Method Statement - Threaded Bar Installation

Uploaded by

Nafees Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
57 views36 pages

Method Statement - Threaded Bar Installation

Uploaded by

Nafees Ahmad
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 36

CONTRACTOR: CONSULTANT: CLIENT:

DOCUMENT SUBMITTAL FORM


PROJECT HATCHERY STRUCTURAL RETROFIT WORKS
NAME:
SUBMITTAL
REV:01 DATE:26/05/24
REF:
1st Submission PREVIOUS
CATAGORY: 2nd Submission SUBMITTAL REF :
Further Submission
Architectural
Shop Drawing
DISCIPLINE : Civil DOCUMENT
Method Statement
Structural TYPE:
Material Submittal
Mechanical
Pre-Qualification
Electrical
Inspection Test Plan
Plumbing
Others
Others
1 x Hard Copies
Approval
ISSUED FOR: DOCUMENT 1 x AutoCAD Copy
Construction
FORMAT: 1 x DXF Copy
Information Previous review comments form attached.

Approval
DOCUMENT
DOCUMENT TITLE REV Status(for
NUMBER
Consultant use)
01 MST-Threaded Bar Installation 01

CONTRACTOR ISSUED
NAME: POSITION: SIGNED: DATE:

Mr. Imran Khan PROJECT MANAGER

We certify that the documents contained in this submission are in accordance with the Contract Documents.

CONSULTANT RECEIVAL

STAMP/DATE:

ANT REVIEWER
NAME: POSITION: SIGNED: DATE:

RESIDENT ENGINEER

REVIEW STATUS
APPROVED WITH REVISE AND
APPROVED REJECTED
COMMENTS RESUMBMIT
CONSULTANT COMMENTS

CLIENT

COMMENTS: SIGNATURE:
METHOD STATEMENT
THREADED BAR (SHEAR STUD) INSTALLATION

Project
HATCHERY STRUCTURAL RETROFIT WORKS
14-Outer Region, NOEM, Kingdom of Saudi Arabia

PMC: CONCESSIONNAIRE:
Revision Status of the Document:

REVISION DATE DESCRIPTION PREPARED APPROVED


BY BY

Nafees ZAHID
METHOD STATEMENT FOR THREADED BAR
01 26.05.2024 Ahmad HUSSAIN
(SHEAR STUD) INSTALLATION.

Submission Details

NO. ITEM DESCRIPTION

1 Reason for Issue / Purpose of issue Issued for Approval

This document has been prepared, checked


and approved in accordance with Management
2 Compliance Statement
System processes and complies with the
Contract, Agreement.

Page 2 of 10
Table of Contents
1 Introduction ......................................................................................... 4
2 Scope of Work ...................................................................................... 4
3 References ........................................................................................... 4
4 Key Personnel....................................................................................... 4
5 Roles and Responsibilities ....................................................................... 5
5.1 Project Manager ................................................................................... 5
5.2 Construction Manager ............................................................................ 5
5.3 QAQC Engineer ..................................................................................... 6
5.4 Site Engineer ....................................................................................... 6
5.5 HSE Engineer / Officer ........................................................................... 7
6 Manpower............................................................................................ 8
7 Specific Training and Communication Requirements ................................... 8
8 Procedure to be Employed for Shear Stud Installation using
(sika_anchorfix_3001) ................................................................................ 8
9 Quality Control and Inspection ................................................................ 9
10 Safety precautions ................................................................................ 9
11 Environmental Considerations ................................................................. 9
12 Monitoring and Compliance ..................................................................... 9
13 Access and Egress................................................................................. 9
14 Fall Protection Measure .........................................................................10
15 Special Identified Residual Hazards .........................................................10
16 Safe Work Loads ..................................................................................10
17 Emergency Procedures and Arrangements ...............................................10
18 First Aid Facilities .................................................................................10
19 Non-Conformance & Defects Control .......................................................10
20 Attachments: ......................................................................................10
20.1(Sika_Anchorfix_3001) (MST) ............................................................... 10
20.2Risk Assessment: ................................................................................10

Page 3 of 10
1 Introduction
The objective of this Method Statement is to outline the efficient and safe method of
work to follow in order to safely and efficiently complete the installation of threaded
bars(shear studs) at Hatchery Structural Retrofit Works. This activity will be
conducted in compliance with relevant safety regulations, local codes, and
industry best practices to ensure the protection of personnel, property, and
the environment.

2 Scope of Work
The purpose of this method statement is to describe the detailed procedure for the safe
and efficient methodology to be applied for shear stud installation.

3 References
• Project Specification
• Approved Project Health and Safety Plan
• Electrical safety management plan
• Fall prevention plan
• Training plan
• Lifting operations management plan
• Injury/illness management plan
• Approved Project Construction Environmental Management Plan
• Approved Project Emergency Response Plan

4 Key Personnel
Position Number
Project Manager 1

Construction Manager 1

QAQC Engineer 1

Site Engineer 1
HSE Engineer / Officer 1

Page 4 of 10
5 Roles and Responsibilities
5.1 Project Manager
• Ensure and facilitate the effective implementation of the Project Health, Safety and
Environmental Management Plan and approved RAMS.
• Ensure that site activities take place in accordance to Project Health, Safety and
Environmental Management Plan and approved RAMS.
• Ensure that incidents, accidents and near miss incidents are recorded, reported and
investigated and that the necessary corrective actions are taken and implemented.
• Ensure that all incidents and accidents are timeously reported to the Client and HSE
Director.
• Ensure that all HSE Observations and NCR’s are closed out within the specified time
period.

5.2 Construction Manager


• Establish, as far as is reasonably practicable, what hazards are related to any work
undertaken at the workplace and ensuring that Risk Assessments are conducted,
recorded and implemented, this includes the development and review of method
statements;
• Ensure and facilitate the effective implementation of the task Method Statement and
Risk Assessment (RAMS);
• Ensure that daily Safety Task Analysis Risk Reduction Talks (START) are conducted
and recorded prior to the commencement of any task / activity;
• Eliminate or mitigate any hazard or potential hazard to the health and safety of
employees;
• Provide and maintain a work environment that is safe and without risk to the health
and safety of the employees and the environment;
• Provide such information, instructions, training and supervision as may be necessary
to ensure, as far as reasonably practicable, the health and safety of the employees
and environmental is protected;
• Taking the necessary, corrective and preventative actions on all deviations reported
and enforcing such measures and discipline as may be necessary in the interests of
employee health and safety and the environment;
• Maintaining proper written records of all aspects to HSE matters and HSE operational
requirements;
• Ensure that high standards and required levels of housekeeping is maintained;
• Ensure that Permit to Work requirements are complied with and adhered to;
• Ensure that ALL incidents are investigated, recorded and discussed at the HSE
Committee Meetings and corrective action implemented and communicated;
• Identifying areas of potential fire hazards and implement required control measures.

Page 5 of 10
5.3 QAQC Engineer
• QA/QC Engineer will manage and coordinate the Inspection and Testing in
accordance with the requirement of the Inspection & Test Plan and responsible for
ensuring all the activities are carried out as per the approved method statement,
project specification and approved quality control procedures.
• He shall ensure the approved & controlled copies of the drawings only using at site,
which are issued to the site supervising team.
• He is responsible for reviewing IRs for all the related day to day activities at site as
per the approved ITP and attending all the required day to day inspection along with
Site Engineer and the Consultant for approvals.
• Conduct surveillance & monitoring activity from time to time on a daily basis while
work is in progress as per approved drawings and project specification.
• Setting out inspection: Obtain approval from Engineer for setting out prior to
commence with installation
• QC inspector will ensure the material shall conform to project specification and
approved samples.
• Work should be carried out as per latest approved drawings.
• QC inspector will confirm the storage and place of the material on site as per project
requirements.
• Ensure MEP clearance & signed off by concerned site engineer (if any) prior to
proceed with installation.
• Prior to final inspection request for consultant, check and ensure required work is
completed.
• He will keep records of all inspections and testing related to the activities.

5.4 Site Engineer


• Organize the project activities so that work is carried out as required in compliance
with standards, specifications and approved RAMS, with minimal risk to men, existing
facilities, equipment, materials or the environment.
• Ensure subordinates are instructed on the requirements of the Job Hazard Analysis,
Safe Work Procedures / Instructions, HSE Procedures and RAMS.
• Ensure that the identified HSE measures for specific tasks are in place prior to
activity commencement, and that corrective action has been taken to eliminate or
control any potential hazard or environmental impact
• Ensure that personnel are adequately trained and competent to complete their
assigned tasks in a safe and efficient manner.
• Monitor and check that subcontractors are working in accordance with the
requirements and approved RAMS.
• Ensure that daily Pre-Start Meetings and weekly Toolbox Talks, are conducted and
recorded.
• Give specific instructions, in consultation with Project HSE / Engineer / Officer, for
safe and correct work method for critical work areas such as working at elevated
positions.

Page 6 of 10
• Ensure that all “No Objection” Certificates and Work Permits are obtained and all
preventive measures mentioned in the permits have been taken prior to
commencement of the work.
• Ensure that required work permits are issued to the Foreman / Site Supervisor before
allowing them to proceed with any related works
• Ensure that all your personnel have received HSE orientation training about site HSE
requirement and other related HSE training before assigning them to work
• Ensure that good housekeeping is maintained at your work site at all times
• Responsible to co-ordinate with sub-contractors (if any) and other contractors in the
work area to avoid any confusion about areas of responsibility.
• Ensure that equipment, both power and hand tools are safe and maintained in good
operating condition and is suitable and safe to do the assigned job;
• Ensure that his Personnel does not leave their work area unless permitted by you in
writing;
• To ensure that all visitors visiting your area of responsibility, comply to the set HSE
requirements and standards as specified in the minimum requirements;
• Assign a competent guide to assist drivers delivering materials to the site and lay
down areas;
• Ensure that NO work requiring permit approval is permitted, unless proper permit
approval is obtained.
• Raising the IR/MIR according to nature of job or specific site requirements

5.5 HSE Engineer / Officer


• Supervise on-site health & safety control and promote the safe conduct of site work
and environmental protection.
• Responsible for overseeing and ensuring the keeping of up-to-date HSE records,
forms and files in accordance to the Project H&S Plan to ensure compliance and to
enable auditing to be carried out.
• To prevent unsafe acts being undertaken by anyone on the site and to stop and
prevent work to continue / commence in prevailing unsafe conditions.
• Ensure that all employees / workers (including subcontractors) are issued with and
properly use the correct PPE and safety devices for the work being performed.
• Report any incidents, accidents or near misses immediately, as per the approved
procedure, (this may include liaison with police and / or authorities) and to secure the
area by preventing that the area be tampered with.
• Investigate incidents, accidents and near miss events to determine the root, basic
and immediate causes and ensure that correction / corrective / preventative actions
are implemented for all H&S related events.
• Ensure site welfare facilities (rest areas, water, toilets, etc.) are sufficient for the
number of personnel, and are being provided by the site supervisory staff as well as
ensuring that high standards of hygiene are maintained.
• Promote a positive HSE attitude to personnel, subcontractors, consultants and
clients.

Page 7 of 10
6 Manpower
• Construction Manager: 1 no.
• Site Engineer: 1 no.
• Safety Engineer / Officer: 1 no.
• QA/QC Engineer: 1 no.
• General Foremen: 1 no.
• Skilled and Unskilled Labor 5- 10 no’s (depends on progress)

7 Specific Training and Communication


Requirements
Experienced and skilled workers will be performing shear stud installation activity.
Installation of shear studs, including drilling and anchor fix application, shall go
through proper job awareness. All the workers will be informed of the potential
hazards during this activity by attending training sessions as well as on-the-job
training. They shall be trained regarding-working at heights, working with lifting
appliances, use of personal protective equipment, health hazards while working
with chemicals and safe operating zones. The safety concept will be maintained by
regular safety meetings throughout the job period.

8 Procedure to be Employed for Shear Stud Installation


using (sika_anchorfix_3001)

8.1 Substrate preparation


➢ The area to be drilled should be marked using any suitable marking tool.
➢ Drill hole with an electric drill to the required diameter and depth as per design.
➢ After drilling, the holes must be cleaned thoroughly using compressed air or
brush

Page 8 of 10
➢ Bar and anchors should be clean and rust free to achieve the design bond
strength.

8.2 Application
See below the attached method statement from the manufacturer. It includes the
entire procedure including substrate preparation, drilling and application.

9 Quality Control and Inspection


➢ Conduct visual inspection of the applied bonding agents to verify uniformity,
coverage, and adhesion to the substrate.
➢ Document all inspection findings and test results for record-keeping and quality
assurance purposes.

10 Safety precautions
➢ Ensure all workers are equipped with appropriate Personal Protective
Equipment (PPE).
➢ Follow safety protocols for handling resins, catalysts, and other materials.
➢ Ensure proper ventilation when working in confined areas.
➢ Implement fall protection measures when working at heights.

11 Environmental Considerations
➢ Ensure compliance with environmental regulations and guidelines for the
handling, storage, and disposal of (sika_anchorfix_3001), catalyst and other
materials.
➢ Take measures to prevent spills, leaks, or contamination of soil, water bodies,
or surrounding vegetation during application of (sika_anchorfix_3001).

12 Monitoring and Compliance


➢ A Site Engineer and HSE officer will be monitoring the activity at all times.
➢ Site Engineer will ensure that the RAMS are communicated to the operatives
prior to commencement of the activity.
➢ Start briefing will be conducted and communicated to the operative. HSE Officer
will ensure that all required documents are valid and available. 3rd party
certificates for equipment, inspection on safety equipment and verify require
training of employees.
➢ Prior to start activity work permit to issue and approved by all relevant parties.

13 Access and Egress


➢ All employees entering the site shall do so by making use of the access
provided. Only authorized employees will be allowed to gain access into the
site.
➢ All employees will attend the health and safety induction prior to entering the
area of operation. Access permits will only be issued to employees on
completion of the induction.

Page 9 of 10
➢ Designated working areas to be identified and barricaded. Approved signage
shall be followed in the working location.

14 Fall Protection Measure


➢ Any identified missing edged protection or openings in floors shall first be
rectified/made safe prior to any other works starting.
➢ Preventing the falling of hand tools such a spanner is important, tool lanyards to
be fitted to all hand tools.

15 Special Identified Residual Hazards


➢ Working at height
➢ Use of chemicals

16 Safe Work Loads


➢ Scaffolding with safety green tag.

17 Emergency Procedures and Arrangements


➢ In case of any Emergency, emergency arrangements will be carried out in
accordance with the Emergency Response Plan.

18 First Aid Facilities


➢ Name of on-site first aider and first aid box location to be posted near the
working area.

19 Non-Conformance & Defects Control


➢ Any defects identified during execution will be clearly communicated with the
team on site. This will ensure that the works can be rectified in a timely manner.

20 Attachments:
20.1 (Sika_Anchorfix_3001) (MST)
20.2 Risk Assessment:

Page 10 of 10
PRODUCT DATA SHEET
Sika AnchorFix®-3001
Epoxy high performance chemical anchoring material

DESCRIPTION ▪ ESR to AC308 by ICC-ES, anchoring in cracked con-


crete for static, wind and earthquake loading
Sika AnchorFix®-3001 is an epoxy resin based, 2-part, ▪ Seismic tested (C1)
thixotropic, 1:1 mixing ratio, high performance an- ▪ Suitable for contact with drinking water
choring material. It is specifically designed for anchor- ▪ Fire resistant
ing threaded rods and reinforcement bars in both ▪ Styrene-free
cracked and un-cracked dry or damp concrete. ▪ Good adhesion to the substrate
Suitable to use in hot and tropical climatic conditions. ▪ Shrinkage-free hardening
▪ Standard sealant guns can be used (250 ml cartridge)
USES ▪ Low wastage

Sika AnchorFix®-3001 may only be used by experi- SUSTAINABILITY


enced professionals.
▪ Conformity with LEED v4 MRc 2 (Option 1): Building
Anchoring material for fixing of non-expanding an- Product Disclosure and Optimization – Environment-
chors in the following: al Product Declarations
Structural work ▪ Conformity with LEED v4 MRc 4 (Option 2): Building
▪ Rebar / steel reinforcement anchoring in new and re- Product Disclosure and Optimization - Material In-
furbishment works gredients
▪ Threaded rods
▪ Bolts and special fastening / fixing systems APPROVALS / CERTIFICATES
Metalwork, carpentry
▪ Handrails, balustrades and supports ▪ CE Marking and Declaration of Performance to ETA
▪ Railings 14/0157, based on ETAG 001 Part 1 and Part 5 - Bon-
▪ Window and door frames ded injection type anchor for use in cracked and un-
Substrates cracked concrete
▪ CE Marking and Declaration of Performance to ETA
▪ Concrete (cracked and un-cracked)
14/0368, based on ETAG 001 Part 1 and Part 5 - Post
▪ Hollow and solid masonry
installed rebar connections
▪ Wood ▪ Adhesive Anchors for Cracked and Un-cracked Con-
▪ Natural and reconstituted stone crete IBC/IRC, Sika AnchorFix®-3001, ICC-ES, Evalu-
▪ Solid rock ation report No. ESR-3608
▪ Drinking Water System Components NSF/ANSI 61,
CHARACTERISTICS / ADVANTAGES Sika AnchorFix®-3001, IAPMO R&T, Certificate No. K-
8319
▪ Long open time ▪ Fire Testing ISO 834-1, Sika AnchorFix®-3001, CSTB,
▪ Can be used in damp concrete Test report No. 26054326/B
▪ High load capacity
▪ ETA to ETAG 001 for anchoring in cracked concrete
▪ ETA to ETAG 001 for rebar connections

Product Data Sheet


Sika AnchorFix®-3001
March 2021, Version 04.01
020205010030000004

1/5
PRODUCT INFORMATION
Composition Epoxy
Packaging 400 ml side by side cartridge 12 cartridges per box
pallet: 60 boxes
600 ml side by side cartridge 12 cartridges per box
pallet: 36 boxes

Colour Part A off-white


Part B dark grey / black
A+B mixed grey

Shelf life 24 months from date of production


Storage conditions The product must be stored in original, unopened and undamaged sealed
packaging in dry conditions at temperatures between +10 °C and +25 °C.
Always refer to packaging.
Density A+B mixed ~1,49 kg/l

TECHNICAL INFORMATION
Compressive strength ~85 N/mm2 (7 days, +20 °C) (ASTM D 695)

Modulus of elasticity in compression ~5 000 N/mm2 (7 days, +20 °C) (ASTM D 695)

Tensile strength in flexure ~45 N/mm2 (7 days, +20 °C) (ASTM D 790)

Tensile strength ~23 N/mm2 (7 days, +20 °C) (ASTM D 638)

Modulus of elasticity in tension ~5 500 N/mm2 (7 days, +20 °C) (ASTM D 638)

Service temperature Long term -40 °C min. / +40 °C max. (ETAG 001, Part 5)
Short term (1–2 hours) +80 °C

SYSTEMS
System structure Ancillary products:
▪ Sika AnchorFix® Flexible Extensions
▪ Sika AnchorFix® Hole Cleaning Brushes-Steel
▪ Sika AnchorFix® Static Mixers -Nozzles
▪ Sika AnchorFix® Straight Extensions
▪ Sika AnchorFix® Perforated Sleeves

APPLICATION INFORMATION
Mixing ratio Part A : Part B = 1 : 1 by volume
Layer thickness ~7 mm max
Sag flow Non-sag, including overhead
Product temperature 10 °C min. / +30 °C max.
Ambient air temperature +5 °C min. / +40 °C max.
Dew point Beware of condensation.
Substrate temperature during application must be at least +3 °C above
dew point.
Substrate temperature +5 °C min. / +40 °C max.

Product Data Sheet


Sika AnchorFix®-3001
March 2021, Version 04.01
020205010030000004

2/5
Curing time Temperature Open time - T gel Curing time - T cur
+40 °C 3 minutes 3 hours
+35 °C to +40 °C 4 minutes 4 hours
+30 °C to +35 °C 6 minutes 5 hours
+25 °C to +30 °C 8 minutes 6 hours
+20 °C to +25 °C 11 minutes 7 hours
+15 °C to +20 °C 15 minutes 8 hours
+10 °C to +15°C 20 minutes 12 hours
+5 °C to +10 °C —* 24 hours
* Minimum cartridge temperature: +10 °C

BASIS OF PRODUCT DATA MIXING


Preparing cartridge: 400 ml and 600 ml
All technical data stated in this Data Sheet are based
1.Unscrew the cap
on laboratory tests. Actual measured data may vary
due to circumstances beyond our control.

FURTHER INFORMATION
▪ For specific information on design refer to: Technical
Documentation Sika AnchorFix®-3001 870 43 10
▪ Sika Method Statement: Sika AnchorFix®
▪ Sika AnchorFix®: Approvals

IMPORTANT CONSIDERATIONS 2. Pull out the red plug

▪ Natural / reconstituted stone and solid rock proper-


ties vary particular with regard to strength, composi-
tion and porosity. For each application, the suitability
of Sika AnchorFix®-3001 must be tested for bond
strength, surface staining and discoloration by first
applying the product to a sample area before full
project application.

ECOLOGY, HEALTH AND SAFETY 3. Screw on the static


mixer
User must read the most recent corresponding Safety
Data Sheets (SDS) before using any products. The SDS
provides information and advice on the safe handling,
storage and disposal of chemical products and con-
tains physical, ecological, toxicological and other
safety-related data.

APPLICATION INSTRUCTIONS
4. Place the cartridge into
SUBSTRATE QUALITY the application gun ready
for use
Mortar and concrete must be at the required design
strength.
Substrate tensile / compressive strengths (concrete,
masonry, natural stone) must be confirmed by testing.
The anchor hole must always be clean, free from oil
and grease etc.
Loose particles must be removed from the holes.
Threaded rods and rebar's must be cleaned thor- When the work is interrupted the static mixer nozzle
oughly and free from dirt, oil, grease, corrosion can remain on the cartridge after the gun pressure has
products or any other substances and particles which been released. If the resin has hardened in the nozzle
could affect adhesion. when work is resumed, a new nozzle must be at-
tached.

Product Data Sheet


Sika AnchorFix®-3001
March 2021, Version 04.01
020205010030000004

3/5
APPLICATION METHOD / TOOLS 7. Pump gun at least 2x
until both parts are ex-
Reference must be made to further documentation truded as a one consistent
where applicable, such as relevant method statement, colour. Do not use this
application manual and installation or working instruc- material. Release the gun
tions. pressure and clean the
Anchors in solid masonry/concrete static mixer opening with
1. Drill hole with an elec- a cloth
tric drill to the diameter
8. Inject the anchoring
and depth required. Drill
material into the drill
hole diameter must be in
hole, starting from the
accordance with anchor
bottom and slowly pull
size
out the static mixer while
2. The drill hole must be extruding the resin into
cleaned with oil free com- the hole. Avoid entrap-
pressed air using an air ping air. For deep holes
lance, pressure: 6 Bar (90 use extension tubing
psi). Start from the bot- 9. Insert the anchor with
tom of the hole and clean a rotary motion into the
minimum 2x until return filled drill hole within the
air stream is free of dust anchoring material open
3. The drill hole must be time. Some of the an-
thoroughly cleaned with choring material must
the special steel brush (at flow out of the hole
least 2x). The diameter of 10. During the resin
the brush must be larger hardening time the an-
than the diameter of the chor must not be moved
drill hole or loaded
4. The drill hole must be
cleaned again as stage 2
Important Note: Anchors in hollow blocks: Use Sika
AnchorFix®-1.
CLEANING OF EQUIPMENT
5. The drill hole must be Clean all tools and application equipment with
thoroughly cleaned again Sika® Colma Cleaner immediately after use. Hardened
as stage 3 material can only be removed mechanically.

LOCAL RESTRICTIONS
6. The drill hole must be Note that as a result of specific local regulations the
cleaned again as stage 2 declared data and recommended uses for this product
&4 may vary from country to country. Consult the local
Product Data Sheet for exact product data and uses.

Product Data Sheet


Sika AnchorFix®-3001
March 2021, Version 04.01
020205010030000004

4/5
LEGAL NOTES
The information, and, in particular, the recommenda-
tions relating to the application and end-use of Sika
products, are given in good faith based on Sika's cur-
rent knowledge and experience of the products when
properly stored, handled and applied under normal
conditions in accordance with Sika's recommenda-
tions. In practice, the differences in materials, sub-
strates and actual site conditions are such that no war-
ranty in respect of merchantability or of fitness for a
particular purpose, nor any liability arising out of any
legal relationship whatsoever, can be inferred either
from this information, or from any written recom-
mendations, or from any other advice offered. The
user of the product must test the product’s suitability
for the intended application and purpose. Sika re-
serves the right to change the properties of its
products. The proprietary rights of third parties must
be observed. All orders are accepted subject to our
current terms of sale and delivery. Users must always
refer to the most recent issue of the local Product
Data Sheet for the product concerned, copies of which
will be supplied on request.

SIKA NORTHERN GULF SIKA SOUTHERN GULF SIKA SAUDI ARABIA


Bahrain / Qatar / Kuwait UAE / Oman / SIC Riyadh / Jeddah / Dammam
Tel: +973 177 38188 Tel: +971 4 439 8200 Tel: +966 11 217 6532
[email protected] [email protected] [email protected]
gcc.sika.com gcc.sika.com gcc.sika.com

SikaAnchorFix-3001-en-AE-(03-2021)-4-1.pdf

Product Data Sheet


Sika AnchorFix®-3001
March 2021, Version 04.01
020205010030000004

5/5
Risk Assessment
Contractor: AQUA BRIDGE GROUP Persons Carrying Out Assessment
Activity: SHEAR STUD INSTALLATION Name

Revision: 01

Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 1 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

Site survey -Un-authored -security breach, 5 4 20 H • All Personnel and CVMPE to have -Security 5 2 10 L
access -minor or major injury valid NEOM QR Code -Managers
-Site vehicle -Risk of getting hit by vehicles • Obtain Permission from relevant -Supervisor
movement authorities
• Site induction to be given to all
-falling objects Human error resulting into injury and personnel which will include
-slip trip and damage emergency exit route, assembly point
fall and emergency services etc.
Slip /Trip/ Fall • Demark designated access point /
New walk ways.
employees & • Adequate PPE should be worn at all-
Young Bites or stings time includes hard hat, reflective
employees jacket, safety goggles, safety
boots/shoes & face mask.
Poor Lighting / • Personnel should be adequately
Excessive trained for the task and aware of
lighting onsite hazard present and
appropriate controls to be
Presence of implemented.
Fauna & Flora • Adequate lighting as per the
NEOM SOP requirements (Section 3.8

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-001-OCT-2022 - ABG Form 01 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 2 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

N E O M - N P R - S O P - 00 8 ) shall
be provided.
• Lux levels at the working area
especially during night shall be
monitored and recorded.
• Maintenance and replacement of
faulty lighting fixtures to be provided.
• Pest Control to be done at all
areas of the site, as rodents attracts
Snakes.
• Food Waste to be disposes on
time as open food waste attracts
rodents.
• Remove unwanted bushes and
close all visible burrows inorder to
reduce the hiding places for
venomous Reptiles and Scorpions.
• Consider that snakes & scorpions
may be at site.
• Wear gloves during manual
handling
• Do not place hands etc. under
rocks without checking first
• Report and highlight visibility of
any of the above
• Conduct awareness TBT and do
not touch or engage any of the
above.
• Should a bite or sting – provide
immediate first aid and seek medical
help.
• Try to take a photograph of
animal for hospital reference – DO
NOT attempt to catch the animal.

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 3 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

Delivery and Vehicle Security Breach 5 5 25 H • Approved TTMP to be Supervisor, 5 2 10 L


mobilization of Personnel Collision implemented Operator,
equipment on site Over speeding Personnel Injury • Training provider cards must be Project
of vehicles Property damage available. Contractors should also manager,
Fire attend NEOM Projects Making Engineer
Vehicle Fuels Explosion Safe Choices training programme.
& chemicals & Unintended release / spills • No plant maintenance facility is
Dust Environmental Pollution permitted to be constructed on
any NEOM site without prior
approval of the Project
Management Consultant,
Delivery Partner, and the
Employer.
• Plant, equipment, and vehicles
intended for deployment/use
should not be older than 15 years

• All drivers must possess a valid


KSA Driving license
• Clearly define traffic route
• Required traffic signages
• All drivers and operators should
be trained and aware about the
site conditions and TTMP
• All plant and equipment must be
inspected in line to NEOM-SOP
34.0 clause 3.6 a requirements

• All Plant & vehicles to have valid


Neom QR Code.
• All necessary approvals to be in-
place.

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 4 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• Proper traffic control


management to be done
• Use designated access way.
• Proper coordination with related
authorities to be implemented.
• Proper traffic management to be
arrange.
• Provision for competent flagman
to assist vehicle movement.
• Appropriate signage to be
provided.
• All driver/operator should have
valid driving registration and
competent certificate.
• Comply with speed limit
requirement.
• Designated banks/flagmen required
•Correct plant and equipment for the
task is selected and maintained.
•Records of inspections and maintenance
including any certification must be
available locally and easily accessible by
those using the equipment. Equipment
must be marked with basic details of in
date certification.
•Operative training and competency
usually in the form of relevant accredited
training provider cards must be available.
Contractors should also attend NEOM
Projects Making Safe Choices training
programme.
•No plant maintenance facility is
permitted to be constructed on any
NEOM site without prior approval of the
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 5 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

Project Management Consultant, Delivery


Partner, and the Employer.
•Plant, equipment, and vehicles intended
for deployment/use should not be older
than 15 years.
• All items of mobile plant must be
capable of 360-degree vision or fitted
with 360-degree visibility aids so that the
driver can see a one-meter-high object,
one meter from all sides of the vehicle.
Curtains or cardboard that can restrict
vision must not be in place.
• All items of mobile plant that
operate in potentially close proximity to
workers should be fitted with a proximity
warning alarm system (PWAS) which
meets the following minimum
performance specification:
• 360-degree area coverage
• Suitable detection range (can be
varied depending on environment / task,
etc.)
• In cab audible and visual alarm
• In cab monitor (screen)
• Employee assigned tags or
wearable device
• Front and rear cameras, 120-
degree angle and night vision / low light
capability

• Drivers and operators daily


checks
• Valid KSA license and 3rd party
certificate

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 6 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• COSSH assessments complete


and communicated to workers
• Appropriate PPE worn
• Ensure employees have a spill kit
available and know how to use it.
• Fuels stored in safe locations, away
from sunlight and in a secure location
• dust suppression by means of water
sprinkling
• Dust masks worn

Chipping and Drilling Use of Power • Entanglement with Rotating parts of 5 4 20 M • Activity Briefing to be provided prior Manager 5 2 10 L
of existing concrete Tools power tools to the start of activity Site Engineer
using Hilti • Flying particles • Approved MSRA should be in work Supervisor
Electricity • Electrocution location and communicate to HSE Officer
• Improper cable management workers prior to commencement of
flying objects, • High level of noise work.
grid and • Fire • Hot work Permit to be obtained
dust • Compressed gas • Competent and trained person only to
• Health hazards be allowed to operate powered tools.
flash back • Make sure cables, sockets used are
Damages to Eye or cause injury or
Compressed industrial type and in good condition
wounds.
gas • Disconnect power source when not in
use
• The trained store person should do
random and routine inspection prior to
the issue of tools.
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 7 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• All connections shall be grounded and


DB shall be protected by ELCB
• Competent Electrician shall carry out
all electrical repairing connection work
• All electrical equipment’s shall be
inspected and passed by HSE
department
• Electrical tools shall be according to
the power supply, use only 110v
• Overloading of power tools and
electrical cables shall be avoided.
• Follow lock out tag out system for
repairing and maintenance Electrical
equipment to be used should be in good
condition and properly insulated
• Industrial sockets should be used for
connection. No bare wires joints will be
used.
• Operatives to check all tools and
cables before usage. Equipment to have
proper guards in place
• Unauthorized operation shall not be
allowed only trained person shall be
assigned for cutting works
• Operator to ensure that work
pieces are to be free of any oils
or other flammable materials
before welding occurs.
• No flammable materials or
liquids are to be near the cutting
operation.
• Gas hoses are to be checked for
any damage before starting the
works.

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 8 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• Flash back arrestors to be


provided for the gas cutting
guns.
• All Workers should be worn overall
and not wear loose-fitting clothing,
chains, or other loose jewellery around
equipment that poses an entanglement
hazard. Long hair should be tied back to
keep it safely out of danger.
• Workers should not work alone with
potentially entangling machinery
• Before performing adjustments or
maintenance operations on entangling
machinery/ tool, qualified workers
should shut down and lockout
equipment
• All tools must be 100% tied off
whenever using at height
• Operative should have well awareness
about entanglement hazard and safety
measures of slow speed drill machine
• All electrical cables shall be routed
above head level
• Hanging stands shall be used to route
cables. Cable protectors shall protect
cables routed through ground level
• Vaccum supported buffing grinders
to be used
• Dust suppression methodologies to
be followed
• Job rotation / job change to be
provided
• Combustible materials to be
removed from 10m surroundings
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 9 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• Appoint competent fire watcher


• Adequate firefighting equipments
to be provided
• Saftey Team has to monitor the
activity frequently
• Proper Material management and
house keeping to be done.

• Use dust masks / goggles.


• Control ventilation or use vacuum.
• Use hearing protections
• Cable protectors to be used while
crossing Toolbox talks to be conducted
before work starts.
• Provision of suitable respiratory
protective equipment, i.e. air fed face
shield or mask (with cartridge).
• Where necessary, work area shall
be enclosed to protect other
workers / vicinity or barriers shall
be erected around the work area
to prevent access.
Scaffold Erection Falling of Severe Personal injuries/ Fatality 5 5 25 H • A competent temporary works Temporary 5 2 10 L
materials Property Damage coordinator is to be appointed. work
Falling of • All temporary works must have a coordinator
personnel design and load calculation Supervisor,
prepared by competent structural Operator,
engineer Project
• All access equipment must be manager,
stable with sound footings, wheels Engineer
locked (where fitted) and tied into
the structure where specification
or design requires.

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 10 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• General and emergency access


routes must be clearly defined,
signed, barricaded, and lit paying
particular attention to emergency
routes.
• Access equipment must be
selected in accordance with the
working at height hierarchy.
• All equipment must be erected /
installed / altered/dismantled by a
competent person who is trained
in the use of the specific system or
equipment in line with the
manufacturers specifications.
• Exclusion zone to be made at the
area below the scaffold erection
to prevent un authorized entry. to
avoid unauthorized entry into the
area.
• While passing scaffold materials
from ground to each stages the
operative below should protect
himself from the risk of falling
component from top.
• Competent scaffolders to be used
to erect scaffold.
• Close supervision of the activity.
• Safe erection procedure to be
followed.
• Full body harness to be used and
attached to firm anchoring point,
ensure 100% tie off

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 11 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• The proposed area of scaffold


erection should be levelled and
compacted.
• Toe boards must rise at least 15
cm above platform level.
• Guardrails must be between 95
cm and 105 cm above platform
and there must be no vertical gaps
between any guardrails or toe
boards which exceeds 47 cm,
there must be no gaps below the
toe boards.
• Sole board of adequate strength
to be used with the scaffold. Do
not exceed the height of screw
jack more than 15 cm. (If using to
level the scaffold in uneven
ground.
• Adequate ties and bracing
supports shall be provided.
• Scaffold should be erected sound
component.
• Modification and alteration of the
structure shall be carried out by
competent scaffolder under
competent supervision.
• Couplers and accessories should
be standard and suitable to the
particular structure
Working on Working at Falling of men from height result in 5 5 25 H • Site survey to be conducted on Scaffold 5 2 10 L
Scaffolding Platform height severe injuries or even fatality. the work area to identify all inspector
Falling from holes, unprotected edges and any Temporary
heights works
other sources of fall.
coordinator
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 12 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

Scaffold • Ensure all working platform are Supervisor,


structure inspected and safe for use by Operator,
collapse designated scaffold inspector Project
Falling manager,
• NEOM daily activity briefing
materials/obje Engineer
cts conducted
• Obtain WAH permit system
• Ensure adequate material
management and housekeeping
at working platform
• All unprotected edges to be
provided with suitable edge
protection and signage.
• Users must be competent and
trained in the use of harnesses
including but not limited to daily
inspection, proper fitting, care,
and storage, maintaining 100%
tie-off whilst using two lanyards
and rescue procedures and
emergency arrangements.
• Fixed length restraint is preferred
to fall arrest.
• Implement proper fall protection.
• Personnel to be trained on safe
working at height requirements
and to be brief of the location
where fall might occur and the
hazard and risk involved.

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 13 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• Ensure provision of safe access


way.
• Ensure no energized systems /
power lines close to the working
area.
• All fall protections to be check
and inspected on daily basis. Fall
arrestors or double lanyard full
body harness to be used and
ensure proper tie off.
• Close Supervision is required.
• Edge Gaps to be covered with toe
boards
• No loose materials on the
platform.
• Tool tethering to be done ( Tools
to be secured with lanyard)..
• Area below the platform should
be protected from other workers
with exclusion zone.

Use of Skin burns, Exposure to chemical 5 4 20 H • Store the chemical in a cool, dry, Temporary 5 2 10 L
chemical/hazardous and well-ventilated area away works
material eye irritation, Improper handling and storage from direct sunlight and ignition coordinator
Supervisor,
sources.
Inhalation of fumes released during the Operator,
respiratory • Ensure containers are tightly
mixing and application. Project
issues due to sealed and clearly labelled manager,
contact with Splashing of chemical • Have spill containment kits Engineer
or inhalation
readily available on-site
of chemicals. Accidental ingestion

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 14 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

Chemical Working in poor ventilated areas. • Follow the manufacturer’s


spill, leaks or instructions for handling, mixing,
other and applying the chemicals.
environmental • Use dispensing tools designed for
contamination
the chemical to minimize direct
contact.
Respiratory
irritation. • Ensure adequate ventilation in
the work area to dissipate fumes.
Chemical • Personal protective equipment
burns (PPE)

Allergic
reactions
Cutting and Entanglement -Severe injuries/death 5 4 20 H • Activity briefing to be given to all the
demolition of existing in the - electric shocks, burns and death associated workforce
structures/block concrete - Injuries to eyes leading to blindness • Ensure power is off before starting
work/concrete cutter -Injuries/Death resulting from • Clear area of debris
machines running over personnel • secure loose clothing/hair
- flying objects
• Remove all jewelry
or cutting
• position cutter away from any power
wheels
source where ejected water may
-Dust from come into contact with electricity
demolished • Only Operatives with training and
concrete/slabs authorized to use cutting tools should
undertake the work
• Concrete PPE to be worn at all times
when using the cutter including
safety goggles and gloves
• make sure all machine guards are in
place
• Training and Supervision of personnel
• Work areas should be properly signed
and barricaded with fences
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 15 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• Portable Fire extinguishers to be


provided

Use of MEWP Operating Personal serious Injuries 5 4 20 H • All MEWP must be undergone for Manager 5 2 10 L
whilst Falling /suspension injury NEOM inspection and certified by Site Engineer
travelling Personnel Injury NEOM/AECOM team. Supervisor
Property Damage HSE Officer
Operative Fall • All operators required to be use
from height PFAS.
Drop Objects
(Tools and • Training to all operators on use of
materials) MEWP

• Designated banks/flagman required


Entrapment /
• 3rd Party trained operators, with
overhead
specific model familiarisation training
service &
is only permitted to operate.
Structure
• Equipment must be inspected by the
strike
operator prior to the task.
• Control of traffic and pedestrians to
be planned.
• Platform capacity must be checked to
ensure sufficient height and Safe
Working Load for the work
undertaken, including number of
men and materials.
• Travelling on the MEWP with
extended / raised platform to be
avoided.
• Beware of overhead obstructions.
• Premise of travelling should be
levelled ground.

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 16 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

• Man holes or floor openings, if any


should be protected/ covered with
materials of adequate strength.
• Thorough 3rd Party examination
& maintenance is required.
• The collapse zone is to be fenced
off.
• Platforms must not be operated
outside limits set by manufacturer.
• The operating area will be firm
and level.
• Stabilisers extended before the
platform is raised;
• Operatives should position
themselves inside the platform.
Overreaching and climbing on the
guardrails to be avoided.
• Full body harness to be used properly
with 100% tie off
• Tool Tethering to be done
• Overloading of materials on the
platform to be avoided.
• No loose materials on the
platform.
• Tools to be secured with lanyard.
• Below the platform should be
protected from other workers with
exclusion zone.
• Trained and experienced operator
with third party certificate.
• Proper planning of the work.
• • Maintain safe distance
from overhead structures while

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 17 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

moving the equipment and


platform.

Working in Extreme Heat, Rain, Personnel Injury 4 4 16 M • Weather to be monitored on Site Engineer 4 2 8 L
weather condition Strong wind Ill-health daily basis. Supervisor
and other • During summer or extreme heat, HSSE Officer
inclement frequent breaks to be
weather implemented.
• Provide cool shaded rest area.
• Provide continuous supply of cool
drinking water,
• Heat stress training to be given to
all.
• Rehydration drink to be provided.
• Work schedule and timings to
adopt the condition.
• Heavy and tiring activity to be
done on early part of the day.
• Implement work rotation, if
necessary, during hot condition.
• Follow mid-day break work rules.
• No external works to be done
during rain and strong winds.
• Make sure all materials and
structure are secured properly to
prevent being blown away.
• All FOD and waste to be
controlled and removed on daily
basis.
• All electrical cables / equipment
to be secured and protected
against water/rain.
• During foggy condition, work will
start/resume until condition is
Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 18 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

safe or fog is limited or given


approval by ABG.

Exposure to dust / Dust Ill-health 3 4 12 M • Daily dust and noise monitoring Site Engineer 3 2 6 L
noise Noise NIHL (Noise induced Hearing loss) to be implemented. Supervisor
Asthma • Appropriate dust control HSSE Officer
Lung disorders measures to be implemented
(e.g. dust suppression by making
the work area dampened down
with water)
• Appropriate noise protection to
be implemented.
• Provide appropriate PPE e.g. dust
mask & hearing protection/ear
plugs.
• All sources of noise and dust to
be contained at its source..
• Replace all noisy equipment with
less noise producing
equipment/tools.

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 19 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

Mediu
High Medium Low High Low
m
Mediu
High Medium Low High Low
m
Total Number of Initial Risks per level Total Number Final Risks per level recorded
Risk Assessment Level Summary: 9 6 0 0 0 15
recorded before controls - after controls -

Reviewed & Approved by :

HSE MANAGER MUHAMMED SHAHABAS

QA QC MANAGER SIMON JIDUGA

PROJECT MANAGER MOHAMMAD IMRAN KHAN

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment
Assessment Number: ABG-HSE-RA-061 Assessment Date: 14-05-2024 Revision Date: 15-05-2024 Page Number: 20 of 20
RISK INITIAL RISK FINAL
TASK STEP HAZARDS RISKS RATING RISK CONTROL MEASURES CONTROLLER RATING RISK
S L RR LEVEL S L RR LEVEL

RISK RATING AND ACTION LEGEND


SEVERITY (S) Risk Rating (RL) Action And Timescale
Work should not be started or continued until the risk has been reduced. If
RR1 = 25-36 =
1 2 3 4 5 6 INTOLERABLE it is not possible to reduce the risk even with unlimited resources, work has
Intolerable
to remain prohibited.
HIGH
Work should not be started until the risk has been reduced. Considerable
2 4 6 8 10 12 RR2 = 20-24 = High HIGH resources may have to be allocated to reduce the risk. Where the impact
involves work in progress, urgent action should be taken.
Where the impact is associated with extremely harmful consequences,
LIKELIHOOD (L)

RR3 = 15-18 = further assessment may be necessary to establish more precisely the
3 6 9 12 15 18 SUBSTANTIAL
Substantial likelihood of harm as a basis for determining the need for improved control
MEDIUM measures. A permit to work may have to be applied to achieve this.
Efforts should be made to reduce the risk, but the cost of prevention should
RR4 = 12 =
4 8 12 16 20 24 MODERATE be carefully measured and limited. Risk reduction measures should be
Moderate
implemented within a defined time period.
No additional control required. Consideration may be given to a more cost-
RR5 = 8-10 =
5 10 15 20 25 30 TOLERABLE effective solution or improvement that imposes no additional cost burden.
Tolerable
LOW Monitoring is required to ensure that the controls are maintained.
RR6 = 1-6 =
6 12 18 24 30 36 TRIVIAL No action is required and no documentary records needs to be kept.
Trivial

Notes : S=Severity of injury L= Likelihood of occurrence Risk Rating score (RR) = S x L RISK LEVEL = Resultant Risk Level being either High, Medium or Low.
HSSEF-018-REV-007-OCT-2021 - ABG Form 061 - Risk Assessment