Azhar 2011 Building Information Modeling (Bim) Trends Benefits Risks and Challenges For The Aec Industry
Azhar 2011 Building Information Modeling (Bim) Trends Benefits Risks and Challenges For The Aec Industry
ABSTRACT: Building information modeling (BIM) is one of the most promising recent
developments in the architecture, engineering, and construction (AEC) industry. With
BIM technology, an accurate virtual model of a building is digitally constructed. This
model, known as a building information model, can be used for planning, design, con-
struction, and operation of the facility. It helps architects, engineers, and constructors
visualize what is to be built in a simulated environment to identify any potential design,
construction, or operational issues. BIM represents a new paradigm within AEC, one
that encourages integration of the roles of all stakeholders on a project. In this paper,
current trends, benefits, possible risks, and future challenges of BIM for the AEC industry
are discussed. The findings of this study provide useful information for AEC industry
practitioners considering implementing BIM technology in their projects.
T
he architecture, engineering, and con- and construction activities required to realize the
struction (AEC) industry has long building (Eastman et al. 2008). After completion, this
sought techniques to decrease project model can be used for operations and maintenance
cost, increase productivity and quality, purposes. Fig. 1 depicts the typical applications of
and reduce project delivery time. BIM at different stages of the project life cycle.
Building information modeling (BIM) A building information model characterizes the
offers the potential to achieve these objectives (Azhar, geometry, spatial relationships, geographic informa-
Nadeem et al. 2008). BIM simulates the construction tion, quantities and properties of building elements,
project in a virtual environment. With BIM technol- cost estimates, material inventories, and project sched-
ogy, an accurate virtual model of a building, known as ule. The model can be used to demonstrate the entire
a building information model, is digitally constructed. building life cycle (Bazjanac 2006). As a result, quan-
When completed, the building information model tities and shared properties of materials can be readily
contains precise geometry and relevant data needed extracted. Scopes of work can be easily isolated and
to support the design, procurement, fabrication, defined. Systems, assemblies, and sequences can be
Figure 1. Different components of a building information model: MEP = mechanical, electrical, and plumbing (Courtesy of
Holder Construction Company, Atlanta, GA).
shown in a relative scale within the entire facility or themselves as adversaries (Azhar, Hein et al. 2008).
group of facilities. Construction documents such as BIM also supports the concept of integrated project de-
drawings, procurement details, submittal processes, livery, which is a novel project delivery approach to
and other specifications can be easily interrelated integrate people, systems, and business structures
(Khemlani et al. 2006). and practices into a collaborative process to reduce
BIM can be viewed as a virtual process that encom- waste and optimize efficiency through all phases of
passes all aspects, disciplines, and systems of a facility the project life cycle (Glick and Guggemos 2009).
within a single, virtual model, allowing all design
team members (owners, architects, engineers, contrac-
APPLICATIONS OF BUILDING INFORMATION
tors, subcontractors, and suppliers) to collaborate more
MODELING
accurately and efficiently than using traditional proc-
esses. As the model is being created, team members A building information model can be used for the
are constantly refining and adjusting their portions following purposes:
according to project specifications and design changes • Visualization: 3D renderings can be easily generated
to ensure the model is as accurate as possible before in house with little additional effort.
the project physically breaks ground (Carmona and • Fabrication/shop drawings: It is easy to generate
Irwin 2007). shop drawings for various building systems. For ex-
It is important to note that BIM is not just software; ample, the sheet metal ductwork shop drawings can
it is a process and software. BIM means not only using be quickly produced once the model is complete.
three-dimensional intelligent models but also making • Code reviews: Fire departments and other officials
significant changes in the workflow and project may use these models for their review of building
delivery processes (Hardin 2009). BIM represents a projects.
new paradigm within AEC, one that encourages • Cost estimating: BIM software has built-in cost
integration of the roles of all stakeholders on a project. estimating features. Material quantities are automa-
It has the potential to promote greater efficiency tically extracted and updated when any changes are
and harmony among players who, in the past, saw made in the model.
stantly and automatically checked for interferences. CURRENT AND FUTURE TRENDS
For example, this process can verify that piping does In this section, the role of BIM in the AEC industry
not intersect with steel beams, ducts, or walls. and its current and future trends are discussed based
• Forensic analysis: A building information model can on the results of two questionnaire surveys. McGraw-
be easily adapted to graphically illustrate potential Hill Construction (2008) published a comprehensive
failures, leaks, evacuation plans, and so forth. market report of BIM’s use in the AEC industry in
• Facilities management: Facilities management de- 2008 and projections for 2009 based on the findings
partments can use it for renovations, space planning, of a questionnaire survey completed by 82 architects,
and maintenance operations. 101 engineers, 80 contractors, and 39 owners (total
The key benefit of a building information model is sample size of 302) in the United States. Some of
its accurate geometrical representation of the parts of the key findings are as follows:
a building in an integrated data environment (CRC • Architects were the heaviest users of BIM—43%
Construction Innovation 2007). Other related benefits used it on more than 60% of their projects—while
are as follows: contractors were the lightest users, with nearly half
(45%) using it on less than 15% of projects and only
• Faster and more effective processes: Information is a quarter (23%) using it on more than 60% of
more easily shared and can be value-added and projects.
reused. • Eighty-two percent of BIM users believed that
• Better design: Building proposals can be rigorously BIM had a very positive impact on their company’s
analyzed, simulations performed quickly, and per- productivity.
formance benchmarked, enabling improved and • Seventy-nine percent of BIM users indicated that
innovative solutions. the use of BIM improved project outcomes, such
• Controlled whole-life costs and environmental data: as fewer requests for information (RFIs) and de-
Environmental performance is more predictable, creased field coordination problems.
and lifecycle costs are better understood. • Sixty-six percent of those surveyed believed
• Better production quality: Documentation output is use of BIM increased their chances of winning
flexible and exploits automation. projects.
• Automated assembly: Digital product data can be • Two-third of users mentioned that BIM had at
exploited in downstream processes and used for least a moderate impact on their external project
manufacturing and assembly of structural systems. practices.
• Better customer service: Proposals are better under- • Sixty-two percent of BIM users planned to use it on
stood through accurate visualization. more than 30% of their projects in 2009.
• Lifecycle data: Requirements, design, construction,
and operational information can be used in facilities The report predicted that prefabrication capabilities of
management. BIM would be widely used to reduce costs and im-
prove the quality of work put in place. As a whole,
After gathering data on 32 major projects, Stanford BIM adoption was expected to expand within firms
University’s Center for Integrated Facilities Engineer- and across the AEC industry.
ing reported the following benefits of BIM (cited in Kunz and Gilligan (2007) conducted a question-
CRC Construction Innovation 2007): naire survey to determine the value from BIM use
and factors that contribute to success. The main find-
• Up to 40% elimination of unbudgeted change, ings of their study are as follows:
• Cost estimation accuracy within 3% as compared to
traditional estimates, • The use of BIM had significantly increased across all
• Up to 80% reduction in time taken to generate a phases of design and construction during the
cost estimate, past year.
Figure 2. Building information models of the Aquarium Hilton Garden Inn Project (Courtesy of Holder Construction
Company, Atlanta, GA).
log with a record of individual images of each collision ital 3D model of the building and its various systems
per the architectural or structural discipline. The col- to help aid operation and maintenance procedures
lision cost savings values were based on estimates for down the road.
making design changes or field modifications had the In a nutshell, the Aquarium Hilton Garden Inn
collision not been detected earlier. More than 590 project realized some excellent benefits through the
clashes were detected before actual construction be- use of BIM technology and certainly exceeded the
gan. The overall cost savings based on the 590 colli- expectations of the owner and other project team
sions detected throughout the project was estimated at members. The cost benefits to the owner were signifi-
$801,565, as shown in Table 1. For calculating net cant, and the unknown costs that were avoided
cost savings, a conservative approach was adopted through collaboration, visualization, understanding,
by assuming that 75% of the identified collisions and identification of conflicts early were in addition
can be detected through conventional practices (e.g., to the reported savings. After this project, the archi-
sequential composite overlay process using light tect and GC began to use BIM technology on all major
Table 1. An Illustration of Cost and Time Savings via Building Information Modeling in the Aquarium Hilton Garden Inn Project
Collision phase Collisions Estimated cost avoidance Estimated crew hours Coordination date
100% design development conflicts 55 $124,500 n/a 30-Jun-06
Construction (MEP collisions)
Basement 41 $21,211 50 hrs 28-Mar-07
Level 1 51 $34,714 79 hrs 3-Apr-07
Level 2 49 $23,250 57 hrs 3-Apr-07
Level 3 72 $40,187 86 hrs 12-Apr-07
Level 4 28 $35,276 68 hrs 14-May-07
Level 5 42 $43,351 88 hrs 29-May-07
Level 6 70 $57,735 112 hrs 19-Jun-07
Level 7 83 $78,898 162 hrs 12-Apr-07
Level 8 29 $37,397 74 hrs 3-Jul-07
Level 9 30 $37,397 74 hrs 3-Jul-07
Level 10 31 $33,546 67 hrs 5-Jul-07
Level 11 30 $45,144 75 hrs 5-Jul-07
Level 12 28 $36,589 72 hrs 5-Jul-07
Level 13 34 $38,557 77 hrs 13-Jul-07
Level 14 1 $484 1 hrs 13-Jul-07
Level 15 1 $484 1 hrs 13-Jul-07
Subtotal construction labor 590 $564,220 1,143 hrs
20% MEP material value $112,844
Subtotal cost avoidance $801,565
Deduct 75% assumed resolved via conventional methods ($601,173)
Net adjusted direct cost avoidance $200,392
Source: Holder Construction Company, Atlanta, GA.
Note. MEP = mechanical, electrical, and plumbing.
planning phase to perform options analysis (value all the virtual models to decide the best option that fit
analysis) for selecting the most economical and work- his requirements. Several collaborative 3D viewing
able building layout. The project details are as follows: sessions were arranged for this purpose. These collabo-
• Project: Higher education facility, Savannah State rative viewing sessions also improved communications
University, Savannah, Georgia and trust between stakeholders and enabled rapid
• Cost: $12 million decision making early in the process. The entire pro-
• Delivery method: CM at-risk, guaranteed maxi- cess took 2 weeks, and the owner achieved roughly
mum price $1,995,000 cost savings at the predesign stage by se-
• BIM scope: Planning, value analysis lecting the most economical design option. Although
• BIM cost to project: $5,000 it could be argued that the owner may have reached
• Cost benefit: $1,995,000 the same conclusion using traditional drawings, the
Figure 3. Scope and budget options for the Savannah State Academic Building: GSF = gross square foot; sf = square foot
(Courtesy of Holder Construction Company, Atlanta, GA).
Figure 4. Use of BIM in the Mansion on Peachtree Project (Courtesy of Holder Construction Company, Atlanta, GA).
The McGraw-Hill Construction (2008) survey of level or above. It also found that the initial system cost
AEC industry participants indicated that 48% of did not seem to be a problem. Doubling the system
respondents were tracking BIM ROI at a moderate cost could reduce ROI only by up to 20% (Autodesk
Figure 5. Use of BIM for options analysis and sun studies in the Emory Psychology Building (Courtesy of Holder
Construction Company, Atlanta, GA).
2007). For this study, detailed cost data from 10 proj- projects. In some projects, BIM savings were measured
ects were acquired from HCC to perform the BIM ROI using “real” construction phase “direct” collision de-
analysis. The results are shown in Table 2. tection cost avoidance, and in other projects, savings
As evident from Table 2, the BIM ROI for different were computed using “planning” or “value analysis”
projects varied from 140% to 39,900%. On average, it phase cost avoidance. Also, none of these cost figures
was 1,633% for all projects and 634% for projects account for indirect, design, construction, or owner
without a planning or value analysis phase. Because administrative or other “second wave” cost savings
of the large data spread, it is hard to conclude a specific that were realized as a result of BIM implementation.
range for BIM ROI. The probable reason for this Hence, the actual BIM ROI can be far greater than
spread is the varying scope of BIM in different reported here.
if the owner is paying for the design, then the owner with others such as the engineers (Rosenberg 2007).
may feel entitled to own it, but if team members As the dimensions of cost and schedule are layered
are providing proprietary information for use on the onto the building information model, responsibility
project, their proprietary information needs to be pro- for the proper technological interface among various
tected as well. Thus, there is no simple answer to the programs becomes an issue. Many sophisticated
question of data ownership; it requires a unique re- contracting teams require subcontractors to submit
sponse for every project depending on the participants’ detailed critical path method schedules and cost
needs. The goal is to avoid inhibitions or disincentives breakdowns itemized by line items of work prior to
that discourage participants from fully realizing the the start of the project. The general contractor then
model’s potential (Thompson 2001). To prevent dis- compiles the data, creating a master schedule and cost
agreement over copyright issues, the best solution is breakdown for the entire project. When the subcon-
to set forth in the contract documents ownership rights tractors and prime contractor use the same software,
the integration can be fluid. In cases where the data
and responsibilities (Rosenberg 2007).
are incomplete or are submitted in a variety of sched-
When project team members other than the owner
uling and costing programs, a team member—usually
and architect/engineer contribute data that are inte-
a general contractor or construction manager—must
grated into the building information model, licensing
re-enter and update a master scheduling and costing
issues can arise. For example, equipment and material
program. That program may be a BIM module or an-
vendors offer designs associated with their products for
other program that is integrated with the building in-
the convenience of the lead designer in hopes of induc- formation model. At present, most of these project
ing the designer to specify the vendor’s equipment. management tools have been developed in isolation.
While this practice might be good for business, licens- Responsibility for the accuracy and coordination of
ing issues can arise if the designs were not produced by cost and scheduling data must be contractually
a designer licensed in the location of the project addressed (Thompson and Miner 2007).
(Thompson and Miner 2007). One of the most effective ways to deal with these
Another contractual issue to address is who will con- risks is to have collaborative, integrated project deliv-
trol the entry of data into the model and be responsible ery contracts in which the risks of using BIM are shared
for any inaccuracies. Taking responsibility for updat- among the project participants along with the rewards.
ing building information model data and ensuring its Recently, the American Institute of Architects released
accuracy entails a great deal of risk. Requests for com- an exhibit on BIM to help project participants define
plicated indemnities by BIM users and the offer of lim- their BIM development plan for integrated project de-
ited warranties and disclaimers of liability by designers livery (Building Design and Construction 2008). This
are essential negotiation points that need to be resolved exhibit may assist project participants in defining
before BIM technology is used. It also requires more model management arrangements, as well as author-
time spent inputting and reviewing BIM data, which ship, ownership, and level-of-development require-
is a new cost in the design and project administration ments, at various project phases.
process. Although these new costs may be dramatically
offset by efficiency and schedule gains, they are still a
cost that someone on the project team will incur. Thus, BIM FUTURE CHALLENGES
before BIM technology can be fully used, not only must The productivity and economic benefits of BIM to
the risks of its use be identified and allocated, but the the AEC industry are widely acknowledged and
cost of its implementation must be paid for as well increasingly well understood. Further, the technology
(Thompson and Miner 2007). to implement BIM is readily available and rapidly ma-
The integrated concept of BIM blurs the level of turing. Yet BIM adoption has been much slower than
responsibility so much that risk and liability are likely anticipated (Azhar, Hein et al. 2008). There are two
to be enhanced. Consider the scenario in which the main reasons, technical and managerial.
computable, and
challenge for owners.
3. The need for well-developed practical strategies
for the purposeful exchange and integration of
meaningful information among the building
information model components. CONCLUSIONS
The management issues cluster around the imple- Building information modeling is emerging as an in-
mentation and use of BIM. Right now, there is no novative way to virtually design and manage projects.
Predictability of building performance and operation
clear consensus on how to implement or use BIM.
is greatly improved by adopting BIM. As the use of
Unlike many other construction practices, there is no
BIM accelerates, collaboration within project teams
single BIM document providing instruction on its
should increase, which will lead to improved profit-
application and use (Associated General Contractors
ability, reduced costs, better time management, and
of America 2005). Furthermore, little progress has
improved customer–client relationships. As shown
been made in establishing model BIM contract docu- in this paper, average BIM ROI for projects under
ments (Post 2009). Several software firms are cashing study was 634%, which clearly depicts its potential
in on the “buzz” of BIM and have programs to address economic benefits. At the same time, teams imple-
certain quantitative aspects of it, but they do not treat menting BIM should be very careful about the legal
the process as a whole. There is a need to standardize pitfalls, which include data ownership and associated
the BIM process and to define guidelines for its im- proprietary issues and risk sharing. Such issues must
plementation. Another contentious issue among the be addressed up front in the contract documents.
AEC industry stakeholders (i.e., owners, designers, BIM represents a new paradigm within AEC, one
and constructors) is who should develop and operate that encourages integration of the roles of all stake-
the building information models and how the devel- holders on a project. This integration has the potential
opmental and operational costs should be distributed. to bring about greater efficiency and harmony among
To optimize BIM performance, either companies or players who all too often in the past saw themselves as
vendors, or both, will have to find a way to lessen the adversaries. As in most paradigm shifts, there will
learning curve of BIM trainees. Software vendors have undoubtedly be risks. Perhaps one of the greatest risks
a larger hurdle of producing a quality product that is the potential elimination of an important check and
customers will find reliable and manageable and that balance mechanism inherent in the current paradigm.
will meet the expectations set by the advertisements. An adversarial stance often brings a more critical
Additionally, the industry will have to develop review of the project in a kind of mutual guarding of
acceptable processes and policies that promote BIM each participant’s own interests. In the early stages of
use and govern today’s issues of ownership and risk BIM, constructors worked from architectural plans
management (Post 2009). since digital models were not shared by architects with
Researchers and practitioners have to develop suit- contractors. The construction modelers inevitably
able solutions to overcome these challenges and other discovered errors and inconsistencies in the plans as
associated risks. As a number of researchers, practi- they created the building information models.
tioners, software vendors, and professional organiza- This brought about a natural redundancy as the con-
tions are working hard to resolve these challenges, struction model put the design to this virtual building
it is expected that the use of BIM will continue to test. With a more trustful sharing of architectural
increase in the AEC industry. drawings, which can easily be imported and serve
In the past, facilities managers have been included as the basis for the building information model, there
in the building planning process in a very limited may be a loss of this critical checking phase. In other
way, implementing maintenance strategies based on words, when all players see themselves as being on the
the as-built condition at the time the owner takes same team, they may cease to look for and find mis-
possession. In the future, BIM modeling may allow takes in each other’s work. In the past, a lack of critical