Test Pump Calculations
Test Pump Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.110 mm
Line number: 1 line
5) Outline (Assume)
LWL -1.6
C1-1
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 1.35m3
h = 0.5m > 0.28 m
L1
h = 0.6 m
LLWL
Manufacturer recommendation
Bottom (approx. 0.3m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 6.0 L/sec/unit
= 0.36 m3/min/unit
Total head H attached Table Pump calculation sheet 14.0 m
Motor P attached Table Pump calculation sheet
Approx. 5.5 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 0.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-2
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Motor Power
C1-3
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.110 mm
Line number: 1 line
5) Outline (Assume)
HWL +14.2
Wet well
GL Discharge
(PS 03 Hagara)
LWL -4.0
C1-4
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 2.4m3
h = 0.6m > 0.50 m
L1
h = 0.8m
LLWL
Manufacturer recommendation
Bottom (approx. 0.4m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 10.8 L/sec/unit
3
= 0.65 m /min/unit
Total head H attached Table Pump calculation sheet 40.0 m
Motor P attached Table Pump calculation sheet
Approx. 22.0 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 1.0 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-5
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Motor Power
C1-6
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.225 mm
Line number: 1 line
Wet well
GL Discharge
(PS 04 Hanuabada)
LWL -2.0
C1-7
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 7.1m3
h = 1.5m > 1.45 m
L1
h = 0.8m
LLWL
Manufacturer recommendation
Bottom (approx. 0.4m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 31.6 L/sec/unit
3
= 1.9 m /min/unit
Total head H attached Table Pump calculation sheet 25.0 m
Motor P attached Table Pump calculation sheet
Approx. 22.0 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 1.0 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-8
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Motor Power
C1-9
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.355 mm
Line number: 1 line
Wet well
GL Discharge
(PS 05 Konedobu)
Force main :
C1-10
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 18m3
h = 1.6m > 1.50 m
L1
h = 0.45m
LLWL
Manufacturer recommendation
Bottom (approx. 0.55m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 200 mm
Capacity Qp 80.0 L/sec/unit
= 4.8 m3/min/unit
Total head H attached Table Pump calculation sheet 17.0 m
Motor P attached Table Pump calculation sheet
Approx. 22.0 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 2.0 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-11
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Motor Power
C1-12
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.450 mm
Line number: 1 line
HWL +28.5
5) Outline (Assume)
Wet well
GL to Gravity Sewer
LWL -5.7
C1-13
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H2 (HWL)
H1 V >16.5m3
Existing Inlet pipe bottom level h = 1.5m > 1.46 m
1.05m L2
h = 0.2 m
L1
h = 0.15m
LLWL
Manufacturer (Forced cooling type)
Bottom recommendation (approx. 0.4m)
H2 (HWL)
3
H1 V >16.5m
h = 1.1m > 1.05 m
L2
h = 0.2 m
L1
h = 0.75m
LLWL
Manufacturer (Forced cooling type)
Bottom recommendation (approx.0.55 m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 200 mm
Capacity Qp 73.3 L/sec/unit
= 4.4 m3/min/unit
Total head H attached Table Pump calculation sheet 42.0 m
Motor P attached Table Pump calculation sheet
Approx. 55.0 kW
Number Duty 2 units
Standby 1 unit
Stock 1 unit
Total 4 units
Specification
Type Manually Geared trolley
Capacity 2.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-14
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-15
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : DCIP (E×isting Pipe)
Diameter : Dia.150 mm
Line number: 1 line
5) Outline (Assume)
GL
to Gravity Sewer
LWL - 0.5
C1-16
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Specification
Type Manually Geared trolley
Capacity 0.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-17
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
0.15m × 1 line
11 D : Inner Pipe Dia. (m) 0.15
12 L : Pipe length (m) 400
13 Cc : Correction coefficient 1.0
Water: 1.0
Sludge: WT99.2% :
14 hf2 0.000
Motor Power
C1-18
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.160 mm
Line number: 1 line
Wet well
GL
to Gravity Sewer
Force main :
Gravity:
HWL -1.4 Dia.160mm × 240 mL
LWL -1.9
C1-19
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
V > 3.5m3
h = 0.5m > 0.46 m
2.73m
L1
h = 0.55 m
LLWL
Manufacturer recommendation
Bottom (approx. 0.35m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 23.3 L/sec/unit
3
= 1.4 m /min/unit
Total head H attached Table Pump calculation sheet 24.0 m
Motor P attached Table Pump calculation sheet
Approx. 15.0 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 1.0 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-20
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Motor Power
C1-21
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.110 mm
Line number: 1 line
5) Outline (Assume)
Wet well
GL
Discharge +2.1
to Gravity Sewer
Force main :
HWL -3.2 Dia.110mm × 640 mL
LWL -3.5
C1-22
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
V > 2.3m3
h = 0.3m > 0.20 m
3.122m
L1
h = 0.2 m
LLWL
Manufacturer recommendation
Bottom (approx. 0.8m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 10.0 L/sec/unit
3
= 0.60 m /min/unit
Total head H attached Table Pump calculation sheet 24.0 m
Motor P attached Table Pump calculation sheet
Approx. 7.5 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 0.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-23
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Motor Power
C1-24
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.450 mm
Line number: 1 line
5) Outline (Assume)
Wet well
GL Discharge +0.6
(PS 10 Lawes Road)
Force main :
HWL -1.45 Dia.450mm × 700 mL
LWL -2.9
C1-25
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 V >14.0m3
h = 1.3m > 1.30 m
1.96m L2
h = 0.15 m
L1
h = 0.15m
LLWL
Manufacturer recommendati (Forced cooling type)
Bottom (approx. 0.35m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 200 mm
Capacity Qp 93.3 L/sec/unit
= 5.6 m3/min/unit
Total head H attached Table Pump calculation sheet 11.0 m
Motor P attached Table Pump calculation sheet
Approx. 15.0 kW
Number Duty 2 units
Standby 1 unit
Stock 1 unit
Total 4 units
Specification
Type Manually Geared trolley
Capacity 1.0 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-26
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-27
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.500 mm
Line number: 1 line
5) Outline (Assume)
Discharge
Wet well (R.M.H)
HWL+23.0
GL
Force main :
Basket HWL -1.7 Dia.500 mm × 2,750 mL
LWL -4.9
C1-28
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H2 (HWL)
H1 V >46.5m3
Inlet pipe bottom level h = 4.5m > 4.10 m
(Existing)
L2
0.03 m h = 0.2 m
L1
h = 0.15m
LLWL
Manufacturer recommendati (Forced cooling type)
Bottom (approx. 0.5 m)
H2 (HWL)
3
H1 V >46.5m
h = 3.0m > 2.95 m
L2
h = 0.2 m
L1
h = 0.15m
LLWL
Manufacturer recommendati (Forced Cooling type)
Bottom (approx. 0.5m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 250 mm
Capacity Qp 103.3 L/sec/unit
3
= 6.2 m /min/unit
Total head H attached Table Pump calculation sheet 42.0 m
Motor P attached Table Pump calculation sheet
Approx. 75.0 kW
Number Duty 2 units
Standby 1 unit
Stock 1 unit
Total 4 units
Specification
Type Manually Geared trolley
Capacity 2.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-29
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-30
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : DCIP (E×isting Pipe)
Diameter : Dia.200 mm
Line number: 1 line
5) Outline (Assume)
HWL +15.0
Wet well
LWL -3.2
C1-31
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 9.7m3
h = 1.0m > 0.81 m
L1
h = 0.2 m
LLWL
Manufacturer recommendation
Bottom (approx. 1.0m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 200 mm
Capacity Qp 43.3 L/sec/unit
= 2.6 m3/min/unit
Total head H attached Table Pump calculation sheet 31.0 m
Motor P attached Table Pump calculation sheet
Approx. 37.0 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 1.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-32
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Motor Power
C1-33
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.400 mm
Line number: 1 line
GL
Force main :
HWL -1.34 Dia.400 mm × 1,160 mL
LWL -2.66
C1-34
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 V > 13.1m3
h = 1.22m > 1.22 m
L2
1.77 m h = 0.1 m
L1
h = 0.1m
LLWL
Manufacturer recommendati (Forced cooling type)
Bottom (approx. 0.3m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 200 mm
Capacity Qp 58.3 L/sec/unit
= 3.5 m3/min/unit
Total head H attached Table Pump calculation sheet 33.0 m
Motor P attached Table Pump calculation sheet
Approx. 45.0 kW
Number Duty 2 units
Standby 1 unit
Stock 1 unit
Total 4 units
Specification
Type Manually Geared trolley
Capacity 2.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-35
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-36
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.110 mm
Line number: 1 line
5) Outline (Assume)
HWL +13.5
Wet well
GL Discharge
(PS 14 Konebada)
LWL -1.0
C1-37
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 0.5m3
h = 0.5m > 0.11 m
L1
h = 0.4 m
LLWL
Manufacturer recommendation
Bottom (approx. 0.3m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 6.0 L/sec/unit
= 0.36 m3/min/unit
Total head H attached Table Pump calculation sheet 20.0 m
Motor P attached Table Pump calculation sheet
Approx. 5.5 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 0.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-38
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
0.11m × 1 line
11 D : Inner Pipe Dia. (m) 0.0964
12 L : Pipe length (m) 230
13 Cc : Correction coefficient 1.0
Water: 1.0
Sludge: WT99.2% :
14 hf2 0.000
Motor Power
C1-39
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.110 mm
Line number: 1 line
Wet well
GL Discharge
(PS 15 Gabutu)
LWL -2.1
C1-40
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 1.7m3
h = 0.5m > 0.34 m
L1
h = 0.4 m
LLWL
Manufacturer recommendation
Bottom (approx. 0.3m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 7.5 L/sec/unit
3
= 0.45 m /min/unit
Total head H attached Table Pump calculation sheet 24.0 m
Motor P attached Table Pump calculation sheet
Approx. 7.5 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 0.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-41
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
0.11m × 1 line
11 D : Inner Pipe Dia. (m) 0.0964
12 L : Pipe length (m) 230
13 Cc : Correction coefficient 1.0
Water: 1.0
Sludge: WT99.2% :
14 hf2 0.000
Motor Power
C1-42
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.125 mm
Line number: 1 line
Discharge
5) Outline (Assume) (R.M.H.)
HWL+23.0
Wet well
GL
Force main :
Basket HWL -2.0 Dia.125mm × 760 mL
LWL -2.6
C1-43
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 2.8m3
h = 0.6m > 0.57 m
L1
h = 0.2 m
LLWL
Manufacturer recommendation
Bottom (approx. 1.0m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 12.5 L/sec/unit
= 0.75 m3/min/unit
Total head H attached Table Pump calculation sheet 43.0 m
Motor P attached Table Pump calculation sheet
Approx. 22.0 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 1.0 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-44
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
0.125m × 1 line
11 D : Inner Pipe Dia. (m) 0.1098
12 L : Pipe length (m) 760
13 Cc : Correction coefficient 1.0
Water: 1.0
Sludge: WT99.2% :
14 hf2 0.000
Motor Power
C1-45
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.225 mm
Line number: 1 line
5) Outline (Assume)
Discharge
Wet well (Kila Kila STP)
HWL+12.1
GL
Force main :
Basket HWL -3.0 Dia.225 mm × 600 mL
LWL -4.2
C1-46
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 (HWL)
V > 5.6m3
h = 1.2m > 1.15 m
L1
h = 0.6m
LLWL
Manufacturer recommendation
Bottom (approx. 0.4m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 100 mm
Capacity Qp 25.0 L/sec/unit
3
= 1.5 m /min/unit
Total head H attached Table Pump calculation sheet 21.0 m
Motor P attached Table Pump calculation sheet
Approx. 11.0 kW
Number Duty 1 unit
Standby 1 unit
Total 2 units
Specification
Type Manually Geared trolley
Capacity 0.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-47
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
0.225m × 1 line
11 D : Inner Pipe Dia. (m) 0.1976
12 L : Pipe length (m) 600
13 Cc : Correction coefficient 1.0
Water: 1.0
Sludge: WT99.2% :
14 hf2 0.000
Motor Power
C1-48
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Gravity
Force main
Design Condition
1) Design Flow
4) Force Main
Material : HDPE
Diameter : Dia.710 mm
Line number: 1 line
5) Outline (Assume)
HWL +20.8
Wet well Discharge
(Kila Kila STP)
GL HWL+12.1
Force main :
Basket HWL +12.3Dia.710mm × 260 mL
LWL+ 9.0
C1-49
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
H1 V > 46.9m3
Inlet pipe bottom level h = 21m > 20.74 m
(Existing)
L2
0.03 m h = 0.2 m
L1
h = 0.85m
LLWL
Manufacturer recommendati (Forced cooling type)
Bottom (approx. 0.75 m)
H2 (HWL)
H1 V > 46.9m3
h = 3.1m > 2.98 m
L2
h = 0.2 m
L1
h = 0.85m
LLWL
Manufacturer recommendation
Bottom (approx. 0.75 m)
Specification
Type Submersible non-clog sewage pump, automatic coupling type
Dia. D Approx. 350 mm
Capacity Qp 208.3 L/sec/unit
3
= 12.5 m /min/unit
Total head H attached Table Pump calculation sheet 15.0 m
Motor P attached Table Pump calculation sheet
Approx. 55.0 kW
Number Duty 2 units
Standby 1 unit
Stock 1 unit
Total 4 units
Specification
Type Manually Geared trolley
Capacity 2.5 Tonf
Lift Approx. 3.0 m
Number Duty 1 unit
Standby 0 unit
Total 1 unit
C1-50
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-51
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
3
Design Flow Q2'-D 36,800 m /day (Hourly Maximum)
3
Q2'-S 0.426 m /sec (Hourly Maximum)
Type Manually Operated Cast Iron Gate
Unit Number UN Ope. Stand-by Total
2 units 0 unit 2 units
2.Design Criteria
Average Velocity V1 Less than 1.0 m/sec
3.Calculation
Dimension Depth H Arrangement 0.5 m
Width W H : W = 1 : 1 or 1.5 : 1 therefore 0.5 m
Velocity V2 Q2'-S × 1 / (H × W × 2) = 0.85 m/sec
Less than 1.0m/sec …OK
2 Medium Screen
1.Design Condition
3
Design Flow Q2'-D 36,800 m /day (Hourly Maximum)
3
Q2'-S 0.426 m /sec (Hourly Maximum)
Type Automatic Drum Screen
Unit Number UN Ope. Stand-by Total
2 unit 0 unit 2 unit
Opening OP 20 mm
3 3
Flow Per Unit Qu Q2'-S / UN = 0.213 m /sec = 18,400 m /day
Cannel Width Width 1.6 m
C1-52
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
3
Design Flow Q1-D 36,800 m /day (Hourly Maximum)
Type Container ( with handcart )
Unit Number UN Ope. Stand-by Total
1 unit 3 units 4 units
Storage days SD 3 days
2.Design Criteria
3 3 3 3
Unit Screenings Generation Volume Vo1 0.001 m /1000m to 0.015 m /1000m
3.Calculation
3 3
Design Screening Volume Vo2 Q1-D × 10-3 × Vo1 = 0.04 m /day to 0.55 m /day
However dehydrate to 70% water content
(Raw Screening water content : 85%)
3 3
therefore 0.018 m /day to 0.28 m /day
3 3
Container Volume Vo3 Vo2 × SD = 0.06 m to 0.83 m
3
4.Specification 0.5 m × 4 units (proposed)
4 Grit Collector
1.Design Condition
3
Design Flow Q2'-D 36,800 m /day (Hourly Maximum)
3
Q2'-S 0.426 m /sec (Hourly Maximum)
Type Vorte× Type
Unit Number UN Ope. Stand-by Total
2 units 0 unit 2 units
Grit Chamber Dimension Dia 1.6m
Channel Number 2 channels
3 3
Flow Per Unit Qu Q2'-S / ( UN )= 0.213 m /sec = 18,400 m /d
C1-53
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Centrifugal Pump
Unit Number UN Ope. Stand-by Total
1 units 1 unit 2 units
3
Sand Pit Volume Vo 2m
2.Design Criteria
Operation Time T Appro×imately 5 min Against Sand Pit Volume
3.Calculation
3
Discharge Flow Per Unit QU Vo/T = 0.5 m /min
Total Pump Head H From Calculation Sheet of Pumps (STP) 7m
3
4.Specification Dia.80 mm × 0.5 m / min × 7 m × 2.2 kW × 2 units (proposed)
6 Grit Separator
1.Design Condition
Type Screw Conveyor Type
Unit Number UN Ope. Stand-by Total
1 unit 0 unit 1 unit
3
Grit Pump Discharge Flow QU 0.5 m /min
2.Design Criteria
Retention Time T More Than 30 sec Against Grit Removal Pump Discharge Flow
3.Calculation
3
Tank Volume Vo QU × T= more than 0.25 m
3
4.Specification 0.5 m / min × 0.75 kW × 1 unit (proposed)
C1-54
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
3
Design Flow Q1'-D 36,800 m /day (Hourly Maximum)
Type Container ( with handcart )
Unit Number UN Ope. Stand-by Total
1 unit 3 units 4 units
Storage days SD 3 days
2.Design Criteria
3 3 3 3
Unit Grit Sedimentation Volume Vo1 0.001 m /1000m to 0.02 m /1000m
3.Calculation
3 3
Design Grit Volume Vo2 Q1'-D × 10-3 × Vo1 = 0.04 m /day to 0.74 m /day
3 3
Container Volume Vo3 Vo2 × SD = 0.11 m to 2.2 m
3
4.Specification 0.5 m × 4 units (proposed)
C1-55
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
3
Design Flow Q2'-D 36,800 m /day (Hourly Maximum)
3
Design Flow Q2'-S 0.426 m /sec (Hourly Maximum)
Type Adjustable Weir, Cast Iron
Unit Number UN Ope. Stand-by Total
4 units 0 unit 4 units
2.Design Criteria
Effluent Height H1 0.10 m to 0.30 m
3.Calculation
3/2
Weir Width W (Q2'-S)/UN/1.84/H1 =
= 1.8 m to 0.35 m
therefore 0.8 m
Check (Q2'/N/1.84/W')^2/3 0.17
C1-56
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
3
Ma×. Design Flow Q2'-D 18,400 m /day (Daily Average + Return Sludge Flow + Bypass Frow)
3
Q2'-S 0.213 m /sec
Type Manually Operated Cast Iron Gate
Unit Number UN Ope. Stand-by Total
1 unit/train 0 unit 1 unit/train
2.Design Criteria
Average Velocity V1 Less than 1 m/sec
3.Calculation
Dimension Depth H Arrangement 0.5 m
Width W H : W = 1 : 1 or 1.5 : 1 therefore 0.5 m
Velocity V2 Q2'-S / (H × W )/ UN = 0.95 m/sec
Less than 1.0m/sec …OK
4.Specification W 500 mm × H 500 mm × 3 units (proposed)
C1-57
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-58
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-59
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
2.Design Criteria
Allowance AL 10 %
3.Calculation
3
Air Demand Q Qa × (1+AL/100) = 40.6 Sm /min/train
3
therefore 42 Sm /min/train
3
4.Specification Dia 200 mm × 42 Sm /min × 70 kPa × 75 kW × 5 units (proposed)
1.Design Condition
Type Submersible Propeller Type Mixer
OD Train Number TN 4 trains (Ultimate)
Unit Number UN Ope. Stand-by Total
4 units/ train 0 unit 4 units/ train
3
OD Tank Volume V 4,600 m /tank
3
2.Design Criteria W 1.5 w/m
4.Specification Dia. Approx. 2.4 m × Approx. 2.3 kW × 12 units (4 units/train × 3 trains, proposed)
(Based on Manufacture's Information)
C1-60
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Submersible Sewage Pump (Non-clog)
Unit Number UN Ope. Stand-by Total (Ultimate)
4 units 4 units 8 units
3
Sludge volume V 1,434 m /day
2.Design Criteria
Operation Time T 5.4 hr/day/unit
3.Calculation
3
Discharge Flow QU V/ ( T× 60) / UN= 1.11 m /min
3
therefore 1.1 m /min
Total Pump Head H From Calculation Sheet of Pumps (STP) 14 m
3
4.Specification Dia.100 mm × 1.1 m /min × 14 m × 5.5 kW × 6 units (proposed)
C1-61
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
3
Design Flow Q2'-D 18,400 m /day (Ultimate Daily Average)
Type Center Driven Column Type
Unit Number UN 4 units (Ultimate)
Dimension Dia.25 m × WD 3.5 m × 4 units
1.Design Condition
Type Centrifugal Pump (Screw type)
Unit Number UN Ope. Stand-by Total (Ultimate)
4 units 4 units 8 units
3
Design Flow Q3'-D 18,400 m /day (Ultimate Daily Average)
3
Q3'-M 12.8 m /min
2.Design Criteria
Return Sludge Ratio RSR 100 %、(Max.200%)
Operation Time T 24 hr/day
3.Calculation
3
Discharge Flow QU Q3'-M × (RSR/100) /UN= 3.19 m /min
3
therefore 3.2 m /min
Total Pump Head H From Calculation Sheet of Pumps (STP) 9m
3
4.Specification Dia.150 mm × 3.2 m /min × 9 m × 11 kW × 6 units (proposed)
C1-62
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
3
Design Flow Q2'-D 36,800 m /day (Hourly Maximum)
3
Q2'-S 0.426 m /sec (Hourly Maximum)
Type Manually Operated Cast Iron Gate
Unit Number UN Ope. Stand-by Total
2 units 0 unit 2 units
2.Design Criteria
Average Velocity V1 Less than 1 m/sec
3.Calculation
Dimension Depth H Arrangement 0.6 m
Width W H : W = 1 : 1 or 1.5 : 1 therefore 0.4 m
Velocity V2 Q2'-S × 1 / (H × W ) = 0.89 m/sec
Less than 1.0m/sec …OK
2.Design Criteria
3
Flow rate per Unit QN Q3'-D / UN = 18,400 m /day
3
Capacity per UV Lump QUV 490 m / day / lamp (Based on Manufacture's Information)
3.Calculation
UV Lamp Number UN QN / QUV = 37.6 lamps per Unit
therefore 42 lamps per Unit
3
4.Specification 18,400 m /day × Approx.15.0 kW × (42 lamps/ lot) × 2 lots
C1-63
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
3 3
4) Specification 7 m × 1 unit, 0 to 0.3 m / hr × 2 units (proposed)
(Mixer 1.5kw)
C1-64
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Supply Unit
1.Design Condition
Type Two Submersible Pumps + Pressure Tank with Control Panel
Unit Number UN Ope. Stand-by Total
1 unit 0 unit 1 unit
2.Design Criteria
Required Water Volume
3
QU2 From Calculation of the Capacity of TE Unit 0.6 m /min
3.Calculation
3
Discharge Flow Per Unit QU 0.6 m /min
Total Pump Head H From Calculation Sheet of Pumps (STP) 42 m
3
4.Specification Dia.50mm × 0.6 m /min × 42 m × 7.4kW × 1 lot (proposed)
(2 pumps/ lot)
5 Defoaming Pump
1.Design Condition
Type Submersible Turbine Pump
Unit Number UN Ope. Stand-by Total
1 unit 1 unit 2 units
Nozzle Number UN1 12 units/train × 4 trains (Ultimate)
3.Calculation
3
Discharge Flow Per Unit QU1 0.6 m /min
Total Pump Head H From Calculation Sheet of Pumps (STP) 29 m
3
4.Specification Dia.100 mm × 0.6 m /min × 29 m × 3.7 kW × 2 units (proposed)
C1-65
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Multi-Diskplate Screw Press
Inlet SS Load S 2,397 kg/ day
3
Inlet Sludge Volume Vo 799 m / day
Sludge Solids Content Ssc 0.3 %
2.Design Criteria
Solid Load per Unit SL 179 kg-DS/hr
Operation Time T1 94 hr/week (104hr × 0.9)
T2 22 hours/day (24hr × 0.9)
2.Calculation
Unit Number UN S × (7 / T1) /SL = 1.0 unit
therefore 1 unit
Ope. Stand-by Total
1 units 1 unit 2 units
C1-66
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
These tanks are used for sludge dewatering unit
Type Cylindrical Steel Tank
Unit Number UN 2 units
Inlet SS Load(Dewatering) S2 2,397 kg/ day
Unit Number (Dewatering) UNd 1 unit
Sludge Dewatering Unit Capacity SLd 179 kg-DS/ hr
2.Design Criteria
Dosage rate per DS(Dewatering) Ird 1.5 %
Dissolving Concentration DC 0.2 %
3.Calculation
Polymer Consumption Weight(Dewatering) W2 S2 × Ird × 7/5 = 64 kg/ day
3
Tank Volume Vo W2 × 100 /DC × 10-3/UN = 16.1 m / tank
3
therefore 17 m / tank
3
4.Specification 17 m × Dia.2,700 mm × Height 3.6 m × 2 units (proposed)
(Agitator 11kw)
C1-67
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Constant Chemical Feeder
Unit Number UN 2 units
Polymer Consumption Weight C 34.0 kg/tank
Polymer Consumption Weight (Dewatering) W2 64 kg/day
Polymer Density η1 0.5 kg/L
2.Design Criteria
Feeding Time T 20 min/tank
Allowance AL 30 %
Storage Days (Hopper) SD more than 1 day
3.Calculation
Feeder Capacity Q C / T × (100 + AL) / 100 = 2.21 kg/min
Hopper Volume Vo (W1+W2) × SD / UN /η1 = 64 L
Therefore 100 L
4.Specification 2.3 kg/ min × 0.4 kW × 2 units (proposed)
1.Design Condition
Type Progressive Cavity Pump
Unit Number UN Ope. Stand-by Total
1 units 1 unit 2 units
Dewatring Solid Load SL 179 kg-DS/hr
2.Design Criteria
Dosage rate per DS Ir 1.5 %
Dissolution Concentration DC 0.2 %
Control range CR 50% to 150%
3.Calculation
Discharge Flow per Unit QU SL × Ir / DC × 10-3 × CR=
3 3
0.7 m /hr to 2.0 m /hr
Total Pump Head H 20 m
(Based on Manufacturer's Information)
3
4.Specification Dia.50mm × 0.7- 2.0 m /hr × 20 m × 1.5 kW × 2 units (proposed)
C1-68
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Submersible Propeller Mixer
Unit Number UN Ope. Stand-by Total
1 unit 0 units 1 unit
Tank Number TN 1 tank
3
Tank Volume V 113 m /tank (W 5m ×L 5m × WD4.5m)
3
2.Design Criteria W 5 w/m
1.Design Condition
Type Non-clog Type Sludge Pump
Unit Number UN Ope. Stand-by Total
1 units 1 units 2 units
3
Waste Water Tank Volume Vo 113 m
2.Design Criteria
Operation Time T 60 min Against Waste Water Volume
3.Calculation
3
Discharge Flow Per Unit QU Vo /T / UN × (1+AL/100) = 1.9 m /min
Total Pump Head H From Table1. Friction Loss Calculation Sheet 14 m
3
4.Specification Dia.100 mm × 2.0 m / min × 14 m × 11 kW × 2 units (proposed)
C1-69
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Motor Driven Cutgate Type
Unit Number UN 1 unit
3
Sludge Volume (Solid) Vo 27 m /day (Ultimate)
3
2.Specification 15 m × (2.2 × 2) kW × 1unit (proposed)
C1-70
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Biological Odor Control
Unit Number UN Ope. Stand-by Total
1 unit 0 unit 1 unit
Odor Gas Flow Q
3 3
m /min therefore 40 m /min
3
Grit Chamber Channel 10.0 m /min
3
Machinery in Grit Chamber 8.0 m /min
3
Distibution Chamber 2.0 m /min
3
Dewatering Unit 4.0 m /min
F Odor Control
3
Machinery in Sludge Facilities 10.0 m /min Fan
3
Scum Pit 4.0 m /min
3
Waste Water Tank 2.0 m /min
2.Design Criteria
Gas Velocity LV 0.1 m/sec
3 3
SV 200 m /m /h
3.Calculation
2
Required Section Area A Q/LV/60= More than 6.67 m
3
Required Media Volume V Q×60/SV= Appro×. 12 m
3
4. Specification 40 m / min × 1 unit
C1-71
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
1.Design Condition
Type Centrifugal Fan
Unit Number UN Ope. Stand-by Total
1 unit 1 unit 2 unit
3
Odor Gas Flow Q 40 m /min
2.Calculation
Total Fan Head H 2.5 kPa
3
3. Specification 40 m / min × 2.5 kPa × 5.5 kW × 2 units
C1-72
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Total Head
H=ha+hf1+hf2+hf3+hf4
5 ha :Actual head (m) 5.0 3.3 5.0 10.5 5.0 2.78 7.8 5.0 5.0 9.5 1.0
=DWL-SWL
6 DWL (m) 13.5 10.2 13.5
7 SWL (m) 3.0 7.42 4.0
8 hf1 : Straight pipe loss (m)= 0.828 1.178 0.151 1.420 0.163 2.428 2.828 0.992 0.744 1.262 1.444
(10.666 × Q^1.85) × L × Cc
(C^1.85×D^4.85)
9Q : Flow (m3/sec) 0.008 0.003 0.005 0.008 0.005 0.107 0.018 0.010 0.010 0.033 0.005
=q × N/60
10 C : Coefficient 110 100 130 130 130 130 130 130 130 130 110
DCIP:110
Steel pipe : 100
HDPE : 130
11 D : Pipe Dia. (m) 0.08 0.0657 0.08 0.0964 0.0788 0.2462 0.1406 0.1406 0.1406 0.1976 0.08
12 L : Pipe length (m) 12 30 10 90 10 100 200 280 210 200 70
13 Cc : Correction coefficient 1.3 1.3 1.0 1.0 1.0 1.3 1.3 1.0 1.0 1.0 1.0
Water: 1.0
Sludge: WT99.2% : 1.3
14 hf2 : Bend and others loss (m) 0.248 0.353 0.045 0.426 0.049 0.728 0.848 0.298 0.223 0.379 0.433
=hf1 × 0.3 (in the building)
15 hf3 : Pump around loss (m) 0.7 0.7 0.7 0.7 0.7 2 0.7 0.7 0.7 0.7 0.7
Horizontal type : 2.0m
Submersible type : 0.7m
16 hf4 :Other head 0 0 0 0 0 0 0 30 20 0 0
17 H' =ha+hf1+hf2+hf3+hf4 (m) 6.78 5.53 5.90 13.05 5.91 7.94 12.18 36.99 26.67 11.84 3.58
18 H : Total head (m) 7.0 6.0 6.0 14.0 6.0 9.0 14.0 42.0 29.0 14.0 5.0
V Velocity 1.66 0.98 1.00 1.14 1.03 2.24 1.18 0.64 0.64 1.09 1.00
Ma×.
Motor Power
19 BKW =0.163*SG*q*H/Pe (kW) 1.90 0.49 0.77 3.00 0.77 7.58 4.18 6.32 3.55 7.61 0.64
20 SG :Specific gravity 1.0 1.0 1.05 1.05 1.05 1.05 1.0 1.0 1.0 1.0 1.05
21 Pe :Pump efficiency 0.3 0.4 0.4 0.4 0.4 0.65 0.6 0.65 0.8 0.6 0.4
22 kW =BKW × C 2.187 0.562 0.886 3.444 0.886 8.721 4.811 7.267 4.077 8.748 0.738
23 C :Coefficient (1.15) 1.15 1.15 1.15 1.15 1.15 1.15 1.15 1.15 1.15 1.15 1.15
24 Motor Power (kW) 2.2 0.75 1.5 3.7 1.5 11 5.5 7.4 3.7 11 1.5
C1-73
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-74
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C1-75
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
SECTION C2: Calculation Sheets for Water Hammer in the pressure mains
Pump spec.
Rated flow 6 Liter/sec/unit
Rated head 14 m
Pump output 5.5 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
2
Standard inertia 0.5 Nm
Force main dia.; 96.4 mm φ
Length of force main; 1090 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -2.7 m
Grade level of sump well; -1.6 m (LWL)
Elevation of discharge point; -0.35 m
Grade level of discharge point -0.3 m
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -1.6 LWL
1 80 0.5
2 80 1.1
3 130 0.1
4 60 0.0
5 210 0.5
6 130 1.0
7 150 0.0
8 75 0.0
9 75 0.0
10 50 -0.1
Discharge
50 -0.3
Point
C2-1
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 10.8 Liter/sec/unit
Rated head 40 m
Pump output 22 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
2
Standard inertia 3.7 Nm
Force main dia.; 96.4 mm φ
Length of force main; 684 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -5.2 m
Grade level of sump well; -4.0 m (LWL)
Elevation of discharge point; 13.7 m
Grade level of discharge point 14.2 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -4.0 LWL
1 36 -0.6
2 50 -0.3
3 86 0.1
4 58 0.2
5 135 0.0
6 30 0.2
7 100 2.0
8 28 3.7
9 45 6.0
10 44 12.2
Discharge
72 14.2 Max. level
Point
C2-2
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 31.6 Liter/sec/unit
Rated head 25 m
Pump output 22 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
Standard inertia 3.7 Nm2
Force main dia.; 197.6 mm φ
Length of force main; 355 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -3.2 m
Grade level of sump well; -2.0 m (LWL)
Elevation of discharge point; 17.9 m
Grade level of discharge point 18 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -2.0 LWL
1 25 2.0
2 93 5.3
3 32 6.7
4 15 7.0
5 15 10.0
6 15 11.0
7 15 12.0
8 15 13.0
9 15 14.0
10 15 15.0
11 15 16.0
12 15 16.6
13 30 17.0
Discharge
40 18.0 Max. level
Point
C2-3
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 80 Liter/sec/unit
Rated head 17 m
Pump output 22 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
2
Standard inertia 3.7 Nm
Force main dia.; 312 mm φ
Length of force main; 443 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -4.6 m
Grade level of sump well; -3.6 m (LWL)
Elevation of discharge point; 8.25 m
Grade level of discharge point 8.4 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -3.6 LWL
1 25 2.0
2 25 4.3
3 40 5.4
4 60 4.2
5 50 3.0
6 20 3.0
7 30 4.0
8 30 5.0
9 35 6.0
10 35 7.0
Discharge
93 8.4 Max. level
Point
C2-4
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 73.3 Liter/sec/unit
Rated head 42 m
Pump output 55 kW
Duty pump unit 2 unit
Rated speed 1500 min-1
Standard inertia 12.9 Nm2
Force main dia.; 395.6 mm φ
Length of force main; 1340 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -7 m
Grade level of sump well; -5.7 m (LWL)
Elevation of discharge point; 27 m
Grade level of discharge point 28.5 m (HWL)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -5.7 LWL
1 245 0.5
2 245 1.3
3 135 -0.1
4 100 -0.2
5 100 -0.1
6 100 -0.6
7 100 5.7
8 117 6.3
9 33 11.3
10 20 13.4
11 30 17.8
12 50 24.5
13 20 27.1
14 33 28.0
Discharge
12 28.5 HWL
Point
C2-5
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 10.8 Liter/sec/unit
Rated head 17 m
Pump output 5.5 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
Standard inertia 0.75 Nm2
Force main dia.; 150 mm φ connect to existing pipe
Length of force main; 400 m
Number of force main; 1 unit
Material of force main; DCIP (C = 80)
Elevation of pump; -1.4 m
Grade level of sump well; -0.5 m (LWL)
Elevation of discharge point; 9.25 m
Grade level of discharge point 10 m (Max. level)
C2-6
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 23.3 Liter/sec/unit
Rated head 24 m
Pump output 15 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
Standard inertia 1.5 Nm2
Force main dia.; 140.6 mm φ
Length of force main; 240 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -3.4 m
Grade level of sump well; -1.9 m (LWL)
Elevation of discharge point; 14 m
Grade level of discharge point 15.6 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -1.9 LWL
1 21 1.6
2 10 3.0
3 18 5.9
4 25 7.5
5 25 9.0
6 25 10.5
7 34 12.8
8 41 14.2
Discharge
41 15.6 Max. level
Point
C2-7
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 10 Liter/sec/unit
Rated head 24 m
Pump output 7.5 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
2
Standard inertia 1.0 Nm
Force main dia.; 96.4 mm φ
Length of force main; 640 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -4.5 m
Grade level of sump well; -3.5 m (LWL)
Elevation of discharge point; 0 m
Grade level of discharge point 2.1 m (HWL)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -2.5 LWL
1 49 0.2
2 55 0.1
3 58 0.3
4 18 0.5
5 39 0.2
6 95 1.1
7 66 0.5
8 100 1.9
9 50 2.5
10 50 1.9
Discharge
60 2.1 HWL
Point
C2-8
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 93.3 Liter/sec/unit
Rated head 11 m
Pump output 15 kW
Duty pump unit 2 unit
Rated speed 1500 min-1
Standard inertia 2.3 Nm2
Force main dia.; 395.6 mm φ
Length of force main; 700 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -3.5 m
Grade level of sump well; -2.9 m (LWL)
Elevation of discharge point; 0.4 m
Grade level of discharge point 0.6 m (HWL)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -2.9 LWL
1 50 0.5
2 100 0.6
3 110 0.6
4 87 -0.1
5 79 -0.1
6 74 -0.1
7 100 0.0
8 40 0.1
9 30 0.4
Discharge
30 0.6 HWL
Point
C2-9
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 103.3 Liter/sec/unit
Rated head 42 m
Pump output 75 kW
Duty pump unit 2 unit
Rated speed 1500 min-1
Standard inertia 23 Nm2
Force main dia.; 439.7 mm φ
Length of force main; 2750 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -6.2 m
Grade level of sump well; -4.9 m (LWL)
Elevation of discharge point; 21 m
Grade level of discharge point 23 m (HWL)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -4.9 LWL
1 10 2.5
2 185 5.2
3 115 15.7
4 137 17.1
5 63 21.1
6 183 23.5 A.V.
7 167 13.9
8 220 5.7
9 130 9.1
10 250 5.4
11 227 14.4
12 373 5.9
Discharge
700 23.0 HWL
Point
C2-10
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 43.3 Liter/sec/unit
Rated head 31 m
Pump output 37 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
2
Standard inertia 6.1 Nm
Force main dia.; 200 mm φ
Length of force main; 380 m
Number of force main; 1 unit
Material of force main; DIP (C = 80)
Elevation of pump; -4.4 m
Grade level of sump well; -3.2 m (LWL)
Elevation of discharge point; 14 m
Grade level of discharge point 15 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -3.2 LWL
1 40 0.0
2 40 1.0
3 40 2.0
4 20 2.5
5 20 3.0
6 35 5.0
7 35 7.0
8 35 9.0
9 35 12.0
10 40 13.5
Discharge
40 15.0 Max. level
point
C2-11
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 58.3 Liter/sec/unit
Rated head 33 m
Pump output 45 kW
Duty pump unit 2 unit
Rated speed 1500 min-1
Standard inertia 5.6 Nm2
Force main dia.; 351.7 mm φ
Length of force main; 1160 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -3.1 m
Grade level of sump well; -2.66 m (LWL)
Elevation of discharge point; 21 m
Grade level of discharge point 23 m (HWL)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -1.4 LWL
1 100 1.6
2 45 2.1
3 25 2.6
4 50 3.8
5 35 4.1
6 40 5.4
7 52 6.5
8 53 6.8
9 60 6.1
10 270 7.5
11 150 10.0
12 40 11.1
13 60 15.9
14 50 18.4
15 60 20.4
Discharge
70 23.0 HWL
Point
C2-12
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 6 Liter/sec/unit
Rated head 20 m
Pump output 5.5 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
Standard inertia 0.5 Nm2
Force main dia.; 96.4 mm φ
Length of force main; 230 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -1.7 m
Grade level of sump well; -1.0 m (LWL)
Elevation of discharge point; 13.4 m
Grade level of discharge point 13.5 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -1.0 LWL
1 10 0.7
2 20 1.1
3 20 1.2
4 20 1.0
5 15 2.4
6 15 2.8
7 15 3.0
8 15 3.5
9 27 6.0
10 28 8.5
11 30 13.5
Discharge
15 13.5 Max. level
Point
C2-13
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 7.5 Liter/sec/unit
Rated head 24 m
Pump output 7.5 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
Standard inertia 1.0 Nm2
Force main dia.; 96.4 mm φ
Length of force main; 230 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -2.8 m
Grade level of sump well; -2.1 m (LWL)
Elevation of discharge point; 15.2 m
Grade level of discharge point 15.3 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -2.1 LWL
1 20 3.3
2 20 3.7
3 20 4.3
4 20 4.9
5 30 6.2
6 35 7.7
7 20 9.2
8 20 10.7
9 20 12.2
10 15 14.8
Discharge
10 15.3 Max. level
Point
C2-14
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 12.5 Liter/sec/unit
Rated head 43 m
Pump output 22 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
2
Standard inertia 3.7 Nm
Force main dia.; 109.8 mm φ
Length of force main; 760 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -3.8 m
Grade level of sump well; -2.6 m (LWL)
Elevation of discharge point; 21 m
Grade level of discharge point 23 m (HWL)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -2.6 LWL
1 50 1.0
2 50 1.1
3 80 2.3
4 45 3.2
5 55 4.6
6 117 8.5
7 68 13.0
8 55 17.2
9 110 21.8
10 40 22.9
Discharge
90 23.0 HWL
Point
C2-15
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 25 Liter/sec/unit
Rated head 21 m
Pump output 11 kW
Duty pump unit 1 unit
Rated speed 1500 min-1
Standard inertia 1.3 Nm2
Force main dia.; 197.6 mm φ
Length of force main; 600 m
Number of force main; 1 unit
Material of force main; HDPE (C = 130)
Elevation of pump; -5.2 m
Grade level of sump well; -4.2 m (LWL)
Elevation of discharge point; 10 m
Grade level of discharge point 12.1 m (HWL)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 -3.8 LWL
1 10 1.5
2 30 -0.7
3 30 -0.7
4 37 -0.6
5 38 -0.5
6 33 0.2
7 32 2.0
8 55 2.0
9 50 1.7
10 100 2.3
Discharge
165 12.1 HWL in STP
Point
C2-16
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
Pump spec.
Rated flow 208.3 Liter/sec/unit
Rated head 15 m
Pump output 55 kW
Duty pump unit 1 unit
Rated speed 1500 min-1 or 1000 min-1
2
Standard inertia 25.7 Nm
Force main dia.; 624.3 mm φ
Length of force main; 260 m
Number of force main; 2 unit
Material of force main; HDPE (C = 130)
Elevation of pump; 7.4 m
Grade level of sump well; 9 m (LWL)
Elevation of discharge point; 20.6 m
Grade level of discharge point 20.8 m (Max. level)
Length of force
Center level of
Node No. main from pump Others
force main (m)
pit (m)
Pump 0 9.0 LWL
1 5 16.5
2 25 15.0
3 10 13.6
4 25 16.0
5 25 16.9
6 35 17.8
7 35 18.6
8 35 19.5
9 35 20.4
Discharge
30 20.8 Max. level
Point
C2-17
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-18
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-19
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-20
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-21
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-22
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-23
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-24
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-25
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-26
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-27
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-28
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-29
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-30
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-31
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-32
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-33
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-34
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-35
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-36
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-37
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-38
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-39
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-40
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-41
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-42
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-43
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-44
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-45
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-46
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-47
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-48
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-49
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-50
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-51
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-52
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-53
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-54
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-55
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-56
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-57
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-58
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-59
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-60
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-61
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-62
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-63
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-64
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-65
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-66
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-67
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-68
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-69
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-70
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-71
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-72
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-73
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-74
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-75
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-76
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-77
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-78
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-79
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-80
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-81
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-82
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-83
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-84
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-85
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-86
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-87
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-88
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-89
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C2-90
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-1
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-2
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-3
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-4
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-5
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-6
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-7
Detailed Design (Phase 2) on Port Moresby Sewerage System Upgrading Project Design Calculations
C3-8