90.1 Building Envelope
90.1 Building Envelope
Overview
DESIGN CONSIDERATIONS The building envelope is important to building energy efficiency. When it is cold
outside, heat loss and air leakage through the building envelope add to the heating
load. On hot days, solar gains through windows contribute to the air-conditioning
load. The building envelope requirements are intended to reduce heat gains and
losses through the building envelope while encouraging daylighting.
Finding the right amount and type of fenestration and optimizing levels of insula-
tion is a complicated process that depends on climate, schedules of operation, internal
gains, and other factors. The code sets minimum levels of thermal performance for
all components of the building envelope and limits fenestration solar gain. While
these limits assure a minimum level of performance, they do not necessarily result in
an optimum design. The designer is encouraged to use the 90.1 Code as a starting
point; minimum compliance may not be the optimum solution.
The building envelope requirements apply only to buildings or portions of buildings
SCOPE that are heated and/or cooled for human comfort. For example, the 90.1 Code does
not apply to refrigerated warehouses that are cooled for purposes other than human
comfort. A building is considered heated for human comfort if a heating system is
installed that is capable of maintaining a temperature of 50°F or more at design condi-
tions or if the output of the heating system exceeds 10 Btu/h-ft2.
Since the requirements do not apply to buildings that are neither heated nor
cooled, shell buildings present a special problem. Shell buildings are built before it is
known how they will be used or even if they will be heated or cooled. While building
officials have discretion in dealing with shell buildings, a common approach is to
postpone compliance until a permit application is filed for a heating and/or cooling
system. At that time, the permit applicant documents compliance with the building
envelope requirements as well as the HVAC requirements. It may be necessary to
upgrade the building envelope for those areas that are heated or cooled, e.g. install
additional insulation. In colder climates, however, some building officials may want
to assume that heating will always be installed for freeze protection and therefore
require a minimum level of insulation during the initial construction of shell build-
ings. This most often applies to ceiling insulation based on the rationale that it is
more costly to add insulation after the roof is finished.
Even with shell buildings, the designer should consider the requirements of the
90.1 Code to avoid problems at the time of future tenant improvements. It would be
good professional practice to assume that the entire building will be heated and/or
cooled and to establish a plan for upgrading the building envelope in the event that it
CALCULATIONS AND This section of the 90.1 Code references acceptable methods and procedures for cal-
SUPPORTING INFORMATION culating the U-factor of building envelope components. Since this section of the code
(402.1) does not contain design requirements per se, it is not included on the Summary form.
Skylight U-factor
The U-factor of exempted skylights, including the frame, shall be no greater than 0.45
in climates with more than 8,000 HDD65 and no greater than 0.70 for other climates.
Skylight U-factors shall be determined in the same manner as vertical fenestration.
The Reference section of this chapter has default tables for skylight U-factors. The
U-factor requirement must be satisfied, even if the skylight area is significantly less
than the maximum allowed. However, some of the exempt skylights may have a
higher U-factor as long as others have a lower U-factor such that the area-weighted
average is less than the criteria.
Air Leakage
Air leakage through the skylight must be less than 0.05 cfm/ft2 of skylight area.
Q The designer of a one-story, 50,000 ft2 warehouse in Richmond, Virginia wants to use
skylights for daylighting. The skylights have a visible light transmission (VLT) of
0.66. The electric lighting will be automatically controlled by photocells. The light-
ing power density for the warehouse is 0.50 W/ft2 and the design lighting level is 30
footcandles. What is the maximum skylight area that may be exempt?
A Table 402.3.1(B) for Richmond permits 2.3% skylight area for skylight glazing mate-
rials with a visible light transmission (VLT) greater than or equal to 0.75 and 3.6%
for glazing materials with a VLT less than or equal to 0.50. Interpolation is permitted
between these values so the maximum exempt skylight area for this building can be
calculated as shown below.
For the 50,000 ft2 building, a total of 1,400 ft2 (2.8 × 50000 / 100) of skylight area
may be exempt, provided the other criteria are satisfied. About forty-three 4 ft × 8 ft
skylights would be permitted or one for each 1,156 ft2.
Q A 100,000 ft2 distribution center located in Boise, Idaho is designed with a total sky-
light area of 8,000 ft2. The skylights have a visible light transmission (VLT) of 0.50.
The electric lighting will be automatically controlled. The lighting power density for
the warehouse is 1.10 W/ft2 and the design lighting level is 45 footcandles. What is
the maximum skylight area that may be exempt?
A Using Table 402.3.1(B) for Boise with the lighting power of 1.10 W/ft2, the design
lighting level is 45 footcandles (use 50 fc which is closest), and the visible light
transmission (VLT) of 0.50, a maximum skylight area representing 6% of the roof
may be exempt. For the 100,000 ft2 building, a total skylight area of 6,000 ft2 may be
exempt. There is a 2,000 ft2 difference between the skylight area in the design and
what can be exempt. If the designer wants all the skylight area to be exempt, either
the skylight area must be reduced or the additional 2,000 ft2 can be included in the
weighted average thermal transmission of the opaque roof. Another option would be
to provide some means of shading the skylights during the peak cooling load so that
the exempted skylight area can be increased by 50% (to 9,000 ft2).
The overall roof criteria for Boise is 0.051. If the U-factor of the skylights is
0.60, then the U-factor of the opaque portion of the roof would have to be 0.039 or
less, as shown below.
0.60 × 2,000 + U × 92,000
0.051 =
94,000
U = 0.039
Note that the total roof area in the weighted average calculation is 94,000 ft2 (the total
of 100,000 ft2 less the 6,000 ft2 that can be exempt).
Prescriptive Criteria
Table 402.4.1.1 contains the prescriptive criteria for walls, including opaque doors.
Table 402.4.1.2 contains the prescriptive criteria for windows.
The window criteria and the mass wall criteria depend on the ILD range. ILD
stands for internal load density and represents the watts/ft2 of heat produced from
lights and equipment. You do not need to calculate ILD when you use the prescrip-
tive tables. The first ILD range, up to 1.50 W/ft2, is used for warehouses, residential
spaces, and hotel/motel guest rooms. The last range, more than 3.00 W/ft2, is used
for small retail spaces less than 2,000 ft2 and for technical and vocational schools less
than 10,000 ft2. The middle range applies to all other building types.
Opaque Walls
Form Table 402.4.1.1 gives the criteria for exterior walls, including opaque doors. Separate
402.4 criteria apply to windows (see below) and walls next to unconditioned space (see
above). The procedure for using Table 402.4.1.1 is illustrated in Figure 402M and
described below.
1. The first step is to calculate the area-weighted average U-factor of all exterior
walls. Exterior wall area is defined on Figure 402C and in the associated text.
The Reference section of this chapter contains default U-factors, and explains ac-
ceptable calculation procedures to use with your construction assembly is not
contained in the default tables. Most buildings have more than one type of wall
construction. In these cases, the U-factor of some walls can be greater than the
requirement as long as others are less than the requirement. It is necessary, how-
ever, to calculate an area-weighted average U-factor and show that this number is
less than the requirement. Example 402F illustrates how this is done.
2. Compare the area-weighted U-factor to the criteria for light-weight walls in the
first row of Table 402.4.1.1. The criteria for light weight walls (HC <= 4.9) is
the easiest to use since it does not depend on the ILD range, the position of the
insulation, or the WWR (window-wall ratio). Separate values are provided in the
two columns for insulation position, but the two numbers are the same for all lo-
cations. The lightweight wall criteria may be used for any type of wall construc-
tion, even mass walls. If the proposed U-factor is less than the criteria for light
weight walls, you can stop, even if some of the walls you included in your area-
weighted average were mass walls.
3. If the building does not comply with the light weight wall criteria and some of the
walls in your area-weighted average are mass walls then you can determine the
criteria for mass walls, which will be a little less stringent. The first step is to de-
Q An architect is designing a small retail store in Abilene, Texas. She wishes to use a
partially grouted, 12-inch concrete block wall construction. The design parameters
are as follows: 19% WWR; heat capacity of the mass is 15.1 Btu/ft2-°F; and the de-
sign features CMU with filled cores (integral insulation). What is the maximum Uow
allowed for a concrete block wall in this project?
A The default internal load density range for a small retail store is 3.01-3.50. At this
ILD range for integral insulation in a wall with an HC of 15.1 Btu/ft2-°F, the maxi-
mum Uow varies from 0.306 Btu/h-ft2-°F at 13% WWR to 0.284 Btu/h-ft2-°F at 68%
WWR. For the 19% WWR of this project the maximum allowable Uow is 0.31 Btu/h-
ft2-°F from interpolation as follows:
{
5.0 - 9.9 0.200 0.272
20 10.0 - 14.9 0.284 0.382
0.00 to 1.50 15.0 0.386 0.420
5.0 - 9.9 0.197 0.272
73 10.0 - 14.9 0.267 0.371
15.0 0.360 0.398
{
5.0 - 9.9 0.204 0.272
15 10.0 - 14.9 0.304 0.404
1.51 to 3.00 15.0 0.408 0.447
5.0 - 9.9 0.199 0.272
74 10.0 - 14.9 0.281 0.381
15.0 0.385 0.419
{
5.0 - 9.9 0.205 0.272
13 10.0 - 14.9 0.306 0.406
3.01 to 3.50 15.0 0.410 0.450
5.0 - 9.9 0.199 0.272
71 10.0 - 14.9 0.282 0.383
15.0 0.387 0.422
{
0.71 - 0.61 19 23 23 20 25 26
0.00 - 0.60 - 0.51 21 26 27 23 28 30
0.25 0.50 - 0.39 24 30 32 25 33 35
0.38 - 0.26 28 38 40 28 40 43
0.25 - 0.00 33 49 54 33 52 58
1.00 - 0.72 22 27 28 23 29 31
0.00 - 0.26 - 0.71 - 0.61 25 32 33 26 34 36
1.50 0.50 0.60 - 0.51 27 36 38 28 38 42
0.50 - 0.39 29 41 44 30 44 48
0.38 - 0.00 33 49 54 33 51 58
1.00 - 0.72 26 34 36 27 37 40
0.50 + 0.71 - 0.61 29 40 42 30 42 46
0.60 - 0.51 31 45 48 32 47 52
0.50 - 0.00 33 50 55 34 52 59
1.00 - 0.72 14 15 16 18 21 22
{
0.71 - 0.61 16 19 19 21 25 27
0.00 - 0.60 - 0.51 19 22 22 23 28 31
0.25 0.50 - 0.39 21 25 26 25 33 37
0.38 - 0.26 25 32 33 29 40 46
0.25 - 0.00 31 44 47 35 53 61
1.00 - 0.72 19 22 22 23 29 32
1.51 - 0.26 - 0.71 - 0.61 22 26 27 26 34 38
3.00 0.50 0.60 - 0.51 24 30 31 28 39 43
0.50 - 0.39 27 35 36 31 44 50
0.38 - 0.00 31 42 45 34 52 61
1.00 - 0.72 23 28 29 27 37 41
0.50 + 0.71 - 0.61 26 33 35 30 42 48
0.60 - 0.51 28 38 40 32 47 55
0.50 - 0.00 31 43 46 35 53 62
1.00 - 0.72 12 13 13 17 19 21
{
0.71 - 0.61 14 16 16 19 23 26
0.00 - 0.60 - 0.51 16 19 19 22 27 30
0.25 0.50 - 0.39 19 22 23 24 31 35
0.38 - 0.26 22 28 29 28 38 44
0.25 - 0.00 28 38 41 33 50 59
1.00 - 0.72 16 19 19 22 27 31
3.01 - 0.26 - 0.71 - 0.61 19 22 23 25 32 36
3.50 0.50 0.60 - 0.51 21 26 27 27 36 42
0.50 - 0.39 24 30 31 29 41 48
0.38 - 0.00 28 37 39 33 49 59
1.00 - 0.72 20 24 25 26 34 39
0.50 + 0.71 - 0.61 23 28 30 29 40 46
0.60 - 0.51 25 33 34 31 45 53
0.50 - 0.00 28 38 40 33 50 60
Q An office building is planned for Savannah, Georgia near the historic district. The
proposed fenestration area is 39% of the gross exterior wall area. The owner is will-
ing to use double (1/2-inch airspace), tinted glazing, but reflective glass is not an ac-
ceptable alternative due to incompatibility with the character of nearby historic build-
ings.
A (a) The internal load density range for the office is 1.51-3.00. (b) The building has
no overhangs, therefore the PF range is 0.000-0.249. (c) The shading coefficient for
the glass from the manufacturer's specifications sheet is 0.48, therefore the SCx range
is 0.50-0.39. (d) The building has no daylighting controls so the base case is se-
lected. (e) The default fenestration U-factor for double-glazing with a 1/2-inch air-
space is 0.61, therefore the Uof range is 0.81 to 0.
The maximum allowable fenestration area is 26%, so modifications are neces-
sary. Under the base case, no daylighting, assumption, either a very large PF or a
very low SCx would be necessary for the 39% fenestration area to comply. If one
looks at the perimeter daylighting option, however, it would qualify provided that the
visible light transmittance is greater than the SC. The automatic daylighting controls
will end up reducing the electric load from both the lighting and the cooling equip-
ment during the late afternoon summer peak demand period. The result is that the
project complies and both energy consumption and energy demand are lower.
TABLE 402.4.1.2 MAXIMUM WALL RATIO (WWR)
Fenestration U-Factor (Uof)
Internal Projection Shading Base Case Perimeter Daylighting
Load Factor Coefficient VLT>=SC
Density (PF) (SCx) 1.15 0.81 1.15 0.81 0.81
(ILD) Range Range to to N/A to to to
Range 0.82 0 0.82 0 0
1.00 - 0.72 19 19 22 22 22
0.71 - 0.61 24 23 26 27 27
0.00 - 0.60 - 0.51 28 26 31 32 32
0.25 0.50 - 0.39 33 30 36 38 39
0.38 - 0.26 42 38 47 50 51
0.25 - 0.00 61 49 67 73 75
1.00 - 0.72 27 28 30 31 32
0.00 - 0.26 - 0.71 - 0.61 33 34 37 38 39
1.50 0.50 0.60 - 0.51 39 40 43 45 46
0.50 - 0.39 46 48 50 54 55
0.38 - 0.00 58 63 63 69 71
1.00 - 0.72 35 37 39 41 42
0.50 + 0.71 - 0.61 43 45 47 50 51
0.60 - 0.51 50 53 55 59 60
0.50 - 0.00 58 63 64 70 71
1.00 - 0.72 15 15 21 21 23
0.71 - 0.61 18 18 26 26 28
0.00 - 0.60 - 0.51 21 22 30 31 33
0.25 0.50 - 0.39 26 26 36 38 40
0.38 - 0.26 33 34 47 49 52
0.25 - 0.00 49 52 67 72 77
1.00 - 0.72 21 21 30 31 33
1.51 - 0.26 - 0.71 - 0.61 26 26 36 39 40
3.00 0.50 0.60 - 0.51 30 31 43 44 47
0.50 - 0.39 36 37 50 53 56
0.38 - 0.00 46 49 64 69 73
1.00 - 0.72 27 28 39 40 43
0.50 + 0.71 - 0.61 33 34 47 50 53
0.60 - 0.51 39 41 55 59 62
0.50 - 0.00 46 49 64 69 73
1.00 - 0.72 12 12 20 20 22
0.71 - 0.61 15 15 24 25 27
0.00 - 0.60 - 0.51 18 18 28 29 32
0.25 0.50 - 0.39 21 22 34 35 38
0.38 - 0.26 28 29 44 46 50
0.25 - 0.00 42 44 63 68 74
1.00 - 0.72 17 17 28 29 31
3.01 - 0.26 - 0.71 - 0.61 21 22 34 35 38
3.50 0.50 0.60 - 0.51 25 26 40 41 45
0.50 - 0.39 30 31 47 50 54
0.38 - 0.00 39 41 60 65 70
1.00 - 0.72 23 23 36 38 41
0.50 + 0.71 - 0.61 28 28 44 46 50
0.60 - 0.51 33 34 51 55 60
0.50 - 0.00 39 40 60 65 70
CITY: 198
N NE
Seattle/Tacoma WA BUILDING: 345 Sunrise Ave BASELINE
CODE <B,C,H>: Both Heated and Cooled
WALL ORIENTATION
E SE S
DATE: 14 March 1992
SW W
WEIGHTED
NW AVERAGE CRITERIA
------- -------------------------------------------------------- -------
}
}
WL AREA| 6750 3000 6750 3000 | 0.10 | 0.300
GL AREA| 400 0.0 400 1200 | WWR | WWR
SCx | .49 0.0 .49 .49 | 0.41 | 0.719
PF | 0.0 0.0 0.0 0.0 | 0.00 | 0.0
VLT | 0.0 0.0 0.0 0.0 | 0.00 | N/A
Uof | .58 0.0 .58 .58 | 0.49 | 0.619
WALL Uo| .08 .08 .089 .08 | 0.08 | 0.096
HC | 9.6 9.6 9.6 9.6 | 9.60 | 1
INS POS| 3 3 3 3 | 3 | N/A
EQUIP | .14 .14 .14 .14 | 0.14 | 0.140
LIGHTS | .89 .89 .89 .89 | 0.89 | 0.890
DLCF | 0.0 0.0 0.0 0.0 | 0.00 | 0.0
------- ---------------------- L O A D S ---------------------- -TOTAL- -------
HEATING| 5.199
COOLING| 0.761
TOTAL | 5.961
2.202
0.059
2.261
4.750
1.282
6.032
2.585
2.543
5.128
| 14.736> 14.485
| 4.645< 15.999
| 19.381< 30.484
===============================================================================
}
F1 Load | F3 Clear Input | F5 Other Screen | F7 Help
F2 Save | F4 Directory | F6 List Cities
********** PASSES
| F10 Copy Across
| F9 Calculate | Esc Exit to DOS
********** }
EQUIP Calculate the area-weighted average for both the retail and the warehouse. A
value of 0.15 W/ft2 is calculated based on information on the plans.
LIGHTS Calculate the area-weighted average for both the retail and the warehouse.
A value of 0.90 W/ft2 is calculated based on information on the plans.
SUMMARY FORMS AND One summary form and two worksheets are provided to assist with the calculations
WORKSHEETS and documentation necessary in showing compliance with the envelope requirements
of the 90.1 Code. Blank copies of these forms are included in Appendix D of this
manual. The Case Study section of this chapter provides examples of completed
forms. A general description of the forms is provided below.
Roof/Floor Worksheet
This worksheet is used to calculate the area-weighted average U-factor for: the pro-
posed gross roof area (including non-exempt skylights); gross wall adjacent to uncon-
ditioned space area (including doors in this wall); and, gross floor over unconditioned
PERMIT APPLICANT'S At permit application, the goal of the applicant is to provide all the necessary infor-
RESPONSIBILITIES mation to show compliance with the 90.1 Code. If the plans examiner is able to ver-
ify compliance with one review, then the permit can be issued and construction started
without delay. To assist in submitting the permit application, the applicant should
review not only the following information specific to the applicant but also the subse-
quent two sections that review responsibilities of the plans examiner and the inspec-
tor. The following section addresses the two common problems with permit applica-
tions: (1) missing information, or (2) incorrect information.
Information may be missing because the applicant is not aware of all of the code
requirements or because the required information is located on the specifications but
not on the plans. Note that building departments generally approve plans, but not
specifications. The Checklist on the back of the Envelope Summary Form provides a
The following case study demonstrates the recommended procedure for documenting
compliance with the envelope requirements (Section 402 of the 90.1 Code). Re-
quirements that must be documented include: air leakage and moisture migration, the
thermal performance of all opaque surfaces, and fenestration (including skylights).
This case study includes a completed summary form, a roof/floor worksheet, and
an exterior wall worksheet. Two compliance paths are demonstrated for the case
study: the prescriptive method and the system performance method. In practice only
one of these paths needs to be followed to show compliance with the 90.1 Code.
The following drawings for the case study are included in Appendix B.
• Floor plan (page B-1): Shows the general layout of the building. Used to deter-
mine wall, roof, skylight, and window areas. This drawing is referred to as “A2”
on the summary form.
• Building elevations (Page B-2): Show each facade of the building. Used to de-
termine wall and window area, and projection factor. These drawings are re-
ferred to as “A5” on the summary form.
• Building sections (Page B-3): Show cross sections of the building at various
locations. Used to determine projection factor, roof area, and wall area. These
drawings are referred to as “A6” on the summary form.
The following drawings are not included in the appendix; however, they are referred
to on the completed summary form. These drawings would be included in a complete
set of building plans submitted to a building department for approval.
• Wall/floor/roof sections: Show the construction assembly of walls and roofs.
Used to determine projection factor, wall and roof area, and U-factor. Also indi-
cates slab edge insulation and vapor barriers to prevent moisture migration.
These drawings are referred to as “A7” on the summary form.
• Wall/floor/roof details. Show the construction assembly of the connections be-
tween the walls and floor and the walls and roof, as well as the wall construction
at doors and windows in detail. Used to supplement the information contained in
the wall/floor/roof section diagrams. These drawings are referred to as “A9” on
the summary form.
• Fenestration details. Show the assembly of all windows and doors in detail.
Used to determine the area of all fenestration. These drawings are referred to as
“P3” and “P3A” on the summary form.
• Lighting plan. Shows the layout of all lighting and describes the lighting con-
trols. Used in conjunction with the lighting fixture schedule to determine the
lighting power density and to verify the existence of daylighting controls. This
drawing is referred to as “E2” on the summary form.
The following information is included with the text of this section, but would ordinar-
ily be included with the plans and/or specifications.
• Window, Door, and Skylight Schedules: Show window, door, and skylight types
and dimensions. Also includes manufacturer specified U-factors, shading coeffi-
BUILDING DESCRIPTION The case study building is a new office to be constructed in Chattanooga, Tennessee.
The building is single story with an insulated slab-on-grade floor. All walls are light
construction. High performance windows and skylights have been specified. The
skylights include light louvers that are connected to a photosensor and to the build-
ing’s daylighting control system. The design lighting level of this building is 50 foot-
candles, and the lighting designer has determined that the lighting power density is
less than 1.0 W/ ft2.
Window/Door/Skylight Schedules
To facilitate the determination of window, door, and skylight areas and performance
characteristics, the designer of this building has included a window/door schedule and
a skylight schedule. Although such schedules are not required by the 90.1 Code, they
are highly recommended, and greatly facilitate not only the completion of the compli-
ance forms, but also the verification of building envelope compliance. A well con-
structed window, door, or skylight schedule should include the following:
• ID: An identification number or letter used to identify the window, door, or sky-
light on the drawings.
• Quantity: The number of windows, doors, or skylights of a given type.
• Dimensions: The frame or rough opening dimensions for each window type.
This allows the total window, door, or skylight area to be easily calculated.
• Physical Description: A brief description of the physical characteristics of each
window, door, or skylight. For windows and skylights, this should include the
frame type, the number of panes, the existence of any coatings, tints, or films, the
presence of any gas fills (such as argon or krypton), and the gap width. For
doors, this would include the type of door, its thickness, what the door is made
of, and whether or not it is insulated.
• Performance characteristics: The U-factor, shading coefficient (SC), and visible
light transmittance (VLT) of skylights and windows, and the U-factor of opaque
doors. These values can be taken from manufacturer’s data or from the default
tables in the Reference section of this chapter. When manufacturer’s literature is
used, copies should be provided to the building department, so that they can ver-
ify the performance characteristics.
• Maximum Infiltration: Shows the appropriate ASTM or AAMA test procedure
which applies.
General Notes
Construction notes and call-outs are typically included on the plans which indicate
that the appropriate envelope infiltration requirements will be met. The following are
notes taken from the case study plan set.
• All exterior joints and openings in the building envelope that are observable
sources of air leakage shall be caulked, gasketed, weatherstripped, or otherwise
sealed.
• Site constructed doors, windows, and skylights shall be caulked between the unit
and the building, and shall be weatherstripped (except for unframed glass doors
and fire doors).
• Manufactured doors and windows installed shall have air infiltration rates certi-
fied by the manufacturer. This is also shown on the schedule.
• All insulating material shall be installed in compliance with the flame spread rat-
ing and smoke density requirements of the applicable building code.
COMPLIANCE DOCUMENTATION The compliance forms that address the building envelope are not difficult to com-
plete, provided that an organized methodology is used to collect and document the
required information. This text discusses the procedure that was used to fill out the
envelope compliance forms for the case study building.
The Envelope Summary, Roof/Floor Worksheet, and the Exterior Wall Work-
sheet are the three forms that must be completed to demonstrate compliance with the
requirements of Section 402. For buildings with only one type of wall, roof, or floor
construction, the Roof/Floor and Exterior Wall Worksheets may be omitted. For
more complex buildings, the two worksheets are used to determine area-weighted
average U-factors and other performance parameters.
The following information is provided as an exercise. The envelope details are given
for a new building to be constructed in the midwestern United States. Enough infor-
mation is provided to complete the required envelope compliance forms.
BUILDING DESCRIPTION
The building used in this example is a new, single story restaurant that will be built in
Columbus, Ohio in the immediate future. The restaurant is to be constructed on an
unheated slab floor, with 2 inch thick, 24 inch deep (vertical), polyisocyanurate foam
insulation. All of the walls in the building are light construction. The exterior walls
consist of 2x6 fir studs spaced at 16 inches, with R-19 fiberglass batt insulation.
Walls adjacent to unconditioned space consist of 2x4 fir studs spaced at 16 inches,
with R-11 fiberglass batt insulation. There are two roof constructions: the first is
used over the perimeter of the building, and consists of a 9.25 inch deep single rafter
wood joist assembly with R-30C insulation. The second roof type is used over the
center of the building, and has the same assembly as the first roof type, with the addi-
tion of one inch of extruded polystyrene foam. The interior load density (ILD) of this
building is between 1.51 and 3.00 W/ft2.
The following area take-offs can be used to determine 90.1 Code compliance:
• Roof Area: The gross roof area, including skylights, is 9,680 ft2. Of this total,
5,480 ft2 is the first roof type described above, and 4,200 ft2 is the second roof
type. There are two skylights (see skylight schedule) in this second roof type.
• Exterior wall area: The gross exterior wall area, including doors and fenestra-
tion, is 4300 ft2. All walls have the same construction assembly.
• Wall adjacent to unconditioned space area: The gross wall area adjacent to un-
conditioned space is 400 ft2. There are no doors located in this wall area.
• Floors over unconditioned space area: There are no floors over unconditioned
space.
• Below grade wall area: There are no below grade walls.
• The area weighted average projection factor for all vertical fenestration in the
building is between 0.26 and 0.50.
Window/Door/Skylight Schedules
In addition to the above information, the following schedules were taken from the
plans for this building. These schedules can be used to determine the area and per-
formance characteristics of the windows, doors, and skylights in the building.
General Notes
The plans for this restaurant also included the following general comments:
• All exterior joints and openings in the building envelope that are observable
sources of air leakage shall be caulked, gasketed, weatherstripped, or otherwise
sealed.
• Site constructed doors, windows, and skylights shall be caulked between the unit
and the building, and shall be weatherstripped (except for unframed glass doors
and fire doors).
• Manufactured doors and windows installed shall have air infiltration rates certi-
fied by the manufacturer. This may also be shown on the schedule.
AREA-WEIGHTED AVERAGES The 90.1 Code requires that you know the U-factor, shading coefficient, visible light
transmission, projection factor, etc. for envelope components. Buildings are usually
complex designs and include many different types of wall, roof, and floor construc-
tion assemblies. Often more than one type of window or overhang will exist in a
building. In these cases, it is necessary to calculate an area-weighted average.
The area-weighted average is like a simple average, except that larger surfaces
are weighted more heavily than smaller surfaces. Suppose that a building has two
roof constructions. The first construction represents an area of 9,000 ft2 and has a
U-factor of 0.030. The second construction represents an area of just 1,000 ft2 and a
U-factor of 0.100. A simple average is 0.065 is calculated as shown below.
0.030 + 0.100
Simple Average = = 0.065
2
Since the higher U-factor represents only 10% of the roof area, the simple average is
inaccurate. The area-weighted average is 0.037, almost half the simple average. The
area-weighted average is calculated by multiplying each U-factor by its area, adding
these products, and dividing the sum by the total area. The area-weighted average
calculation is shown below.
Q A single-story warehouse distribution center has 15,000 ft2 of gross exterior wall.
The fenestration area is only 200 ft2, but there are 20 truck loading doors, each 20 ft
wide and 10 ft high. The U-factor is 0.12 for the insulated concrete wall, but only
1.15 for the uninsulated metal roll-up doors (not much different from a single-glazed
window). What is the opaque wall U-factor for the entire building?
A A weighted average U-factor must be calculated that takes account of both the
U-factor of the roll-up doors and the exterior wall. This is done as follows:
FENESTRATION PERFORMANCE The term "fenestration" refers to the light-transmitting areas of a wall or roof, mainly
windows and skylights. The 90.1 Code sets performance requirements for fenestra-
tion by limiting fenestration area. The fenestration area allowed depends on the shad-
ing coefficient, the size of overhangs, the thermal performance (U-factor), and
whether or not daylighting controls are installed. These terms are defined below and
default values are given which may be used in compliance calculations.
Controlling solar gains and maximizing daylighting can significantly affect en-
ergy use in buildings. Solar gains through windows add to cooling loads in the sum-
mer and during other times when the building is air conditioned. On cold days, solar
gains can also offset heating loads, although this is generally not a significant benefit
in commercial buildings, because high internal heat gains typically reduce the hours
heating is needed when the building is occupied. The more significant benefit of
sunlight is daylighting. Light is solar radiation in the visible spectrum − with a wave
length between about 380 and 770 nanometers. With the right type of electric light-
ing system and controls, daylight can be a significant benefit. The ideal fenestration
would allow light to enter the building, but block solar radiation outside the visible
spectrum − that in the ultraviolet and near infrared part of the solar spectrum.
Solar gain can be limited through the use of tinted or reflective glazing or
through the use of overhangs. The code also offers credits for glazing that does a
good job of bringing in daylight while limiting solar gains.
Fenestration U-factor
Fenestration U-factor (Uof) is the rate of heat flow through the fenestration when there
is a one degree temperature difference between the air on one side and the air on the
other side. In the United States, the units are Btu per hour per degree Fahrenheit or
HEAT CAPACITY (HC) HC is the heat capacity per square foot of wall area (Btu/ft2-°F) and is used in the
90.1 Code to quantify the amount of thermal mass in exterior walls. It is used with
both the prescriptive and system performance methods. With both methods, a benefit
is assigned to exterior wall mass that can be traded off against less insulation, and
with the system performance method, increased glass area. It is not necessary to cal-
culate HC for light weight walls; a default of 1.0 Btu/(ft2-°F) may be assumed.
HC is calculated by using the following equation. The term "i" is an index of
each layer in the wall and "n" is the total number of layers that have significant mass.
n
HC = ∑ Density i × Specific Heat i × Thickness i
i =1
Enter 0.48 for the north wall orientation, 0.52 for the east, 0.51 for the south and
0.48 for the west.
Q What is the heat capacity (HC) for the wall construction depicted below? The exte-
rior wall consists of 8 in. partially grouted Concrete Masonry Unit (CMU), and the
interior has R-11 batt insulation between 2×4 studs (16 in. o.c.) with an interior layer
of 5/8 in. gypsum board.
A The HC is the sum of the density times the specific heat times the thickness for each
layer of the wall. The calculation can be structured in tabular form as shown below.
Specific Heat
Weight Fraction of (Btu/lb-°F) HC
Item (lb/ft2) Wall (Btu/ft2-°F)
8" Partially Grouted CMU (105 lb/ft3) 47.00 1.00 0.20 9.40
2 × 4 Wood Studs 9.30 0.15 0.33 0.46
R-11 Batt 0.25 0.85 0.30 0.06
5/8" Gypsum Board 2.60 1.00 0.26 0.68
Total 10.60
OVERHANG PROJECTION Overhangs can control solar gains by blocking direct sun during the summer when the
FACTOR (PF) sun is high in the sky. During the winter when there may be a heating load, a properly
designed south overhang can allow the sun to penetrate into the building, providing
some heating benefit. The benefit of overhangs depends on the orientation of the
window, the latitude of the building site, and the balance point of the building. The
most accurate way to assess the benefits of overhangs is through computer simula-
tions that calculate thermal loads for each hour of the year, taking the position of the
sun into account for each hour.
The figure of merit used to characterize the performance of overhangs with the
prescriptive and system performance methods is the projection factor which is the
ratio of the projection (A) of the overhang from the glazing surface to the height (B)
distance from the window sill to the bottom of the overhang (see Figure 402V). Nei-
ther the prescriptive method nor the system performance method offers additional
benefits for overhangs with projection factors greater than 0.50. This size overhang
has a projection half as great as the distance from the window sill to the bottom of the
overhang. Projections greater than 0.50 can be entered in the ENVSTD program and
can be used with the prescriptive tables, but the benefit assigned is the same as if a
projection factor of 0.50 were entered.
Q
What is the area-weighted average projection factor for a 10-story office building
with light shelves on the south side, but none on the north side? The long axis of the
60 ft by 200 ft building runs east-west and there are no windows on the east or west
ends. Each floor on both the north and south sides has two continuous bands of win-
dows – the lower band is 4 ft of tinted low-e double-glazing which starts 3 ft above
the floor and the upper band is 1 ft 6 in. of clear low-e double-glazing which starts 8
ft above the floor. (All glass is recessed so that the exterior surface of the glass is 6
in. from the exterior surfaces of the wall.) On the south side only a horizontal light
shelf begins 6 in. above the top of the lower window and extends 1 ft 8 in. out from
the exterior wall surface.
A The projection factor of the lower band of glass on the south side is 0.37 (20 in./4 ft +
6 in.) The area-weighted average PF for all glazing is:
PFoverall = [(1'6" × 200' × 10 stories × 0.00)
+ (4' × 200' × 10 stories × 0.00)
+ (1'6" × 200' × 10 stories × 0.00)
+ (4' × 200' × 10 stories × 0.37)]
/ [(1'6"+4') × 200' × 10 stories × 2 facades]
= (0 + 0 + 0 + 2960) / 22,000 = 0.13
Use the 0.000 - 0.249 range. (There has been no benefit from doing the calculations.)
For the ENVSTD program, calculate an area-weighted average PF for each ori-
entation.
PFnorth = no light shelves, so assume 0.00
PFsouth = [(1'6" × 200' × 10 stories × 0.00)
+ (4' × 200' × 10 stories × 0.37)]
/ [(1'6"+4') × 200' × 10 stories]
= (0 + 2960) / 11,000 = 0.27
For the ENVSTD program, enter 0.00 for PF for the north wall orientation and 0.27
for the south.
Basic Concepts
U-factor The U-factor is the rate of steady-state heat flow. It is the amount of heat in Btu
(British thermal units) that flows each hour through one square foot, when there is a
one degree temperature difference between the inside air and outside air. The heat
flow can be in either direction, as heat will flow from the warmer side to the cooler
side. Steady-state heat flow assumes that temperatures on both sides of a building
envelope element (while different) are held constant for a sufficient period of time so
that heat flow on both sides of the assembly is steady. The steady-state heat flow
method is a simplification, because in the real world, temperatures change constantly.
It can, however, predict average heat flow rates over time, and is used by the 90.1
Code to limit conductive heat losses and gains. Because they are easy to understand
and use, the terms for steady-state heat flow are part of the basic vocabulary of build-
ing energy performance.
Each layer of a building assembly, such as the sheathing and the insulation, has
its own conductance, or rate of heat transfer. The conductance for an individual layer
is like the U-factor, and it has the same units. The difference is that it is only for a
single element or layer. The U-factor includes the conductance of every element of
the building assembly, including the air films on the interior and exterior surfaces of
the construction assembly. The surface conductances quantify the rate at which heat
is transferred between the surface of the construction assembly and the surrounding
environment.
For light frame walls, the steady-state U-factors provide an adequate description
of heat transfer. For heavy concrete and masonry walls, however, this is only true
under constant or average temperature conditions. The dynamic heat storage proper-
ties of the concrete and masonry alter the thermal behavior of the wall, and the
U-factor becomes less accurate as a predictor of heat flow rates.
R-value R-values are also used to describe steady-state heat flow, but in a slightly different
way. The R-value is the thermal resistance to heat flow. A larger R-value has
greater thermal resistance, or more insulating ability, than a smaller R- value. The big
advantage of R-values is that they can be added together. For homogeneous assem-
blies, the total R-value of a construction assembly is the sum of the R-values of each
of the layers. The layers should include the sheathing and finishes, the insulation and
weatherproofing elements, and the surface air films. The U-factor is the inverse of
the total R-value.
1
U - Value =
Total R - Value
The R-value is widely recognized in the building industry and is used to describe in-
sulation effectiveness. The insulation R-value is not the total R-value of the wall,
however. It only describes the thermal resistance of the insulation material. The R-
Default U-factors
Precalculated U-factors are provided in this section for typical construction assem-
blies, including roofs, floors, and doors. These values are calculated using acceptable
methods, and may be used for compliance with the code.
Data in this table apply when both the framing and the building surface are metal. It is the
situation most vulnerable to thermal short-circuits.
Laboratory Tests x x x x
Series-Parallel Path (Isothermal Planes) x x
Parallel Path Correction Factors x
Two-Dimensional Models x x x x
Zone Method x
Laboratory Tests
Laboratory tests are the most accurate way to determine the U-factor of a construction
assembly, and are acceptable for all types of construction. An 8 ft by 8 ft sample of
the construction assembly is placed in a test unit. For steady-state measurements, the
temperatures on either side of the wall are held constant until temperatures within the
construction have stabilized; then the rate of heat flow is measured. The biggest ad-
vantage of laboratory testing is that it gives equally good data for any type of con-
struction assembly. The major disadvantage is that it is costly and time consuming.
There is a large variety of possible construction assemblies, and it is impractical to
test them all. For this reason, it is usually more cost effective to use calculation
methods. Laboratory measurements must use one of the following test procedures:
Guarded Hot Plate (ASTM C-177-85), Heat Flow Meter (ASTM C-518-85), Guarded
Hot Box (ASTM C-236-87), or Calibrated Hot Box (ASTM C-976-82).
Q What is the thermal transmittance of the wood framed wall shown in the following
drawing?
A The series and parallel path method may be used for this type of construction. The
U-factor is calculated separately for the cavity and framing portions of the wall based
on the thermal resistance of each element of the wall. These calculations are made in
the following table:
Cavity Framing
Outside air film 0.17 0.17
7/8 in. stucco 0.18 0.18
Building paper 0.06 0.06
Cavity insulation 13.00
Framing 4.375
1/2 in. gypsum board 0.45 0.45
Inside air film 0.68 0.68
Sum of thermal resistance 14.54 5.01
The estimated framing is 15% of the wall area and the U-factor may be calculated as
shown below.
0.15 1 − 0.15
U= + = 0.088
5.01 14.54
Zone Method
For conditions for which there are no parallel path correction factors, the zone
method may be used. It may be used for construction assemblies with metal framing
and non-metallic sheathing, such as concrete or masonry. The use of this method is
documented in the ASHRAE Fundamentals Handbook (1985) and involves dividing
the construction assembly into zones. Heat flow in the zone near the metal framing is
assumed to be conducted toward the framing and the thermal resistance is smaller.
Compressed Insulation
Insulation that is compressed must be derated in accordance with Table 402T. or the
reduction may be calculated in accordance with the procedures in the ASHRAE Fun-
damentals Handbook (1985).
Table 402S Effective R-values for Wall Insulation Installed Between Metal Framing
Nominal Framing Depth Nominal Insulation Correction Factor Effective R-value
R-value
4"@16"o.c. R-11 0.50 R-5.5
R-13 0.46 R-6.0
R-15 0.43 R-6.4
4"@24"o.c. R-11 0.60 R-6.6
R-13 0.55 R-7.2
R-15 0.52 R-7.8
6"@16"o.c. R-19 0.37 R-7.1
R-21 0.35 R-7.4
6"@24"o.c. R-19 0.45 R-8.6
R-21 0.43 R-9.0
8"@16"o.c. R-25 0.31 R-7.8
8"@24"o.c. R-25 0.38 R-9.6
The correction factors for metal framed walls may be used with metal studs of 16 ga. or lighter.
Table 402T Effective R-value of Fiberglass Batts Compressed in Various Depth Cavities (h-ft2-°F/Btu)
Nominal Lumber Actual Depth of Insulation R-values at Standard Thickness
Size Cavity
38C 38 30C 30 25 22 21 19 15 13 11 8 5 3
2" × 12" 11-1/4" 38 37
2" × 10" 9-1/4" 32 30
2" × 8" 7-1/4" 27 26 24
2" × 6" 5-1/2" 21 20 21 18
2" × 4" 3-1/2" 14 13 15 13 11
2" × 3" 2-1/2" 10
2" × 2" 1-1/2" 6.5 6.0 5.7
2" × 1" 1/2" 3.2 3.0
The standard thicknesses are as follows: 10-1/4" for R-38C, 12" for R-38, 8-1/4" for R-30C, 9-1/2" for R-30, 8" for R-25, 6-3/4" for R-22, 5-1/2" for R-21, 6-
1/4" for R-19, 3-1/2" for R-15, 3-1/2" for R-13, 3-1/2" for R-11, 2-1/2" for R-8, 1-1/2" for R-5 and 3/4" for R-3.
Q What is the thermal transmittance of the metal framed wall shown in the following
drawing?
Component R-value
A The parallel path correction factors may be used for this type of construction. This
calculation method is available for wall sections with non-metal skin attached to metal
stud framing. It is a modified form of the equivalent circuit method. It uses the paral-
lel path correction factors listed in Table 402.1.2.1b. The correction factor for a 2×4
metal stud framing at 24 in. o.c. with R-11 fiberglass cavity insulation is 0.60. The
thermal transmittance of this assembly is given by the following equations:
The thermal resistance of the framing and insulation
R e = R insulation × Fc = 11.0 × 0.60 = 6.6 with thermal bridging accounted for. The parallel path
correction factor of 0.60 is taken from Table
402.1.2.1b of the code.
The thermal resistance of the materials in "series"
∑ R i = 0.17 + 0.21 + 4.00 + 0.45 + 6.60 + 0.45 + 0.68 = 12.56
i
The overall thermal transmittance of the assembly
1 1
Ut = = = 0. 0796
R t 12.56
Zone Method
For conditions for which there are no parallel path correction factors, the zone
method may be used. It may be used for construction assemblies with metal framing
and non-metallic sheathing, such as concrete or masonry. The use of this method is
documented in the ASHRAE Fundamentals Handbook (1985) and involves dividing
the construction assembly into zones. Heat flow in the zone near the metal framing is
assumed to be conducted toward the framing and the thermal resistance is smaller.
Compressed Insulation
Insulation that is compressed must be derated in accordance with Table 402T or the
reduction may be calculated in accordance with the procedures in the ASHRAE Fun-
damentals Handbook (1985).
Table 402U Effective R-value of Fiberglass Batts Compressed in Various Depth Cavities (h-ft2-°F/Btu)
Nominal Lumber Actual Depth of Insulation R-values at Standard Thickness
Size Cavity
38C 38 30C 30 25 22 21 19 15 13 11 8 5 3
2" × 12" 11-1/4" 38 37
2" × 10" 9-1/4" 32 30
2" × 8" 7-1/4" 27 26 24
2" × 6" 5-1/2" 21 20 21 18
2" × 4" 3-1/2" 14 13 15 13 11
2" × 3" 2-1/2" 10
2" × 2" 1-1/2" 6.5 6.0 5.7
2" × 1" 1/2" 3.2 3.0
The standard thicknesses are as follows: 10-1/4" for R-38C, 12" for R-38, 8-1/4" for R-30C, 9-1/2" for R-30, 8" for R-25, 6-3/4" for R-22, 5-1/2" for R-21, 6-
1/4" for R-19, 3-1/2" for R-15, 3-1/2" for R-13, 3-1/2" for R-11, 2-1/2" for R-8, 1-1/2" for R-5 and 3/4" for R-3.