Hfy 3800 0000 Civ Itp 0004 0 Itp Building Code A
Hfy 3800 0000 Civ Itp 0004 0 Itp Building Code A
HFY-CON/F&C0940-0964
1
ITP FOR BUILDINGS
2
ITP FOR BUILDINGS
CONTENT
1.Members and materials.....................................................................................................5
2.Erection..............................................................................................................................5
3.Masonry..............................................................................................................................6
4.Plaster.................................................................................................................................7
5.Door and windows.............................................................................................................8
6.Painting...............................................................................................................................9
7.Roof work............................................................................................................................9
8.Floor & tiling......................................................................................................................10
9.Ceiling................................................................................................................................11
10.Gypsum board wall.........................................................................................................13
11.Sandwich panel and fittings..........................................................................................14
12.Plumbing, drainage& sanitary fixing............................................................................15
ATTACHMENT:
3
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
DISCIPLINE:CIVIL DESCRIPTION OF WORK : BUILDINGS SITE INSPECTION & TEST PLAN HFY-3800-0000-CIV-ITP-0004
COMMENTS DEFINITION OF INSPECTION AND TEST PLAN SYMBOLS APPLICABLE TO ALL SIGNATORIES
S-CON = Sub-Contractor
CPECC = China Petroleum Engineering Construction
Corporation PMC: Project Management Consultant
“H” - HOLD: A point beyond which work shall not proceed without formal approval by the appropriate inspection.
Contractor shall notify the COMPANY / PMC and raise RFI.
“W” - WITNESS: A point beyond which work may proceed without formal documented approval by any of the inspection.
Achievement of “W” points shall be notified to PMC in accordance with the contract.
"S" - SURVEILLANCE: A point where CPECC and others may carry out surveillance of work in progress and documentation
associated on an unscheduled basis, with no notification required by any party and without
amendment to the scheduled production program.
“R” - REVIEW: The documents are to be submitted to the appropriate inspection for review by PMC. Note that where a
document is subject to CPECC/PMC approval, work shall not proceed until CPECC/PMC approval is
given.
REMARKS:
4
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Date: Prepared By: CPECC QC DEPARTMENT Approved By: CPECC QC DEPARTMENT
Item Inspection Activity and Specific Acceptance Criteria, Verifying RESPONSIBILITY
ACTIVITY
No. Check Point Area Code & Standard Document CONTRACTOR OWNER
1.Members
and 1.1 To check prefabricated Construction drawings
materials. members, accessories and Construction
erection materials as per design procedures of civil
engineering W S
drawings and manufacturer’s
recommendations.
1.2 To in detail record the Construction drawings S
W
quantities of members and Construction
materials. procedures of civil
engineering
HFY-Checklist-3-5-1
1 Construction drawings
1.3 To separately store and pile Construction W S
unqualified and defective procedures of civil
members and materials, and engineering
dispose them as per procedures.
2 Erection
Construction drawings W
2.1 To review the dimensions Construction
S
and level of building foundation procedures of civil
as per drawing. engineering
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S –Surveillance R –Review
5
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE: CIVIL DESCRIPTION OF WORK:BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Date: Prepared By: CPECC QC DEPARTMENT Approved By: CPECC QC DEPARTMENT
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
6
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK:BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
7
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
8
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK:BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
9
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
10
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
11
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
12
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
13
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
14
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
15
CPECC PROVISION OF ENGINEERING, PROCUREMENT, CONSTRUCTION, COMMISSIONING,
OPERATION AND MAINTENANCE SERVICE FOR GAS PROCESSING PLANT
SITE INSPECTION
DISCIPLINE:CIVIL DESCRIPTION OF WORK: BUILDINGS HFY-3800-0000-CIV-ITP-0004
& TEST PLAN
HFY-Checklist-3-5-6
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R –Review
16
inspection CheckList
Brick Masonry
Document # : HFY-Checklist-3-5-1
RFI # :
Dwg # : Location:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
Unloading of Bricks:
3 Yes No
Ensure that unloading of bricks shall take place by hand to avoid damages.
Results______________________
Openings: Yes No
9
Check sizes for openings of doors , windows and other services. Remarks:...........................
17
Curing: Yes No
10 All constructed masonry work to be cured for minimum three days after construction and
keep damped continuously during the curing period.
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
18
inspection CheckList
Cement Plastering
Document # : HFY-Checklist-3-5-2
Report # : PRID #: Project Name: Contractor :
RFI # :
Inspection time: Start: Finish: Inspection date:
Dwg # : Location:
Spec.Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
Availability of AFC DWGs:
1
Are AFC Drawings available at site? DWG#:..........................
Finishing:
7 Ensure plumb, rounding / chamfer of corners and evenness of surface are finished Yes No
according to drawings and thickness of plastering is as per drawings
Curing:
8 Yes No
Curing of plastered surfaces is done on time for minimum 3 days.
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
19
inspection CheckList
Doors, Windows
Document # : HFY-Checklist-3-5-3
Report # : PRID #: Project Name: Contractor :
RFI # :
Inspection time: Start: Finish: Inspection date:
Dwg #/Line# : Location/Joint #:
Spec.Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
Check Door Locks , Latches, Handles , Hinges, Weather Stripping and Door Stoppers shall Yes No
6 require approval Remarks:..........................
All opening sections to doors and windows are fitted with approved weather seals and Yes No
7 checked for water/ air tightness. Remarks:..........................
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
20
inspection CheckList
Roof Water Proofing
Document # : HFY-Checklist-3-5-4
Report # : PRID #: Project Name: Contractor :
RFI # :
Inspection time: Start: Finish: Inspection date:
Dwg #/ Line # : Location/Joint#:
Spec. Reference:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
Availability of AFC DWG: Yes No
1 Are AFC Drawings available at site?
Remarks:..........................
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
21
inspection CheckList
Painting and Decoration
Document # : HFY-Checklist-3-5-5
RFI # :
Dwg # : Location:
Inspector's Checklist
Inspector's Observation
Sr # Description of Activity (State NA if not applicable)
(Record the Data)
2 All the tiles materials are according to specifications, drawings , and tiles samples
already approved by owner/PMC.
Spec#..............................
Approval of procedure:
4 Tiles installation procedure is already approved by owner/PMC. Yes No
Remarks:...........................
Color Coding:
5 Ensure that the owner color coding specifications is followed by contractor and Yes No
PMC approved the type of painting. Remarks:...........................
No of Coats:
6 Check and confirm the required numbers of paint coats applied. Yes No
Remarks:...........................
22
Remarks:...........................
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or
applicable, other activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
23
Inspection Check List
Plumbing, Drainage, Sanitary& Concealed Work
Document # : HFY-Checklist-3-5-6
Report # : PRID #: Project Name: Contractor :
RFI # :
Inspector's Checklist
Inspector's Observation
(State NA if not
Sr # Description of Activity
applicable)
Material Inspection
1 Ensure that the matrial and fittings for plumbing, drainage and sanitary work has been
approved. Yes No
Conceal Work:
Ensure the following has been checked by discipline engineers prior to conceal:
1. Pressure Test of Water Supply System.
5 2. Pressure Test of Fire Protection Water System. Yes No
3. Installation of Fire Detectors
4. Electrical conduits, earthing & other fittings.
5. hanger rods
Note : Checklist is not all inclusive and must not relieve Contractor of its obligation to Contract requirements
(Specifications, Codes and Standards, Equipment Manufacturer's recommendations). Where relevant or applicable, other
activities can be added to the checklist.
CONTRACTOR PMC
Name
Date
Signature
24