CSSP: Basic Infrastructure Program (BIP) - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Multi-Purpose Building, Barangay Bahay, Libmanan, Camarines Sur
Libmanan, Camarines Sur
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST %
QTY.
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT) DIRECT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated COST
B.7(1) Occupational Safety and Health Program 10.00 - month 302,978.10 - 30,297.81 - 34,357.72 - 0.96
VOLUME III
PART III-A EARTHWORK
801(1) Removal of Structures and Obstructions 1.00 - L.S. 130,536.97 - 130,536.97 - 164,476.58 - 0.41
804(1)b Embankment (from Borrow) 421.50 - cu.m. 356,667.27 - 846.19 - 1,066.19 - 1.13
900(1)c2 Structural Concrete, Footings and Slab on Fill (Class A, 28 days) 155.30 - cu.m. 982,992.88 - 6,329.64 - 7,975.34 - 3.11
900(1)c3 Structural Concrete, Footing Tie Beams (Class A, 28 days) 9.20 - cu.m. 62,758.31 - 6,821.56 - 8,595.16 - 0.20
900(1)c4 Structural Concrete, Columns (Class A, 28 days) 21.70 - cu.m. 148,027.76 - 6,821.56 - 8,595.16 - 0.47
902(1)a Reinforcing Steel (Deformed, Grade 40) 15,889.00 - kgs. 1,196,173.66 - 75.28 - 94.86 - 3.79
903(2) Formworks and Falseworks 1,835.00 - sq.m. 711,903.03 - 387.96 - 488.83 - 2.25
CSSP: Basic Infrastructure Program (BIP) - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Multi-Purpose Building, Barangay Bahay, Libmanan, Camarines Sur
Libmanan, Camarines Sur
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST %
QTY.
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT) DIRECT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated COST
PART III-C FINISHINGS AND OTHER CIVIL WORKS
1000(1) Soil Poisoning 12,000.00 - Liters 4,795,075.56 - 399.59 - 503.48 - 15.18
1001(8) Sewer Line Works 1.00 - L.S. 177,272.23 - 177,272.23 - 223,363.01 - 0.56
1001(9) Storm Drainage and Downspout 1.00 - L.S. 96,563.63 - 96,563.63 - 121,670.18 - 0.31
1002(24) Cold Water Lines 1.00 - L.S. 29,506.40 - 29,506.40 - 37,178.06 - 0.09
1003(1)e1 Ceiling (Gypsum Board, Metal Frame) 135.00 - sq.m. 127,968.34 - 947.91 - 1,194.37 - 0.41
1006(6) Steel Doors and Frames 1.00 - L.S 241,809.71 - 241,809.71 - 304,680.24 - 0.77
1008(1)c Aluminum Glass Windows (Awning Type) 87.60 - sq.m. 323,042.28 - 3,687.70 - 4,646.50 - 1.02
1008(1)d Aluminum Glass Windows (Fixed Type) 6.40 - sq.m. 23,601.26 - 3,687.70 - 4,646.50 - 0.07
1013(2)a1 Fabricated Metal Roofing Accessory, gauge 26 (Ridge/Hip Rolls) 35.00 - L.M. 14,082.59 - 402.36 - 506.97 - 0.04
1013(2)a2 Fabricated Metal Roofing Accessory, gauge 26 (Flashings) 156.00 - L.M. 62,768.10 - 402.36 - 506.97 - 0.20
1013(2)b1 Fabricated Metal Roofing Accessory, gauge 24 (Gutters) 86.00 L.M. 43,112.22 - 501.30 - 631.64 - 0.14
Pre-painted Metal Sheets, Corrugated Type (Long Span, above
1014(1)b1 841.00 - sq.m. 552,993.53 - 657.54 - 828.50 - 1.75
0.427mm)
1018(1) Glazed Tiles and Trims 28.00 sq.m. 42,992.41 - 1,535.44 - 1,934.66 - 0.14
1021(1)c Cement Floor Finish (with Floor Hardener) 897.00 - sq.m. 307,077.40 - 342.34 - 431.35 - 0.97
1027(1) Cement Plaster Finish 1,807.00 - sq.m. 341,471.45 - 188.97 - 238.10 - 1.08
1032(1)a Painting Works (Masonry/Concrete) 3,651.00 - sq.m. 896,601.63 - 245.58 - 309.43 - 2.84
1032(1)b Painting Works (Wood) 135.00 - sq.m. 30,876.75 - 228.72 - 288.18 - 0.10
1046(2)a1 CHB Non Load Bearing (including Reinforcing Steel, 100mm) 13.00 - sq.m. 9,760.05 - 750.77 - 945.97 - 0.03
1046(2)a2 CHB Non Load Bearing (including Reinforcing Steel, 150mm) 1,005.00 - sq.m. 1,143,640.88 - 1,137.95 - 1,433.82 - 3.62
CSSP: Basic Infrastructure Program (BIP) - Multi-Purpose Buildings/ Facilities to support Social Services - Construction of Multi-Purpose Building, Barangay Bahay, Libmanan, Camarines Sur
Libmanan, Camarines Sur
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST %
QTY.
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST (DIRECT+INDIRECT) DIRECT
As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated As Submitted As Evaluated COST
PART III-D ELECTRICAL
1100(10) Conduits, Boxes & Fittings (Conduit Works/Conduit Rough-in) 1.00 - L.S. 393,805.79 - 393,805.79 - 496,195.30 - 1.25
1101(33) Wires and Wiring Devices 1.00 - L.S. 651,416.47 - 651,416.47 - 820,784.75 - 2.06
1102(1) Panelboard with Main & Branch Breakers 1.00 - L.S. 113,403.29 - 113,403.29 - 142,888.15 - 0.36
Pad Mounted Distribution Transformer (OISC) with Complete
1102(8) 1.00 - L.S. 836,181.84 - 836,181.84 - 1,053,589.12 - 2.65
Accessories (Free Standing)
1103(1) Lighting Fixtures and Lamps 1.00 - L.S. 499,339.10 - 499,339.10 - 629,167.27 - 1.58
1208(1) Fire Alarm System 1.00 - L.S. 207,078.72 - 207,078.72 - 260,919.18 - 0.66
VOLUME II
104(2)a Embankment from Borrow (Common Soil) 1,920.00 - cu.m. 1,610,414.59 - 838.76 - 1,056.83 - 5.10
105(1)a Subgrade Preparation (Common Material) 1,023.00 - sq.m. 16,411.92 - 16.04 - 20.21 - 0.05
300(2) Crushed Aggregate Surface Course 226.50 - cu.m. 280,714.50 - 1,239.36 - 1,561.59 - 0.89
311(1)c1 PCC Pavement (Unreinforced, 0.23m thk.) - 14 days 1,023.00 - sq.m. 1,412,121.83 - 1,380.37 - 1,739.27 - 4.47
404(1)a Reinforcing Steel (Grade 40) 4,257.00 - kgs. 311,915.83 - 73.27 - 92.32 - 0.99
405(1)a3 Structural Concrete, Class A (20.68 Mpa, 28 days) 18.00 - cu.m. 137,615.45 - 7,645.30 - 9,633.08 - 0.44
407(8) Lean Concrete, Class B (16.5 Mpa) 0.50 - cu.m. 2,563.15 - 5,126.31 - 6,459.15 - 0.01
502(5) Metal Frames and Gratings, Drainage Inlet 40.00 - pair 16,264.90 - 406.62 - 512.34 - 0.05