Bobot
Bobot
I PEKERJAAN PERSIAPAN
1 Mobilisasi 1.00 Ls 16,000,000.00 16,000,000.00 0.28 1.00 16,000,000.00 0.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Manajemen Mutu 1.00 Ls 20,000,000.00 20,000,000.00 0.35 1.00 20,000,000.00 0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Sub Jumlah 36,000,000.00 0.63 36,000,000.00 0.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
II PEKERJAAN PEMBONGKARAN
1 Pembongkaran Perkerasan Jalan Beton / Aspal (Excavator Hidrolic / Jack Hammer) 318.00 m³ 332,000.00 105,576,000.00 1.86 32.30 10,723,600.00 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.67
Sub Jumlah 105,576,000.00 1.86 10,723,600.00 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.67
III PEKERJAAN TANAH DAN GEOOSINTETIK
1 Galian biasa untuk dibuang (waste) 1,196.29 m³ 88,000.00 105,273,520.00 1.85 46.29 4,073,520.00 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.78
Sub Jumlah 105,273,520.00 1.85 4,073,520.00 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.78
IV PEMASANGAN GEOTEKSTIL
1 Geotekstill Non Woven 282.30 m² 21,400.00 6,041,220.00 0.11 107.65 2,303,710.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
Sub Jumlah 6,041,220.00 0.11 2,303,710.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
V PERSIAPAN TANAH DASAR
1 Pemadatan dengan Stamper 1,060.00 m² 4,400.00 4,664,000.00 0.08 107.65 473,660.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
Sub Jumlah 4,664,000.00 0.08 473,660.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
VI LAPIS PONDASI AGREGAT
1 Lapisan Pondasi Agregat Kelas A 212.00 m³ 260,000.00 55,120,000.00 0.97 21.53 5,597,800.00 0.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.87
2 Lapisan Pondasi Agregat Kelas B 265.00 m³ 260,000.00 68,900,000.00 1.21 24.76 6,437,600.00 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.10
Sub Jumlah 124,020,000.00 2.18 12,035,400.00 0.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.97
VII PERKERASAN
1 Pengersan Beton Semen Single Wire Mesh Fast Track 3 hari 945.45 m³ 2,450,000.00 2,316,352,500.00 40.79 32.30 79,135,000.00 1.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.39
Sub Jumlah 2,316,352,500.00 40.79 79,135,000.00 1.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.39
IX PEKERJAAN CUTTING
Sealant Cutting (lebar 0,5, tebal 5 cm 4,434.60 m 21,000.00 93,126,600.00 1.64 720.84 15,137,640.00 0.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.37
Sub Jumlah 93,126,600.00 1.64 15,137,640.00 0.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.37
X PEKERJAAN GROUTING
Grouting Portland Cement + Additive 2,100.00 m² 215,000.00 451,500,000.00 7.95 341.36 73,392,400.00 1.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.66
Sub Jumlah 451,500,000.00 7.95 73,392,400.00 1.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.66
XII PEKERJAAN PATCHING
1 Patching Tipe 3 750.00 m 250,000.00 187,500,000.00 3.30 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.30
2 Patching Tipe 4 (penghamparan) 800.00 zak 95,000.00 76,000,000.00 1.34 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.34
Sub Jumlah 187,500,000.00 3.30 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.30
XIII PEKERJAAN EXPANTION JOINT ASPAL
1 Expantion Joint Aspal (Asphaltic Plig Joint) 700.00 m 2,662,900.00 1,864,030,000.00 32.82 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.82
Sub Jumlah 1,864,030,000.00 32.82 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.82
VII PENGAMANAN LALU LINTAS
1 Pengamanan dan Pengaturan lalu lintas Tipe A 53.00 Hari 1,120,000.00 59,360,000.00 1.05 12.00 13,440,000.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.81
2 Pengamanan dan Pengaturan lalu lintas Tipe B 457.00 Hari 843,000.00 385,251,000.00 6.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.78
Sub Jumlah 385,251,000.00 6.78 13,440,000.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.78
JUMLAH HARGA DAN BOBOT 5,679,334,840.00 100.00 246,714,930.00 4.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 95.89