0% found this document useful (0 votes)
8 views

Bobot

Uploaded by

andi rohandi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
8 views

Bobot

Uploaded by

andi rohandi
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

PROYEK : PEMELIHARAAN PERIODIK (SFO) DAN REKONSTRUKSI PERKERASAN PADA LAPORAN

RUAS JALAN TOL PALIKANCI 2024 PELAKSANAAN PEKERJAAN MINGGUAN

PEKERJAAN Rekonstruksi Perkerasan Beton pada Ruas Jalan Tol Palikanci


LOKASI Gerbang Tol Palikanci Barat KONTRAKTOR PELAKSANA
NO. KONTRAK MINGGU ke - 1
TGL. KONTRAK PERIODE I
PROGRESS S.D SAAT INI 4.11 %

NILAI KONTRAK REKON L1 REKON L2 REKON L3 REKON L4 EXPANTION JOINT


BOBOT YANG BELUM
NO URAIAN PEKERJAAN VOLUME KONTRAK SAT JUMLAH JUMLAH JUMLAH
HARGA SATUAN (Rp) JUMLAH HARGA (Rp) BOBOT (%) VOLUME JUMLAH HARGA (Rp) BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME BOBOT (%) VOLUME JUMLAH HARGA (Rp) BOBOT (%) DIKERJAKAN (%)
HARGA (Rp) HARGA (Rp) HARGA (Rp)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23

I PEKERJAAN PERSIAPAN
1 Mobilisasi 1.00 Ls 16,000,000.00 16,000,000.00 0.28 1.00 16,000,000.00 0.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
2 Manajemen Mutu 1.00 Ls 20,000,000.00 20,000,000.00 0.35 1.00 20,000,000.00 0.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Sub Jumlah 36,000,000.00 0.63 36,000,000.00 0.63 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
II PEKERJAAN PEMBONGKARAN
1 Pembongkaran Perkerasan Jalan Beton / Aspal (Excavator Hidrolic / Jack Hammer) 318.00 m³ 332,000.00 105,576,000.00 1.86 32.30 10,723,600.00 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.67
Sub Jumlah 105,576,000.00 1.86 10,723,600.00 0.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.67
III PEKERJAAN TANAH DAN GEOOSINTETIK
1 Galian biasa untuk dibuang (waste) 1,196.29 m³ 88,000.00 105,273,520.00 1.85 46.29 4,073,520.00 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.78
Sub Jumlah 105,273,520.00 1.85 4,073,520.00 0.07 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.78
IV PEMASANGAN GEOTEKSTIL
1 Geotekstill Non Woven 282.30 m² 21,400.00 6,041,220.00 0.11 107.65 2,303,710.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
Sub Jumlah 6,041,220.00 0.11 2,303,710.00 0.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
V PERSIAPAN TANAH DASAR
1 Pemadatan dengan Stamper 1,060.00 m² 4,400.00 4,664,000.00 0.08 107.65 473,660.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
Sub Jumlah 4,664,000.00 0.08 473,660.00 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.07
VI LAPIS PONDASI AGREGAT
1 Lapisan Pondasi Agregat Kelas A 212.00 m³ 260,000.00 55,120,000.00 0.97 21.53 5,597,800.00 0.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.87
2 Lapisan Pondasi Agregat Kelas B 265.00 m³ 260,000.00 68,900,000.00 1.21 24.76 6,437,600.00 0.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.10
Sub Jumlah 124,020,000.00 2.18 12,035,400.00 0.21 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.97
VII PERKERASAN
1 Pengersan Beton Semen Single Wire Mesh Fast Track 3 hari 945.45 m³ 2,450,000.00 2,316,352,500.00 40.79 32.30 79,135,000.00 1.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.39
Sub Jumlah 2,316,352,500.00 40.79 79,135,000.00 1.39 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 39.39
IX PEKERJAAN CUTTING
Sealant Cutting (lebar 0,5, tebal 5 cm 4,434.60 m 21,000.00 93,126,600.00 1.64 720.84 15,137,640.00 0.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.37
Sub Jumlah 93,126,600.00 1.64 15,137,640.00 0.27 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.37
X PEKERJAAN GROUTING
Grouting Portland Cement + Additive 2,100.00 m² 215,000.00 451,500,000.00 7.95 341.36 73,392,400.00 1.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.66
Sub Jumlah 451,500,000.00 7.95 73,392,400.00 1.29 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.66
XII PEKERJAAN PATCHING
1 Patching Tipe 3 750.00 m 250,000.00 187,500,000.00 3.30 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.30
2 Patching Tipe 4 (penghamparan) 800.00 zak 95,000.00 76,000,000.00 1.34 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.34
Sub Jumlah 187,500,000.00 3.30 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.30
XIII PEKERJAAN EXPANTION JOINT ASPAL
1 Expantion Joint Aspal (Asphaltic Plig Joint) 700.00 m 2,662,900.00 1,864,030,000.00 32.82 0.00 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.82
Sub Jumlah 1,864,030,000.00 32.82 0.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 32.82
VII PENGAMANAN LALU LINTAS
1 Pengamanan dan Pengaturan lalu lintas Tipe A 53.00 Hari 1,120,000.00 59,360,000.00 1.05 12.00 13,440,000.00 0.24 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.81
2 Pengamanan dan Pengaturan lalu lintas Tipe B 457.00 Hari 843,000.00 385,251,000.00 6.78 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.78
Sub Jumlah 385,251,000.00 6.78 13,440,000.00 - 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 6.78

JUMLAH HARGA DAN BOBOT 5,679,334,840.00 100.00 246,714,930.00 4.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 95.89

Disetujui Oleh, Diperiksa Oleh,


Pengawas Lapangan

YUSWADI, ST
Nip. 19760521 200904 1 004

You might also like