Method Statement - Threaded Bar Installation
Method Statement - Threaded Bar Installation
Approval
DOCUMENT
DOCUMENT TITLE REV Status(for
NUMBER
Consultant use)
01 MST-Threaded Bar Installation 01
CONTRACTOR ISSUED
NAME: POSITION: SIGNED: DATE:
We certify that the documents contained in this submission are in accordance with the Contract Documents.
CONSULTANT RECEIVAL
STAMP/DATE:
ANT REVIEWER
NAME: POSITION: SIGNED: DATE:
RESIDENT ENGINEER
REVIEW STATUS
APPROVED WITH REVISE AND
APPROVED REJECTED
COMMENTS RESUMBMIT
CONSULTANT COMMENTS
CLIENT
COMMENTS: SIGNATURE:
METHOD STATEMENT
THREADED BAR (SHEAR STUD) INSTALLATION
Project
HATCHERY STRUCTURAL RETROFIT WORKS
14-Outer Region, NOEM, Kingdom of Saudi Arabia
PMC: CONCESSIONNAIRE:
Revision Status of the Document:
Nafees ZAHID
METHOD STATEMENT FOR THREADED BAR
01 26.05.2024 Ahmad HUSSAIN
(SHEAR STUD) INSTALLATION.
Submission Details
Page 2 of 10
Table of Contents
1 Introduction ......................................................................................... 4
2 Scope of Work ...................................................................................... 4
3 References ........................................................................................... 4
4 Key Personnel....................................................................................... 4
5 Roles and Responsibilities ....................................................................... 5
5.1 Project Manager ................................................................................... 5
5.2 Construction Manager ............................................................................ 5
5.3 QAQC Engineer ..................................................................................... 6
5.4 Site Engineer ....................................................................................... 6
5.5 HSE Engineer / Officer ........................................................................... 7
6 Manpower............................................................................................ 8
7 Specific Training and Communication Requirements ................................... 8
8 Procedure to be Employed for Shear Stud Installation using
(sika_anchorfix_3001) ................................................................................ 8
9 Quality Control and Inspection ................................................................ 9
10 Safety precautions ................................................................................ 9
11 Environmental Considerations ................................................................. 9
12 Monitoring and Compliance ..................................................................... 9
13 Access and Egress................................................................................. 9
14 Fall Protection Measure .........................................................................10
15 Special Identified Residual Hazards .........................................................10
16 Safe Work Loads ..................................................................................10
17 Emergency Procedures and Arrangements ...............................................10
18 First Aid Facilities .................................................................................10
19 Non-Conformance & Defects Control .......................................................10
20 Attachments: ......................................................................................10
20.1(Sika_Anchorfix_3001) (MST) ............................................................... 10
20.2Risk Assessment: ................................................................................10
Page 3 of 10
1 Introduction
The objective of this Method Statement is to outline the efficient and safe method of
work to follow in order to safely and efficiently complete the installation of threaded
bars(shear studs) at Hatchery Structural Retrofit Works. This activity will be
conducted in compliance with relevant safety regulations, local codes, and
industry best practices to ensure the protection of personnel, property, and
the environment.
2 Scope of Work
The purpose of this method statement is to describe the detailed procedure for the safe
and efficient methodology to be applied for shear stud installation.
3 References
• Project Specification
• Approved Project Health and Safety Plan
• Electrical safety management plan
• Fall prevention plan
• Training plan
• Lifting operations management plan
• Injury/illness management plan
• Approved Project Construction Environmental Management Plan
• Approved Project Emergency Response Plan
4 Key Personnel
Position Number
Project Manager 1
Construction Manager 1
QAQC Engineer 1
Site Engineer 1
HSE Engineer / Officer 1
Page 4 of 10
5 Roles and Responsibilities
5.1 Project Manager
• Ensure and facilitate the effective implementation of the Project Health, Safety and
Environmental Management Plan and approved RAMS.
• Ensure that site activities take place in accordance to Project Health, Safety and
Environmental Management Plan and approved RAMS.
• Ensure that incidents, accidents and near miss incidents are recorded, reported and
investigated and that the necessary corrective actions are taken and implemented.
• Ensure that all incidents and accidents are timeously reported to the Client and HSE
Director.
• Ensure that all HSE Observations and NCR’s are closed out within the specified time
period.
Page 5 of 10
5.3 QAQC Engineer
• QA/QC Engineer will manage and coordinate the Inspection and Testing in
accordance with the requirement of the Inspection & Test Plan and responsible for
ensuring all the activities are carried out as per the approved method statement,
project specification and approved quality control procedures.
• He shall ensure the approved & controlled copies of the drawings only using at site,
which are issued to the site supervising team.
• He is responsible for reviewing IRs for all the related day to day activities at site as
per the approved ITP and attending all the required day to day inspection along with
Site Engineer and the Consultant for approvals.
• Conduct surveillance & monitoring activity from time to time on a daily basis while
work is in progress as per approved drawings and project specification.
• Setting out inspection: Obtain approval from Engineer for setting out prior to
commence with installation
• QC inspector will ensure the material shall conform to project specification and
approved samples.
• Work should be carried out as per latest approved drawings.
• QC inspector will confirm the storage and place of the material on site as per project
requirements.
• Ensure MEP clearance & signed off by concerned site engineer (if any) prior to
proceed with installation.
• Prior to final inspection request for consultant, check and ensure required work is
completed.
• He will keep records of all inspections and testing related to the activities.
Page 6 of 10
• Ensure that all “No Objection” Certificates and Work Permits are obtained and all
preventive measures mentioned in the permits have been taken prior to
commencement of the work.
• Ensure that required work permits are issued to the Foreman / Site Supervisor before
allowing them to proceed with any related works
• Ensure that all your personnel have received HSE orientation training about site HSE
requirement and other related HSE training before assigning them to work
• Ensure that good housekeeping is maintained at your work site at all times
• Responsible to co-ordinate with sub-contractors (if any) and other contractors in the
work area to avoid any confusion about areas of responsibility.
• Ensure that equipment, both power and hand tools are safe and maintained in good
operating condition and is suitable and safe to do the assigned job;
• Ensure that his Personnel does not leave their work area unless permitted by you in
writing;
• To ensure that all visitors visiting your area of responsibility, comply to the set HSE
requirements and standards as specified in the minimum requirements;
• Assign a competent guide to assist drivers delivering materials to the site and lay
down areas;
• Ensure that NO work requiring permit approval is permitted, unless proper permit
approval is obtained.
• Raising the IR/MIR according to nature of job or specific site requirements
Page 7 of 10
6 Manpower
• Construction Manager: 1 no.
• Site Engineer: 1 no.
• Safety Engineer / Officer: 1 no.
• QA/QC Engineer: 1 no.
• General Foremen: 1 no.
• Skilled and Unskilled Labor 5- 10 no’s (depends on progress)
Page 8 of 10
➢ Bar and anchors should be clean and rust free to achieve the design bond
strength.
8.2 Application
See below the attached method statement from the manufacturer. It includes the
entire procedure including substrate preparation, drilling and application.
10 Safety precautions
➢ Ensure all workers are equipped with appropriate Personal Protective
Equipment (PPE).
➢ Follow safety protocols for handling resins, catalysts, and other materials.
➢ Ensure proper ventilation when working in confined areas.
➢ Implement fall protection measures when working at heights.
11 Environmental Considerations
➢ Ensure compliance with environmental regulations and guidelines for the
handling, storage, and disposal of (sika_anchorfix_3001), catalyst and other
materials.
➢ Take measures to prevent spills, leaks, or contamination of soil, water bodies,
or surrounding vegetation during application of (sika_anchorfix_3001).
Page 9 of 10
➢ Designated working areas to be identified and barricaded. Approved signage
shall be followed in the working location.
20 Attachments:
20.1 (Sika_Anchorfix_3001) (MST)
20.2 Risk Assessment:
Page 10 of 10
PRODUCT DATA SHEET
Sika AnchorFix®-3001
Epoxy high performance chemical anchoring material
1/5
PRODUCT INFORMATION
Composition Epoxy
Packaging 400 ml side by side cartridge 12 cartridges per box
pallet: 60 boxes
600 ml side by side cartridge 12 cartridges per box
pallet: 36 boxes
TECHNICAL INFORMATION
Compressive strength ~85 N/mm2 (7 days, +20 °C) (ASTM D 695)
Modulus of elasticity in compression ~5 000 N/mm2 (7 days, +20 °C) (ASTM D 695)
Tensile strength in flexure ~45 N/mm2 (7 days, +20 °C) (ASTM D 790)
Modulus of elasticity in tension ~5 500 N/mm2 (7 days, +20 °C) (ASTM D 638)
Service temperature Long term -40 °C min. / +40 °C max. (ETAG 001, Part 5)
Short term (1–2 hours) +80 °C
SYSTEMS
System structure Ancillary products:
▪ Sika AnchorFix® Flexible Extensions
▪ Sika AnchorFix® Hole Cleaning Brushes-Steel
▪ Sika AnchorFix® Static Mixers -Nozzles
▪ Sika AnchorFix® Straight Extensions
▪ Sika AnchorFix® Perforated Sleeves
APPLICATION INFORMATION
Mixing ratio Part A : Part B = 1 : 1 by volume
Layer thickness ~7 mm max
Sag flow Non-sag, including overhead
Product temperature 10 °C min. / +30 °C max.
Ambient air temperature +5 °C min. / +40 °C max.
Dew point Beware of condensation.
Substrate temperature during application must be at least +3 °C above
dew point.
Substrate temperature +5 °C min. / +40 °C max.
2/5
Curing time Temperature Open time - T gel Curing time - T cur
+40 °C 3 minutes 3 hours
+35 °C to +40 °C 4 minutes 4 hours
+30 °C to +35 °C 6 minutes 5 hours
+25 °C to +30 °C 8 minutes 6 hours
+20 °C to +25 °C 11 minutes 7 hours
+15 °C to +20 °C 15 minutes 8 hours
+10 °C to +15°C 20 minutes 12 hours
+5 °C to +10 °C —* 24 hours
* Minimum cartridge temperature: +10 °C
FURTHER INFORMATION
▪ For specific information on design refer to: Technical
Documentation Sika AnchorFix®-3001 870 43 10
▪ Sika Method Statement: Sika AnchorFix®
▪ Sika AnchorFix®: Approvals
APPLICATION INSTRUCTIONS
4. Place the cartridge into
SUBSTRATE QUALITY the application gun ready
for use
Mortar and concrete must be at the required design
strength.
Substrate tensile / compressive strengths (concrete,
masonry, natural stone) must be confirmed by testing.
The anchor hole must always be clean, free from oil
and grease etc.
Loose particles must be removed from the holes.
Threaded rods and rebar's must be cleaned thor- When the work is interrupted the static mixer nozzle
oughly and free from dirt, oil, grease, corrosion can remain on the cartridge after the gun pressure has
products or any other substances and particles which been released. If the resin has hardened in the nozzle
could affect adhesion. when work is resumed, a new nozzle must be at-
tached.
3/5
APPLICATION METHOD / TOOLS 7. Pump gun at least 2x
until both parts are ex-
Reference must be made to further documentation truded as a one consistent
where applicable, such as relevant method statement, colour. Do not use this
application manual and installation or working instruc- material. Release the gun
tions. pressure and clean the
Anchors in solid masonry/concrete static mixer opening with
1. Drill hole with an elec- a cloth
tric drill to the diameter
8. Inject the anchoring
and depth required. Drill
material into the drill
hole diameter must be in
hole, starting from the
accordance with anchor
bottom and slowly pull
size
out the static mixer while
2. The drill hole must be extruding the resin into
cleaned with oil free com- the hole. Avoid entrap-
pressed air using an air ping air. For deep holes
lance, pressure: 6 Bar (90 use extension tubing
psi). Start from the bot- 9. Insert the anchor with
tom of the hole and clean a rotary motion into the
minimum 2x until return filled drill hole within the
air stream is free of dust anchoring material open
3. The drill hole must be time. Some of the an-
thoroughly cleaned with choring material must
the special steel brush (at flow out of the hole
least 2x). The diameter of 10. During the resin
the brush must be larger hardening time the an-
than the diameter of the chor must not be moved
drill hole or loaded
4. The drill hole must be
cleaned again as stage 2
Important Note: Anchors in hollow blocks: Use Sika
AnchorFix®-1.
CLEANING OF EQUIPMENT
5. The drill hole must be Clean all tools and application equipment with
thoroughly cleaned again Sika® Colma Cleaner immediately after use. Hardened
as stage 3 material can only be removed mechanically.
LOCAL RESTRICTIONS
6. The drill hole must be Note that as a result of specific local regulations the
cleaned again as stage 2 declared data and recommended uses for this product
&4 may vary from country to country. Consult the local
Product Data Sheet for exact product data and uses.
4/5
LEGAL NOTES
The information, and, in particular, the recommenda-
tions relating to the application and end-use of Sika
products, are given in good faith based on Sika's cur-
rent knowledge and experience of the products when
properly stored, handled and applied under normal
conditions in accordance with Sika's recommenda-
tions. In practice, the differences in materials, sub-
strates and actual site conditions are such that no war-
ranty in respect of merchantability or of fitness for a
particular purpose, nor any liability arising out of any
legal relationship whatsoever, can be inferred either
from this information, or from any written recom-
mendations, or from any other advice offered. The
user of the product must test the product’s suitability
for the intended application and purpose. Sika re-
serves the right to change the properties of its
products. The proprietary rights of third parties must
be observed. All orders are accepted subject to our
current terms of sale and delivery. Users must always
refer to the most recent issue of the local Product
Data Sheet for the product concerned, copies of which
will be supplied on request.
SikaAnchorFix-3001-en-AE-(03-2021)-4-1.pdf
5/5
Risk Assessment
Contractor: AQUA BRIDGE GROUP Persons Carrying Out Assessment
Activity: SHEAR STUD INSTALLATION Name
Revision: 01
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 1 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Site survey -Un-authored -security breach, 5 4 20 H • All Personnel and CVMPE to have -Security 5 2 10 L
access -minor or major injury valid NEOM QR Code -Managers
-Site vehicle -Risk of getting hit by vehicles • Obtain Permission from relevant -Supervisor
movement authorities
• Site induction to be given to all
-falling objects Human error resulting into injury and personnel which will include
-slip trip and damage emergency exit route, assembly point
fall and emergency services etc.
Slip /Trip/ Fall • Demark designated access point /
New walk ways.
employees & • Adequate PPE should be worn at all-
Young Bites or stings time includes hard hat, reflective
employees jacket, safety goggles, safety
boots/shoes & face mask.
Poor Lighting / • Personnel should be adequately
Excessive trained for the task and aware of
lighting onsite hazard present and
appropriate controls to be
Presence of implemented.
Fauna & Flora • Adequate lighting as per the
NEOM SOP requirements (Section 3.8
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-001-OCT-2022 - ABG Form 01 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 2 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
N E O M - N P R - S O P - 00 8 ) shall
be provided.
• Lux levels at the working area
especially during night shall be
monitored and recorded.
• Maintenance and replacement of
faulty lighting fixtures to be provided.
• Pest Control to be done at all
areas of the site, as rodents attracts
Snakes.
• Food Waste to be disposes on
time as open food waste attracts
rodents.
• Remove unwanted bushes and
close all visible burrows inorder to
reduce the hiding places for
venomous Reptiles and Scorpions.
• Consider that snakes & scorpions
may be at site.
• Wear gloves during manual
handling
• Do not place hands etc. under
rocks without checking first
• Report and highlight visibility of
any of the above
• Conduct awareness TBT and do
not touch or engage any of the
above.
• Should a bite or sting – provide
immediate first aid and seek medical
help.
• Try to take a photograph of
animal for hospital reference – DO
NOT attempt to catch the animal.
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 3 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 4 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 6 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Chipping and Drilling Use of Power • Entanglement with Rotating parts of 5 4 20 M • Activity Briefing to be provided prior Manager 5 2 10 L
of existing concrete Tools power tools to the start of activity Site Engineer
using Hilti • Flying particles • Approved MSRA should be in work Supervisor
Electricity • Electrocution location and communicate to HSE Officer
• Improper cable management workers prior to commencement of
flying objects, • High level of noise work.
grid and • Fire • Hot work Permit to be obtained
dust • Compressed gas • Competent and trained person only to
• Health hazards be allowed to operate powered tools.
flash back • Make sure cables, sockets used are
Damages to Eye or cause injury or
Compressed industrial type and in good condition
wounds.
gas • Disconnect power source when not in
use
• The trained store person should do
random and routine inspection prior to
the issue of tools.
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 7 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 8 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 10 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 11 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 13 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Use of Skin burns, Exposure to chemical 5 4 20 H • Store the chemical in a cool, dry, Temporary 5 2 10 L
chemical/hazardous and well-ventilated area away works
material eye irritation, Improper handling and storage from direct sunlight and ignition coordinator
Supervisor,
sources.
Inhalation of fumes released during the Operator,
respiratory • Ensure containers are tightly
mixing and application. Project
issues due to sealed and clearly labelled manager,
contact with Splashing of chemical • Have spill containment kits Engineer
or inhalation
readily available on-site
of chemicals. Accidental ingestion
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 14 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Allergic
reactions
Cutting and Entanglement -Severe injuries/death 5 4 20 H • Activity briefing to be given to all the
demolition of existing in the - electric shocks, burns and death associated workforce
structures/block concrete - Injuries to eyes leading to blindness • Ensure power is off before starting
work/concrete cutter -Injuries/Death resulting from • Clear area of debris
machines running over personnel • secure loose clothing/hair
- flying objects
• Remove all jewelry
or cutting
• position cutter away from any power
wheels
source where ejected water may
-Dust from come into contact with electricity
demolished • Only Operatives with training and
concrete/slabs authorized to use cutting tools should
undertake the work
• Concrete PPE to be worn at all times
when using the cutter including
safety goggles and gloves
• make sure all machine guards are in
place
• Training and Supervision of personnel
• Work areas should be properly signed
and barricaded with fences
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 15 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 16 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 17 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Working in Extreme Heat, Rain, Personnel Injury 4 4 16 M • Weather to be monitored on Site Engineer 4 2 8 L
weather condition Strong wind Ill-health daily basis. Supervisor
and other • During summer or extreme heat, HSSE Officer
inclement frequent breaks to be
weather implemented.
• Provide cool shaded rest area.
• Provide continuous supply of cool
drinking water,
• Heat stress training to be given to
all.
• Rehydration drink to be provided.
• Work schedule and timings to
adopt the condition.
• Heavy and tiring activity to be
done on early part of the day.
• Implement work rotation, if
necessary, during hot condition.
• Follow mid-day break work rules.
• No external works to be done
during rain and strong winds.
• Make sure all materials and
structure are secured properly to
prevent being blown away.
• All FOD and waste to be
controlled and removed on daily
basis.
• All electrical cables / equipment
to be secured and protected
against water/rain.
• During foggy condition, work will
start/resume until condition is
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 18 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Exposure to dust / Dust Ill-health 3 4 12 M • Daily dust and noise monitoring Site Engineer 3 2 6 L
noise Noise NIHL (Noise induced Hearing loss) to be implemented. Supervisor
Asthma • Appropriate dust control HSSE Officer
Lung disorders measures to be implemented
(e.g. dust suppression by making
the work area dampened down
with water)
• Appropriate noise protection to
be implemented.
• Provide appropriate PPE e.g. dust
mask & hearing protection/ear
plugs.
• All sources of noise and dust to
be contained at its source..
• Replace all noisy equipment with
less noise producing
equipment/tools.
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 19 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
Mediu
High Medium Low High Low
m
Mediu
High Medium Low High Low
m
Total Number of Initial Risks per level Total Number Final Risks per level recorded
Risk Assessment Level Summary: 9 6 0 0 0 15
recorded before controls - after controls -
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 20 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL
RR3 = 15-18 = further assessment may be necessary to establish more precisely the
3 6 9 12 15 18 SUBSTANTIAL
Substantial likelihood of harm as a basis for determining the need for improved control
MEDIUM measures. A permit to work may have to be applied to achieve this.
Efforts should be made to reduce the risk, but the cost of prevention should
RR4 = 12 =
4 8 12 16 20 24 MODERATE be carefully measured and limited. Risk reduction measures should be
Moderate
implemented within a defined time period.
No additional control required. Consideration may be given to a more cost-
RR5 = 8-10 =
5 10 15 20 25 30 TOLERABLE effective solution or improvement that imposes no additional cost burden.
Tolerable
LOW Monitoring is required to ensure that the controls are maintained.
RR6 = 1-6 =
6 12 18 24 30 36 TRIVIAL No action is required and no documentary records needs to be kept.
Trivial
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment