Risk Management
Risk Management
Institution Affiliation:
Student Name:
Assignment
2
Decision Strategy
Pay-off tables
Considering the three possibilities and two different nature states, with which
sophisticated quantity should PDC choose from? To answer this question, they will
need to have vast knowledge on the the repercussions linked to each choice option
and each natural condition. In the choice analysis, we refer to the outcome coming
from a particular combination of a choice option and a condition of nature as a
payout. A table giving payoffs considering each combination of choice options and
states that nature provides is a payback table (C.F, 2016).
3
4
Nature States
DA S1 S2
Sd1 8 7
Md2 14 5
Ld3 20 -9
First, complete the study. Next, if the study's conclusion is positive, select LD3.
Otherwise, if the conclusion is bad, choose MD2. The highest possible EMV for the
previously mentioned proposed judgment is 15.9347 million rials.
6
7
Abbreviations
The table below depicts the data as collected by Quality Sweaters company from
their mails and to mark their expectations in terms of profit or loss. In their case, the
outcome proved to be of positive to the company and it is efforts to maintain the
positive outcome.
At the rate of response of 8%, the entity expects a positive yield of $17400,
upon receiving 8000 responses from the mails sent. Goal Seek provided an
acknowledgment rate of 5.77% and an income of $0. As a result, if the
acknowledgement rate is 5.77%, the company breaks even. If the initial reaction rate
is more than 5.77%, the firm gains money.
Although the data table findings imply a loss (with no positive revenue) when
the number of responses is The corporation's future view implies a profit of $7.80 per
transaction, with a possibility for an increase in revenue if each respondent
purchases an additional two times, given that many customers are likely to renew in
the future.
9
As a result, the corporation may earn $46,800 or $3000 ($7.80) (2), which is
higher than the hypothetical scenario suggests. In this framework, unpredictability is
a factor since the model parameters are known with confidence. However, the
degree of ambiguity is what is crucial. The average size of a client order for Quality
Sweaters companyis known; however, it may fluctuate. As a result, it is more
appropriate to express the possibility that Great Embroidery will break even or that
its earnings will be a specific amount.
subject ¿(s . t)
Linear programming consists of four components: choice variables,
constraints, objective functions, and non-negativity limitations. Decision parameters
are unknown values in an optimization issue, such as a corporation's production
levels. Constraints are constraints on resources like time and expense (Chatterjee,
2022). Objective units are real-valued equations that need to be carefully optimized
for the lowest or greatest possible output. Non-negativity limitation assures that
decision elements constantly yield positive values, guaranteeing they are larger than
or identical to 0.
Using Excel open solver, the model fomulated revealed the number of tons
per item. Fuel Addictive total ton was 25 and the solvent base of 20, giving a
maximizing profit of $1600. The table below ilustrates the the model and the solver
outcome.
Model
Variables
Fuel
Addictive=f Solvent Base=s
Ton produced F&S 25 20
maximize profit =
D14*F20+E14*G20 1600
and 3 has depicted optimal usage of the of quantities available for use, while
Material Output
80
70
60
50
40
30
20
10
0
0 5 10 15 20 25 30 35 40 45
In project administration, the PERT is used to determine the time it takes to perform
a certain job or activity. It is a system that helps with the correct programming and
organization of all jobs during a project. It also helps maintain track of the entire
endeavor's progress, or lack thereof. In the 1950s, the US Navy created a Project
Evaluation Review Technique to oversee its Special Projects Office's Polaris
underwater missile program. Identifying the time it should take to complete a project
is vital, as it helps project directors decide on other elements such as the budget and
task allocation. Estimations matter how large or small an undertaking is, estimations
might be excessively positive or negative, but employing a PERT chart can help
identify accurate estimates (Team, 2024).
13
¿+4 tm+tp
6
Activity Immediate
O M P ET variance
No Predecessor
1 0.5 1 1.5 1 0.028
2 6 7 8 1 7 0.111
3 12 14 16 1 14 0.444
4 18 21 30 1 22 4.000
5 5 7 9 4 7 0.444
6 13 14 21 1 15 1.778
7 17 21 25 6 21 1.778
8 6 7 8 1 7 0.111
9 5 5 11 8,12 6 1.000
10 6 8 10 8,12 8 0.444
11 19 20 27 2,3 21 1.778
12 1 2 3 2,5,7 2 0.111
13 7 8 9 10 8 0.111
14 5 7 9 10 7 0.444
15 6 7 8 10 7 0.111
16 7 7 13 10 8 1.000
17 5 6 13 10 7 1.778
18 0.5 1 1.5 9,10,11 1 0.028
1,2,13,14,15,1
19 5 7 9 7 0.444
6
20 1 2 3 5,18,19 2 0.111
21 1.5 2 2.5 20 2 0.028
22 1 1 1 21 1 0.000
23 1 2 3 22 2 0.111
14
Network Diagram
The table below analyzes the Network diagram and critical path;
7
6
23 1 2 3 67 69 69 0
9
1 - 6 – 7 – 12 - 10 – 13 – 19 – 20 – 21 – 22 – 23 and 1 – 6 – 7 – 12 – 10 – 16 -19 –
20 – 21 – 22 – 23
Z value={68−69 }/2.22
Z=0.4505
P(Z)=0.3262
Z value={68−69 }/2.42
Z=0.4132
16
P(Z)=NORMAL DISTRIBUTION ¿
P(0 Z)=0.3397
Probability=0.1108
17
PERT
In order to better predict the duration of activity changes and provide more
effective and trustworthy project duration estimates, previous studies have used
unpredictability during network analysis. Due to the presence of several
unpredictable risk variables, variations in activity length are inevitable in building
projects. Volatility in network analysis has prompted the development of many
probabilistic approaches. Some of these approaches are PERT, PNET, and NRA
(narrowed dependability association) (Illumoka, 1987; Chapman, 1990) as well as a
Monte Carlo simulation (MCS). According to Diaz and Hadipriono (1993), PERT is
the cheapest and most positive technique, while MCS is the most cautious. ' They
employed many kinds of connections, and the assessment is based on mortality
functionals and computing time. Ranasinghe (1994) has provided an equation to
represent the unknown duration of activity and produced a measurement for
variability in project length.
The project logic as per the attached paper executed the the project table below;
Upon analysing the dataset, the project diagram is identified to have a critical path of
1 – 2 – 3 – 4 – 7 – 10 – 11 ;
This is as they are aligned to the activities and their predecessors. It is therefore
simplified for the management on areas to put more efforts in order to implement a
Methodology Implementation
This section covers a strategy for forecasting changes in activity duration and
their influence on risk factors. Risk factors may induce difference in activity duration,
and their impacts may shift from one activity to another for a project once it has been
established. Some volatility factors will have the same influence regardless of time,
such as soil and site quality and labor productivity, while others might vary over time
to time and have different figure from this activity to the other. In this scenario,
random numbers are brought in for each activity or a specified time in the project
calendar.
Several disseminations are applied to represent risk factors, as illustrated (Bekr,
1990). It is anticipated that each risk factor has an influence on variations in activity
duration. A matrix that displays the influence of the risk factors on changes in activity
duration. Each volatility factor has a clear charge to activity differences, with each
component having a 20% influence on duration differences in activity A. On any
single action, the cumulative impact of all components should be 100%.
After assigning the distribution of risk factors using historical data and
knowledge of distribution theories, the last stage is the calculation of activity
duration. To compute this, an equation is created,a randomn is any number derived
using a typical dissemination of volatility factor and variables on changes in activity
duration.
In reality, factors' influence will be studied mentally using knowledge dispensation,
which will be described later in the text.
20
With the data, we can use it to come up with the model below:
The project's delivery phase entails executing the implementation plan and
guiding and encouraging the team to ensure all parts align. The project closing stage
facilitates seamless transition and closure operations, verifying deliverables,
gathering lessons learned, and concluding administrative, financial, and contractual
needs. The aim is to complete the project effectively, and the project closing process
should be handled smoothly, ensuring everyone involved stays centered around the
overall goal. The toolkit includes several tools to administer project stages, allowing
for adaptation and flexibility throughout the project's lifespan.
21
but requires consideration due the limitations that it comes with. A nunform
distribution might over simplify the the variability of weather conditions, hence a
chance to leasd to high risk of inaccurate assessments. Therefore it is noted that the
choice of distribution directly influence, as having all weather scenarios could affect
the extreme weather events, again, sensitivity to the specified range is crucial as it
These statistical consequences tests entail some type of splitting and dividing
the parameters being tested into numerous hypothetical disseminations regarding a
corresponding segmentation of the outcome distribution, (C-rick et al. 1987). In a
sectionv of the scenarios shown here, the meddle figure of the dosage deviation is
selected as the dividing point. For a particular variable, all input data corresponding
to a dosage below the range of the median is said to belong to one randomized
sample, while input data linked to a dose over the median belongs to a second
random sample. Those two uncontrolled samples are utilized to build the falsifiable
disseminations . These falsifiable disseminations are given comparison to determine
whether they are significantly equal. In the second mathematical example, input
values are subdivided according to the large ramges Bekr, G.A.R. (1990). Because
their findings are specific to the partition point, the sensitiveness tests conducted on
subdivided information are not compared to the experiments outlined above.
Conclusion
The aim of this paper is to evaluate a strategy that anticipates changes in exercise
time and is dependent on risk factors. It is believed that such an approach may boost
project length predictions and equip practitioners with a tool for assessing many
mitigation approaches to counteract bad events and their influence on project
duration.
The procedure was outlined in the fictitious case study, and it was
encapsulated in a simulation model that was created and utilized. It was discovered
that the technique's outcomes are very helpful in accurately anticipating project
length and determining how risk variables affect project duration. It should be noted
that there are a number of limitations to using this method in the real world. For
example, distributing the risk factors' impact on changes in the activity's duration
requires a great deal of experience and judgment; identifying and demonstrating risk
factors is very subjective and subject to error; the approach depends on historical
data; and most construction companies lack precise records of the locations of their
buildings.
23
References