NTPC LTD V SPML Infra LTD
NTPC LTD V SPML Infra LTD
5 Dispute resolution was provided under clause 6.1 of the General Conditions of Contract and clause 3
of Special Conditions of Contract; hereinafter ‘the Dispute Resolution Clause’; Clause 6.1 of the General
Conditions of Contract is as under:
“6. Settlement of Disputes
6.1 Adjudicator
6.1.1 If any dispute of any kind whatsoever shall arise between the Employer and the Contractor in
connection with or arising out of the Contract, including without prejudice to the generality of the
foregoing, any question regarding its existence, validity or termination, or the execution of the Facilities-
whether during the progress of the Facilities or after their completion and whether before or after the
termination, abandonment or breach of the Contract- the parties shall seek to resolve any such dispute
or difference by mutual consultation. If the parties fail to resolve such a dispute or difference by mutual
consultation, then the dispute shall be referred in writing by either party to the Adjudicator, with a copy
to the other party.”
6 (2019) 8 SCC 714.
7 (2021) 2 SCC 1. (hereinafter ‘Vidya Drolia’)
8 (2017) 9 SCC 729.
9 (2021) 9 SCC 732.
10 (2020) 4 SCC 621.
3
14. Submissions by the Parties: Shri Adarsh Tripathi, Advocate appearing with and
on behalf of the Solicitor General, for NTPC, submitted that the Settlement Agreement
dated 27.05.2020 was arrived at during the pendency of the Writ Petition before the High
Court. The allegations of coercion and economic duress were, therefore, false and
unbelievable. He also submitted that SPML never raised claims during the subsistence of
the contract, before the Completion Certificate was issued, or even before the final
payment was made. Further, the conduct of SPML, in waiting for the release of the Bank
Guarantees as per the Settlement Agreement before withdrawing the Writ Petition, and
thereafter instituting the Arbitration Petition, clearly demonstrated that the allegation of
coercion was not bona fide. Finally, he submitted that the High Court was under an
obligation to undertake a limited scrutiny to examine whether a matter is prima facie
arbitrable. For this purpose, he relied on a recent decision of this Court in Emaar India Ltd.
v. Tarun Aggarwal Projects LLP & Anr11.
15. Shri Jaideep Gupta, Advocate appearing for the Respondent, SPML, has submitted
that the legal principles governing an application under Section 11(6) of the Act are well-
settled following the decisions of this Court in Mayavati Trading (supra) and Vidya Drolia
(supra). At the pre-referral stage, the jurisdiction of the court is restricted to the
examination of whether an arbitration agreement exists between the parties. He submitted
that the decision of the High Court was unexceptionable, since the question as to whether
the Settlement Agreement was executed under undue influence or coercion could be
determined by an Arbitral Tribunal.
16. Position of Law: In the present case, we are concerned with the pre-referral
jurisdiction of the High Court under Section 11 of the Act and would like to underscore the
limited scope within which an application under Section 11(6) 12 of the Act has to be
considered.
17. The position of law with respect to the pre-referral jurisdiction, as it existed before
the advent of Section 11(6A) in the Act, was based on a well-articulated principle
formulated by this Court in National Insurance Co. Ltd. v. Boghara Polyfab (P) Ltd13. In
Boghara Polyfab, this Court held that the issue of non-arbitrability of a dispute will have to
be examined by the court in cases where accord and discharge of the contract is alleged.
Following the principle in Boghara Polyfab, this Court in Union of India & Ors. v. Master
Construction Co. 14 observed that when the validity of a discharge voucher, no-claim
certificate or a settlement agreement is in dispute, the court must prima facie examine the
“18. In our opinion, there is no rule of the absolute kind. In a case where the claimant contends that a
discharge voucher or no-claim certificate has been obtained by fraud, coercion, duress or undue
influence and the other side contests the correctness thereof, the Chief Justice/his designate must look
into this aspect to find out at least, prima facie, whether or not the dispute is bona fide and genuine.
Where the dispute raised by the claimant with regard to validity of the discharge voucher or no-claim
certificate or settlement agreement, prima facie, appears to be lacking in credibility, there may not be a
necessity to refer the dispute for arbitration at all.”
4
credibility of the allegations before referring the parties to arbitration. Yet again in New
India Assurance Co. Ltd. v. Genus Power Infrastructure Ltd.15, this Court observed that
allegations of fraud, coercion, duress or undue influence must be prima facie substantiated
through evidence by the party raising the allegations.
18. In a legislative response to these precedents, through the Arbitration and
Conciliation (Amendment) Act 2015,16 sub-section (6A) was added to Section 11 of the
Act, which reads as follows:
“(6-A) The Supreme Court or, as the case may be, the High Court, while considering any
application under subsection (4) or sub-section (5) or sub-section (6), shall, notwithstanding any
judgment, decree or order of any court, confine to the examination of the existence of an
arbitration agreement.”
(emphasis supplied)
19. Taking cognizance of the legislative change, this Court in Duro Felguera (supra),
noted that post the 2015 Amendments, the jurisdiction of the court under Section 11(6) of
the Act is limited to examining whether an arbitration agreement exists between the parties
– “nothing more, nothing less”17.
20. However, in the year 2019, in United India Insurance Co. Ltd. v. Antique Art Exports
Pvt. Ltd.18, this Court had nevertheless accepted an objection of ‘accord and satisfaction’
in opposition to an application for reference to arbitration.
21. It did not take much time for this Court to reverse the approach in Antique Art
Exports (supra). A three-judge bench in Mayavati Trading (supra) expressly overruled the
above-referred decision in Antique Art Exports, observing that:
“10. This being the position, it is clear that the law prior to the 2015 Amendment that has been
laid down by this Court, which would have included going into whether accord and satisfaction
2015 Amendments’.
17 Duro Felguera supra note 7, para 59 (concurring opinion of Kurian Joseph, J).
18 (2019) 5 SCC 362:
“21. In the instant case, prima facie no dispute subsisted after the discharge voucher being signed
by the respondent without any demur or protest and claim being finally settled with accord and
satisfaction and after 11 weeks of the settlement of claim a letter was sent on 27-7-2016 for the
first time raising a voice in the form of protest that the discharge voucher was signed under undue
influence and coercion with no supportive prima facie evidence being placed on record in absence
thereof, it must follow that the claim had been settled with accord and satisfaction leaving no
arbitral dispute subsisting under the agreement to be referred to the arbitrator for adjudication.
22. In our considered view, the High Court has committed a manifest error in passing the
impugned order and adopting a mechanical process in appointing the arbitrator without any
supportive evidence on record to prima facie substantiate that an arbitral dispute subsisted under
the agreement which needed to be referred to the arbitrator for adjudication.”
5
has taken place, has now been legislatively overruled. This being the position, it is difficult to
agree with the reasoning contained in the aforesaid judgment, as Section 11(6-A) is confined to
the examination of the existence of an arbitration agreement and is to be understood in the narrow
sense as has been laid down in the judgment in Duro Felguera, SA.”
22. The entire case law on the subject was considered by a threejudge bench of this
Court in Vidya Drolia (supra), and an overarching principle with respect to the pre-referral
jurisdiction under Section 11(6) of the Act was laid down. The relevant portion of the
judgment is as follows:
“153. Accordingly, we hold that the expression “existence of an arbitration agreement” in Section
11 of the Arbitration Act, would include aspect of validity of an arbitration agreement, albeit the
court at the referral stage would apply the prima facie test on the basis of principles set out in this
judgment. In cases of debatable and disputable facts, and good reasonable arguable case, etc.,
the court would force the parties to abide by the arbitration agreement as the Arbitral Tribunal has
primary jurisdiction and authority to decide the disputes including the question of jurisdiction and
nonarbitrability.
154. Discussion under the heading “Who Decides Arbitrability?” can be crystallised as under:
154.1. Ratio of the decision in Patel Engg. Ltd. [SBP & Co. v. Patel Engg. Ltd., (2005) 8
SCC 618] on the scope of judicial review by the court while deciding an application under Sections
8 or 11 of the Arbitration Act, post the amendments by Act 3 of 2016 (with retrospective effect
from 23-10-2015) and even post the amendments vide Act 33 of 2019 (with effect from 9-8-2019),
is no longer applicable.
154.2. Scope of judicial review and jurisdiction of the court under Sections 8 and 11 of the
Arbitration Act is identical but extremely limited and restricted. 154.3. The general rule and
principle, in view of the legislative mandate clear from Act 3 of 2016 and Act 33 of 2019, and the
principle of severability and competence-competence, is that the Arbitral Tribunal is the preferred
first authority to determine and decide all questions of non-arbitrability. The court has been
conferred power of “second look” on aspects of non-arbitrability post the award in terms of sub-
clauses (i), (ii) or (iv) of Section 34(2)(a) or sub-clause (i) of Section 34(2)(b) of the Arbitration
Act.
154.4. Rarely as a demurrer the court may interfere at Section 8 or 11 stage when it is manifestly
and ex facie certain that the arbitration agreement is non-existent, invalid or the disputes are non-
arbitrable, though the nature and facet of non-arbitrability would, to some extent, determine the
level and nature of judicial scrutiny. The restricted and limited review is to check and protect
parties from being forced to arbitrate when the matter is demonstrably “non-arbitrable” and to cut
off the deadwood. The court by default would refer the matter when contentions relating to non-
arbitrability are plainly arguable; when consideration in summary proceedings would be
insufficient and inconclusive; when facts are contested; when the party opposing arbitration
adopts delaying tactics or impairs conduct of arbitration proceedings. This is not the stage for the
court to enter into a mini trial or elaborate review so as to usurp the jurisdiction of the Arbitral
Tribunal but to affirm and uphold integrity and efficacy of arbitration as an alternative dispute
resolution mechanism.”
(emphasis supplied)
23. The limited scope of judicial scrutiny at the pre-referral stage is navigated through
the test of a ‘prima facie review’. This is explained as under:
“133. Prima facie case in the context of Section 8 is not to be confused with the merits of the case
put up by the parties which has to be established before the Arbitral Tribunal. It is restricted to the
subject-matter of the suit being prima facie arbitrable under a valid arbitration agreement. Prima
facie case means that the assertions on these aspects are bona fide. When read with the
principles of separation and competence-competence and Section 34 of the Arbitration Act, the
6
referral court without getting bogged down would compel the parties to abide unless there are
good and substantial reasons to the contrary.
134. Prima facie examination is not full review but a primary first review to weed out manifestly
and ex facie non-existent and invalid arbitration agreements and nonarbitrable disputes. The
prima facie review at the reference stage is to cut the deadwood and trim off the side branches in
straightforward cases where dismissal is barefaced and pellucid and when on the facts and law
the litigation must stop at the first stage. Only when the court is certain that no valid arbitration
agreement exists or the disputes/subject-matter are not arbitrable, the application under Section
8 would be rejected. At this stage, the court should not get lost in thickets and decide debatable
questions of facts. Referral proceedings are preliminary and summary and not a mini trial…
…
138…On the other hand, issues relating to contract formation, existence, validity and non-
arbitrability would be connected and intertwined with the issues underlying the merits of the
respective disputes/claims. They would be factual and disputed and for the Arbitral Tribunal to
decide.
139. We would not like to be too prescriptive, albeit observe that the court may for legitimate
reasons, to prevent wastage of public and private resources, can exercise judicial discretion to
conduct an intense yet summary prima facie review while remaining conscious that it is to assist
the arbitration procedure and not usurp jurisdiction of the Arbitral Tribunal. Undertaking a detailed
full review or a long-drawn review at the referral stage would obstruct and cause delay
undermining the integrity and efficacy of arbitration as a dispute resolution mechanism.
Conversely, if the court becomes too reluctant to intervene, it may undermine effectiveness of
both the arbitration and the court. There are certain cases where the prima facie examination may
require a deeper consideration. The court’s challenge is to find the right amount of and the context
when it would examine the prima facie case or exercise restraint. The legal order needs a right
balance between avoiding arbitration obstructing tactics at referral stage and protecting parties
from being forced to arbitrate when the matter is clearly non-arbitrable.
140. Accordingly, when it appears that prima facie review would be inconclusive, or on
consideration inadequate as it requires detailed examination, the matter should be left for final
determination by the Arbitral Tribunal selected by the parties by consent. The underlying rationale
being not to delay or defer and to discourage parties from using referral proceeding as a ruse to
delay and obstruct. In such cases a full review by the courts at this stage would encroach on the
jurisdiction of the Arbitral Tribunal and violate the legislative scheme allocating jurisdiction
between the courts and the Arbitral Tribunal. Centralisation of litigation with the Arbitral Tribunal
as the primary and first adjudicator is beneficent as it helps in quicker and efficient resolution of
disputes.”
(emphasis supplied)
24. Following the general rule and the principle laid down in Vidya Drolia (supra), this
Court has consistently been holding that the arbitral tribunal is the preferred first authority
to determine and decide all questions of non-arbitrability. In Pravin Electricals Pvt. Ltd. v.
Galaxy Infra and Engg. Pvt. Ltd.19, Sanjiv Prakash v. Seema Kukreja and Ors.20, and
Indian Oil Corporation Ltd. v. NCC Ltd.,21 the parties were referred to arbitration, as the
prima facie review in each of these cases on the objection of non-arbitrability was found
to be inconclusive. Following the exception to the general principle that the court may not
refer parties to arbitration when it is clear that the case is manifestly and ex facie non-
33 DLF Home Developers Limited v. Rajapura Homes Pvt. Ltd 2021 SCC OnLine SC 781, paras 18, 20.
9
…
6. In the meanwhile, the respondents are restrained from invoking the bank guarantees, subject
to the petitioner keeping the same alive.”
37. On 23.07.2019, SPML sent a Notice to NTPC, intimating its intention to invoke
Arbitration under the Dispute Resolution Clause.
38. During the pendency of the Writ Petition, the parties engaged themselves in multiple
discussions about their claims and counter-claims. All that culminated in the Settlement
Agreement dated 27.05.2020. The Terms of the Settlement Agreement are as follows:
“NOW THEREFORE, in consideration of the premises and mutual promises contained herein, the
parties agree as follows:
1. That the Agency undertakes to withdraw WP No. 7213/2019 filed in the Hon’ble High Court
upon execution of the present agreement immediately upon receipt of original Bank Guarantees
stated herein below lying with NTPC as mentioned herein below at Para 4.
2. That the Agency has agreed not to initiate any further proceedings in relation with the
present contract agreement and work executed by the Agency, of any nature whatsoever. Further,
the Agency has undertaken not to raise any claim of any nature whatsoever against the NTPC
Ltd. in relation with the present contract agreement and work executed by the Agency, be it
Arbitration proceedings, civil suit, writ petition, or any other proceedings before any judicial or
quasi-judicial forum.
3. That the Agency has confirmed it has received entire payments arising out of the present
contract and the same stands closed, and no further sum/money is payable to the Agency in any
manner whatsoever by NTPC Ltd. under the subject contract.
…
5. That NTPC Ltd. has further agreed not to raise any contempt proceedings against the Agency
for not keeping alive the BGs as directed by the Hon’ble High Court of Delhi in pending Writ
Petition.”
39. In compliance with the Settlement Agreement, NTPC released the Bank
Guarantees on 30.06.2020, which were the subject matter of the pending Writ Petition.
40. It is noteworthy that the Bank Guarantees expired on 19.11.2019 and 16.12.2019,
despite the specific direction by the High Court to SPML to keep its Bank Guarantees
alive. However, in compliance with its express undertaking in the Settlement Agreement,
NTPC did not file any contempt proceedings against SPML.
41. Following the release of the Bank Guarantees as per the Settlement Agreement,
SPML withdrew the Writ Petition, as recorded by the High Court in its Order dated
21.09.2020.
42. One month later, on 10.10.2020, SPML filed the Arbitration Petition under Section
11(6) of the Act alleging coercion and economic duress in the execution of the Settlement
Agreement. It was also alleged that the Settlement Agreement was repudiated on
22.07.2020 through SPML’s letter to NTPC, disputing the Settlement Agreement.
43. In its reply to the Arbitration Petition, NTPC specifically pointed out that SPML never
raised any claims with respect to the dues amounting to Rs. 72,01,53,899/- during the
pendency of the contract, and that the allegations of coercion and economic duress are
completely false. NTPC alleged that the Arbitration Petition lacked bona fide.
44. A simple narration of the bare facts, as indicated above, leads us to conclude that
the allegations of coercion and economic duress are not bona fide, and that there were
10
no pending claims between the parties for submission to arbitration. The Respondent’s
claim fits in the description of an attempt to initiate “ex facie meritless, frivolous and
dishonest litigation”34. We will endeavor to give reasons for our conclusion.
45. The whole dispute revolves around the solitary act of the Appellant, NTPC, in not
returning the Bank Guarantees despite the successful completion of work. This continued
even after SPML issued the No-Demand Certificate and NTPC released the final payment.
These undisputed facts led to the institution of the Writ Petition before the Delhi High
Court. There were no allegations of coercion or economic duress compelling SPML to
withdraw any pending claims under the subject contract as a condition for the return of the
Bank Guarantees. On the contrary, the only allegation by SPML was with respect to
NTPC’s “illegal” action of interlinking the release of the Bank Guarantees with some other
contracts. This was precisely the argument before the High Court, and, in fact, this
submission is recorded by the High Court while issuing notice and injuncting NTPC. This
fact clearly indicates that the plea of coercion and economic duress leading to the
Settlement Agreement is an afterthought.
46. We will now examine whether the allegations of coercion and economic duress in
the execution of the Settlement Agreement are bona fide or not. This inquiry has a direct
bearing on the arbitrability of the dispute. It was during the subsistence of the Writ Petition
and the High Court’s interim order, when SPML had complete protection of the Court, that
the parties entered into the Settlement Agreement. This agreement was comprehensive.
It inter alia provided for (i) the release of Bank Guarantees by NTPC, (ii) the withdrawal of
SPML’s Writ Petition, (iii) restraining NTPC from filing contempt proceedings against
SPML for letting the Bank Guarantees expire, and finally, (iv) restraining SPML from
initiating any proceedings under the subject contract, including arbitration. The Settlement
Agreement also recorded that there were no subsisting issues pending between the
parties.
47. The plea of coercion and economic duress must be seen in the context of the
execution of the Settlement Agreement not being disputed, and its implementation leading
to the release of the Bank Guarantees on 30.06.2020 also not being disputed. Almost
three weeks after the release of the Bank Guarantees, a letter of repudiation was issued
by SPML on 22.07.2020. This letter was issued about two months after the Settlement
Agreement was executed and in fact during the subsistence of the Writ Petition. After
reaping the benefits of the Settlement Agreement, the Writ Petition was withdrawn on
21.09.2020. It is thereafter that the present application under Section 11(6) of the Act was
filed. The sequence of events leads us to conclude that the letter of repudiation was issued
only to wriggle out of the terms of the Settlement Agreement.
48. The foregoing clarifies beyond doubt that the claims sought to be submitted to
arbitration were raised as an afterthought. Further, SPML’s allegations of coercion and
economic duress in the execution of the Settlement Agreement lack bona fide. They are
liable to be knocked down as ex facie frivolous and untenable.
49. In view of the above-referred facts, which speak for themselves, we are of the
opinion that this is a case where the High Court should have exercised the prima facie
test to screen and strike down the ex-facie meritless and dishonest litigation. These are
the kinds of cases where the High Court should exercise the restricted and limited review
to check and protect parties from being forced to arbitrate.
12