Assignment 2 2024 Semester 1 Completed
Assignment 2 2024 Semester 1 Completed
Family
First Name Gary Zhang Student ID No 23209425
Name
In order to ensure fair and honest assessment results for all students, it is a requirement that the
work that you hand in for assessment is your own work. If you are uncertain about any of these
matters, then please discuss them with your lecturer.
Plagiarism and Dishonesty are methods of cheating for the purposes of General Academic Regulations
(GAR) http://www.aut.ac.nz/calendar
Assignments will not be accepted if this section is not completed and signed.
Student’s Statement:
This assessment is entirely my own work and has not been submitted in any other course of study. I
have submitted a copy of this assessment to Turnitin, if required. In this assessment I have
acknowledged, to the best of my ability:
The information on this form is collected for the primary purpose of submitting your assignment for assessment.
Other purposes of collection include receiving your acknowledgement of plagiarism polices and attending to
administrative matters. If you choose not to complete all questions on this form, it may not be possible for the
Faculty of Design and Creative Technologies to accept your assignment.
Submission Requirements:
This is an individual assignment. The cover page must have your ID number and Name (in full)
Please use 1.5-line spacing and 12-point font (no handwritten assignment will be marked except for
drawing the AOA diagram)
Include page numbers.
Page 2 of 8
COMP507- ITPM Semester 1 2024
Table 1
Business Case for MYH
ROI 946%
Payback before Year X
1.1 What is the total budget at completion (BAC) for the project? (3 marks)
Assume that the work for the first week is completed in the project. The following information has
been provided as a result of work done so far.
Answer the following questions (1.2 – 1.6). You must show all the workings to support your answers.
1.2 Explain a likely reason for the difference between PV and AC for the first week of this project. (5
marks)
AC higher than PV means the project costing is being overrun for the first week. It might be because
the cost for the project is higher than expected, or the project team is not productive enough.
1.3 Calculate the cost variance (CV) and the cost performance index (CPI) for the first week of this
project. Is the project under or over budget? (7 marks)
1.4 Calculate the schedule variance (SV) and the schedule performance index (SPI) for the first week of
this project. Is the project ahead of or behind schedule? (7 marks)
1.5 Calculate the new estimate at completion (EAC) for this project after the completion of the first
week’s work. (4 marks)
1.6 Calculate how long it will now take to finish this project after working on the project for a week. (4
marks)
Page 4 of 8
COMP507- ITPM Semester 1 2024
Table 2
Activities Schedule for Auckland City IT Infrastructure Project
3.1 Complete the PERT estimation to show the duration of each activity. (10 marks)
A: (12+4*14+26)/6 = 15.67
B: (14+4*18+24)/6 = 18.33
C: (21+4*23+32)/6 = 24.17
D: (12+4*17+26)/6 = 17.67
E: (11+4*13+16)/6 = 13.17
F: (16+4*19+21)/6 = 18.83
G: (8+4*6+11)/6 = 7.17
H: (6+4*4+12)/6 = 5.67
I: (8+4*6+13)/6 = 7.5
J: (8+4*7+16)/6 = 8.67
K: (9+4*7+13)/6 = 8.33
L: (10+4*8+12)/6 = 9
Page 5 of 8
COMP507- ITPM Semester 1 2024
3.2 Draw the network diagram (AOA) to show the order in which all the activities will be undertaken in
this project. The diagram must be clearly labelled. (5 marks)
3.3 List all the possible paths for this project with their total durations. (4 marks)
A – C – E – I – L = 69.51 days
A – D – F – I – L = 68.67 days
A – B – G – I – L = 57.67 days
A – B – H – J – K – L = 65.67 days
3.4 Clearly identify and briefly explain the critical path for this project. (10 marks)
Critical Path is the path with longest durations. In this project, the longest durations path is A – C – E
– I – L, with 69.51 days duration.
3.5 This network is expected to be up and running within 4 months from the time the work on the
project is started. Does this opening date appear feasible? Justify with your calculations. (6 marks)
The critical path for this project takes 69.51 days to complete. If we consider 5 working days a week,
22 working days a month, we will have 88 days to complete this project, which is more than the
durations of the critical path. So it is feasible.
You are required to perform analysis to help identify the order in which the projects will be undertaken
from the available four projects.
3.1 Use the information below to create a table that must show the weighted score and priority for each
project for a software vendor environment. (10 marks)
The factors that impact the success of a project include (a) the availability of a principal engineer
(20%); (b) a development team assigned based on at least 4 senior software engineers with local
development experience (20%); (c) availability of a product manager as an on-site customer) (20%);
(d) support for the project from the sales and marketing team (20%); (e) availability of an agile
tester (10%); and (f) an established product backlog based on high-level requirements (10%).
Table 3 below provides the scores based on these factors for each project.
Table 3
Criteria for Projects 1-4
Project / Criteria a b c d e f
Project 1 65 45 45 60 55 60
Project 2 70 65 55 65 85 70
Project 3 75 70 75 75 85 50
Project 4 60 70 75 75 85 70
3.2 Explain the order in which these 4 projects should be undertaken. Justify with your calculations. (5
marks)
Project 2 and Project 4 have the same priority with a 68.5 weight score.
Page 7 of 8
COMP507- ITPM Semester 1 2024
4.4 Explain the contingency reserve for each project. Justify with your calculations. (10 marks)
Project1 contains 2 risks both with negative impact, -$60000 * 40% = -$24000 for Risk 1 EMV, and -$70000
*60% = -$42000 for Risk 2 EMV, so it needs $24000 + $42000 = $66000 for Contingency Reserve.
Project2 contains 2 positive risks and 1 negative risk. Each Estimated Impact * Each Chance of Outcome =
EMV. -$20000 + $15000 + $44000 = $39000 for Contingency Reserve.
Project3 contains 2 positive risks and 1 negative risk. Each Estimated Impact * Each Chance of Outcome =
EMV. $12000 + $18750 - $16500 = $14250 for Contingency Reserve.
Project4 contains 2 positive risks and 1 negative risk. Each Estimated Impact * Each Chance of Outcome =
EMV. $24000 + $14000 - $20000 = $18000 for Contingency Reserve.
Page 8 of 8