Admin
Admin
ACCOMPLISHMENT
I GENERAL REQUIREMENT
a. Mobilization/Demobilization 1.00 lot 5.86% 40.00% 25.00% 65.00%
b. CARI and Bonds 1.00 lot 2.11% 40.00% 25.00% 65.00%
c. Water & Power Consumption 1.00 lot
d. Cleaning/Housekeeping Works/Safety 1.00 lot 3.09% 40.00% 25.00% 65.00%
e. TemporaryFacility/Barraks 1.00 lot 2.60% 40.00% 25.00% 65.00%
f. Supervision 1.00 lot 3.74% 40.00% 25.00% 65.00%
g. Disposal of unused materials and debris 1.00 lot 4.55% 40.00% 25.00% 65.00%
h. Delivery and hauling 1.00 lot 3.90% 40.00% 25.00% 65.00%
i. Testing and Commissioning 1.00 lot 0.98% 40.00% 25.00% 65.00%
SUB-TOTAL I 26.84% 40.00% 25.00% 65.00%
II Supply Materials and Installation works
A. ADMIN OFFICE
For Civil and Architectural works
1. Demolition of existing CHB partition wall including
1.00 lot 1.28% 80.00% 20.00% 100.00%
restoration works
2. Dismanling of existing steel door and jamb 1.00 set 0.09% 80.00% 20.00% 100.00%
3. Enclosure of wall due to dismantled of existing door
3.00 sq.m 0.19% 80.00% 20.00% 100.00%
opening using chb with cement plastered finish
4. Restoration of existing acoustic ceiling. 11.84 sq.m 0.25% 80.00% 20.00% 100.00%
5. Add new acoustic ceiling ( same spec of existing) 15.31 sq.m 0.83% 80.00% 20.00% 100.00%
6. Painting works on walls and Existing steel door 77.21 sq.m 1.30% 80.00% 15.00% 95.00%
7. Replacement of existing vinyl tiles(6mm thickness) 27.15 sq.m 1.63% 80.00% 20.00% 100.00%
8. Signage 1.00 pcs 0.05% 80.00% 80.00%