Question Bank-1
Question Bank-1
8. The areas within the contour line at the site of proposed dam are as follows.
Calculate capacity of dam.
Contour Area m2
102 200
104 500
106 215
108 324
110 478
112 255
a. Direct ranging
b. Indirect ranging
11. List out and explain any five tape corrections with their equations.
12. What is compass surveying? Explain about The Whole Circle Bearing System &
1.Manhole
2. Invert level
3. Fall
15. Define contouring. State and explain the characteristics of a contour map with
diagrams.
16. a. Define Surveying.
17. Referring the Maldivian Land Title system, briefly explain the guidelines for
18. With a detailed neat sketch explain the working principle of Auto level
20. State any two factors that affect selection of an appropriate contour interval.
21. State the merits and demerits of using different contouring methods mentioned in
above question?
i. Level Line
x. Change Point
1) Level line
2) Horizontal line
3) Datum
4) Bench mark
5) Reduced level
26. Find the reduced level of point A using rise and fall method for the profile given.
29. What is the purpose of survey lines, survey stations, tie stations, check lines and tie
31. The practice of surveying requires experience in handling the equipment used in
field and office work, a familiarity with the care and adjustment of the surveying
1.A nominal distance of 30 meters was set out with a 30 m steel tape from a mark on the top of
one peg to a mark on the top of another, the tape being in catenary under a pull of 10 kg and at a
mean temperature of 750 F. The top of one peg was 0. 4 meter below the top of the other. The top
of the higher peg was 365 meters above mean sea level. Take radius of earth = 6370 km, Density
of tape = 6.26 g/cm3, cross-section of tape = 0.05 sq.cm, Co-efficient of expansion= 6.3x10-6 per 10
F, Young’s modulus= 2.1x106 kg/cm2. Calculate the exact horizontal distance between the marks
on the two pegs and reduce it to mean sea level, if the tape was standardized at a temperature of
(a) 9 kg
(b) 11 kg
(c) 15 kg
2.The following perpendicular offsets were taken at 8m intervals from a survey line to an irregular
continuously sloping ground at regular intervals of 15m as 0.835, 1.030, 1.925, 2.825, 3.730, 4.685,
0.625, 2.005, 3.110, 4.485m. The instrument was changes after 7th & 11th reading. The first reading
was taken at a B.M of elevation 123.45m. Enter the readings in a level book format and reduce the
levels. Apply the checks and Calculate the gradient of the slope. b) Calculate the missing entries
4. An observer standing on the deck of a ship just sees the lighthouse. The top of the lighthouse
is 42m above the sea level and the observer’s eye is 6m above the sea level. Find how far he is
from lighthouse. b) The areas within the contour line at the site of reservoir and the face of the
enclosed between the survey line, irregular boundary line and the survey line by
5. The following staff readings were observed during the leveling carried out for drainage works.
Cross section readings were taken at 0, 10 & 20m. The pipeline should have a gradient of 1 in
40m. Calculate the excavation/fill quantities for the drainage trench. Provided depth of trench
6.The following bearings were observed with a compass. Calculate the interior angles using
7.The following are observed fore-bearings of the lines. Find their back bearings.
LM 112040’
MN 45050’
PQ ‘N 180 0' E’
QR ‘S 120 24' E’
RS ‘S 59018'W’
ST ‘N 86012'W’
AM ‘203045’
BC 1090 44'
CD 2650 30'
DE 3840 28'
32. Find the reduced level using rise and fall method for the profile shown in Figure
Point A has the bench mark of elevation 100m from the MSL.
33. Seven readings were taken with the level in sequence as follows: 2.585, 0.15, 3.305,
2.25, 3.125, 0.265, 2.35m. The level was shifted after fourth and sixth reading. The
second change point was the bench mark of elevation 105.975m. Find the reduced
level of the remaining stations. Use height of collimation method.
34. Explain the process of direct and indirect method of contouring with advantages
and disadvantages of using each method.
35. The following staff readings were observed during the leveling carried out for
drainage works. Cross section readings were taken at 0, 10 & 20m. The pipeline
should have a gradient of 1 in 40m. Calculate the excavation/fill quantities for the
drainage trench. Provided depth of trench including pipe thickness is 750mm and
width of excavation as 0.4m
36. A series of offsets were taken from a chain line to curved boundary line at intervals
of 5m in the following order: 1.210, 3.65, 1.578, 2.875, 4.365. 0.786, 4.195, 5.858m.
Compute the area between chain line and the boundary and the end offset by
removed.
Figure 2
38. The following bearings were observed with a compass. Calculate the interior angles
AB 142030’
BC 223015’
CD 287000’
DE 12045’
EA 60000’
39. The following staff reading 0.915, 2.672, 3.145, 2.112, 1.215, 1.725, 2.315, 3.315, 3.623,
1.292, 1.550, 2.355 were taken using an automatic level during surveying. The level
was shifted after second and 6th and 9th reading, the elevation of B.M at 2nd reading
is 323.3m. Calculate the elevations of the points using rise and fall method.
40. The following staff readings were taken on a land, calculate the elevations of the
points. The staff reading on the B.M with elev. 0.450 m was 100m. Find the reduced
41. A survey was conducted for laying drainage pipes in a surface. The following staff
readings were observed during the leveling. Cross section readings were taken at
0, 20 & 30m. The pipeline should have a gradient of 1 in 40m. Calculate the
excavation/fill quantities for the drainage trench. Provided depth of trench
including pipe thickness is 750mm and width of excavation as 0.4m
2 3 1.25
3 6 1.215
4 3 0.324
5 6 0.478
6 10 1.255
7 3 1.521
8 6 3.21
9 3 0.568
10 6 1.78
11 20 0.978
12 3 1.115
13 6 2.56
14 3 3.45
15 6 2.188