc.. The accepted and issued
second version is 1.1 or 2.0, depending on the magnitude of the change.
Refer to the Project Management Fact Sheet: Document Control, for more information at
www.egovernment.tas.gov.au
The contribution of the following individuals in preparing this document is gratefully acknowledged:
<Contributors/reviewers/developers>
This document has been derived from a template prepared by the Department of Premier and
Cabinet, Tasmania. The structure is based on the Tasmanian Government Project Management
Guidelines.
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 6 of 15
Document Acceptance and Release Notice
This document is Version <n.n>Version No of the <Project Title> Project Review and Closure
Report.
The Project Review and Closure Report is a managed document. For identification of amendments
each page contains a release number and a page number. Changes will only be issued as a
complete replacement document. Recipients should remove superseded versions from circulation.
This document is authorised for release once all signatures have been obtained.
PREPARED: Date: / /
(for acceptance) <Name, Title>
<Project Title> Project Manager
ACCEPTED: Date: / /
(for release) <Name, Title>
<Project Title> Project Sponsor
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 7 of 15
Document Development History
Build Status:
Version Date Author Reason Sections
<n.n> <dd-mm -yyyy> <name> Initial Release All
List the most
recent amendment
first
Distribution:
Copy No Version Issue Date Issued To
1 <n.n> <dd-mm-yyyy> <name, title, organisation>
2
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 8 of 15
Table of Contents
1 Executive Summary....................................................................................................................13
1.1 Background.......................................................................................................................13
1.2 Reason for Closing the Project.........................................................................................13
1.3 Highlights and Innovations................................................................................................13
1.4 Summary of Recommendations.......................................................................................13
2 Project Performance...................................................................................................................14
3 Lessons Learnt...........................................................................................................................15
4 Closure Activities........................................................................................................................16
4.1 Recommendations............................................................................................................16
5 Appendices..................................................................................................................................16
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 9 of 15
Closure Activities
1 Executive Summary
1.1 Background
Briefly describe the background to the Project.
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 11 of 15
Closure Activities
2 Project Performance
Summarise the actual performance of the project against the planned performance. All projects
vary to some extent from the original plan, these variations should be identified and the reasons for
the variance described.
2.6 Recommendations
List the recommendations that arise from this section of the Report.
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 12 of 15
Closure Activities
3 Lessons Learnt
You may wish to briefly describe the methodology used to collect the lessons learnt, if it was not
described in Section 2.
3.3 Recommendations
List the recommendations that arise from this section of the Report.
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 13 of 15
Closure Activities
4 Closure Activities
This section should cover the various activities required to close the project. Where relevant, the
sub-sections should include:
Project Staff: - Describe what steps are being taken to manage the movement of project staff
from the project to other roles, including the timing of their move and the capture of their
project knowledge.
Issues Management – Identify any outstanding issues and who will continue to progress the
issues.
Risk Management – Identify any risks that will transfer to an operational area and who will;
take on responsibility for monitoring them.
Financial Management – Outline the final financial position and what will happen to any excess
funds.
Asset Management - Describe any assets which were required by the project, and who will
manage them upon completion of the project.
Records Management – Identify what arrangements have been put in place for the storage,
security and backup of hard copy and soft (electronic) copy records and project documents.
Post Project Responsibilities - List any matters that are outstanding, what actions are required
to address them and who is responsible. This should include such things like outcomes yet to
be achieved, outputs not yet delivered, maintenance of the outputs or other operational
matters such as meeting future training requirements that are outstanding or have not been
formally agreed prior to this stage.
Where appropriate, if the project is to be repeated at another time, for example annual events
such as organising a Conference or the development of an Agency’s Annual Report identify
how the report will be utilised as a tool for continuous improvement.
4.1 Recommendations
List any recommendations that arise from this section of the Report. It would be expected that one
of the recommendations would be for the Project Sponsor to agree that the project can be deemed
closed as it has fulfilled all of the requirements as documented in the relevant Project Business
Plan or Brief, or where this is not the case, the Project Sponsor is satisfied that all outstanding
items have been satisfactorily addressed.
5 Appendices
This section is optional. Where necessary, appendices can be attached to provide any relevant
supporting information, such as:
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 14 of 15
Closure Activities
Any information to promote improvement of future projects of a similar nature, as all necessary
information is contained within a single document.
<Project Title>
Project Review and Closure Report
Version <n.n> Date: <dd-mm-yyyy>
Page 15 of 15