DESIGN OF OVERHEAD TANK AT NAI BASTI, JAMMU

1.00 INTRODUCTION
The following sheets pertain to the design of 2 lakh gallon capacity RCC Circular Overhead T
The tank is proposed to be built at east of Jammu city, at Nai Basti under the water supply p
It is basically a circular intze type tank with RCC shaft supporting the tank and the shaft is r
on open foundation.

2.00 REFERENCES
IS 3370 -2009 Code of Practice for Concrete structures for the storage of liquids
Part 1 : General Requirements
Part 2 : Reinforced Concrete Structures
IS 11682 -1985 Criteria for design of RCC staging for overhead water tanks
IS 875 : 1987 Code of Practice for Design Loads (other than earthquake) for buildings & s
Part 2 : Imposed Loads
Part 3 : Wind Loads
IS 1893 : 1984 Criteria for earthquake resistant design of structures
IS 11089: 1984 Code of Practice for Design & Construction of Ring Foundation
Kuang-han Chu & Omar.F.Afandi : Analysis of circular & annular slabs for chimney foundation

3.00 PRINCIPAL PARAMETERS

General
Capacity of tank proposed V = 909 m3
Free board hb = 0.60 m
SBC of soil = 15.00 T/m2
Density of water = 9.81 kN/m3
Density of concrete = 24.00 kN/m3
Density of soil = 19.00 kN/m3
Type of Foundation = Solid Circular Raft Foundation
Depth of foundation below ground level = 1.50 m

Material Properties
Grade of Concrete tank = M30
shaft = M30
foundation = M30

Grade of Reinforcement = Fe500

Top Dome
Inner Radius r1 = 6.00 m
Rise h1 = 2.00 m
Thickness t1 = 0.10 m

Ring beam below dome


Depth = 400 mm
Width = 400 mm

Bottom Dome
Inner Radius r3 = 4.00 m
Rise h2 = 1.60 m
Thickness t3 = 0.20 m

Cylindrical Tank wall


Inner Radius r2 = 6.00 m
Thickness t2 = 0.40 m
Height h = 6.30 m

Ring beam below wall


Depth = 600 mm
Width = 800 mm

Conical Shell below wall


Thickness = 0.60 m
Extent of shell h3 = 4.00 m

Ring beam below bottom dome


Depth = 600 mm
Width = 800 mm

RCC Shaft
Diameter = 8.00 m
Thickness = 0.20 m
Height of shaft = 20.00 m

Annular Circular Foundation


Width of foundation = 3.00 m
Thk. of footing = 0.60 m

Design Parameters ( IS 3370-2009 Part II)

Clear cover to reinforcement = 40 mm

Concrete stresses N/mm2 M30


Direct tensile stress in concrete = 1.5
Bending Tensile stress in concrete = 2.0
Direct comp. stress in concrete = 8.0
Comp. stress in bending in concrete = 10.0

Reinforcement stresses N/mm2 IS 3370 Part-2


Direct tension, bending & shear = 130
Direct Compression = 140
Acceleration due to gravity g = 9.81 m2/s

3.10 DESIGN CONSTANTS M30


Modular ratio m= 280 9.33
3 x cbc
Neutral Axis Constant k= 1.00 0.42
1 + (st / m.cbc )
Lever Arm constant j= 1 - k/3 0.86

MOR constant N/mm2 Q= 0.5 x cbc x k x j 1.80

4.00 DESIGN VOLUME

Volume of water inside tank =  3 (r12 + r22) ( h - hb ) + 2 (r22 + r2.r3 +


6
= 3.14 1231.20 +
6.00
= 920.65 m3

Total height of structure above ground = 30.50 m


5.00 DESIGN OF TOP DOME

Live Load on dome roof = Max.(0.4, 0.75 - 0.52h12/(2r1)2) =


Area exposed = 2 x 10.00 x
=
Self weight of roof = 0.10 x 24.00 =

Total Load on dome, w = 3.14 kN/m2

From geometry of dome , we have

R2 - (R - 2.00 )2 = 6.00 2

R= 10.000 m

sin  = D = 6.00 = 0.6000


2R 10.000
= 36.87 o ( 0.644 rad.)

cos  = 0.800

5.10 Hoop stress at springing level = wR cos - 1 =


(compressive) t 1 + cos
=
=
<

Hoop stress at crown = 0 N/mm2

Hence, providing minimum steel of 0.24% as per IS3370- 2009 Part II, we have

Ast reqd. = 0.24 % = 240.00 mm2

Ast provided = T10 @ 200 mm c/c = 392.70 mm2

5.20 Meridional thrust at springing level, T = wR =


1 + cos
=
Meridional stress = 17.42 =
0.10 =
>

Hence, providing minimum steel of 0.24% as per IS3370- 2009 Part II, we have

Ast reqd. = 0.24 % = 240.00 mm2


Ast provided = T10 @ 200 mm c/c = 392.70 mm2

Total Load of dome = Surface Area of dome x Intensity of loading

= 2 x 10.00 x
= 301.59 kN

c.g of this load = 3 (2R - h1)2 where h1=


4 (3R - h1) R=
= 972.00
112.00
= 8.68 m above the centre of the sphere
6.00 DESIGN OF RING BEAM AT JUNCTION OF TOP DOME & WALL

Hoop tension on ring beam = T cos .D = 17.42 x


2 = 83.61 kN

Steel area reqd. = 83.61 x 1000 =


130

Provide 6 No. bars 12 mm bars (= 678.58 mm2

Hoop stress in concrete = T = 83.61 x


Ac + (m-1) As 160000 +
= 0.50 N/mm2
> 1.50 N/mm2

Volume of beam = 2 x 6.20 x


= 6.23 m 3

Weight of beam = 149.59 kN

7.00 DESIGN OF CYLINDRICAL SIDE WALL

Hoop tension on wall base = 6.00 x 61.80


= 370.82 kN

Steel area reqd. = 370.82 x 1000


(total of both faces) 130
= 2852.45 mm2

Ast provided = T20 @ 200 mm c/c = 1570.80 mm2


(each face)

Hoop stress in concrete = T = 370.82 x


Ac + (m-1) As 400000 +
= 0.87 N/mm2
> 1.50 N/mm2

Distribution steel = 0.24 % = 960.00 mm2

Ast provided = T12 @ 200 mm c/c = 565.49 mm2

Volume of wall = 2 x 6.20 x


= 98.17 m3

Weight of wall = 2356.04 kN


8.00 DESIGN OF RING BEAM AT BOTTOM OF WALL

Length of beam = 2 x 6.40


= 40.21 m

Load of dome on beam = 301.59 = 7.50 kN/m


40.21

Load of top ring beam = 149.59 = 3.72 kN/m


40.21

Load of wall on beam = 2356.04 = 58.59 kN/m


40.21

Self weight of beam = 0.60 x 0.80 x


= 11.52 kN/m

Total vertical load on beam


V1 = 7.50 + 3.72 +
81.33 kN/m

Angle between wall & conical shell,  = tan-1 h3 =


r1 - r3
Horz.force on beam due to V1 H= V1 cot =

Hoop tension due to above load , Hv = H.D /2


= 40.67 x

Hoop tension due to water Hw = wh x d x D/2

Hw = 61.80 x
= 148.33 kN

Total Hoop Tension = Hv + Hw = 392.32 kN

Steel area reqd. = 392.32 x 1000 =


130

Provide 8 No. bars 25 mm bars (= 3926.99 mm2

Weight of beam = 11.52 x 40.21 =

Hoop stress in concrete = T = 392.32 x


Ac + (m-1) As 480000 +
= 0.72 N/mm2
< 1.50 N/mm2

Min. shear steel, Asv = 0.4b.d = 1476.92 mm2


fy
Provide 4 L stirrups 10 mm @ 200 mm c/c
Shear Steel provided = 1570.80 mm2
9.00 DESIGN OF CONICAL DOME

The conical dome shall be designed for


a) Hoop Tension
b) Meridonial thrust

6.30 10.30

2.00

Area of water on conical slab = (6.3 + 10.3) x


2
Average radius of conical shell = (6 + 4 ) =
2
Weight of water on conical slab, Ww = 16.60 x 2
= 5115.96 kN
Lever arm, x = 0.92 m

Weight of conical slab, Ws = 4.57 x


= 2313.02 kN

Total load at base of conical slab = 3270.47 +


= 10699.45 kN

Load per unit length V2 = 10699.45


5.000 x 2

a) Meridional Thrust T = V2 cosec.


= 340.57 x

Meridional Stress = 380.77 x 1000 =


1000.00 x 600
>

b) Hoop tension
The hoop tension will be maximum at the top of the conical slab as the diameter is max.
at this location.

Hoop tension H = ( p cosec. + q cot. ) D/2

Average height of water = (6.3 + 10.3 = 8.30 m


2
Water pressure, p = 8.30 x 9.81 =

Conical slab weight, q = 0.600 x 24.00 =

Angle ,  = 63.43 o

Hence, H =( 81.42 x 1.12 + 14.40 x


= 589.40 kN

Hoop stress in concrete = T = 589.40 x


Ac + (m-1) As 600000 +
= 0.92 N/mm2
> 1.50 N/mm2

Ast reqd. = 589.40 x 1000 = 4533.86 N/mm2


(both faces) 130

Ast provided = T25 @ 200 mm c/c = 2454.37 mm2

Distribution steel reqd. = 0.24 % = 1440.00 mm2

Ast provided = T20 @ 200 mm c/c = 1570.80 mm2

c.g of the conical slab from base = (r22 + 2r2.r3 + 3r32) h3


4 (r22 + r2.r3 + r32)
= 1.74 m
### DESIGN OF BOTTOM DOME

Total Load on dome, w = 5226.59 kN/m2

From geometry of dome , we have

R2 - (R - 1.60 )2 = 4.00 2

R= 5.80 m

sin  = D = 4.00 = 0.6897


2R 5.80
= 43.60 o

cos  = 0.724

Water Load on dome =x 4.00 2


x 10.30 -

= 4946.71 kN
Area of dome surface = 2 x 5.80 x

Self weight of dome = 58.31 x 0.20 x

Total load intensity on dome = 4946.71 + 4.80 =


58.31

a) Hoop stress at springing level = wR cos - 1 =


(compressive) t 1 + cos
=
=
>

Hence, providing minimum steel of 0.24% as per IS3370- 2009 Part II, we have

Ast reqd. = 0.24 % = 480.00 mm2

Ast provided = T12 @ 200 mm c/c = 565.49 mm2

b) Meridional thrust at springing level, T = wR =


1 + cos
=
Meridional compresssive stress = 301.54 =
0.20 =
<
Hence, providing minimum steel of 0.24% as per IS3370- 2009 Part II, we have

c.g of this load = 3 (2R - h1)2 where h1=


4 (3R - h1) R=
= 300.00
63.20
= 4.75 m above the centre of the sphere
11.0 DESIGN OF RING BEAM AT JUNCTION OF BOTTOM DOME & SHAFT WALL

Weight of water = 920.65 x


Weight of top dome & ring beam = 301.59 +
Weight of side wall & ring beam = 2356.04 +
Weight of conical wall & bottom dome = 2313.02 +
Self wt. of beam =2 x x 0.6 x 0.8 x 24
Total Load on beam

Load intensity on beam = 15213.39


25.13
= 605.32 kN/m

Angles  = 63.43 o
 = 43.60 0

Thrust from conical slab = 451.18 + 2819.29 +


= 10699.45 kN

Thrust intensity of T1 = 10699.45 = 425.72 kN/m


25.13
Thrust from bottom dome = 4946.71 + 279.88 =

Thrust intensity of T2 = 4946.71 = 196.82 kN/m


25.13

Hoop tension on ring beam = T1 cos - T2 cos =

Steel area reqd. = 258.91 x 1000 =


130

Provide 8 No. bars 20 mm bars (= 2513.27 mm2

Hoop stress in concrete = T = 258.91 x


Ac + (m-1) As 480000 +
= 0.52 N/mm2
> 1.50 N/mm2

Direct stress due to vertical load = 605.32 x


600 x
= 1.26 N/mm2
< 8.00 N/mm2
12.0 DESIGN OF ANNULAR R.C.C SHAFT

Grade of Concrete = M30

AS per IS 11682:1985,
Min. thickness of shaft < 150 + (D-6000) where D =
120 =
< 166.67 mm
Hence, provide thk t = 200.00 mm

Opening size at base = 1.00 m x 2.10m

From sketch, = 0.125

Wind Pressure considered


w= 1.50 kN/m2

Volume of shaft = 20.00 x 2 x 4.100 x

Slf Weight of shaft = 103.04 x 24.00 =

Summary of Forces on Shaft


Weight Area exposed
Component
(kN) A (sqm.)
Top dome 301.59 125.66
Ring beam below top dome 149.59 5.12
Side wall 2356.04 80.64
Ring beam below wall 463.25 8.16
Conical slab 2313.02 44.80
Bottom dome 279.88
Ring beam below bot. dome 318.48 5.76
RCC Annular shaft 2473.06 168.00
Total self weight of tank W= 8654.91 kN

Weight of water 9031.54 kN

Wind Load Moment, Mw =  F.y = 12815.31 kNm

Ovalising Moment , Mo = 3.3pr2 (Refer IS 11682:1985)


where r = mean radius of shaft =
and p = wind pressure in Mpa
Hence, Mo = 8.32 kNm/m
From IS 11682, we have

Max. compressive stress in concrete

Parameters Empty Tank Full Tank


W 8654.91 17686.45
e (M/P) 1.48 0.72
e/r 0.36 0.18
0.42 0.42

Max. stress in concrete (Mpa) 3.27 5.26


Permissible stress (Mpa) 8.00 8.00
OK OK

As per IS11682, Cl.8.2.2,


Provide vertical steel min. = 0.25 % distributed in both faces
= 500.00 mm2
Ast provided each face = T10 @ 200 mm c/c =

Provide hoop steel min. = 0.20 % distributed in both faces


= 400.00 mm2
Ast provided each face = T10 @ 200 mm c/c =
12.1 Seismic Analysis of shaft (As per provisions of IS1893:1984)
Since Jammu is in Zone-IV, we have

Mod. of elasticity of concrete Ec = 5000 fck =


Zone factor  = 1.0
Moment of Inertia MI = (2r)3.t /8 =
Seismic Zone Factor Fo = 0.25
Importance Factor I = 1.5
Type of soil = Medium

Parameters Empty
Weight considered (kN) 7006.21
Deflection (m) =Wl3/3EI 0.020
Time Period T (sec.) 2 / g 0.28
For 5% damping Sa/g 0.20
Horizontal Seismic Coefficient .I.Fo.Sa/g 0.075
Base shear, H (kNm) 525.47
Base Moment, M (kNm) 10509.31
e/r 0.30
Max. compressive stress in conc. (Mpa) 3.03
Permissible stress (Mpa) 10.66
OK
14.0 DESIGN OF CIRCULAR RAFT FOUNDATION
ity RCC Circular Overhead Tank.
sti under the water supply project.
g the tank and the shaft is rested

storage of liquids

water tanks
arthquake) for buildings & structures

ng Foundation
labs for chimney foundations

ar Raft Foundation

h1
r1
h

r2
h2 h3
r3

M25
1.5
2.0
6.0
8.5

IS 456 :2000
230
190
M25
10.98

0.29

0.90

1.11

( h - hb ) + 2 (r22 + r2.r3 + r32) h3 - (3r32 + h22) h2

608.00 - 80.90

>V, Hence OK
0.74 kN/m2
2.00
125.66 m2
2.40 kN/m2 125.66

31.36 x 0.24
0.10
76.65 kN/m2
0.08 N/mm2
8.00 N/mm2
OK

art II, we have

OK

31.36
1.80
17.42 kN/m
174.20 kN/m2
0.17 N/mm2
8.00 N/mm2
OK
art II, we have
OK

nsity of loading

2.00 x 2.40

2.00 m
10.00 m

entre of the sphere


0.800 x 6.00

643.19 mm2

) OK

1000
5655

OK

0.40 x 0.40

6.3

OK 61.80 kN/m2

1000
26180

OK

each face OK

0.40 x 6.30
24

58.59 + 11.52

63.43 o

81.33 = 40.67 kN/m


2.00

6.00 = 243.99 kN

where d = depth of beam


wh = water load

0.40 x 6.00

3017.82 mm2

) OK

463.25 kN

1000
65450
OK

/m

/m OK
2.00 = 16.60 m2

5.000 m

x 5.000 x 9.81

x 11.200 x 0.60 x 24

5115.96 + 2313.02

= 340.57 kN/m

1.12 = 380.77 kN

0.63 N/mm2

8.00 N/mm2
OK

as the diameter is max.


81.42 kN/m2

14.40 kN/m2

0.50 )x 6.00

1000
40906

OK

each face OK

OK

+ 3r32) h3
1.60 2 ( 3 x5.8-1.6) 9.81
3

1.60 = 58.31 m2

24.00 = 279.88 kN

89.64 kN/m2

519.90 x 0.144
0.20
374.69 kN/m2
0.37 N/mm2
8.00 N/mm2 OK

art II, we have

OK

519.90
1.724
301.54 kN/m
1507.71 kN/m2
1.51 N/mm2
8.00 N/mm2 OK
art II, we have

1.60 m
5.80 m

entre of the sphere


SHAFT WALL

9.81 = 9031.54 kN
149.59 = 451.18 kN
463.25 = 2819.29 kN
279.88 = 2592.90 kN
= 318.48 kN
15213.39 kN

2313.02 + 5115.96

5226.59 kN

-258.91 kN/m
indicates compression
1991.58 mm2

) OK

1000
20944

OK

1000
800

OK
internal dia of shaft
8000 mm

OK

0.20 = 103.04 m3

2473.06 kN

Force (A x w) c.g from GL


F (kN) y (m)
188.50 29.18
7.68 28.20
120.96 24.85
12.24 21.40
67.20 18.84

8.64 19.80
252.00 9.50
657.22 kN

4100 mm
oth faces

392.70 mm2 OK

oth faces

392.70 mm2 OK
27386 N/mm2

43.30 m4

Full
16037.74
0.045
0.42
0.18
0.068
1082.55
21650.95
0.30
6.20
10.66
OK
BILL OF QUANTITIES FOR R.C.C OVERHEAD TANK

Sl. Items of Concrete Measurement


1.00 Top Dome 2 x 10.00 x 2.00 x 0.10
2 x 10.00 x 2.00

2.00 Top dome beam 2 x 6.20 x 0.40 x 0.40


2 x 6.20 x 1.20

3.00 Side wall 2 x 6.20 x 0.40 x 6.30


2 x 6.20 x 12.60

4.00 Beam below wall 2 x 6.40 x 0.60 x 0.80


2 x 6.40 x 2.00

5.00 Conical slab  x 4.57 x 0.60 x 11.20


 x 4.57 x 11.20

6.00 Bottom dome 2 x 5.80 x 1.60 x 0.20


2 x 5.80 x 1.60

7.00 Bottom dome beam 2 x 4.40 x 0.60 x 0.80


2 x 4.40 x 2.00

8.00 Shaft 2 x 4.10 x 0.20 x 20.00


2 x 4.10 x 40.00

8.10 Openings ventilators 6 0.50 x 0.50


door 1 2.10 x 1.50

9.00 Type of Foundation Pile Foundation

Annular Footing

kicker 2 x 4.10 x 0.40 x 0.60


2 x 4.10 x 0.60
stem 2 x 4.10 x 0.60 x 0.30
2 x 4.10 x 0.30
base 2 x 4.10 x 3.00 x 0.60
2 x 4.10 x 0.60
OR

Pile Foundation
Dia = 600  x 0.090 x 25.00 x 40
Length = 25000
No. = 40
Capacity = 125MT
Pile cap
Width = 3000 2 x 4.10 x 3.00 x 1.00
Depth = 1000 2 x 4.10 x 1.00

OR

Solid Circular Footing  x 7.85 x 7.85 x 1.00


2 x 7.85 x 1.00

10.00 Walkway
10.10 Around tank 1.00 m wide 4 x 6.90 x 1.00 x 0.12
( 2 Nos.) 0.12 m thk 4 x 6.90 x 1.00
10.20 Landings 1.00 m wide 9 x 1.00 x 1.00 x 0.12
0.12 m thk 9 x 1.00 x 1.00
1.50 m wide 1 x 1.50 x 1.50 x 0.15
0.15 m thk 1 x 1.50 x 1.50
5.00 m wide 1 x 5.00 x 0.75 x 0.35
0.35 m thk 1 x 5.00 x 5.00
1.90 m wide 1 x 1.90 x 1.00 x 0.15
0.15 m thk 1 x 1.90 x 1.90
0.50 m wide 1 x 0.50 x 1.00 x 0.15
0.15 m thk 1 x 0.50 x 0.50

11.00 Inner circular partition wall 2 x 5.80 x 0.20 x 6.30


(optional) 2 x 5.80 x 12.60

12.00 M.S Ladder with railing

13.00 Additional railing on landings

14.00 Aluminium Ladder inside tank 2 x 8.00

15.00 Excavation footings  x 5.60 x 5.60 x 1.50


pilecap  x 4.10 x 4.10 x 1.10

16.00 PCC footing 2 x 4.10 x 3.20 x 0.10


pilecap 2 x 4.10 x 3.30 x 0.10
inside shaft  x 16.00 x 0.15

17.00 Painting
17.10 walls inside 2 x 6.00 x 6.30
outside 2 x 6.40 x 6.30
17.20 conical inside 2 x 5.00 x 4.57
outside 2 x 5.60 x 4.57
17.30 bot.dome inside
outside
17.40 Top dome inside
outside
17.50 Shaft inside 2 x 4.00 x 20.00
outside 2 x 4.20 x 20.00
17.60 Partition wall inside 2 x 5.70 x 6.30
outside 2 x 5.90 x 6.30
17.70 Walkways
Formwork
Volume (m3) (m2) Length (m) HYSD Steel (MT)
12.57 0.75% 0.80
125.66

6.23 1.50% 0.70


46.75

98.17 2.75% 21.60


490.84

19.30 1.00% 1.50


80.42

96.38 3.00% 23.20


321.25

11.66 0.75% 0.70


58.31

13.27 0.75% 0.80


55.29

103.04 1.20% 9.90


1030.44

0.30 1.50
0.63 3.15

57.19
38.64
6.18 1.50% 0.70
15.46
4.64 2.00% 0.70
7.73
46.37 1.50% 5.60
15.46

282.74 2.00% 45.30


77.28 2.75% 17.00
25.76

193.59 2.00% 31.00


49.32

10.40 1.50% 1.20


86.71
1.08 1.50% 0.10
9.00
0.34 1.50% 0.00
2.25
1.31 1.50% 0.20
25.00
0.29 1.50% 0.00
3.61
0.08 1.50% 0.00
0.25

45.92 2.20% 8.10


459.18
131.10

23.00

117.86

16.00

148.00
59.00

8.00
9.00
7.54

237.50
253.34
143.42
160.63
58.31
58.31
125.66
125.66
502.65
527.79
225.63
233.55
126.82
Annular Circular Footing
Solid Circular Footing
Pile Foundation
Karnataka Municipal Reforms Project (KMRP) Detailed Project Report- New OHTat Jewargi Town

Civil Work Items - RCC Over Head Tank of 2000 cu.m capacity and over 30m staging
height

Si. No. Description Unit Qty.

1 Earth work excavation


0 to 2 mtr Depth
a In all soils Cum 59.00
b In disintegrated rock, soft rock wihtout resorting to blasting.

2m to 4 mtr Depth Cum

c Earthwork in excavation for foundation for pile caps in all types of strata other
than hard rock upto 3m depth Cum

2 Boring in all types of soil (excluding rock) for piling of 600 dia piles including
protection of sides by either using temporary liner or driller's mud, etc.
complete R.M 25.00

3 PCC M7.5B below pilecap Cum 9.00


PCC M10B within shaft wall area at ground level
Cum 7.60

4 Providing M-35 for R.C.C. 600 dia cast in situ bored piles, each of load
capacity as designed, place through steel shell sunk to the required depth
through all type of strata excluding provision of reinforcement including
placing concrete by tremmy arrangment including all leads and
lifts,compaction of concrete including chipping and dressing of RCC
Piles,cleaning the reinforcement etc complete.

Cum 282.80
Pilecap Cum 77.30

Shah Technical Consultants Pvt Ltd (STC) 44of 47


Karnataka Municipal Reforms Project (KMRP) Detailed Project Report- New OHTat Jewargi Town

Si. No. Description Unit Qty.

5 RCC M 30C grade concrete for RCC Shaft.


102.20

6 RCC M 30C grade for RCC work (excluding cost of reinforcement)

Top, middle and bottom ring beam Cum 38.90


Bottom dome Cum 11.66
Conical dome Cum 96.38
Walkway Slab Cum 13.50
Side wall Cum 98.20
Top dome Cum 12.60
Internal RCC Circular Partition wall Cum 46.00

Shah Technical Consultants Pvt Ltd (STC) 45of 47


Karnataka Municipal Reforms Project (KMRP) Detailed Project Report- New OHTat Jewargi Town

Si. No. Description Unit Qty.

7 Cement mortar plastering 1:3 proportion 12 mm thick for both inside and
outside surface for top dome Cum 3.10

8 HYSD steel reinforcement M Ton 132.00

9 Plastering in C.M. 1:3 proportion including smooth finishing with minimum 2%


of approved quality of water proof compound for RCC over head tank and
giving satisfactory water proof testing for side walls, shell portion, bottom
dome, bottom slabs
Sqm 564.90

10 Two coats of water proof cement painting of approved colour and shade over
one coat of primer before removal of scaffolding for new R.C.C. over head
tanks 2779.30

11 M.S. ladder 45 cms. wide using angle iron of size 65 mm x 65 mm x 8 mm


and 20 mm M.S. bars at 25cms. centre to centre with necessary supports of
same angle iron as directed including hand railing on both sides with 25mm
dia G.I. pipes with angle iron props at 2 mtrs, interval and 0.5 mtr, height

23.00

12 M.S. Inspection door of size 60 cms x 60 cms. including M.S. frame, size 50
x 50 x 6 mm and shutters of 3mm thickness with hinges at top and locking
arrangements, painting
1

13 Aluminium monkey ladder 45 cms. wide including hand railing & cage to be
provided inside the tank 16.00

Shah Technical Consultants Pvt Ltd (STC) 46of 47


Karnataka Municipal Reforms Project (KMRP) Detailed Project Report- New OHTat Jewargi Town

Si. No. Description Unit Qty.

14 Supplying & fixing 40 mm dia G.I. medium duty pipes hand railing
3 rows fixed to 1:2:4 (M-150) vibrated R.C.C. post of size 100 x 150 mm at
top and 150 x 150 mm at bottom placed at 2 Mtr. intervals for a height of 750
mm painting G.I. pipes with two coats of anticorrosive steel paint over a
primer coat

Mtr 117.90

15 Pull and push type rolling shutters of approved make as per specifications
Sqm 3.15

16 Refilling pipeline trenches and foundation with selected available earth from
trench excavation and foundation Cum 41.00

Shah Technical Consultants Pvt Ltd (STC) 47of 47