Foundation Design 8 PDF Free
Foundation Design 8 PDF Free
Teaching notes
Foundations:
Shallow Foundations
Introduction. Foundation loading intensities. Bearing capacity, (ultimate, safe, gross and
allowable). Influence of ground water table, sloping ground, inclined and eccentric loads on
allowable bearing capacity. Design of shallow foundations for shear strength and settlements.
Examples of foundation design (e.g. strips, pad), combined footings, raft footings.
Piled Foundation
Types of piles driven and bored pile, friction and end bearing pile. Design of piles by soil
mechanics methods, end bearing, skin friction and ultimate bearing resistance. Piles in sands.
Piles in cohesive soils - total and effective stress analysis. Design from pile tests data.
End bearing piles on rock. Settlement of piles. Dynamic formula. Negative skin friction. Pile
groups - bearing capacity in cohesive and cohesionless soils.
Design of earth embankment - homogenous and zoned dams. Definitions e.g. fetch, water
spread, shell free board etc. Factors influencing site selection. Spillways. Settlements of
embankments. Protection of upstream and downstream slopes.
Site Investigations
Introduction, purpose of Site Investigation, organization of Site investigation for different types
of structures e.g. buildings, irrigation or water supply projects, highways and airport pavements,
etc. Methods of Investigation. Sampling. Borehole logs. Geophysical methods. Geotechnical
reports.
Syllabus ................................................................................................................................... i
Chapter one ................................................................................................................................ 1
Shallow foundations ................................................................................................................... 1
1.1 Types of foundations .................................................................................................. 1
1.2 Introduction to shallow foundations ........................................................................... 1
1.2 Bearing capacity of soils ............................................................................................ 2
1.2.1 Bearing capacity terms ......................................................................................... 2
1.2.2 Ultimate bearing capacity..................................................................................... 3
1.2.3 The net foundation pressure ............................................................................... 12
1.2.4 Allowable bearing pressure ................................................................................ 13
1.2.5 Field methods for the determination of bearing capacity of soils ...................... 14
1.2.6 Presumed bearing capacity of soils and rocks .................................................... 23
1.3 Proportioning of shallow foundations ...................................................................... 24
1.3.1 Contact pressure distribution .............................................................................. 24
1.3.1 Proportioning the foundations ............................................................................ 25
1.3.2 General consideration in the selection of the foundation depth ......................... 34
1.3.3 Foundations for common buildings.................................................................... 35
1.4 Foundations for difficult soils .................................................................................. 36
1.4.1 Foundations on expansive clays ......................................................................... 36
1.4.2 Foundations on loose sands ................................................................................ 41
1.5 Tutorial examples on chapter one ............................................................................ 43
Chapter two .............................................................................................................................. 45
Deep Foundations ..................................................................................................................... 45
2.1 Pile foundations ........................................................................................................ 45
2.1.1 Introduction ........................................................................................................ 45
2.1.2 Classification of Piles by materials and construction......................................... 46
2.1.3 Driven piles ........................................................................................................ 48
2.1.4 Bored piles.......................................................................................................... 51
2.1.5 Determination of pile load carrying capacity ..................................................... 53
2.1.6 Determination of load carrying capacity dynamic methods............................... 59
2.1.6 Determination of load carrying capacity pile testing ......................................... 61
2.1.7 Negative skin friction ......................................................................................... 62
Foundations that are encountered in practice may be classified into two broad categories
namely shallow and deep foundations. Under shallow foundations the following categories
are usually encountered:-
Under deep foundations the following two types of foundations are encountered :-
a) Piles
b) Caissons
The design and construction of deep foundations is dealt with in the next chapter.
In the selection of the foundations to adopt for a structure it is usually necessary to
consider the function of the structure, its loads, the subsurface conditions and the cost of the
foundation being adopted in comparison to other possible types of foundations.
The foundation is the part of the structure that transmits the loads directly to the underlying
soil. If the soil is sufficiently strong it is possible to use shallow foundation. On the other
hand if the soil is not strong enough the foundation is taken deeper into the ground and is
referred to as a deep foundation. A definition which sometimes conflicts with the definition
of the shallow foundation defines a shallow foundation as one whose depth is less or equal to
its least width. The foundation must satisfy two fundamental requirements:-
The damage being mitigated in the design of the structures can be classified as architectural,
functional or structural. In the case of framed structures settlement damage is usually
confined to the cladding and finishes (architectural damage). It is usual to expect a certain
amount of damage. What is critical is to ensure that the damage to the services is limited.
Angular distortion limits were proposed by Craig (1987) and are shown on Table 1.1. In
general the limiting angular distortion to prevent damage is 1/300. For individual footings
this translates to a maximum settlement of about 50mm in sand and 75mm in clay. An
accurate damage criterion is to limit the tensile strain at which the cracking occurs. The
concept of tensile strain should be used in analysis using an idealization of the structure and
the foundation in elastic strain analysis when the fundamental properties of the foundations
are known.
The design of the foundations is usually a two process exercise. The first is to determine the
allowable bearing of the soil while the second is to size the foundation on the design strata
based on the allowable bearing capacity. These two parts are now discussed.
Ultimate bearing capacity is the value of the average contact pressure between the foundation
and the soil which will produce shear failure in the soil.
The net foundation pressure is the increase in the pressure at the foundation level due to the
structure loads
The safe net foundation pressure is the net foundation pressure divided by a suitable factor of
safety
Allowable bearing pressure is the maximum allowable net loading intensity on the soil
allowing for both shear and settlement effects.
Pressure
a
Settlement
b) local shear failure
c
b
p γD
The vertical pressure is q which is a result of the structure loads. By use of Rankine active
pressure theory, a lateral pressure p holds the soil in equilibrium below the foundation. For
particles just beyond the edge of the foundation the lateral pressure is more than the vertical
pressure γD resulting from the overburden. The vertical pressure γD is the minor principle
stress and p is the principal stress. By use of the Rankine earth pressure theory Equations 1.1
through 1.3 can be deduced.
For a cohesionless soil the bearing capacity is dependent on the overburden and equals to
zero for a foundation on the ground surface. Bells development for a c-υ is given in Equation
1.4
For a purely υ =0 soil the ultimate bearing capacity is given by Equation 1.5
q D 4c 1. 5
q
D
O
πB
The foundation is assumed to fail by rotation about a slip surface of radius equal to the width
of the base B and at the edge of the foundation O. At ultimate conditions the disturbing
moment (Md) is given by Equation 1.6
Md q*L*B* B 1. 6
2
The resisting moment (Mr) about O is a summation of the resistance due to the cohesion on
the cylindrical surface, on the vertical surface and the weight of the overburden as given in
Equation 1.7
qf
qo
A B 45+φ/2
E F
45-φ/2
D C G
Using plastic theory the ultimate bearing capacity below a strip footing on a surface of a
weightless soil is given by Equation 1.9. This is for undrained condition where υu = 0
In general the foundation is located at a depth and imposes a surcharge qo = γD. The weight
of the surcharge and the pressure of the foundation produce stresses on the moving masses of
soil at plastic conditions.
The ultimate bearing capacity of the soil under shallow strip footing can be
expressed by the following general equation suggested by Terzaghi.
Nγ, Nc and Nq are bearing capacity factors which depend on the values of υ. Nγ
represents the contribution to the bearing capacity resulting from the self weight of the soil.
Nc is the contribution due to the constant component of the shear strength and Nq is the
contribution of the surcharge pressure. Values of Nγ, Nc and Nq can be obtained from
Equations 1.11 through 1.13 the values for Nc and Nq were suggested by Meyerhof (1955)
while the values of Nγ, were suggested by Hansen (1970) These values are plotted in terms of
υ in Figure 1. 5.
Nc (Nq 1)cot 1. 11
Nq tan2 (45/ 2)e tan 1. 12
N 1.5(Nq 1)tan 1. 13
Nq
100 Nγ
Values of Nc, Nq, Nγ
Nc
10
1
0 10 20 30 40
φ - Degrees
The factors for rectangular footing are an interpolation of the square and the strip footing and
are shown on Equation 1.16
It showed be noted that the values of the bearing capacity factors are very sensitive to the
values of shear strength parameters c and υ. Due consideration should therefore be given to
the degree of accuracy of these values. In general the following observations have been made
Skempton’s values of Nc
Skempton (1951) showed that for a cohesive soil (υ =0) the value of Nc increases with the
value of foundation depth D. He suggested that the values of Nc applicable to circular, square
and strip foundations are given in Figure 1.6. The value of the rectangular footings of
dimensions BxL (where B<L) is the value of a square footing multiplied by (0.84+0.16B/L).
10
8
Nc
7 Nc (Strip)
6 Nc (Circular or
Square)
5
4
0 1 2 3 4 5
D/B
B' B2eB 1. 17
L' L2eL 1. 18
In the case of inclined load (Figure 1.8) on a width B and inclination the effective
foundation width is B-2e. In addition the bearing capacity factors are multiplied by the
inclination factors shown on Equations 1.19 and 1.20
ic iq (1/90o )2 1. 19
i (1/)2 1. 20
1) The base of a long retaining wall is 3m wide and is 1m below the ground in front
of the retaining wall. The water table is well below the base level. The vertical
and horizontal components of the base are 282kN/m and 102kN/m respectively.
The eccentricity of the base reaction is 0.36m. The appropriate shear strength
parameters are c’= 0 and υ’ = 35o. The unit weight of soil is 18kN/m3.
1m 282kN/m
282kN/
102kN/m
1.14m .36m m1.5m
Solution
The angle of the inclination to the vertical α = tan -1 (102/282) = 20o hence the inclination
factors according to Meyerhof are
An alternative approach in the case of inclined loads is to use the empirical formula shown on
Equation 1.21
L’
Y
B’
B eB
X
eL
PV / Pav PH / Pah 1 1. 21
Where Pv is the vertical component of the inclined load and PH is the horizontal
component of the inclined load. Pva is the allowable vertical load and PHa is the horizontal
load (a fraction of the available passive resistance).
α P
Pv
PH
qnett q D 1. 22
For a strip footing the net foundation pressure is shown on equation 1.23
The safe net bearing pressure (qsafe) is the net bearing pressure factored by an appropriate
factor of safety as shown on Equation 1.24
qsafeqnett/ FOS 1. 24
For cohesive soils the value of υ is small and the term ɣsubBNɣ is of little account.
Consequently the bearing capacity is not affected by the ground water variation below the
foundation level. For sandy soils the term CNc is zero and the term 0.5γsubBNγ is about half
0.5γBNγ. The effect of the groundwater is significant.
considerations it is therefore not necessary to consider the weight of the foundation below the
ground level (Figure 1.9)
The plate bearing test results are best reported in graphical way as shown on Figure 1.10.
The weak soft clays and loose sands will reach the ultimate bearing capacity in the region of
100-200 kN/m2 while the stiffer clays and dense sands and gravels will continue increasing
in the bearing pressure with increasing settlement.
-2.5
Settlement (mm)
-5
-7.5
-12.5
-15
B
b
1.5b
1.5B
Weak stratum
Settlement of the stratum increases with increasing loaded area and the main
problem is in the extrapolation of the test results to full scale scenario. Ideally the plate test
should be carried out using plates of different sizes and at different depths. However, this is
usually not economical.
Notwithstanding this shortcomings the following procedure was been proposed by
Terzaghi and Peck (1948) and can be used as a guide to use of plate bearing test results. The
settlement of a square footing kept at a constant pressure increases as the footing size
increases. The relationship is shown on Equation 1.27 relates the settlement of the test plate
of 300 mm square and that of a square foundation of width B.
S S1 *(2B/(B0.3))2 1. 27
Where S1 = settlement of the loaded area under a 305mm plate for a given pressure
intensity p
S= the settlement of a square foundation of width B in metres under pressure p
In order to use the plate bearing results the maximum allowable settlement is determined. A
value of 25mm is generally accepted as an allowable settlement. S is then equated to 25 and
a numerical value of B is inserted in the formula to enable the determination of the S1. From
the relationship of p and s1 the value of p corresponding to the calculated value of S1 is the
allowable bearing pressure subject to any adjustments certain to the ground water conditions.
namely particle size analysis and Atterberg limits when the sample has some degree of
plasticity. When used in gravels the sampler is replaced with a 60 o cone which does not
sample the soil.
Figure 1.12 shows the main features of standard penetration test equipment. The
drive shoe and the sampler consist of 51 mm external diameter and 35 mm internal diameter.
It is 450-600 mm long. This is connected to a drive assembly at the bottom of the boring
rods. A pick and release mechanism which ensures a free fall of a hammer weigh 65
kilograms through of 760 mm + or – 20 mm is used to drive the sampler or the cone in the
case of the gravelly strata
The procedure requires that the borehole is cleaned carefully to ensure that disturbed soil at
the bottom of the borehole is removed. When boring below the ground water table it is
prudent to maintain the water in the borehole at the same level or higher than the general
ground water. A hydraulic balance is needed to avoid the risk of boiling of the strata at
bottom occasioned by a high hydraulic gradient.
The sampler and the hammer are lowered to the bottom of the borehole. If after
touching the bottom the sampler penetration exceeds 450 mm on its own weight and that of
the hammer, the SPT value also known as N value is recorded as zero. Otherwise after the
initial penetration on own weight the test is driven in two stages known as seating drive and
test drive
The seating drive is the initial 150mm penetration or 25 blows whichever is reached
first. The test drive is the further penetration of 300mm or 50 blows which ever is reached
first. The number of blows for the 300 mm penetration is recorded as the SPT value ‘N’. If
300 mm penetration can not be reached in 50 blows the test drive is terminated. In this case a
hard stratum has been encountered and further driving results in damage of the split sampler.
It is usual to record the blows for every 75 mm penetration. If the test drive is terminated the
penetration corresponding to 25 and 50 blows is recorded.
The relative density of a soil affects the N values. Terzaghi and Peck (1948) evolved a
qualitative relationship between the relative density and the standard penetration N values.
Gibbs and Hortz put values of relative density. Table 1.3 shows the two relationships
The effective stress at the level of the test also affects the penetration of the SPT split barrel
sampler. This effect can be related to the effective overburden at the level of the testing.
Craig (1986) has summarized the correction of the overburden into Equation 1.29.
N' CN N 1. 29
500
Standard penetration resistance increases with increasing particle size, increasing over-
consolidation ratio and increasing angle of internal friction of the soil. A correlation between
shear strength parameter and N, and effective overburden is shown on Figure 1. It provides
rough estimate of value of and should not be used for very shallow foundations.
50
40 φ=25
30 φ=30
SPT - N
φ=35
20
φ=40
10 φ=45
φ=50
0
0 50 100 150 200 250
Effective overburden (kN/m2)
Figure 1.13 Correlation between shear strength parameter φ and N and effective
overburden
Cw 0.50.5Dw /(D B) 1. 30
Where Dw= depth of the water table below the ground level and D
D =the depth of the foundation
B = the width of the foundation
-2.5
Penetration (mm)
-5
-7.5
-10
-12.5
-15
From the data the value of Nγ used in Terzaghi Equation for the Ultimate Bearing Capacity
can be estimated from Equation 1.31 the value of internal angle of friction can be obtained
from Figure 1.5 which then enables the determination Nq and the ultimate bearing capacity.
Other empirical values of qa can be obtained from equations 1.32 through 1.33
N qc /80 1. 31
qa qc / 30 for B< 1.2m 1. 32
qa qc /50*((B0.3)/ B)2 for B> 1.2m 1. 33
Bowles (1982) stated that the settlement is more often the concern than the bearing capacity.
Consequently most effort should be taken in the determination of modulus E and Poisson’s
ratio η so that an estimate of the settlement can be made. Alternatively he suggested that one
should use a large factor of safety on the unconfined compression strength of the intact
fragments obtained from the borings. The factor of safety should depend on the RQD and
typically range between 6and 10.
Tomlinson and Boorman (1986) reported the presumed bearing capacity must not
exceed half of the unconfined compression strength of the intact rock fragments. Ibi (1986)
reported presumed allowable bearing capacity values of various rocks varying from 12,500
kN/m2 for igneous and limestone rocks to as low as 150 kN/m2 for weak un-cemented
mudstones.
Rock strength designations based on the unconfined compressive strengths have
been suggested by BS 5930 (Ibi (1986) and the Canadian Geotechnical Society (Franklin and
Dussealt, 1989) are shown on Tables 1.4 and 1.5 respectively.
Very soft clays and expansive clays and silts Not applicable
Peat, organic soils, made up ground and fill areas Not applicable
Yielding foundation
The stiffness of such foundation is zero. Here the contact pressure distribution has the same
variation as that of the load. Because of its zero stiffness there will be no moments induced
in the footing. Such a condition exists in fresh concrete before it sets. It has no practical
significance.
Rigid foundations
Contrary to the yielding foundation the rigid foundation has infinity rigidity. They are so
rigid that they do not deflect. Most of the foundations considered in practice are rigid
foundations. The analysis is simple and leads to economical design of the footings.
Flexible foundations
The stiffness of such foundations lies between rigid and the yielding foundations. The
foundations in this category deflect to a certain degree depending on the magnitude of their
stiffness. The analysis of such foundations is complicated but leads to an economical design.
However this is not usually done in practice and is not considered in these notes.
The plan area of the foundations is determined assuming that all the forces are
transmitted to the soils without exceeding the allowable bearing pressure. The distribution of
the pressure is assumed to be planar. In no case should the extreme pressure be less than
zero. All parts of the foundation in contact with the soil should be included in the assessment
of the contact pressure. Subsequently the designer carries out the structural design of the
foundations. Typical foundations are now discussed
d) Pressure distribution
c) Combined foundation
Figure 1.17 Pressure distribution below individual and strip foundations under axial
load
Where
σ(x,y) = contact pressure at any given point (x, y)
P = the vertical load
x,y = coordinate of the point at which the contact pressure is calculated
My and Mx = the moment about y and x axis respectfully
Ix and Iy = moment of inertia of the footing area about the x and y axis respectively
=L*B3/12 and BL3/12 respectively.
y
L
P Mx and My
B y ex
Mx
ey x
ex
ex
My
When Equation 1.34 results in negative values in some areas, this means that the foundation
soil is taking tension. It is then necessary to change the dimensions to have only compression
pressure at the base. This is difficult and requires trial and error approach for solution of
maximum and minimum pressures. It is prudent to place the foundation such that that there
is only eccentricity in one axis direction as explained below.
q PBL(16e L) 1. 35
P P P
M M
L M
e LL
L L
e
When the eccentricity inside mid-third of the base (Figure 1.19a,e<l/6) the computed
minimum pressure is positive soil pressure and the computed maximum pressure should not
exceed the allowable bearing pressure. At e=l/6 Figure 1.19b the minimum soil pressure q=0
and the footing is fully effective in bearing. This limit of eccentricity means that as long as
the eccentricity is less than l/6 also described as falling within the mid-third of the foundation
the entire footing is effective. When the eccentricity is large (Figure 1.19c) and e>l/6 the
computed minimum pressure is negative soil pressure. This is an indication of a tensile stress
between the soil and footing. This in not feasible and the soil pressure has to be evaluated
neglecting any soil tension. The eccentricity is said to be outside mid-third.
For eccentricity outside middle third with respect one axis the maximum soil pressure
redistributes itself since the base cannot take negative pressure. The distribution of pressure
is triangular and is shown on Figure 1.20. The equations applicable in this case can be
derived as follows:-
L
L’
e=M/P L’/3
Solving the two equations to obtain the maximum soil pressure q, Equation 1. is obtained
q 2*P 1.36
3B(l / 2e)
It may not be possible to place columns at the centre of spread footings if they are near the
property line, near mechanical equipment or irregularly spaced columns. Columns located
off center will result in a non uniform soil pressure. In order to avoid the non uniform soil
pressure, an alternative is to enlarge the footing and place one or more of the columns in the
same footing to enable the center of gravity of the columns loads to coincide with the center
of the footing (Figure 1. . The assumption here is that the footing is rigid. The column loads
are taken as point loads and distributed into the footing. The footings are statically
determinate for any number of columns. The column loads are known and the resulting
pressure is shown in equation 1.37
q P/ A 1. 37
P1 P2
variable
S
b
a
X’
From Figure 1.22 the position of the centre of area of the footing is x’. The centre of the area
is to coincide with the center of gravity of the loads from the two or more columns being
supported by the trapezoidal footing. The position of the base cannot be extended beyond the
length dimension L. L is therefore a known dimension. The value of the area of the
foundation is obtained from the allowable bearing pressure and the total column loads (
A P/ qa ). . The area of the base is shown in Equation 1.38 and the position of the centre
of the area is shown in Equation 1.39. The solution to the two equations leads to unique
values of a and b representing the dimensions of the trapezoidal footing.
A a b L 1. 38
2
x1 L * 2a b 1. 39
3 a b
From Equation 1.39 and Figure 1.22 it can be seen that the solution for a=0 is a triangular
footing and for a=b it is a rectangle. The solution for a trapezoid footing exists only for
Lx1 L
3 2
R1 *S1 P1S
R1 P1 S1 1. 40
S
R2 P1 P2 R1 1. 41
L1 / 2 e x 1. 42
R1 B1 *L1 *qa and R2 B2 *L2 *qa 1. 43
S P2
P1
x e L2
L1/2
S1
R1 R2
a) The strap must be rigid (Istrap/Ifooting>2. This rigidity is necessary to avoid rotation of
the exterior footing.
b) The footing should be proportioned to approximately the same soil pressures and
avoidance of large differential settlements
c) The strap should be out of contact with the soil so that there are no soil reactions and
is weightless
A strap footing is to be considered only as a last option when other options would not work.
The extra labor involved in the forming of the deep beam and accompanying costs make it
only an attractive alternative when other options have been exhausted.
Raft foundations
A raft foundation is a large concrete slab used as a foundation of a several columns in several
lines. It may encompass the entire foundation area or only a portion. Raft foundations are
generally used to support storage tanks, several pieces of industrial equipment or high rise
buildings. Figure 1.24 shows some typical raft foundations
A raft foundation is used where the supporting soil has a low bearing capacity.
Traditionally the raft is adopted when pad and structural wall foundations cover over half the
area enclosed by the columns and the structural walls. However this should be evaluated on a
case by case basis since the raft foundations end up with negative moments and top and
bottom reinforcement. This arrangement could end up being more expensive than closely
spaced pads which require only bottom reinforcement.
(a (b (c
) ) )
(a) Flat slab; (b) Thickened under columns or beam slab (c) Basement walls as part of the raft or
cellular construction
The advantages of the raft foundations over the other foundations include:-
a) The effect of combining the column bases is increase in the bearing capacity of the
foundation. This is because the bearing capacity increases with the breadth of the
base.
b) The raft foundations bridge over the weak spots
c) They reduce settlement and are particularly suitable for structures sensitive to
settlement.
Raft foundations are usually designed as infinitely rigid in comparison to the supporting soil.
This assumption simplifies the pressure under the raft to a linearly distributed contact
pressure. The centroid of the contact pressure coincides with the line of action of the
resultant force of all the loads acting on the raft. Figure 1.25 shows the pressure distribution
and the resultant of the vertical loads.
σmin
σmax
A raft foundation is considered as rigid if the column spacing is less than 1.75/λ. λ is given by
Equation 1.44
Ks *b
1/ 4
1. 44
4*Ec *I
Bowles (1982) suggests that the coefficient of subgrade reaction be estimated from Equation
1.45.
Ks 40*F*qa 1. 45
Where F = the factor of safety applied to the ultimate bearing capacity
qa = the allowable bearing capacity
Equation 1.44 is applicable when the column loads do not vary in magnitude by more than
20%. The column loads should also be uniformly spaced. The design of the raft follows the
following basic steps
P*ey * y P*ex *x
(x,y) P 1. 46
A Ix Iy
It is conventional to obtain the pressures at the four corners and then interpolate in between to
enable the determination of moments and shears for the structural design of the raft
y My
P1 PP2 P3
2
ex ex ∑P
B
ey Mx x
P4 ey
P5 P6
P9
P7
P8 L
Once the geometry of the foundation of the foundation has been found, it is necessary to
determine an appropriate depth of the foundation. The following are general considerations
which the designers should take into consideration.
a) Usually the foundation should be placed below the depth with minimum moisture
variation over the years. This eliminates the shrinkage and collapse effects of the
foundation soil. In this country a depth of between 1.0 and 1.5 metres is usually
sufficient.
b) The foundation should be placed below top soil and below depths with roots of tress.
The roots are potential water paths which weaken the foundations.
c) The foundations should be sited with due consideration to existing nearby structures.
The exaction of the foundation in the vicinity of the existing structures could lead to
loss of lateral support of the neighboring structures.
d) Special attention should be taken to foundations supported on expansive soils and
those on loose sandy silts which are likely to be saturated during the lifetime of the
structure.
e) For water structures viz: - river bridges it is necessary to take extra care to ensure that
scouring of the foundation vicinity does not impair the safety of the foundation. It is
usual to use gabions in areas where scouring is likely to erode the foundations such as
downstream of box culverts and around abutments and pier foundations
f) It is preferable to place foundations at one level throughout. None the less if it is not
practical to have the foundations at one level, the change of level should be at one
plane. Sloping foundation levels should be completely avoided even if they are on
rock. There is a risk of the foundation sliding.
200-150 mm thick
masonry wall
100mm slab with BRC no 65 at the top
face
200-150 DPC
Damp proof membrane
The following are the general considerations in the usage of the standard footing.
a) No reinforcement is needed for strips where the load can be distributed through 45o.
b) The foundations should be excavated and the last 150mm excavation be finalized
when the concreting can be done without further delay. This minimizes the softening
of the foundation
c) The mass concrete is in mass concrete usually by volume batching to achieve grade
15 concrete. A ratio of 1:3:6 for cement sand and ballast respectively is generally
sufficient.
d) Reinforced concrete foundations are done for areas with concentrated loads. These are
usually column supports. Grade 25 concrete is the lowest class of concrete allowed in
the new BS 8110, but grade 20 of concrete can be considered.
a) Moisture control
b) Soil stabilization
c) Structural measures
Moisture control
The main course of heave and shrinkage is the fluctuations of moisture under and around the
structures in question. Depending on the topographical, geological and weather conditions
the natural ground water fluctuates during the year. This seasonal fluctuation decreases with
depth. In some areas the depth to the fluation zone is as low as 1.5 meters. In other areas it
will be deeper going down to over three meters. In addition to the ground water fluctuation
the surface water from rains or bust pipes seeps into the foundations and course moisture
migration.
A satisfactory solution to the problem would to devise an economical way of
stabilizing the soil moisture under and around the structure. It does not matter whether the
moisture is maintained high or low in so far as it can be maintained throughout the year. An
effective procedure of achieving this is to provide a water tight apron of approximately one
metre round the building. A subsurface drain one metre round the building is provided with
augur holes provided at every 2 meters. The holes are filled with sand and interconnected at
the top. In effect the augur drain is and the impervious apron ensures that the moisture at the
foundation area remains the same. Figure 1. 28 shows such an arrangement of the drains for
ensures that the moisture content of the foundations remain the same
The subsurface drain is used to intercept the gravity flow, or; perched water of free
water to lower ground. It also arrests capillary moisture water movement. The subsurface
drain should be lend to a positive outlet. In general the ground surface around the building
should be graded so that surface water will flow away from the building foundations all h the
time.
Expansive soil
Soil stabilization
Soil stabilization consists of one of the following operations
(a) Pre-wetting or flooding the in-situ soil to achieve swelling prior to construction.
(b) Compaction control
(c) Soil replacement
(d) Chemical stabilization
Pre-wetting or flooding the in-situ soil to achieve swelling prior to construction involves the
flooding of the site under consideration prior to construction. The soil would heave and the
potential danger of cracking is eliminated. Pre-wetting has been used with success when the
active zones are not large. It is very difficult to saturate high plasticity clays. There is danger
that expansion of the clays could continue after the construction has taken place. This
procedure should be considered for stabilizing pavement or canal linings. In only rare cases
should the method be considered for use below ground floor slabs. Its application below
building foundations is risky and questionable.
Compaction control has been used in pavement construction. Expansive clays expand very
little when compacted at low densities and high moisture contents. But will expand
considerably when compacted to high densities at low moisture contents. The approach is to
compact swelling clays at moisture contents slightly above their natural moisture content for
good result. In this method it is not necessary to introduce large amounts of water into the
soil. Dry compaction of expansive soils was done along the Lodwar-Kakuma road.
Soil replacement is the simplest an easiest solution for slabs and footings founded on
expansive soils. The expansive foundation soils are replaced with non-heaving materials.
The method requires the selection of the replacement material and the depth to replacement.
In Nairobi the depth of the expansive black cotton soils is in the region of 1.0 to 1.5 metres.
In this case it has been found desirable to remove the entire expansive soil below buildings
and replace with suitable granular material. When the expansive soil is deeper building slabs
can be constructed above the compacted soil covering the expansive soil but the foundation
of main structure needs further consideration.
This method is particularly useful for the construction of highway pavement in a site
completely overlaid with expansive soils where the alternative to reroute the road is not
viable. In this case it the lower expansive soils are overlaid with the compacted replaced
material to a depth of 1.5 metres.
Chemical stabilization is the process of mixing additives like cement and lime to expansive
soil to alter its chemical structure and in the process retard its potential expansiveness. Lime
reduces the plasticity of the soil and hence its swelling potential. The amounts used range
from two to eight percent by weight. Cement on the other hand reduces the liquid limit,
plasticity and potential volume change. Stabilization has been used mainly in highway and
airport construction.
Structural measures include several methods have been reported in literature such methods
include
kN/m2. This magnitude is small considering that the swell pressure of the expansive soils
commonly found in Kenya has been estimated at between 300 and 500 kN/m2. Results of
such an approach have been mixed where they have been tried. This method needs further
research.
Reinforcement of brick walls have been tried in South Africa. In this method reinforcement is
placed in brick walls. The reinforcement is placed where cracking usually takes place. This
is typically above and below openings. The structure is made also semi flexible by providing
joints in the brickwork so that when heave takes place the building will conform to the new
ground shape and consequently reduce the bending moment induced in the walls. The joints
are typically 1.5cm.
Foundation on piles is a very successful procedure which ignores the heave by placing the
footing to a sufficient depth (Figure ). The depth of the pile should leave an expansion zone
between the ground and the building to allow the soil to swell without causing detrimental
effect to the building. One way of installing the piles is to provide a pile with bell at the
bottom. The bell or under reamed section should be well below the active zone. The bell is
installed with special equipment and anchors the pile into the ground. The pile can be
installed in an oversize shaft which is subsequently filled with straw saw dust as filler to
eliminate uplifting of the pile by heaving soil. Alternatively the pile could be a straight and
the effect of the uplift calculated using Equation 1.47 The friction below the active zone is
utilized in the calculation of the bearing capacity of the pile.
1. 47
Beam Beam
Stable Active zone
Uplift
Uplift
h
Active
zone
friction
friction
Skin
Skin
h1
Stable
zone
zone
Straight pile Under ream
pile
Figure 1. 29 Pile systems for expansive soils
The third type of the buildings was the staff residential bungalows. These were
constructed with a ground beam and masonry walls. The roof of the buildings was a concrete
slab. However as the rains came and went in there stormy characteristics the residential
houses developed cracks in the walls. The cracks were particularly severe in the external
walls and after about 10 years of service and needed attention (Plate 1.1
Based on the satisfactory behavior of the framed structures it was found prudent to
introduce columns at the masonry wall corners in a repair scheme. Plate … It is therefore
recommended for foundations on loose sands the masonry should be reinforced with columns
at the corners. In addition the foundations should be kept as far as is possible free from
percolating water. In this way the in the event of settlement the frame will be able to absolve
the stressed attributable to additional settlement and reduce the severity of the cracks.
1) A footing 2.25 m square is located at a depth of 1.5m. The strength parameters are c’= 0
and υ’ = 38o. Determine the ultimate bearing capacity
Given that the unit weight of sand above the water is 18 kN/m3. The saturated
unit weight of soil is 20kN/m3.
4) You are responsible for the design of a combined footing to support two columns
as shown in the figure below. The vertical dead loads on column A and B are 500
and 1400KN respectively. The design requires that the resultant of the column
loads acts through the centroid of the footing. In addition the dead loads, columns
A and B also can carry vertical live loads of up to 800 and 1200 KN respectively.
The live loads vary with time, and thus may be present some days and absent
other days. In addition the live load on each column is independent of that on the
other column. Check that the design meets all eccentricity requirements if the
worst possible combination of live loads is imposed
5) A column is carrying a load of 1200kN. The column is located 300mm form the
boundary of wall. Calculate the pressure distribution if the column is founded on a
square base of 1500mm x1500mm. is the foundation safe if the allowable bearing
pressure is estimated at 300kN/m2
7) Your client acquires the next plot and you are not limited by the boundary wall.
Calculate the safe bearing pressure below the columns described in questions 1 and 2.
Assume a detailed site investigation has established the following strength parameters.
4 Four columns are carrying a tower. If the columns are on a square grid of
2.5mssquare, calculate the pressure at each of the four column positions if a raft
foundation of 3 mmx3m is designed to carry the foundation loads estimated at
4000kN, 5000kN, 6000kN and 7000kN
Deep foundation can be categorized into three major types. These include
i. Pile foundations
ii. Drilled piers
iii. Caisson foundations.
The ground and structural conditions which require the use of the two types are discussed
under each of the sections dealing with the two types of the foundations.
2.1.1 Introduction
Pile foundations are structural members used to transmit surface loads to lower levels in the
soil mass. They are used when soil beneath the level at an appropriate raft or conventional
footing is too weak or too compressible to provide adequate support to the structure load.
The piles have small cross-section area compared to their lengths. The pile materials
generally include timber, steel or concrete. The transfer is by vertical distribution of load
along the pile surface and at the pile end point.
f) In structures which have considerable uplift, horizontal and/or inclined forces. This is
especially true for marine and harbor works.
g) To increase the bearing capacity by vibration and compaction of granular layers of
soil.
h) In soils where deep excavations would result in damage of existing buildings.
Piles can be distinguished by the function they are intended to perform or by the material and
construction procedures used in their construction. The various types of piles by function are
shown on Figure 2.1. The main function of the piles is to take the loads by end bearing or by
friction or by combination of the two. Other functions exist and two which can be sited here
include tension piles and fender piles. The tension piles take lateral forces in place of
traditional retaining walls while fender piles also referred to as dolphin piles are marine
structures principally for taking horizontal loads from vessels in the docking areas. Section
2.2 is presentation of piles by their material and construction procedures.
Soft soil
Friction
Firm
resistance
strata
Hard
strata
Tension resistance
b) RC d) Cast in-situ
a) H and c) Shell
Precast pile tube withdrawn e) Bored pile
pipe piles Pile
Timber Piles
Timber piles are made of trunks of timber. The timber should be preserved to prevent decay.
Untreated timber embedded below the ground water table has a long life. If the timber is
exposed to alternating wetting and drying it is subject to decay. These types of piles are not
very common.
Steel Piles
Steel piles (Figure 2.2a) are usually in form of H-Piles and pipe piles. H piles are preferred
where high depth is required while the pipe piles are usually filled with concrete after driving.
In the case of H-Piles the flanges and the web are equal thickness in order to
withstand large impact forces. Steel H piles penetrate the ground more readily than other pile
types because of the relatively small cross-section area. They are subsequently used to reach
stronger bearing stratum at great depth. Steel H piles have also relatively large bearing
capacity of between 500 and 2,000 kN per pile depending on the size of the H section. The
pile H sections are usually 250x250 to 350x350 with varying section thickness.
Pipe piles are of the range of 250mm to 750 mm diameter. The wall thickness is
usually over 2.54mm. In the event that the wall thickness is less than 4.54mm the pile has to
driven with a mandrel. When the thickness of wall is over 2.5mm the pipe acts with any
concrete in carrying the load. Pipe piles are usually driven with the lower end closed with a
plate. In some instances conical driving shoes have been attached. The advantage is not
significant.
Steel piles are subjected to corrosion. The corrosion is minimal when the entire pile
is embedded in natural soil. However, the corrosion can significantly increase in the event of
entrapped oxygen. Zones of water table variation are particularly vulnerable. Severe attacks
are encountered on sea structural sections exposed to high and low water tides where the salt
sprays can significantly cause corrosion. The standard practice is to use piles which have a
factory applied epoxy coating. The most vulnerable sections of the piles should be encased in
concrete.
Hard driving and driving through obstructions causes the piles to twist and bend.
They can easily go out of plumb without the piling team recognizing since the depth is at
depth. Deviations from the vertical of below 10% are usually accepted. A penetration of 2 to
2.5mm per blow should be considered as refusal and further driving would generally cause
deterioration.
a) Handling of the preformed sections which could lead to damage of the piles before
installation.
b) Noise arising from the hammer dropping on to the pile. This can be particularly
undesirable in sites in the busy neighborhoods.
c) Spoiling of the pile in the driving operations include the spoiling of pile heads and or
pile toes. This usually takes place due to overdriving piles when refusal has been
reached. It is usually sufficient to achieve a penetration of 2-2.5 mm per blow in the
last stages of piling.
d) Piles of small cross-section especially H piles driven in boulderly strata could easily
alignment. Vertical piles could end up having bent up shapes and hence lose their
carrying capacity.
a) With casing
i. Poor base preparation after the bearing strata has been reached. Loose particles will
have reached the bottom of the bore and will be difficult to detect or remove. The
base the pile will consequently have a lower bearing capacity than would have been
expected
ii. Poor concreting control where the pile is being cast under artesian conditions. This
usually results from poor shaft control as the concreting continues. The result is
necking of the concrete and/or washout of various sections of the pile. Under ideal
conditions the concreter under tremie conditions should always be placed inside the
wet concrete.
iii. Vibration and movement of the ground in the vicinity of the pile under construction.
It is to be noted that these difficulties are also present in the driven cast in place piles where
the casing is withdrawn as concreting proceeds
Where
= Ultimate Load carrying capacity of the pile
Ultimate Load carrying capacity of the base of the pile
= Ultimate Load carrying capacity of the pile side friction
2. 1
Where
Ab= Area of the pile at the toe of the pile
qf = Ultimate bearing capacity at the toe of the pile
= Surface area of the pile shaft
= Ultimate shearing resistance of the shaft of the pile generally referred to as the
shaft friction
An appropriate factor of safety is applied to the ultimate load. It is prudent to apply different
values for the base and the side friction. This is primarily because the movement needed to
mobilize the friction resistance is much less than the movement needed to mobilize the base
resistance. Initially as the pile is loaded the load is taken by the side friction and as load is
increased the base takes more load. At failure the proportion of load supported by friction
may actually decrease slightly due to plastic flow of the soil near the base of the pile.
Equation 2.2 shows the allowable load when allowing for a factor of safety of 2 and 3 for side
friction and base resistance respectively.
2.2
Qs
Qb
2. 3
Where
= bearing capacity factor which is usually taken as 9.0
= undisturbed un-drained shear strength of the soil at the base of the pile
= the cross section area of the pile at the base
In the case of driven piles the clay adjacent to the pile is displaced both laterally and
vertically. Upward movement of the clay results in heave of the ground around the pile and
can cause reduction of the bearing capacity of the pile. The clay in the vicinity of the pile is
completely remolded during driving. Excess pore water pressures are set up during driving.
This pore pressure dissipates in a few months and in any case before significant load is
applied to the pile
In the case of bored pile, the clay area around the pile will be remolded. Additionally
as the water seeps towards the created borehole their softening of the soil in the vicinity of
the pile. Water can also be absolved from the wet concrete when it comes in contact with the
clay. The upshot of this is and subsequent reduction of the pile bearing capacity.
Side resistance is based on the friction mobilized on the surface of the pile. Equation 2.4 and
2.5 shows the estimation of the side friction
̅̅̅ 2. 4
̅̅̅ 2. 5
Where
= adhesion factor between the pile and the soil
̅̅̅ = the average undisturbed shear strength of soil adjoining the pile
= the shaft area which contributes to the friction resistance
Most of the load of a pile installed in a clay soil is derived from the shaft friction and the
problem usually revolves accurate determination of the value of α. For soft clays driving of
piles tend to increase strength around the pile. A value of α equal to 1 can be used. It is
however unlikely that the soil will not in the long run return to its original soft status after
some time. In over-consolidated clays the value varies from 0.3 to 0.6 (Smith and Smith,
1998). A value of 0.45 is usually used for design purposes.
An alternative is approach is to express skin friction in terms of effective stress. The
rationale of this approach is that the area of disturbance during pile installation is relatively
small. The excess pore water pressure induced in the installation process dissipates ahead of
the application of load.
̅̅̅ ́ 2. 6
Where
Ks = the average coefficient of earth pressure and
̅̅̅ = the average effective overburden pressure adjacent to the pile shaft
́ = the angle of internal friction of the remolded clay. The cohesion intercept of
remolded clay in an drained triaxial test being zero.
Cohesionless soils
Base resistance: The ultimate bearing load carried by a pile depends mainly on the relative
density of the sand in which it is driven. The ultimate bearing capacity at the base of the pile
is given by
Where
= The bearing capacity coefficient.
̀ = The effective overburden pressure at the base of the pile
It is to be noted that the bearing capacity attributable to Nγ usually ignored in pile design as
the value of B is usually small. The values suggested by Berezantzv et al (1961) are often
used and are shown on Figure
100
Value of Nq
Nq
10
25 35 45
φ in Degrees
Side friction: Meyerhof (1959) suggested the average value of friction to be estimated from
Equation 2.6. As can be seen from the Equation the value of fs continues to increase as the
effective overburden increase. However field tests have shown that the maximum value of fs
occurs when the embedded length of the pile is between ten and twenty diameters. In practice
a maximum value of 100 kN/m2 of fs is taken.
̅̅̅ 2. 7
̀ ̅̅̅ 2.8
Equation 2.8 shows the allowable load when allowing for a factor of safety of 2 and 3 for
side friction and base resistance respectively.
̀ ̅̅̅̅
2.9
Cr (kN/m2)
Depth (m)
Estimated depth
of the pile
3d
Table 2.3 Skin friction (fs) values from Dutch cone test results
Type of pile fs kN/m2
Driven piles in dense sand ̅̅̅
Where
̅̅̅ is the cone resistance along the embedded length of the pile
The allowable bearing load of the pile as before based on the Dutch Cone Test results is
given by Equation 2.9
2.10
2. 11
Where
M = the mass of the hammer
g = the acceleration of the hammer
h = the drop the hammer
R = the pile capacity
S = the settlement of the hammer as result of the drop h
In practice the above Equation has been modified to take account of several losses which take
place during the driving process. The main losses of energy occur as a result of sound, heat,
friction, quake, losses associated with elastic behavior of the pile and those associated with
the pile head compression. The net energy is equated to the work done in penetrating the
ground by the pile. Figure 2.9 shows the sequence of the pile driving and the
Wh
e fW
h efeivWh
h
(sso+ses)
(sso)
(ses)
b) Penetration of pile upon falling of hammer on to a driven pile
The potential energy of the hammer is Wh. Upon contact with the pile the available energy to
drive the pile into the ground is ef.eiv.Wh, where ef is the efficiency upon falling and eiv is
the efficiency upon impact. The penetration of the pile as shown on Figure 2.9b can be
shown to result in permanent ;penetration attributable to the pile and soil spp aand sso. In
addition there will be elastic penetration sep and ses attributable to the pile and soil
respectively. The work done and the pile resistance equation can now be rewritten as shown
on Equation 2.11.
2. 12
Equation 2.10 is known as Hiley formula. In the field the final stages of the pile are
monitored and recorded as can be seen on
Figure 2.10. It is usual to drive the piles to a minimum set of 2.5mm. Harder driving only
goes to damage the toe of the pile and could reduce the pile capacity in the process. Pile
driving formulas should be used in the piles driven in sand and gravel and in any case should
be calibrated with a load test.
Elastic comp = c3
Elastic comp = c2
set = s1 set = s2
Kenteledge
Kentledge
Support Jack Existing ground level
Test pile
Test pile
Tension pile
Tension pile
If the test pile is a purely test pile ahead of the main installation of the pile the maximum load
to be applied is equal to two and half times the estimated safe carrying capacity of the pile.
It is usual to load the pile to 1.5 times the design allowable pile load when a working pile is
tested for ascertaining the integrity of the piles installed.
In this method the load is applied by a constant rate of penetration by a jack in order to
maintain a constant penetration rate (Figure 2.11b). it is usual to maintain penetration rates
of 1.5mm per minute and 0.75mm per minute in the case of sands and clays respectively.
Interpretation of test results
The results are plotted on a load settlement curve as shown on Figure 2.12. In the two
procedures ultimate pile load is taken as the load which achieves a settlement equal to 10
percent the diameter of the pile as is seen in test pile a Figure 2.11b. (BS 8004). The ultimate
pile load could also be reached when the shear failure of the pile soil interface or the pile toe
occurs (Figure 2.12b). The allowable pile load is obtained by dividing the ultimate load by
an appropriate factor of safety. The factor of safety usually ranges from 1.3 to 2.0
Load
Load
Time
Settlement
Settlement
Ultimate a
load (a)
Ultimate b
load (b)
Penetration =
Load
Penetration
b) Constant rate penetration test results
mud etc settles on account of consolidation which may be initiated by ground water lowering
or increase in overburden pressure.
As clay layer settles, piles are dragged into the soil by the consolidating soil and the
overburden soil. The direction of the friction is reversed increases the load on the pile. The
friction generated on the perimeter of the pile due to this dragging is carried by the column
instead of assisting in carrying he pile load. The effect is to reduce the carrying capacity of
the pile. This is the phenomenon known as negative skin friction
Figure 2.13. The negative skin friction may be estimated from Equation 212 for
single piles and Equation2. For group piles
Length of settling soil=l
l-fill
Fill
Compressible clay
l-clay
Where
= the ultimate force generated by the negative friction
= the shearing resistance of the soil
= length embedded above the bottom of the compressible layer
= the pile diameter
= the coefficient of earth pressure at rest
= angle of shearing resistance in terms of effective stress
̅ = average effective overburden pressure
12 – Pile
Figure 2.14 Typical arrangement of pile groups
For piles in sand, the group action is complicated by dilatancy and densification
characteristics of the sand. When the spacing of the piles is less than eight times the pile
diameter, group action takes place (Department of Navy, Naval Facilities Engineering
Command, 1982). In dense sand the effect of driving piles is to loosen the sand and hence
the angle of internal friction of the sand in the vicinity of the piles. This results in overall
reduction of the pile bearing capacity. The group efficiency factor is less than one. In loose
sand the effect of driving piles is to increase the density of the sand. The bearing capacity of
the loose sand will therefore be increased. In this case the efficiency factor is more than one.
An efficiency factor of 1.2 is often used. In the case of bored piles in sand the resulting
loosening of sand in the boring operation results in efficiency factors less than 2/3. The
difficulties in the quantification of the design parameters of either loosened or densified sand
strata in piling operations remains a real problem for engineers (Mwea, 1984). Nonetheless
experimental evidence has it that the piles at the centre of a group in sand carry more load
than the piles on the periphery.
For piles in clay the effect of the pile group is to reduce the bearing capacity of the
pile group. This is because the effect of placing piles in a group is to have one large block
taking friction on the sides and base resistance over the block base. The spacing of piles in
clay is of the order of two times the pile diameter to four times the diameter. The efficiency
of the groups range from 0.6 to unity as the pile spacing increases from two diameters to four
diameters. The ultimate load in the case of a pile group is given by Equation 2.13. In the
case where the pile cap rests on the ground the ultimate load should be taken as the less of the
block capacity or the sum of the individual piles on the group.
2. 14
Whitker (1957) in a series of model tests showed that block failure as a group in clays occurs
when the spacing of the piles is not more than 1.5d apart. General practice is however to
space the piles at between 2 and 3d. In such cases the efficiency of the group is
approximately 0.7.
Settlement of groups
The settlement o a group of piles can be estimated by assuming that the entire load acts at a
depth as an equivalent raft. In clays the raft is assumed to be located at a depth of 2/3 D
where D is the depth of the pile group. The load is at spread of 1:4 from the underside of the
pile cap to allow for friction transfer. After the assumed depth of the raft the load is
distributed at a spread of 1:2 (Error! Reference source not found.a). Immediate settlement
and consolidation settlement can then be estimated for the layers of soil below 2/3D by
application of normal methods.
For groups in sand the equivalent raft is at a depth of 2/3Db from depth 2/3D. The
spread from the perimeter of the piles is 1:4 followed by a spread of 1:2 Error! Reference
source not found.b). The settlement of the underlying sand stratum is then gotten from
application of standard penetration data and or the cone penetration resistance
Db 1:4 2/3Db
1:2
University of Nairobi –FCE 511 Geotechnical Engineering IV
- 66- Deep Foundations
i. The soil contains large boulders which would otherwise obstruct the penetration of
piles and or construction of cast in place piles.
ii. A massive substructure is needed to extend below the river bend to provide resistance
against floating objects and scour.
iii. Foundation is subjected to very large lateral forces.
i. Open caissons
ii. Pneumatic caissons
iii. Box caissons or floating caissons
Open caissons
An open caisson essentially consists of a box open at the top and bottom ( Figure 2.16). the
soil is removed from the caisson by grabbing, dredging from inside the caisson. The sinking
of the caisson proceeds by the caissons self weight assisted by cutting edges of the walls.
When the desired level has been reached concrete is poured under onto the base of the
caisson by tremie pipe. In some cases the caisson has been pumped out. But in most of the
cases the caisson has been left in place. The bearing capacity of the soil below is usually
determined by normal bearing equations.
The concrete seal at the bottom is placed as a plug at the bottom of the caisson but
later serves as a permanent base of the caisson. Its thickness can be obtained from the
equations below
Where
= thickness of the seal
σo = contact pressure or hydrostatic pressure
R = radius of the caisson in the case of circular caisson
fc = the allowable concrete stress in tension (0.1 to 0.2cube strength)
b= width or the short side of the caisson in the case of a rectangular caisson
l= length or the long side of the caisson in the case of a rectangular caisson
β = coefficient which depends on the l/b ratio
Water level
Ground surface
Cutting edge
Box caisson
Circular open caisson
Figure 2.16 Open Caissons
Pneumatic caissons
Pneumatic caissons provide an airtight enclosure (Figure 2.17). In effect water is prevented
from getting into the enclosure and the workers can excavate and pour concrete under dry
conditions. The reliability of the quality in this case is better in so the mechanical ventilation
is carried out to the strictest of the specifications. Pneumatic caissons are costly and should
be considered only with the following conditions in mind:
When the excavation has reached the desired stratum the concrete is sent down to the
working chamber carefully to fill any weak points on the exposed strata. After this initial
filling the area is filled except a small portion of the chamber below the roof of the chamber.
This final portion is filled with grout which also fills any spaces which might have been left
behind during the concreting.
The seal design and estimation of the bearing capacity is the same as that of the open
caissons
Compressed air in
working chamber
Figure 2.17 Pneumatic caissons
Box caissons
Open caissons are usually cast on the ground and then towed to the site. They area then
lowered to a prepared ground. They are carefully aligned on place and then made stable by
placement of ballast. The design and construction of box caissons do not bring any new
design requirements. The ground upon which the caisson is being laid needs to have been
exhaustively investigated to ascertain the foundation depth and any likely difficulties likely to
be encountered. After the caisson is in place it may be filled with either sand concrete or
sand. The caisson should be checked against stability as it is floated to the final place of the
intended foundation.
Design of caissons
The caissons will be designed to resist vertical loads including superstructures, own weight
minus buoyancy forces. The lateral forces will typically include forces due to wind,
earthquake, earth and water pressures, and traction from traffic and pressure from current
flow.
The forces acting on a caisson must be estimated as accurately as can be to enable a
safe design. There are many methods adopted by various geotechnical engineers but the for
stability of the caisson the following combination of forces will suffice
It has been found out that analysis of the caisson in a direction transverse to the direction of
the axis is more critical. From Figure ***-* the three equations of static equilibrium are
solved. This are
W = Base reaction + skin friction
Q = Passive pressure created on BF – Passive pressure on DE – Base friction
Q (H+D) = Moment of all the forces
Q Q
From structural
analyses h
From geotechnical D
analyses
From structural Q
analysis W H
A
From D
geotechnical F
analysis
D1
O E B C
γD(Kp-Ka) γD(Kp-Ka)
Moments about O:
Qmax (H+D)=1/2 γD2 (Kp-Ka)D*1/3- ½*2* D (Kp-Ka)*D*D1*1/3
Therefore D1 and Qmax can be calculated and necessary adjustments of the caisson are
made depending on values of Kp and Ka
a) An equation for the estimation of pile working load if the pile is to terminate
in the sand zone.
b) An equation for the estimation of the pile working load if the pile is to
terminate in the clay zone.
2) A precast reinforced concrete pile measured 450mm x450mm. The pile was driven to
a depth of 15 metres to a set of 3mm by a drop hammer of 2.5 tones freely through 1.5
metres. The piling arrangement was changed to have a 4.2 tone hammer falling
through 2 metres. Assuming the same resistance with the new hammer, determine the
set achieved if the following information is also available.
3) A pile under test has started showing considerable settlement under load of seventy
tones. The pile diameter is 500mm and a length of 8.5metres in stiff clay. Assuming
below the 8.5metres the clay was soft clay and did not contribute to any resistance
evaluate the magnitude of the unit shear along its skin. (Answer 10.5tones per m2).
4) A 500mm diameter bored pile is to be made in stiff clay to a depth of 20metres. The
un-drained strength of the clay varies with depth as shown in the following table
Depth 4 6 8 142 16 20 24
2
Cu (kN/m ) 78 86 102 132 157 184 212
Determine the maximum load that may be applied to the pile. The following factors
may be taken.
(Answer 1025kN).
3.1 Introduction
Advances in geotechnical engineering have enabled design and construction of high dams
impounding large amounts of water. The design and construction follows well documented
procedures gained over the last years from design construction and monitoring of both
successful and unsuccessful projects. The procedures now taken include
The design and construction techniques covered in this chapter are applicable to all dams.
However the design and construction of small dams in Kenya is well covered in the manual
prepared by Ministry of Water (1985). Small dams are those whose height does not exceed
15 metres and or its impounded volume does not exceed one million cubic meters (Bureau of
reclamation 1985). The procedures covered in this chapter are inappropriate for the design
and construction of dam materials presenting the followings characteristics
These conditions require specialized testing and analysis of the presenting conditions in order
to arrive at an appropriate design
As with all dams the diaphragm dam should be designed and constructed with care
and precision. All internal diaphragms whether made of rigid materials like concrete or even
compacted earth have potential of cracking caused by differential movement of induced
during consolidation of the dam embankment materials, fluctuating water levels or settling
foundations. Internal concrete diaphragms can not be readily inspected. Earth diaphragms
on the surface require protection with filters, protection against erosion and wave action.
These types of diaphragms are unusually protected by rock fill and rock riprap. The earth
diaphragm is also not readily inspected during routine or emergency inspections. The earth
diaphragms are usually protected from internal erosion by filters usually in the form of
geotextiles.
If most of the material in a diaphragm dam is rock, then this type of dam is referred to
as a rock dam discussed below.
Zoned types
In this dams, a central core is of impervious material is franked by more pervious materials.
The design of these dams requires that the permeability of dam embankment materials
increases from the core to the outside franking shells. The materials enclose support and
protect an internal impervious core. The upstream sections provide stability during rapid
drawdown. The downstream pervious materials act as drainage to control the line of seepage.
It is usual to place a filter material between the impervious material and the downstream
pervious materials.
The impervious inner layers are basically clays typically the red coffee soils. The
pervious layers are sands, gravels, cobbles, boulders and rocks. If a variety of soils are
available the type of dam of choice is the zoned dam (Bureau of reclamation 1985). It has
inherent advantages of stability and reduced seepage across the dam wall.
i) The embankment, foundation, abutments, and reservoir sides must be stable and
should not develop unacceptable deformations during construction or during the usage
of the structure
ii) Sufficient seepage control must be ensured to ensure that excessive piping, instability;
sloughing, material erosion is under control. Additionally the loss should be such that
it dose not impair the intended usage of the facility by excessive loss of water.
iii) The reservoir sides should be stable under all operating conditions to prevent
landslides into the reservoir. It is to be noted that a landslide into the reservoir could
cause large wave to overtop the dam
iv) The embankment must be provided with adequately sized spillway which allows
design flow floods to pass without overtopping the embankment.
v) Free board allowance should be sufficient to prevent waves from overtopping the
dam.
vi) The dam should be provided with camber which allows settlement of the foundation
and the abutment to take place. This camber is not included in the freeboard
calculations.
vii) The upstream slope must be protected against the wave action while the down slope is
protected against rain erosion and animal grazing
in the treatment of the foundations. Because the foundations of different materials demand
different treatments the foundations are grouped into three different classes. These classes
can be grouped into
i) Rock foundations
ii) Foundations of coarse grained materials (sand and gravel)
iii) Foundations of fine grained materials (silt and clay)
Rock foundations
Ordinarily the rock foundations do not present any bearing capacity problems. Instead it is
the seepage problems which have to be addressed A thorough site investigation should be
undertaken to establish faults and any areas of excessive weathering which could lead to loss
of water. The procedure would be usually to perform in-situ tests to determine the
permeability of the rock structure. This is undertaken together with a site survey of the
fissures of the rock. If excessive erosive leakage , uplift pressures, high water pressures can
occur though rock crevices, fissures, permeable strata, and/or fault planes, consideration
should be made to grout the foundation.
The foundation grout is basically injection of a sealing material under pressure into
underlying formations through grout holes. Grout ordinarily consists of cement water
mixture in the ration of 10:1 in the case of rich mix to 0.8:1 in the case of a lean mix. Some
additives to the cement water mix is usually done to improve the pumping. The most used
additive is betonite
The injected grout eventually fills the cavities and potential avenues of water.
Grouting is a procedure requiring specialized personnel and equipment to effectively carry
out the operations. In general a centerline curtain of grout of holes spaced at three to six
meters is adequate. Where large zones of fracture occur below the dam wall and in the
immediate upstream of the dam a blanket grout on grid is desirable. The depth of the grouting
is usually in the region of three to ten metres. In most cases a blanket grouting of the
foundation directly below the impervious zone is desirable.
magnitude of the seepage forces should also be determined by analyzing the flow net of the
water flow under the dam. This topic has been covered in FCE 411.
The various methods of treatment of the foundations of sands and gravel should aim
at economical control of the under seepage and the control of the subsequent seepage forces
to prevent the undesirable effect of foundation erosion and piping at the exit of the dam.
Excessive treatment of a detention dam might not be necessary while treatment of foundation
of a water supply dam might be prudent. The various treatment techniques are now presented.
i) Cutoff Trenches
Where possible this is usually the treatment of choice. The cutoff should extend down to
bedrock or to other impervious strata. This treatment ensures no future difficulty will be
experienced in piping and or uplift of the dam. A minimum width of the cutoff trench is
shown on Figure 3.1
d Sand gravel
w Rock
The action of the partial cut off is similar to that of an obstruction of in a pipe. The reduction
in flow is not proportional to the reduction in the area of the pipe. Experiments have shown
that a 50% cutoff results in 25% reduction of the seepage while an 80% cutoff results in 50%
reduction in the seepage.
This is a trench excavated and filled with concrete below the impervious layer. The trench is
kept in position by placing bentonite before concreting to form
v) Grouting
Various materials have been used to develop grouting procedures to improve the stability and
reduce the permeability of pervious foundations under dam walls. These materials include
a) Cement – water
b) Cement – bentonite – water
c) Bentonite
It is to be noted that grouting is usually an expensive process and it should be allowed after
extensive testing and evaluation.
Achieved by
a) Extending the downstream zones
b) Pervious downstream shells or by use of horizontal blankets
c) By use of toe drains
ii) Steady seepage conditions. The core of the dams act as the water barrier of the earth
fill dam. However even the tightest of the clay cores will allow some water
penetration. The rate of penetration will depend on the permeability of the core
material an in due time will reach steady seepage conditions where a phreatic surface
will be developed at the highest level in the embankment. The steady seepage
conditions is critical for the downstream slope. Under these conditions the water has
been impounded the seepage has stabilized through the embankment. The flow net
has been established. All the excess pore water pressures have dissipated. The slopes
of the dam are checked using drained parameters of the foundations and the
embankment materials. The downstream slope is in critical condition during the
steady seepage
iii) Rapid drawdown conditions. Under these conditions the stabilizing effects of the
water in the reservoir has been removed on the upstream slope. The rapid drawdown
leaves high pore-water pressure in the embankment. The upstream slope is usually in
its weakest state. The upstream slope of the dam is checked using drained parameters
of the foundations and the embankment materials. It is to be noted that a drawdown
of up to 40 meters per day is considered as rapid.
iv) Stability under severe seismic conditions. The above conditions should be subjected
to acceleration of the embankment occasioned by seismic activities
The stability check is usually to ensure that the shear stresses induced in the embankments
are resisted by the mobilized shear strength. The shear stresses are from the externally
applied loads which include reservoir weight and earthquake forces. Additionally internally
generated forces from the self weight of embankment The shear stresses at the slopes being
checked can be shown on Figure **** below the shear stresses to be resisted is shown on
Equation 3.1
τ
σ σ3
θ
̅
3.1
The external and internal forces produce a compressive stress along the sliding surface. This
mobilizes the shearing strength which resists shearing along the surface being checked. The
shearing strength is given by Equation 3.2
̅
3.2
It is to be noted that while the shear strength is reduced by the increase in the pore water
pressure the shear stress remains the same. This shows the need of understanding and taking
care of the changes in the pore water regime. In practice the design involves the checking of
the slope stability and application of a suitable factor of safety
Compaction
Compaction of earthworks is a key activity to ensure that the envisaged strength and water
tightness is achieved. When the compressibility and loading of the embankment are constant
the more saturated the soil is the higher the likely hood of developing high pore-water
pressures. To minimize the development of high pore-water pressures it is compact the
earthworks just dry of optimum. However for low dams it has been found satisfactory to
compact earthworks at MDD and OMC.. At this moisture content the material is able to
conform to the shape of the foundation and the abutments.
Spillway
i) You might wish to recalculate the adequacy of the spillway. This topic is
covered separately under hydrology
ii) Check field indicators of adequacy of the spillway – water marks
iii) Blockages
iv) Is the gear control working
v) Structural failures in the concrete
vi) Note any cracks
Gauge house
i) Are the instruments in good working order
ii) Have they been vandalized
Reservoir area
i) Assess the siltation
ii) Assess the conservation measures being undertaken in the neighborhood of the
dam
iii) What is the state of the fence of the reservoir fence for the fenced reservoirs?
AOB
70000
1
2000 masl 1
3.5 Core 4000
10000
Drainage layers Filter drain
3 2.75
1
culvert 1 2.25
1 1985
intake Drainage blanket 5000 masl
2.2
1
outlet
Original Ground level
Draw-off pipe
embankment
5.5mpipe
3 Protective
1 Core 2
10mstand off pipe Hand placed gravel 300mm 1
Drawoff riprap300mm sand filter
pipe Toe drain
1000
Figure 3.3: Embankment details of Kwa Tabitha Dam, Kitui district Dam
300mmProtective gravel
Normal water level
2.5 2.5
1 300mmHand placed riprap 1
5000
Crest
7000
Gross freeboard
1500
500
Normal water level
300mm Protective gravel 2.5 7000
3 Homogeneous embankment 1
5000 1 300mm Hand placed riprap 1000 sand filter
4000
5000 1000
4.1 Introduction
Site investigations are also referred to as soil exploration. It consists of investigating the
condition on which construction is planned. From site investigation it should be possible to
obtain information for the following geotechnical engineering activities
The site investigation should form a part of a coordinated chain of design from inception of
the project through preliminary to the final detailed design of a civil engineering project. It
should indeed continue post construction monitoring of the completed schemes. Because of
the diversity of civil engineering schemes a set of standard procedures is not possible for all
site investigations. The varying civil engineering schemes require a variety of options in
breadth and detail needed for the various schemes. The objectives for which a site
investigation is carried out also differ with various schemes. The main objectives of carrying
out a site investigation are now presented
i) A study of any existing site investigation reports for the area or in the neighborhood
should form the basis of this stage of investigations.
ii) A study of geographical a geological maps of the site in the case of large sites.
Topographical characteristics should lead to useful information such faulty areas.
Heavily forested areas are an indication of deep rooted top soils.
iii) A site inspection of the existing buildings and any existing structures. Any signs of
distress which can be related to the settlement of the foundations. Any information
from archives, previous records held by the local authorities.
iv) Inspection of the soil profiles, in cut areas, old used quarries. Structured questions to
local people with regard to the geotechnical information being sought yields
considerable information. Such questions are:
v) Aerial survey of the site could give useful information with regard to land formations
and soil profiles.
vi) Seismic refractions could be carried out at this stage of investigations. Usually a
specialist is needed to interpret the results.
vii) Preliminary trial pits
Geophysical methods
Geophysical methods involve sending of seismic or electrical waves through the ground. The
determination of the soil strata is based on the fact that the velocity or the resistance seismic
wave transmission or resistance to electrical flow differs with different rock types and soils.
The method allows the boundaries of the soils to be determined seismic refraction is
described below
Seismic refraction is conducted by having a source of seismic waves (Figure 4.1). The
seismic waves are induced by detonating a small explosive or by striking a metal plate hard.
Waves are subsequently emitted in all directions, through the air, and through the soil in all
directions. Seismic wave transducers called geophones are placed radially from the
epicenter. A circuit connects the geophones and the detonator for accurate determination of
time. A direct wave will reach the geophone first since it is the shortest distance covered.
When there is a dense stratum at depth a refracted wave will travel along the top of the bed
rock. As it travels it leaks energy to the surface which can be picked by the geophone.
Seismic source
Geophones
For short distances the direct waves reach the geophones first. For longer distances
the refracted wave reaches first though the distances is longer than t he surface direct
distance. This is so because the speed of the wave in the dense material is higher than that in
the overburden material of less density. The geophone has a mechanism which records the
first wave and ignores the others. This enables a plot of arrival time versus the distance.
The first section of the graph represents the direct wave measurements while the second
section represents the refracted wave measurements (
Figure 4.2). The inverse of these curves are the velocities of the seismic waves. The
general types of the rocks are determined by geophysics from the knowledge of velocity
versus rock type. It is also used in the determination of depth to water table and thicknesses
of multiple strata. The depth D to the bedrock can be estimated from the formula.
Time
d Distance
v. Obtain undisturbed samples when you can for the different layers of strata
encountered. These samples can then be taken to the laboratory for tests
For large sites the pits should then be surveyed and located in a grid system for incorporation
into the site investigation report.
Sounding tests
These are basically are penetration tests carried out to supplementing trial pits and borings.
The penetration resistance is measured and related to the bearing capacity. They are widely
used in site investigations. They consist of the cone penetrometer already presented in
chapter 1. The other commonly used penetration equipment is the dynamic cone
penetrometer used in the estimation of the California bearing ratio (CBR) of road pavement
layers. This enables the design of the pavement layers to be carried out
Boring methods
When a deep stratum has to be investigated it will usually be necessary to perform boring
operations to ascertain the strata below the ground to be used in the support of the proposed
structures. Several boring methods are available and are summarized as follows
Percussion drilling consists of a derrick, a power unit and a winch carrying a light steel cable
which passes thorough a pulley. The unit can be towed by a vehicle after the assembly is
folded. The assembly drops a chisel on the ground and strata being drilled
Rod
Chisel
The excavation is effected by the drilling chisel. The drilling rods provide the necessary
weight for the penetration the strata. Further weight may be added when need arises. The
winch raises and lowers the chisel and its attachments
Below the water table the loosened soil forms slurry. Above the water table water is
introduced to form the slurry. Periodically the slurry is bailed out by a shell or a bailer to
make progress into the soil. In boreholes which are liable to collapse the borehole must be
cased. In some cases the casings slide on their own weight. On completion of the job, the
casing is jacked out.
Percussion drilling is usually done in diameters of 150mm to 300mm. the borehole
depth investigated by this drilling method can be up to 50 to 60 metres. This method of
drilling can be done on virtually all types of soils including those with boulders and cobbles.
The rig is versatile enough to place mechanical augers and penetrating testing equipments at
appropriate depths.
Power operated augers are usually on vehicles. Downward pressure is applied by pressure
or dead weight. The augurs are 75-300mm diameters. Augers are usually used in self
supporting soils. Casing is usually not needed since the augers have to be removed before
driving. In full flight augers the rod and the helix cover the entire length being investigated.
The augur is then brought up. The soil is ejected by reverse rotation. The likely hood of soil
from different strata being mixed up is very high. In the short flight augur the auger is
advanced into the soil and then raised. The soil is also ejected by reverse rotation.
The continuous flight augurs are sometimes fitted with a hollow stem which is plugged
during the drilling operations. When samples are needed the plug and the rods are removed
and a sampler is introduced for the recovery of a sample. The sample may be undisturbed
depending on the sampler utilized. The flight augurs are not suitable for use in loose soils
which are likely to collapse as the augur is inserted and removed from the hole.
Hand and portable augers are usually operated by persons by turning the handle of the
augur. The hand augers are typically of 75 – 300mm diameters. The soil is locked in the
auger and frequent removal is needed to ensure that the augur does not get stack in the soil.
Undisturbed samples may be obtained by introduction of small diameter tubes which are
hammered into the strata under investigation. This method is suitable for self supporting
soils. It is not possible to penetrate coarse granular soils.
Wash boring is a method of boring where water is pumped through boring rods and released
through narrow holes in the chisel attached at eth lower ends of the boring arrangement
(Figure ****).
To sump
Drilling bit
In this method the soil is loosened and broken by water jet. This is aided by the up an down
movements of the chisel. An attachment to the rods called a tiller enable the rotation on the
drilling bit. The drilling winch is able to raise and lower the chisel and hence get the
chopping action of the chisel.
This method is suitable for most soils but progress is slow if the particles of coarse
gravel larger particles are present. The accurate identification of the soil types is difficult.
The method cannot be used to recover soil samples for testing. However tube samplers can
be advanced into the borehole for obtaining relatively undisturbed samples.
Rotary drilling is done by use of drilling bits that cuts and grinds the subsoil or rock at the
bottom of the borehole. Water is usually pumped down hollow rods passing under pressure
through to the drilling tools. This cools and lubricates the bits. The fluid also provides
support for the borehole where there is no casing.
Two methods of rotary drilling are available. The first is open drilling where the soils
and rocks are broken within the diameter of the hole. Subsequently the tubes are removed and
tube samplers and testing continues below the borehole. This advances the drilling. The
second method is known as core drilling and involves creation of an annular hole in the
material and intact rock enters the drilling core. This advances the drilling and enables
samples to be retrieved from the borehole. The sample is then subjected to immediate field
description and taken to the laboratory for various tests. Typical core diameters range from
41mm to 165mm. The method is fast, but in large gravelly soils the speed is slowed by
rotation of the bit without advancement into the ground.
4.2.3 Sampling
Disturbed samples
Disturbed samples are recovered from trial pits and along drilling tools where there is no
attempt to retain the soil constituents. Disturbed samples should however be collected
carefully and placed in airtight tins or jars or in plastic sampling bags. The samples should be
labeled to give the borehole or trial pit identification number, depth of recovery and field
description should be done. The disturbed samples are used for identification tests namely
Field moisture content, PI, grading, compaction and CBR.
x100%
De
De
Di
Di
Borehole logs
Borehole logs summarizes all the laboratory an field tests carried out on samples representing
the various strata encountered in the boring operations. All ground conditions encountered at
the site are also included. The log enables a rapid accurate assessment of the soil profile on a
vertical scale. The details of the various strata encountered including all their geological
formation details which can be inferred are given. The details captured should include the
depth to which ground water was encountered. The description is based on particle
distribution and plasticity based visual inspection and feel. Soil color should also be
recorded.
For highways and runways during preliminary design the subgrade soils along the proposed
alignment should be sampled at 1000metres and the samples should be tested to establish the
in-situ CBR, grading and plasticity of the materials. At this stage the material site should be
investigated at 60 meter intervals. In the detailed stage the subgrade is sampled at 500meters
while the material sites are sampled at 30metres.
Depth of investigation
The depth should be such as to capture the geotechnical information needed for the design of
the facility. Equally important is to capture the information needed in the quantification of
the bill of quantities to ensure an accurate specification of the works is carried out. The
recommended depths below the formation of investigation for the various civil engineering
schemes is shown on Table 4.4 based on Figure 4.9 below.
a) Structural foundations
L L
In fill In cut H
b) Highway earthworks
D
c) Pipe works
Title page
Gives the title of the project at a glance
Abstract
The abstract should be approximately 200 words. It is a very important element of the
project and should be prepared with care. It must convey the essence of the site investigation
and all the important findings without ambiguity.
List of contents
Guides the reader to the various chapters
Field work
A brief and complete description of what was done in the field. Boreholes, and trial pits
performed, field testing etc. Actual procedures of standard tests need not be repeated. A
mention of the tests performed is sufficient. New procedures and peculiar fieldwork should
be explained.
Laboratory work
A brief and complete description of what was done in the laboratory work carried out . as in
the case of field testing actual procedures of standard tests need not be repeated. A mention
of the tests performed is sufficient. New procedures and peculiar laboratory equipment and
procedures should however be explained
Discussion
A reasoned discussion of what design and construction problems are likely to be encountered
in relation to the site and its geological situations.
References
A list of the books, papers, referred to in the work
Appendices
Appendix A – should contain site plan, borehole logs, photographs, etc
Appendix B – should contain tables of results of field and laboratory test those not included
in Appendix A
Appendix C – Any special or unusual test procedures adopted in the investigation
References:
Craig FR, 1987, Soil mechanics, Van Nostrand Reinhold (International) London
Bowles JE , 1982, Foundation Engineering, McGraw-Hill international book company,
Tokyo.
Tomlinson MJ and Boorman R (1986), Foundation and construction, Longman scientific and
technical, England
Franklin JA and Dussealt MB (1989) Rock Engineering, McGraw-Hill international editions,
London
Chen FH (1975) Foundations on expansive soils, Elsevier scientific Publishing Company