Labor Productivity Rate
Labor Productivity Rate
Productivity
# Activity Crew UOM
(Units/Manday(10h))
1 Block Works 2 Mason m2 10
2 Cement Plaster 1 Mason m2 15
3 Floor Screed 4 Mason m2 20
4 Gypsum Ceiling Grid 2 Gypsum Carpenter m2 15
5 Gypsum Boarding 2 Gypsum Carpenter m2 20
6 Gypsum Primer & Stucco 1 Painter m2 15
7 Gypsum Partition Framing 2 Gypsum Carpenter m2 15
8 Gypsum Partition Closing 2 Gypsum Carpenter m2 20
9 Suraface Preparation 1 Painter m2 20
10 Primer & Stucco 1 Painter m2 15
11 First Coat Paint 1 Painter m2 25
12 Final Coat Paint 1 Painter m2 20
13 Marble Flooring 2 Mason m2 15
14 Wall Marble 2 Mason m2 10
15 Marble Skirting 2 Mason mts 30
16 Wood Flooring 2 Carpenters m2 15
17 Door Frames 2 Carpenters nos. 5
18 Door Shutters 2 Carpenters nos. 5
19 Door Hardware 2 Carpenters nos. 5
20 Wooden Ceiling 2 Carpenters m2 20
21 Wooden Wall Cladding 2 Carpenters m2 20
22 Wardrobe 3 Carpenters nos. 1
23 Kitchen Counter 3 Carpenters nos. 1
24 Kitchen Cabinets 3 Carpenters nos. 1
25 Metal Cladding 2 Fabricators m2 20
26 Glass Partition 2 Fabricators m2 12
Labor Productivity Chart
Productivity
# Activity Crew UOM
(Units/Manday(10h))
27 Glass Doors 2 Fabricators m2 3
28 Mirrors 2 Fabricators nos. 3
29 Light Fixtures 2 Electricians nos. 15
30 Terrazo floor 2 Masons Sqm 20
31 Waterproofing 2 Masons Sqm 20
32 Wall cover 2 Wallcover Installer Sqm 15
33 Wooden Skirting 2 Carpenters mts 30
34 Marble Skirting 2 Masons mts 30
35 Sanitaryware Fixtures 2 Plumbers Nos 22