Estimating Process of Smaller Builders v.0
Estimating Process of Smaller Builders v.0
Martin Skitmore
Department of Surveying
University of Salford
Salford M5 4WT
John Wilcock
Department of Construction and Surveying
The Fylde College of Technology and Arts
Bispham
Blackpool
Lancashire
SMALLER BUILDERS
ABSTRACT
would normally use to price each item, their 'normal' price rate
kurtosis indicated that the item total was the main factor
INTRODUCTION
1979), it was found that only one estimator kept formal records
unrefuted.
normally use to rate each item, their 'normal' rate and their
skewness and kurtosis indicated that the item total was the main
THE SAMPLE
Size of company
industry.
Location
few multi million pound projects and many projects are within
Survey of builders
from each of nine of the firms agreed to take part in the study.
in May and June 1990 and eight of these later completed a postal
The Interviews
the work sent to them at the time of the study. The amount of
essential and the practise varied from visiting one in ten sites
million pound project, he would drive past the site on his way
obvious interest.
Item rates. When the estimators rated items in detail they did
with experience and luck. All the estimators said that the
the estimators rated only what they felt the Architect would
minimum.
The Questionnaire
detailed analysis (D); experience (E); "what the job will stand"
constants. It was also felt that the source of such rates and
From a total of 324 item ratings, 173 were made by method D, 126
experience, 4.3% were "what the job would stand", 3.4% were
of quantities, this would mean that just over one half the items
Fig 1 shows the relationship between the item total and the
D of item rating and the item total, (a) for all the items and
between the frequency of the use of method D and the item total
was (i) for all items r=0.48 (n=37 p=0.001), (ii) for Groundwork
r=0.34 (n=12 p=0.137) and (iv) for Masonry items r=0.64 (n=9
concrete items.
kurtosis.
16
kurtosis is the same for both the item rates and item total.
for each of the 36 items are shown in Table 1. The top right
the skewness and kurtosis were also correlated with each other
variation.
work.
Discussion
use methods other than the prescribed detailed rate analysis and
1
As a matter of interest, these variables were also
regressed on the transformed data standard deviations (the
results are the same for both item rate and total item values).
This produced an adjusted r2 of 0.440 (p=0.001, SE=0.173) with
only the mean item rate variable being significant (beta=-0.595)
18
between the method of item rating and item total for each of the
method across estimators and item total, was found for each work
significant.
NOT the value of the unit rate itself that is being considered
agreed that the significant amount was not a static amount but
further research.
opportunity cost.
Introduction
figure.
Data
Analysis 1
b-a
σ=
6
23
b = maximum value
a = minimum value
The data included an item for steel reinforcing that was rated
this outlier.
plotted for each estimator both with and without the outlier.
sampling process. This was done for the seven estimators for
Having pooled the data, the first test was to check the
of the data collected was such that it was not possible to test
Discussion
measure of variability.
Analysis 2
Having pooled the data, the first test was to check the
F=1.634, p=0.020 with outlier removed) but not with item totals
nature of the data collected was such that it was not possible
item size effects once the work section effects are removed.
the regression lines for each individual work section and the
Barnes' Assumption
in more detail.
of variation.
maximum rate and how much more frequently rates applied will be
estimator would insert only one rate against each item, thus
∑ qi2 S i2
Vt =
∑ q i xi
Vt = Variability of total
qi = quantity of item
xi = AA mean of item
items. This was repeated for all the estimators and the results
Conclusion
1. The relationship between the value of the unit rate and the
such items is more extensive than for low value items. This
is described from which it was found that only just over half of
the item, the item rate, the item quantity, the item total, the
that this reflected the range of accuracy with which the items
ACKNOWLEDGEMENTS
reviewers and the editors for their kind and helpful comments in
REFERENCES
Key Statistics for Urban Areas, 1981, The north cities and
Local Authority School; floor area 500m2; location within 5 miles of head
office.
Bill of Quantities prepared in accordance with SMM7.
Please look at the following extracts from the Bill of Quantities for the
above. If you were tendering for the contract, which items would you price
in detail (please mark these D), which would you price from experience
(please mark E), which items would you ignore (please mark I), and which you
would price for what the job will stand (S).
Total responses
D E I S
Item.
GROUNDWORK
Excavating and filling
22. Columns 10 m3 7 2 0 0
23. Staircases 5 m3 7 2 0 0
Formwork for in-situ concrete
MASONRY
Concrete commons in cement mortar (1:3)
─────────────────────────────────────────────────────────────────────────────────────
───────────────────
Item Lab Q cntrib mean SD mean SD COV skew1
kurtosis
(%) (%) rate total
─────────────────────────────────────────────────────────────────────────────────────
───────────────────
1 22 400 0.46 0.43 0.3424 174.00 136.9713 78.72 1.76 3.11
2 22 10 0.10 2.41 1.8285 24.09 18.2855 75.91 1.93 4.05
3 22 300 1.57 1.78 0.7227 533.25 216.8125 40.66 -0.14 -1.25
4 20 50 0.80 5.94 2.0764 296.88 103.8188 34.97 -0.44 -0.07
5 20 10 0.19 7.98 2.5859 79.84 25.8595 32.39 -0.15 -1.24
6 20 225 3.06 6.14 2.5809 1382.06 580.7065 42.02 2.13 4.39
7 20 30 0.81 10.39 6.4959 311.70 194.8766 62.52 0.75 0.81
8 72 200 1.43 2.45 1.9011 489.50 380.2146 77.67 0.73 -0.29
9 - - 0.04 25.00 46.2910 25.00 46.2910 185.16 1.44 0.00
10 - 555 10.27 7.03 1.2241 3903.73 679.3898 17.40 0.64 -0.62
11 53 100 0.76 2.40 0.9680 240.25 96.8028 40.29 0.69 0.56
12 47 60 1.32 5.24 4.2861 314.40 257.1644 81.80 2.04 4.62
13 18 60 2.25 15.22 2.2591 913.05 135.5434 14.85 0.73 1.24
14 28 400 1.07 1.02 0.4694 407.00 187.7719 46.14 0.88 0.83
15 100 400 0.46 0.38 0.2023 152.50 80.9215 53.06 -0.09 -0.41
16 17 100 9.06 58.57 5.5407 5856.86 554.0720 9.46 0.67 1.51
17 21 5 0.55 70.79 24.7654 353.94 123.8272 34.99 2.45 6.30
18 36 5 0.55 72.60 21.3184 363.02 106.5920 29.36 1.80 3.74
19 37 10 1.04 67.08 5.3446 670.79 53.4457 7.97 -0.55 1.78
20 32 80 7.91 63.90 6.2844 5112.34 502.7519 9.83 0.63 1.24
21 29 20 1.88 60.59 7.4871 1211.86 149.7423 12.36 0.82 -0.44
22 43 10 1.31 86.14 23.2135 861.44 232.1348 26.95 0.80 -0.13
23 49 5 0.65 84.61 23.5816 423.07 117.9081 27.87 1.75 2.56
24 74 200 3.10 10.13 6.2471 2025.14 1249.4169 61.70 0.74 -1.33
25 68 15 0.49 21.10 13.2154 316.48 198.2303 62.64 0.90 0.80
26 27 0 0.52 673.48 217.5849 336.74 108.7924 32.31 0.13 -0.48
27 71 400 1.11 1.79 0.7749 717.14 309.9653 43.22 1.00 -0.79
28 59 20 0.57 18.67 4.3635 373.37 87.2696 23.37 -0.80 2.42
29 41 600 35.49 38.72 7.8824 23234.57 4729.4526 20.36 1.05 0.69
30 38 50 4.58 60.24 13.1016 3011.79 655.0778 21.75 0.72 2.26
31 50 590 15.54 17.39 5.0843 10260.10 2999.7115 29.24 -0.50 -0.94
32 86 50 0.20 2.67 1.7246 133.36 86.2316 64.66 0.34 -2.32
33 82 595 1.10 1.21 0.8436 720.80 501.9608 69.64 1.99 4.38
34 67 25 0.07 1.80 0.6725 44.96 16.8117 37.39 0.04 -0.20
35 58 195 0.45 1.48 0.4260 288.32 83.0635 28.81 -0.23 2.92
36 75 10 0.03 1.75 0.8702 17.49 8.7022 49.77 1.52 3.10
─────────────────────────────────────────────────────────────────────────────────────
───────────────────
1
Significant values in bold
Table 1: Item variables
43
Kurt 1.00
Table 2: Correlations
44
Estimators
1 2 3 4 5 6 7 8
Including outlier
Crit r @ 95% conf 0.325 0.325 0.325 0.325 0.325 0.325 0.325 0.325
Crit r @ 99% conf 0.418 0.418 0.418 0.418 0.418 0.418 0.418 0.623
Excluding outlier
Crit r @ 95% conf 0.330 0.330 0.330 0.300 0.330 0.330 0.330 -
Crit r @ 99% conf 0.424 0.424 0.424 0.424 0.424 0.424 0.424 -
All
sections
Mean 0.675 0.000 -0.920 0.088 0.067 0.000
Outlier 0.365 0.000 -0.040 0.884 0.034 0.000
removed
Total 0.026 ns
Outlier 0.011 ns
removed
Work
section 1
Mean 0.829 0.000 -0.892 0.000 0.249 0.000
Total 0.045 ns
Work
section 2
Mean 0.684 0.000 -3.267 0.069 0.071 0.000
Outlier 0.399 0.000 0.320 0.173 0.014 0.000
removed
Total 0.094 0.392
Outlier 0.043 0.710
removed
Work
section 3
Mean 0.780 0.000 0.026 0.682 0.023 0.000
-6
Total 0.330 0.008 0.287 0.001 0.265(10 ) 0.008
Estimators
1 2 3 4 5 6 7 8
All items
Crit r @ 95% conf 0.325 0.325 0.325 0.325 0.325 0.325 0.325 0.497
Crit r @ 99% conf 0.418 0.418 0.418 0.418 0.418 0.418 0.418 0.418
Crit r @ 95% conf 0.330 0.330 0.330 0.330 0.330 0.330 0.330 -
Crit r @ 99% conf 0.424 0.424 0.424 0.424 0.424 0.424 0.424 -
All
sections
Mean 0.004 0.948
Outlier 0.122 0.050
removed
Total 0.087 0.158
Outlier 0.086 0.164
removed
Work
section 1
Mean 0.201 0.028 0.053 0.000 0.002 0.028
Total 0.031 0.742
Work
section 2
Mean 0.246 0.024 0.024 0.000 3.88(10-5) 0.024
-5
Outlier 0.415 0.000 0.044 0.000 3.28(10 ) 0.000
removed
Total 0.111 0.316
Outlier 0.086 0.458
removed
Work
section 3
Mean 0.172 0.177
Total 0.163 0.202
Estimators
1 2 3 4 5 6 7 8 Total % of
items
Coefficient
of variation
>0 and <2 11 7 10 7 3 25 34 1 98 36.7
>2 and <5 12 11 17 18 33 5 96 36.0
<5 and <10 10 10 8 9 1 14 52 19.5
>10 3 8 1 2 5 2 21 7.8
Total 36 36 36 36 36 36 36 15 267 100.0
Fig 1: Regression line of builders undertaking detailed analysis and item total
52
53
Fig 2: Variability of the total sum related to the number of items for contractors 1 to 8