Checklist for Pile foundation Work in Transmission Line

Uploaded by

sAuRaBh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
155 views4 pages

T&D - TL Civil - Checklist For Pile Foundation

Checklist for Pile foundation Work in Transmission Line

Uploaded by

sAuRaBh
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 4

Process Sub-Process Parameter to be checked

Pile Foundation Documentation Availability of Approved drawings

Pile Foundation Pile Marking Cut-off Level (50* Dia): Drawing Point No 11

Pile Foundation Pile Marking Centre Point of pile hole (As per Tower Schedule coordinate)

Pile Foundation Drilling Boring Start Time (Record as per site work)

Pile Foundation Drilling Boring End Time (Record as per site work)

Pile Foundation Drilling Diameter of Bore (750 mm as per pile foundation dwg)

Depth of Pile hole (19.075 meter +cut off +additional 0.5-1.0


Pile Foundation Drilling
meter (for avoid caving)

Pile Foundation Drilling Hole properly cleaned before installation of cage

Length of MS liner below Cut-off level


Pile Foundation Permanent Casing
(7 meter , 6 mm thickness)

Pile Foundation Permanent Casing Thickness of MS liner (6 mm thickness)

Pile Foundation Permanent Casing Quality of welding on liner (Double side welding)

Pile Foundation Reinforcement Approved Brand Steel (As per approved document)

Pile Foundation Reinforcement Steel free from rust or any foreign material

Pile Foundation Reinforcement Spacing of re-bar (As per drawing: 150 mm C/C)

Pile Foundation Reinforcement Cage length (19.075+CUT OFF): Spiral to Spiral

Pile Foundation Reinforcement All welding points as per drawing

Pile Foundation Reinforcement Cage free from mud, oil and grease

Pile Foundation Reinforcement Lapping between cages as per drawing

Pile Foundation Reinforcement Clear cover to rebar (75 mm)

Drilling Fluid
Pile Foundation Specific gravity of fresh Bentonite slurry
(Bentonite Slurry)
Drilling Fluid
Pile Foundation Specific gravity of Bentonite slurry after flushing
(Bentonite Slurry)

Pile Foundation Concreting Depth of bore hole checked after flushing using Sounding Chain

Pile Foundation Concreting Start time

Pile Foundation Concreting End Time

Volume of concrete pour (As per mix design ratio or nominal mix
Pile Foundation Concreting
ratio): (pie*radius*radius*length of pile)

Pile Foundation Concreting Concrete Slump Value (As per Approved checklist)

Depth to concrete continuously measured and recorded as well


Pile Foundation Concreting
as tremie pipe length (As per GL level)

Pile Foundation Concreting Casing extraction Monitored

Pile Foundation Concreting Weather Condition (good, fair, Rain)

Reinforcement cage stays in right position during casting


Pile Foundation Concreting
(Central of pit hole)

Pile Foundation Concreting Nos of cube taken (As per approved FQP)

Note Separation of pile must to be avoid by proper poking of tremie pipe and not to be lift up suddenly, it sho
Spiral Overlapping must to be done (50 times of lapping rod diameter)
Spacer should be min 1.5 meter along the longitude
Subparameter Unit
Latest Revision of Approved drawing NA

Material as per designing drawing NA

Physical Checking Coordinate

As per SOP/ WI Time

Dimension of Structure Time

Physical Checking MM

Physical Checking MM

Physical Checking NA

Physical Checking MM

Physical Checking MM

Physical Checking NA

Approved brand letter /Physical Checking NA

Physical Checking NA

As per designing drawing MM

Physical Checking MM

Physical Checking NA

Physical Checking NA

As per designing drawing MM

Physical Checking MM

Physical Checking NA
Physical Checking NA

Physical Checking MM

Physical Checking Time

Physical Checking Time

As per designing drawing Cum

As per designing drawing MM

As per designing drawing MM

Physical Checking NA

Physical Checking NA

Physical Checking NA

As per Requirement Nos

ot to be lift up suddenly, it should gradually pour concrete