Investment in Transmission Gridworks
Investment in Transmission Gridworks
IN TRANSMISSION
Four business models for emerging markets
Table of contents
Four business models to facilitate 3
private investment in transmission
An introduction to independent 9
transmission projects
• It is more practical to raise capital for ITPs 4 See Linking Up: Public-Private Partnerships in Power Transmission in Africa, World Bank, 2017.
5 See Extending Competition in Electricity Transmission: Impact Assessment, 2016, by Ofgem.
using project finance techniques than it is to 6 See Rethinking Power Sector Reform in the Developing World, Vivien Foster and Anshul Rana, 2019, pg.
14.
7 Linking Up, pg. 39.
8 Id.
Private Investment in Transmission 8
An introduction to independent
transmission projects
INVESTORS
HOST
Equity contributions, Government COUNTRY
shareholdings support
agreement
LENDERS
Financial
Credit risk Host government Unless a state-owned transmission company has an investment
grade credit rating—which is highly unusual in emerging
markets—some form of credit support for the payment
obligations of the state-owned transmission utility will be
necessary. This may take the form of a sovereign guarantee, a
partial credit guarantee, partial risk guarantee, or a put and call
option agreement combined with liquidity support. Each of these
forms of support is likely to have a different fiscal treatment.
The more robust the form of support available, the lower the
credit risk and therefore it is likely that a lower cost of capital
will be available to fund the project. In many African countries
sovereign debt capacity is a limiting factor for expansion of
transmission networks at present and offering a put and call
option agreement with liquidity support to mitigate credit risk
may be a good solution to support private investment.
Land
Land acquisition State-owned The cost of acquiring the rights of way, easements, and other
transmission interests in land that are required by the project may be borne
company by the state-owned transmission utility or the project company,
regardless of which of them is responsible for acquiring those
interests. The acquisition of all of the required interests in land
would typically constitute a condition precedent to the first
disbursement of the project’s loans.
Technical
Construction and Project company The project company is responsible for constructing and
commissioning of commissioning new assets.
new assets
Operations and State-owned The maintenance of the assets can either be the responsibility
maintenance, transmission of the state-owned transmission company or the project
technical company or project company. Factors in determining which is the best approach
performance company may include
(i) how closely integrated the assets are in the existing
transmission network maintained by the state-owned
transmission company, (ii) how effective the state-owned
transmission company is with current O&M operations, (iii) the
scale of the assets, and (iv) Government policy in this respect.
How the payment under the Transmission Services Agreement
is calculated (and the extent to which it may be variable)
will typically depend to some extent on whether the project
company is responsible for maintaining the assets and ensuring
their availability or whether its responsibilities are narrower and
only pertain to developing, funding and constructing the assets.
The variability of payments based on availability/performance
are the means through which risk is passed to the project
company if it is responsible for maintenance. It is likely that the
project company will also take risk on variations of the cost of
providing these services over the period of the Transmission
Services Agreement, subject to periodic adjustments for
inflation.
Initial issuance of Government, state- The project company must apply for and diligently prosecute its
licenses and permits owned transmission applications for all licenses and permits. Significant licenses are
utility, and project granted prior to financial close and usually have a term that is
company the same as the term of the transmission purchase agreement.
If a public authority fails to grant a license or permit when the
applicable requirements have been met, that failure would
typically be treated as a political force majeure event.
Social and
environmental
Social and Project company The project company will typically be responsible for conducting
environmental social and environmental impact assessments, complying with
impacts the stakeholder consultation and environmental laws of the
host country, and, if the project company’s lenders are party to
the Equator Principles, for complying with relevant performance
standards issued by the International Finance Corporation.
Occupational health Project company The project company is responsible for complying with the
and safety occupational health and safety laws of the host country, and,
if the project company’s lenders are party to the Equator
Principles, for complying with relevant performance standards
issued by the International Finance Corporation.
Extraordinary events
Changes in law Consumers, Changes in law that increase the costs incurred by the project
government company or decrease the revenues earned by the project
company should be addressed through changes to the
availability payments or by one-time payments, depending
on the nature of the change in law. To the extent they are not,
they should be addressed through a change in law clause
in the government support agreement, which will typically
provide certain remedies to the project company in respect of
changes in law. Those remedies may include the payment of a
termination payment and transfer of the assets to Government.
Changes in tax Consumers, Changes in tax that increase (or decrease) the tax obligations
government of the project company should be addressed through changes
to the availability payments. To the extent they are not, then
they should be dealt with through a change in law clause in the
government support agreement.
Force majeure events Project company, The project company must mitigate the effects of force majeure
consumers events to the extent possible. Where it is practical to do so, the
project company will be required to insure against these risks.
Political force majeure Consumers, If the project company is prevented from performing its
events government, state- obligations or exercising its rights under the project agreements
owned transmission in a manner that is material due to the occurrence of a political
utility force majeure event and the effects of such events continue for
a prolonged period of time, an event of default may occur under
the transmission purchase agreement and the government
support agreement.
Disputes
Resolution of disputes n/a Disputes arising under the project agreements are resolved
under contracts by international arbitration to the extent they are not resolved
informally.
Enabling environment
Network industries require ongoing investment. As
a result, even a concession over of a transmission
system that does not require significant expansion
will require the concessionaire to incur capital
expenditures to replace worn-out equipment,
restore and refurbish existing equipment, and
upgrade the transmission system as a whole
over the term of the concession. In most African
jurisdictions, it is likely that a concessionaire
will be required to commit significant funds
to expand the transmission network over the
course of the concession to meet energy access
targets. As a result, the rates that are charged by a
concessionaire for transmission service cannot be
set and fixed at the beginning of the concession.
Instead of establishing rates for the term of the
concession at the outset, one of two approaches
is usually adopted. The most common approach
is for a concessionaire to be subject to technical
and economic regulation by an independent
regulator. The regulatory approaches regulators
use to regulate utilities generally, and concessions
in particular, will be covered in a separate article.
These approaches require that a regulator
HOST
REGULATOR
COUNTRY
INDUSTRIAL
GENERATOR CONCESSIONAIRE
Transmission Transmission CONSUMERS
Service Service
Agreement Agreement
OTHER LOAD
GENERATOR SERVING
Transmission Transmission
Service
Concession
Service ENTITIES
Agreement
Agreement Agreement
STATE-OWNED
TRANSMISSION
UTILITY
1 See Tonci Bakovic, Bernard Tenenbaum, and Fiona Woolf, Regulation by Contract –
A New Way to Privatize Electricity Distribution?, 2003.
Several issues are critical to the bankability of • the depreciation component of a utility’s
concession transactions. Those issues include annual revenue requirement provides
how investors with the return of its investment;
buy-out payments are calculated, some currency- • shorter depreciation periods increase
related considerations, and the allocation of rates over the short term by increasing the
risks among the parties to the transaction depreciation component of a utility’s annual
and consumers.There are few examples of revenue requirement but increase the overall
privately funded transmission concessions on returns paid by consumers because assets
the continent of Africa at present, so this article remain in the rate base for a longer period of
draws from the general principles applied to this time; and
model when it has been used elsewhere in the
• that many of the assets of a transmission
world. Specific concessions will normally have
utility have very long service lives and
targeted approaches to address a specific local
correspondingly long depreciation periods.
environment.
To use a simple example, let’s examine the
following fact pattern. A state-owned utility (the
Buy-out payments “grantor”) enters into a concession with a 20-year
In a prior article in this series that describes how term. The concessionaire places a transformer
network utilities are regulatedlearned that: with an acquisition cost of $1 million into service
on the first day of the concession. The regulator
• the component (RateBasey x WACCy) provides
requires the concessionaire to use straight-line
a utility with a return on its investment;
If a host country is not satisfied with the The operations and maintenance component
performance of a concessionaire, it may raise and other components of the annual revenue
funds to pay the buy-out payment by awarding a requirement would be partially denominated
new concession that requires the payment of an in the same foreign currency and partially
up-front concession fee that matches the amount denominated in the currency of the host country.
of the buy-out payment. In the alternative, a host The percentage of those components that are
government in this position could re-capitalise denominated in the foreign currency would
the grantor by injecting equity into the grantor and correspond to the percentage of the costs incurred
causing the grantor to raise an appropriately sized that are denominated in the foreign currency. A
amount of debt to fund the remaining portion of large part of the operations and maintenance
the buy-out payment. A grantor could raise that costs incurred by a transmission utility is for labor.
debt by issuing multiple series of bonds with As a result, a large part of the operations and
tenors that correspond to the depreciation profile maintenance component of the annual revenue
of the assets that constitute the regulated asset requirement would usually also be denominated in
base, by borrowing from a syndicate of banks, or the local currency.
using a combination of these approaches.
Risks
Currency considerations An appropriate allocation of risks is essential to
With the limited exception of countries that use a attracting investment in the form of both debt and
foreign currency to conduct financial transactions equity. The risk matrix that follows describes how
within their own economy and other very limited a range of risks might be allocated in a typical
circumstances, the rates that are paid by electricity concession transaction.
consumers are denominated in the currency of the
host country. In many emerging market countries,
capital markets and the market for loans from
local banks are not sufficiently liquid to fund the
debt component of the regulatory asset base of a
transmission utility. Where this is the case, rates
will need to be adjusted for changes in foreign
exchange rates regularly.
Financial
Demand risk Consumers Demand risk is effectively allocated to consumers by the tariff
guidelines. The tariff guidelines usually provide that if the
concessionaire does not earn revenues equal to the annual
revenue requirement during a particular year due to errors in
forecasting the demand for transmission service, then the
portion of the annual revenue requirement not earned as a
result of the forecasting error is added to the annual revenue
requirement for the following year, with interest.
Credit risk Concessionaire, The risk that purchasers of transmission service may not pay for
consumers transmission service promptly is borne by the concessionaire
but may be mitigated by (i) the use in the tariff guidelines of
a target collection ratio that is less than 100% (typically only
suitable in a model with a high number of off-takers), and (ii)
a sovereign guarantee of payment by state-owned enterprises
that purchase transmission service, or another form of liquidity
support and/or support for termination payments in the event of
non-payment.
Interest rates Consumers Rates are typically adjusted for changes in interest rates
regularly. The frequency of the adjustment may depend on how
the concessionaire raised, or could reasonably be expected
to have raised, debt financing. This can be a difficult risk to
apportion in a market with variable liquidity such as those found
in many African countries. The least cost approach to funding
transmission services will usually be to adjust for changes in
actual interest rates regularly.
Foreign exchange Consumers Rates are typically adjusted for changes in foreign exchange
rates rates regularly. These adjustments are usually made each
quarter.
Land
Pre-existing defects Consumers The cost of remedying pre-existing title defects on behalf of the
in title grantor constitutes a capital cost that increases the regulated
asset base.
Land acquisition for Consumers The cost of land acquired for new projects is included in the
expansions regulated asset base, usually when the asset is placed into
service.
Technical
Operations and Concessionaire If the concessionaire incurs O&M costs that exceed the O&M
maintenance, component of the annual revenue requirement approved by the
technical regulator, then the concessionaire will not achieve the cost of
performance equity established by the regulator. The risk of underperforming
against KPIs (see below) will need to be balanced carefully
against O&M cost overruns when a concession is designed.
Key performance Concessionaire If the concessionaire does not achieve the key performance
indicators, service indicators and/or the required service levels, it will incur
levels penalties, which may be used to reduce rates. For transmission
concessions, typical key performance indicators include
measure of the frequency and duration of outages and
measures of technical and commercial losses.
Initial issuance of Government, grantor, The concessionaire must apply for and diligently prosecute its
licenses and permits and concessionaire applications for all licenses and permits. Significant licenses are
granted at the commencement of the concession and usually
have a term that is the same as the concession. If a public
authority fails to grant a license or permit when the applicable
requirements have been met, that failure will be treated as a
political force majeure event.
Social and Concessionaire The concessionaire is responsible for conducting social and
environmental environmental impact assessments, complying with the
impacts stakeholder consultation and environmental laws of the host
country, and, if the concessionaire’s lenders are party to the
Equator Principles, for complying with relevant performance
standards issued by the International Finance Corporation.
Occupational health Concessionaire The concessionaire is responsible for complying with the
and safety occupational health and safety laws of the host country, and, if
the concessionaire’s lenders are party to the Equator Principles,
for complying with relevant performance standards issued by
the International Finance Corporation.
Extraordinary events
Changes in law Consumers, Changes in law that increase the costs incurred by the
government concessionaire or decrease the revenues earned by the
concessionaire should be addressed through changes to the
annual revenue requirement. To the extent they are not, they
should be addressed through a change in law clause in the
government support agreement.
Changes in tax Consumers, Changes in tax that increase (or decrease) the tax obligations of
government the concessionaire should be addressed through changes to the
annual revenue requirement. To the extent they are not, through
a change in law clause in the government support agreement.
Force majeure events Concessionaire, The concessionaire must mitigate the effects of force majeure
consumers events to the extent possible. Where it is practical to do so, the
concessionaire may insure against these risks. The cost of
the insurance is included in the operations and maintenance
component of the annual revenue requirement. Capital costs
associated with the replacement or repair of asset affected by a
force majeure event are included in the regulated asset base to
the extent they are not covered by insurance proceeds.
Political force majeure Consumers, If the concessionaire is prevented from performing its
events government, grantor obligations or exercising its rights under the concession in a
manner that is material due to the occurrence of a political force
majeure event and the effects of such events continue for a
prolonged period of time, an event of default may occur under
the concession agreement.
Disputes
Resolution of disputes n/a Disputes arising under the project agreements are resolved
under contracts by international arbitration to the extent they are not resolved
informally.
Resolution of disputes n/a Disputes arising in relation to the application of the tariff
arising in relation to methodology may result in claims under the change in law
the tariff methodology clauses of the government support agreement. Disputes
regarding the proper application of such a change in law clause
are then resolved by international arbitration to the extent they
are not resolved informally.
Chris Flavin
Chris is Head of Business Development at Gridworks Development
Partners, a development and investment platform focused on
investments in transmission, distribution and off-grid electricity in
Africa. Chris has extensive international project development and
M&A experience which spans Africa, Asia and Europe. Chris began
his career as a private practice lawyer advising a wide range of
institutional investors before joining Gridworks’ parent company,
British International Investment, in 2014. He was involved in the
strategy which led to Gridworks’ formation in 2019 and has served
on Gridworks’ senior management team since it was founded. Chris
is responsible for project development and investment activities
at Gridworks. Chris sits on the Board of a number of Gridworks
portfolio companies including Amari Power Transmission which
is developing the first privately financed transmission project
in Uganda. He is a regular contributor to publications and panel
discussions on the African Infrastructure sector.
gridworkspartners.com