Ass 1 Memo
Ass 1 Memo
ASSIGNMENT 1
BARCODE
EPT2602/103/0/2024
ASSIGNMENT 1
QUESTION 1
1.1 Differentiate between scheduling for service operation and scheduling for
manufacturing operation. (4)
• Inventories can help smooth demand for manufacturers√, but many service
systems do not maintain inventories√.
• Services are labor intensive, and the demand for this labor can be highly variable.
• Legal considerations, such as wage and hour laws and union contracts that limit
hours worked per shift, week, or month, constrained scheduling decisions.
• Because services usually schedule people rather than material, behavioral, social,
seniority, and status issues complicates scheduling.
1.2 A company has the following ten jobs that are awaiting processing at their 3D print
shop. Processing times as well as due dates are given in the table. If today is day
50 on the planning calendar, determine the optimum sequence of the jobs using
the critical ratio rule. Show full calculations. (6)
B 85 15
C 72 8
D 63 9
E 94 20
2
EPT2602/103/0/2024
F 70 12
G 84 24
H 100 18
I 78 9
J 110 25
B 85 15
C 72 8
D 63 9
E 94 20
F 70 12
G 84 24
H 100 18
I 78 9
J 110 25
3
EPT2602/103/0/2024
1.3 The following eight (8) jobs are ready for scheduling at a job shop in Rosslyn.
Today on the planning calendar is day 100, and none of the jobs have been
started or scheduled yet:
Using the shortest processing time (SPT) and the earliest due date (EDD)
scheduling techniques, determine the following:
SPT: A-F-G-C-E-D-B-H
EDD: E-A-F-C-B-D-H-G
1.3.2 The average job lateness of the job schedules above. Show full
calculations. (8)
SPT
0.1666 marks each for Flow time, completion time and Job lateness
Production Date
Flow Today's Completion Job
Job Days Order
time date time lateness
Needed Due
EDD
Production Date
Flow Today's Completion Job
Job Days Order
time date time lateness
Needed Due
[20]
QUESTION 2
2.1 The following eight (8) jobs are ready to be processed through a two-step
operation at a paint shop in Silverton, in an order of operation 1 before operation
2. The processing times for each operation (in hours) are as follows:
A 2 3
B 4 2
C 3 1
D 1 3
5
EPT2602/103/0/2024
E 4 5
F 8 6
G 6 4
H 7 7
2.1.1 Using the Johnson’s rule, determine a sequence that will minimize the total
completion time for these jobs and illustrate your answer graphically. (8)
2 Marks
D A E H F G B C
2.2 Johannesburg Hospital is extending its emergency ward. The project activities,
activity times as well as the precedence relationships for this project are shown in
the table below:
A None 3
B None 2
C A, B 4
D C 5
E B,C 6
F D, E 6
G F 8
A-C-E-F-G√√
[19]
QUESTION 3
3.1 Discuss ways in which a retailer such as Checkers supermarket should manage
and monitor their inventory. (6)
3.2 To build a composite deck, the following eight (8) major activities are undertaken.
The activities have been labelled A to H. The activities’ optimistic, pessimistic and
most likely times (in weeks) as well as their predecessors are shown in the table
below.
7
EPT2602/103/0/2024
Task Immediate a m b
predecessor/s
A None 3 4 5
B None 2 4 6
C A 7 8 10
D B 4 7 9
E C,D 3 5 7
F E 1 2 4
G C,F 5 8 9
H F 3 6 8
3.2.1 Determine the expected time and the variance of each project activity.
Convert the expected time to the nearest whole number (12)
A None 4 0.11
B A 4 0.44
C B 8.17≈ 8 0.25
D B,C 6.83≈ 7 0.69
E D 5 0.44
F D,E 2.17≈ 2 0.25
G C,E,F 7.67≈ 8 0.44
H G 5.83≈ 6 0.69
3.2.2 Determine the critical path and completion time of the project. (4)
3.2.4 What is the probability that the project will be completed two weeks before
the project completion time? (3)
√√
The probability of completing the job before the due date is 0.0505 = 5.05 %√
[27]
QUESTION 4
One of the first steps in establishing the project’s objectives, is to carefully break it
down into manageable parts. This work breakdown structure (WBS) defines the
project by dividing it into its major tasks, which are then subdivided into more
detailed components, and finally into a set of activities and their related costs. This
breakdown is critical for the successful scheduling and management of the project
Making a WBS is the first step in developing a project schedule. It defines all the
work that needs to be completed (and in what order) to achieve the project goals
and objectives. By visualizing your project in this manner, you can understand
your project scope, and allocate resources for all your project tasks
4.2 ZAR Carpet and Trim installs carpets in commercial offices. The company has
been given a new contract to install carpets at a new office block in Renbo office
park. A list of activities and their predecessor/s are shown below.
9
EPT2602/103/0/2024
A - 5
B - 3
C A 8
D B,C 10
E C 6
F B,D 4
G E,F 7
H E 5
4.2.1 Complete the table below to complete the forward and backward passes for
the project. (14)
A - 5
B - 3
C A 8
D B,C 10
E C 6
F B,D 4
G E,F 7
H E 5
A - 5 0 5 0 5 0
B - 3 0 3 10 13 10
C A 8 5 13 5 13 0
D B,C 10 13 23 13 23 0
E C 6 13 19 21 27 8
F B,D 4 23 27 23 27 0
10
EPT2602/103/0/2024
G E,F 7 27 34 27 34 0
H E 5 19 24 29 34 10
[20]
QUESTION 5
5.1 A company delivers closed-cell foam to a bike seat manufacturer in Rosslyn two
(2) times a year. The reorder point without safety stock is 40 units. The holding
cost is R120 per unit per year, and the cost of a stockout is R160 per unit. Below
are the demand probabilities during the reorder period:
5.1.1 Calculate the amount of safety stock the company needs to carry to
minimise total costs (holding + stockout). Show full calculations. (10)
11
EPT2602/103/0/2024
1-1000kg R30
1001-2000kg R28
12
EPT2602/103/0/2024
2001kg+ R26
5.2.1 Which price structure must the company select to keep costs low? Show full
calculations (10)
√√
√√
√; Adjusted to 2001
√√
[20]
13
EPT2602/103/0/2024
©
UNISA 2024
14