Emb. and Rockfills
Emb. and Rockfills
------------------------------------
Preparing Activity: USACE Superseding
UFGS-35 73 13 (January 2008)
SECTION 35 73 13
11/18
PART 1 GENERAL
SECTION 35 73 13 Page 1
1.3.6 Rock Fill
1.3.7 Unsatisfactory Materials
1.3.8 Unsatisfactory vs Satisfactory
1.4 SYSTEM DESCRIPTION
1.4.1 Haul Roads
1.4.2 Stockpiling from [Approved Borrow Sources][Required
Excavations]
1.5 SUBMITTALS
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 General
2.1.2 Impervious Fill
2.1.3 Random Fill
2.1.4 Pervious Fill
2.1.5 Uncompacted Fill
2.1.6 Backfill
2.1.7 Filter Drainage Layers
2.1.8 Rock Fill
2.1.8.1 Rock
PART 3 EXECUTION
3.1 CONSTRUCTION
3.1.1 Lines and Grades
3.1.2 Conduct on the Work
3.2 PREPARATION OF FOUNDATION, PARTIAL FILL SURFACES AND ABUTMENTS
3.2.1 Earth
3.2.2 Rock
3.2.3 Foundation Inspection and Mapping Procedures
3.2.4 Foundation Condition Evaluation
3.2.5 Excavation and Foundation Mapping
3.2.6 Equipment for Foundation Excavation and Mapping
3.3 PLACEMENT
3.3.1 General
3.3.2 Frozen Material
3.3.3 Rate of Placement
3.3.4 Impervious Fill
3.3.5 Random Fill
3.3.6 Pervious Fill
3.3.7 Filter Drainage Layers
3.3.8 Rockfill
3.3.9 Spreading
3.4 MOISTURE CONTROL
3.4.1 Impervious Sections
3.4.2 Random Sections
3.4.3 Pervious Section
3.4.4 Filter Drainage Layers
3.4.5 Rock Fill
3.5 COMPACTION
3.5.1 Equipment
3.5.1.1 Tamping Rollers
3.5.1.1.1 Towed
3.5.1.1.2 Self-propelled
3.5.1.2 Vibratory Rollers
3.5.1.3 Rubber-tired Rollers
3.5.1.4 Power Tampers
3.5.2 Impervious Fill
SECTION 35 73 13 Page 2
3.5.3 Pervious Fill
3.5.4 Additional Rolling for Compaction
3.5.5 Filter and Transition Drainage Layers
3.5.6 Rock Fill
3.6 BACKFILL
3.6.1 General
3.6.2 Placement
3.7 FIELD QUALITY CONTROL
3.7.1 Materials Testing
3.7.1.1 Soil Classification Tests
3.7.1.2 Cohesive Material Testing
3.7.1.3 Moisture Density Relationships
3.7.1.4 Water (Moisture) Content Tests
3.7.1.5 In-place Density Testing for Cohesive Materials
3.7.1.6 Cohesionless Material Testing
3.7.1.6.1 Compaction Tests
3.7.1.6.2 In-place Density Tests
3.7.1.6.3 Water (Moisture) Content Tests
3.7.1.6.4 Additional Testing
3.7.1.7 Materials
3.7.1.8 Fill Placement
3.7.1.9 Grade and Cross Section
3.7.1.10 Testing by the Government
3.7.1.11 Reporting
3.8 SLIDES
3.9 PIEZOMETERS, SETTLEMENT GAGES AND SURFACE REFERENCE MARKS
3.9.1 Government Installed Piezometers
3.9.2 Location and Installation of Settlement Gages
3.9.3 Surface Reference Marks
SECTION 35 73 13 Page 3
**************************************************************************
USACE / NAVFAC / AFCEC UFGS-35 73 13 (November 2018)
------------------------------------
Preparing Activity: USACE Superseding
UFGS-35 73 13 (January 2008)
SECTION 35 73 13
**************************************************************************
NOTES: This guide specification covers the
requirements for preparing the embankment and
blanket foundations and placing and compacting all
permanent fills and backfills for earth and rock
fill dams. This section was originally developed
for USACE Civil Works projects.
PART 1 GENERAL
**************************************************************************
NOTE: This guide specification provides for
furnishing all plant, labor, and equipment, and
performing all operations in connection with the
SECTION 35 73 13 Page 4
placement of embankment materials for earthen or
rockfill dams.
**************************************************************************
NOTE: If Section 01 20 00 PRICE AND PAYMENT
PROCEDURES is included in the project
specifications, this paragraph title (UNIT PRICES)
should be deleted from this section and the
remaining appropriately edited subparagraphs below
should be inserted into Section 01 20 00 as
appropriate.
**************************************************************************
**************************************************************************
NOTE: Include separate paragraphs for each type of
compacted fill material that will be required for
the construction of the dam, and select the
appropriate bracketed description for each.
**************************************************************************
1.1.1.1 Payment
SECTION 35 73 13 Page 5
1.1.1.3 Unit of Measure
**************************************************************************
NOTE: Include separate paragraphs for each type of
backfill material that will be required for the
construction of the dam, and select the appropriate
bracketed description for each.
**************************************************************************
1.1.2.1 Payment
1.1.2.2 Measurement
**************************************************************************
NOTE: If several classes of material are to be used
to include transition zones or a multi-stage filter,
a separate pay item should be included for each
class.
**************************************************************************
1.1.3.1 Payment
Payment will be made for costs associated with obtaining filter [sand]
[gravel] [rock], [transportation to the site (whether from required
excavation, borrow, or commercial source),] mixing the materials to the
required gradation, spreading, moisture control, compacting, removing
objectionable materials, and all other incidental work required for the
construction, protection, and maintenance of the filter. This payment is
in addition to any payment for excavation (from required excavation or
borrow) of the material as specified in Section 31 00 00 EARTHWORK.
SECTION 35 73 13 Page 6
1.1.3.2 Measurement
**************************************************************************
NOTE: If several classes of rock fill material are
used, a separate pay item should be included for
each class of material.
**************************************************************************
1.1.4.1 Payment
Payment will be made for costs associated with rock fill, including all
operations with excavation, quarrying, stockpiling, hauling, placing,
moisture conditioning, removing objectionable material, and all other
operations incidental to the placement of the rock fill.
1.1.4.2 Measurement
Rock fill will be measured for payment in place based upon the established
limit lines and the payment lines indicated on the cross sections shown on
the plans or as otherwise established. Limit lines will be established by
the volume between the foundation lines as determined on the basis of a
survey made from excavation [and accomplishment of foundation preparation
(except scarifying) ]and the lines, grades and slopes of the accepted
embankment.
**************************************************************************
NOTE: If an end result (production) specification
is used for compaction in section COMPACTION, delete
this item.
**************************************************************************
1.1.5.1 Payment
Payment will be made for costs associated with additional rolling for
compaction.
1.1.5.2 Measurement
**************************************************************************
SECTION 35 73 13 Page 7
NOTE: Delete the bracketed reference to Section
35 73 13 if this paragraph is not moved to Section
01 20 00.
**************************************************************************
**************************************************************************
NOTE: The installation of instrumentation is not
strictly speaking an activity of construction of an
embankment dam. This activity should be placed
within its own specification division as an item of
SPECIAL CONSTRUCTION. There is presently no UFGS
guide specification for this item. The
specification writer should consider the use of a
section for SPECIAL CONSTRUCTION, and if so, delete
the following paragraphs.
1.1.6.1 Payment
1.1.6.2 Measurement
1.2 REFERENCES
**************************************************************************
NOTE: This paragraph is used to list the
publications cited in the text of the guide
specification. The publications are referred to in
the text by basic designation only and listed in
this paragraph by organization, designation, date,
and title.
SECTION 35 73 13 Page 8
Use the Reference Wizard's Check Reference feature
when you add a Reference Identifier (RID) outside of
the Section's Reference Article to automatically
place the reference in the Reference Article. Also
use the Reference Wizard's Check Reference feature
to update the issue dates.
SECTION 35 73 13 Page 9
ASTM D2937 (2017; E 2017; E 2018) Standard Test
Method for Density of Soil in Place by the
Drive-Cylinder Method
1.3 DEFINITIONS
**************************************************************************
NOTE: Add applicable definitions as appropriate for
the project.
**************************************************************************
1.3.1 Embankment
Compacted fill includes all fill, except backfill and rock fill, deposited
in layers and compacted by rolling or tamping. The types of compacted
earth fill are:
SECTION 35 73 13 Page 10
d. Filter drainage layers forming the horizontal [and/or vertical or
inclined] pervious drainage blankets.
All fill, deposited in layers but not compacted except by the controlled
movement of hauling and spreading equipment.
1.3.4 Backfill
**************************************************************************
NOTE: Unsatisfactory material will be defined in
accordance with ASTM D2487. This paragraph should
be edited as appropriate to delete inapplicable
materials.
**************************************************************************
**************************************************************************
SECTION 35 73 13 Page 11
NOTES: Where roads are to be used by other
Contractors, the limits of responsibility should be
stated in the specifications.
1.5 SUBMITTALS
**************************************************************************
NOTE: Review Submittal Description (SD) definitions
in Section 01 33 00 SUBMITTAL PROCEDURES and edit
the following list, and corresponding submittal
items in the text, to reflect only the submittals
required for the project. The Guide Specification
technical editors have classified those items that
require Government approval, due to their complexity
or criticality, with a "G." Generally, other
submittal items can be reviewed by the Contractor's
Quality Control System. Only add a “G” to an item
if the submittal is sufficiently important or
complex in context of the project.
SECTION 35 73 13 Page 12
For Army projects, fill in the empty brackets
following the "G" classification, with a code of up
to three characters to indicate the approving
authority. Codes for Army projects using the
Resident Management System (RMS) are: "AE" for
Architect-Engineer; "DO" for District Office
(Engineering Division or other organization in the
District Office); "AO" for Area Office; "RO" for
Resident Office; and "PO" for Project Office. Codes
following the "G" typically are not used for Navy
and Air Force projects.
Plan of Operations; G, DO
Foundation Inspection; G, DO
SECTION 35 73 13 Page 13
Professional Geotechnical Engineer or Geologist, documenting the
inspection. The report must include, at a minimum, a description
of each geologic stratum encountered along the slopes and
excavation bottom, laboratory testing results if any tests were
performed, and other pertinent information. The report's main
body must be a color copy submitted to the Government within four
calendar days of completion of the inspection by the Contractor's
geologist. Include figures, tables and photographs as necessary.
Testing; G, RO
SD-07 Certificates
Testing; G, RO
Nuclear Density; G, RO
PART 2 PRODUCTS
2.1 MATERIALS
**************************************************************************
NOTE: This paragraph may be modified to specify
soils for various types of fill in accordance with
the Unified Soil Classification System. When this
is done, the optional sentence should be selected.
**************************************************************************
SECTION 35 73 13 Page 14
2.1.1 General
The origin of any fill material in no way determines where it may be used
in the embankment. Obtain materials for embankment fills from required
excavations, from the borrow areas indicated, or from off-site commercial
sources as required. The intention is to use the most suitable materials
obtainable from these sources. Material to be wasted will be specifically
designated at the time the material is excavated. Materials containing
brush, roots, sod, organics or other perishable materials will not be
considered suitable. The suitability of the materials are subject to
approval and their disposition in the embankment will be as directed.
Excavate in the borrow areas in the location determined by the Contracting
Officer, whenever such control is necessary to obtain the type of material
required for the embankment. Use borrow pits in accordance with Section
31 00 00 EARTHWORK paragraph SELECTION OF BORROW MATERIAL and paragraph
OPENING AND DRAINAGE OF EXCAVATION AND BORROW PITS. Mixing of materials
during the excavating process at the borrow area may be required.
**************************************************************************
NOTE: The designer may choose to limit the
definition of impervious with restriction on liquid
limit, plasticity index, or fines content. If so,
those restrictions should be added to paragraph
2.1.2.
**************************************************************************
Provide material for compacted random fill consisting of any or all types
of satisfactory material which are suitable for use in the dam embankment.
Material for compacted pervious fill must be clean, free draining sand or
sand and gravel obtained from natural deposits [within borrow areas and
from designated excavations][ or ][from sources designated]. Provide
particles of material that are free from any objectionable coating and not
more than [_____] percent of the material, by weight, and passing a 0.075
mm No. 200 sieve.
2.1.6 Backfill
SECTION 35 73 13 Page 15
otherwise directed.
[_____] [_____]
[_____] [_____]
[_____] [_____]
2.1.8.1 Rock
Stone classed as "rock" must be sound; well graded and free draining.[
The presence of rock meeting the requirements of slope protection, Section
35 31 19 STONE, CHANNEL, SHORELINE/COASTAL PROTECTION FOR STRUCTURES, will
not be objectionable.] Obtain rock from required excavation[ and from
already existing stockpiles][ and from designated quarries]. Shales,
mudstone and other rock and excavated material unsuitable for use as rock
fill, will be wasted in designated spoil areas.
PART 3 EXECUTION
3.1 CONSTRUCTION
**************************************************************************
NOTE: If settlement of the foundation is expected
during construction, install settlement gages as
detailed in 3.9.2 and 1.1.11.
**************************************************************************
SECTION 35 73 13 Page 16
made to compensate for shrinkage or consolidation of the embankment
material or foundation during construction of the embankment, will not
exceed five percent of the height above the foundation indicated without
the approval of the Contracting Officer. The end slopes and side slopes
of partial fill sections must not be steeper than[ one vertical on [_____]
horizontal][ those shown].
**************************************************************************
NOTE: General preparation of the foundation for dam
construction should be addressed in Section 31 66 10
ROCK FOUNDATION PREPARATION. The following
paragraphs may be deleted or modified as appropriate
to provide explicit direction to preparation of
surfaces for placement of embankment fill.
**************************************************************************
3.2.1 Earth
SECTION 35 73 13 Page 17
trench] and immediately prior to placement of compacted fill in any
section of the embankment, loosen the foundation of such section
thoroughly by scarifying, plowing, discing or harrowing to a minimum depth
of [_____] mm [_____] inches, and adjust the moisture content to the
amount specified in paragraph MOISTURE CONTROL for the appropriate type of
material, except in areas where this requirement is waived by the
Contracting Officer. After removal of roots or other debris turned up in
the process of loosening, compact the entire surface of the embankment
foundation area [by [_____] complete coverages of the compaction equipment
as specified for the appropriate type of fill in accordance with paragraph
COMPACTION.] [compacted to a density of [_____] percent in accordance with
paragraph COMPACTION.][ Proof roll foundation areas in accordance with
Section 31 00 00 EARTHWORK paragraph PROOF ROLLING.]
3.2.2 Rock
Claen all rock surfaces upon which or against which embankment materials
are to be placed in accordance with the applicable provisions of Section
31 00 00 EARTHWORK and Section 31 66 10 ROCK FOUNDATION PREPARATION.[
Prior to the placement of embankment material upon or against a rock
surface, fill all open joints and cracks in that surface with mortar to
the depths cleaned. Fill those portions of such rock surfaces where, in
the opinion of the Contracting Officer, the compaction of the embankment
materials cannot be accomplished satisfactorily with power tampers or
other specified compaction equipment with mortar or concrete as directed
to the extent necessary to permit satisfactory use of the compaction
equipment. Do no leave a thin coat of mortar on smooth, intact rock
surfaces. Remove large rock overhangs and protrusions by pre-splitting or
line drilling techniques in such a manner as to minimize damage to the
underlying rock, or the spaces beneath overhangs and fill around
protrusions with consolidated concrete so that satisfactory compaction of
embankment materials can be accomplished. Provide vertical surfaces that
are no more than [_____] meters [_____] feet in height, and provide
benches of sufficient width as necessary so that the average slope of any
rock face is not steeper than [_____] vertical on [_____] horizontal.
Provide mortar and concrete, including forming as necessary, conforming
with the applicable provisions of Section [03 30 53 MISCELLANEOUS
CAST-IN-PLACE CONCRETE][03 30 00 CAST-IN-PLACE CONCRETE][_____].]
SECTION 35 73 13 Page 18
the surface preparation and placement of Embankment Fill, Filter Material,
Mud Mat, or concrete. The Contractor will cooperate to the extent
necessary to assist in the inspection. This will include having equipment
and personnel available to assist excavating, compacting, proof rolling,
cleaning, etc. The Contractor must coordinate his schedule for foundation
preparation and final cleanup with the Contracting Officer to ensure that
the cleanup and inspection proceed in an orderly manner.
][Proof roll the earth foundation by a fully loaded dump truck or approved
roller to detect and eliminate soft spots in the foundation.
a. Keep traffic and equipment away from test areas during testing to
ensure personnel safety and to prevent ground vibrations;
SECTION 35 73 13 Page 19
preparation, and before dental treatment. During excavation and
foundation mapping, remove any temporary ramps covering side slopes such
that the excavation side slopes can be documented and mapped by the
Government. The Contractor must provide equipment to perform test pits as
deemed necessary by the Government geologist and engineers performing the
excavation mapping.
d. Water jet - A water jet consists of a high flow nozzle with a supply
hose connected to a suitable source of water. Provide a system
capable of delivering up to 24 gpm. The flow rate must be
controllable at the nozzle.
]3.3 PLACEMENT
3.3.1 General
Do not place fill on any part of the embankment foundation until such
areas have been inspected and approved by the Contracting Officer in
writing. The gradation and distribution of materials throughout the
compacted earth fill section of the dam must be such that the embankment
will be free from lenses, pockets, streaks, and layers of material
differing substantially in texture or gradation from surrounding material
of the same classification. Dump successive loads of material at
locations on the fill as directed or approved. Do not place fill upon a
frozen surface, nor incorporate snow, ice, or frozen earth in the
embankment. Fill will not be placed on or against any dry surface, but
against a surface that is moist or damp.
SECTION 35 73 13 Page 20
3.3.3 Rate of Placement
**************************************************************************
NOTE: If construction of the embankment involves a
closure section, the following considerations should
be taken into account and specified by the designer,
if required.
Place random fill in the random sections of the embankment as shown on the
plans.
SECTION 35 73 13 Page 21
impervious section to the [pervious section][outer portions of the
embankment].
**************************************************************************
NOTE: Where there are vertical or inclined filters
and horizontal filters, a different tolerance may be
indicated for each.
**************************************************************************
Place [sand filters][, gravel filters,][ and ][sand and gravel filters] in
the embankment in the manner described and to the lines and grades
indicated. Tolerance of plus or minus [_____] mm inches will be allowed.
3.3.8 Rockfill
3.3.9 Spreading
SECTION 35 73 13 Page 22
properly with the succeeding layers, loosen it by harrowing, or by any
other approved method, before the succeeding layer is placed. At all
times during the dumping and spreading processes, maintain a force of men
adequate to remove all roots and debris from all embankment materials and
all stones of greater than [_____] mm inches in maximum dimension from
impervious materials and greater than [_____] mm inches in maximum
dimension from pervious materials, except filters. Remove stone, roots,
and debris from the embankment and dispose of in an approved manner.
Maintain the entire surface of any section of the embankment under
construction in such condition that construction equipment can travel on
any part of any one section. Remove ruts in the surface of any layer by
scarifying before placing and compacting additional material.
**************************************************************************
NOTE: It is preferable to moisture condition the
impervious fill material either at the excavation
site, borrow site, or another area that is not on
the embankment itself.
**************************************************************************
The moisture content after compaction must be uniform throughout any one
layer of impervious materials placed. The moisture content after
compaction as determined by ASTM D2216 must be within the limits of
[_____] percentage points above optimum and [_____] percentage points
below optimum moisture content.
Process material such that the moisture content is within [_____] percent
of the specified range prior to placing the material on the embankment.
This may require material processing either at the borrow/excavation site
or other location near the embankment. Harrowing, or other approved
methods may be required ensure a uniform distribution of moisture.
If, in the opinion of the Contracting Officer, the top or contact surfaces
of the partial fill section become too dry to permit suitable bond with
the succeeding lift, the Contractor will be required to moisture condition
the materials on the fill. The Contractor will loosen the dried materials
by scarifying or discing to such depths as may be directed by the COR,
dampen the loosened material to an acceptable moisture content, and
SECTION 35 73 13 Page 23
compact this layer in accordance with the applicable requirements of
paragraph COMPACTION, subparagraph IMPERVIOUS FILL.
**************************************************************************
NOTE: The designer should determine if specified
control of the moisture content of the random
portions of the embankment is important. In many
cases, the density is the only consideration and the
random sections may be specified to achieve a
certain density regardless of moisture content.
**************************************************************************
The upper and lower limits of moisture content, and the moisture control
procedures for random materials must be [the same as that specified for
impervious material, or pervious material, dependent upon which of these
types it most nearly resembles][such that the specified density can be
achieved].
Moisture control of graded gravel filter and bedding layers will not be
required and sluicing will not be permitted. Moisture control of filters
containing a predominate amount of sand particles will be as required to
achieve the density specified in paragraph COMPACTION.
3.5 COMPACTION
3.5.1 Equipment
**************************************************************************
NOTES: In determining the use of a method
specification versus an end-result (production)
SECTION 35 73 13 Page 24
specification, the following should be considered:
SECTION 35 73 13 Page 25
c. In compacting materials consisting of shales,
sandstones, weathered rock and similar random
materials, consideration should be given to
specifying sheepfoot-type tamping equipment that has
been modified by replacing the standard feet with
"chisel" point tamper feet generally referred to as
"shale breakers". The end areas of these modified
tamper feet tend to break up weathered rock to
prevent the bridling effect sometimes created by
large rock particles.
3.5.1.1.1 Towed
**************************************************************************
NOTE: Towed rollers are generally obsolete and
seldom used in modern construction. The
specification writer should delete this section
unless there is an expectation that towed roller
will be used.
**************************************************************************
SECTION 35 73 13 Page 26
personnel responsible for opening pressure-relief valves periodically to
ascertain that valve openings are free from plugging to assure that any
pressure developed in roller drums is released at each inspection.]
Provide at least one tamping foot for each [_____] square mm[_____] square
feet of drum surface. The length of each tamping foot from the outside
surface of the drum must be not more than [_____] mm [_____] inches and
must be maintained at not less than [_____] mm [_____] inches. The
bearing surface of each tamping foot must be flat with a surface area not
less than [_____] mm [_____] inches nor more than [_____] mm [_____] inches.
During the operation of rolling, the spaces between the tamping feet must
be maintained clear of materials which would impair the effectiveness of
the tamping rollers. The weight of a roller when fully loaded must be not
less than [_____] N/m[_____] pounds per foot of drum length, and the
weight of a roller empty must be not more than [_____] N/m[_____] pounds
per foot of drum length. The bearing surface, tamping foot size, the drum
loading, and the operation of the rollers must be as required to obtain
the desired compaction. If more than one roller is used on any one layer
of fill, all rollers so used must be of the same type and essentially of
the same dimensions. Draw rollers by crawler-type or rubber-tired
tractors at a speed not to exceed [_____] km/h[_____] mph. Discontinue
the use of rubber-tired towing equipment if the tires leave ruts that
prevent uniform compaction by the tamping roller, and the substitution of
crawler-type towing equipment may be directed.
3.5.1.1.2 Self-propelled
SECTION 35 73 13 Page 27
than [_____] N[_____] pounds. [For self-propelled rollers with drums
capable of being ballasted with fluid, equip each drum with at least one
pressure-relief valve and with at least one safety head. The safety head
must be equal to union type safety heads equipped with rupture discs
suitable for rupturing pressures between 350 and 500 kPa50 and 75 psi.
The pressure relief valve is a manually operated valve and must be opened
periodically. Instruct personnel responsible for opening pressure-relief
valves periodically to ascertain that valve openings are free from
plugging to assure that any pressure developed in roller drums is released
at each inspection.] For self-propelled rollers in which steering is
accomplished through the use of rubber-tired wheels, the tire pressure
must not exceed [_____] kPa[_____] psi. Discontinue use of the compactor
if the tires leave ruts that prevent uniform compaction by the tamping
roller and the substitution of appropriate towed tamping rollers may be
directed. When a self-propelled roller is provided with a dozer blade, do
not count coverages made with the blade in operation as compaction
coverages. Operate self-propelled rollers at a speed not to exceed
[_____] km/h[_____] mph.
Equip vibratory rollers for compacting rock fills, pervious sand and
gravel fills, or filter and transition drainage layers with a smooth steel
compaction drum and operate at a frequency of vibration during compaction
operations between 1100 and 1500 vibrations per minute (vpm). Provide
vibratory rollers that are either towed or self-propelled and that have an
unsprung drum weight that is a minimum of 60 percent of the rollers'
static weight. Provide towed rollers that have at least 90 percent of
their weight transmitted to the ground through the compaction drum when
the roller is standing in a level position hitched to the towing vehicle.
Rollers for compacting rock fill, [sand and gravel fills, or filter and
drainage layers] must have a minimum static weight of [_____] kN [_____]
pounds, a minimum dynamic force of [_____] kN [_____] pounds when
operating at 1400 vpm, and an applied force not less than [_____] kN/m
[_____] pounds per foot of compaction drum length. [Rollers for
compacting sand and gravel fills or filter and drainage layers must have a
minimum static weight of [_____] kN [_____] pounds, a minimum dynamic
force of [_____] kN [_____] pounds when operating at 1400 vpm, and an
applied force not less than [_____] kN [_____] pounds nor greater than
[_____] kN/m [_____] pounds per foot of compaction drum length.] The
level of amplitude and vibration frequency during compaction will be
maintained uniform throughout the embankment zone within which it is
operating. Operate rollers at speeds not to exceed [_____] km/h [_____]
mph.
SECTION 35 73 13 Page 28
[_____] mph. The character and efficiency of this equipment will be
subject to approval.
After a layer of impervious fill material has been dumped and spread,
harrow it if required, to break up and blend the fill materials, to remove
laminations, ruts or smooth surfaces to enhance bonding between layers.
Perform harrowing to the full depth of the layer.
When the moisture content and the condition of the layer is satisfactory,
compact the lift [to at least [_____] percent of maximum dry density as
determined by ASTM D698, prior to placement of the next layer.
Determination of in-place density must be in accordance with
ASTM D1556/D1556M and ASTM D6938.][by [not less than ][[_____] complete
coverages of the tampering roller][[_____] complete coverages of the
rubber-tired roller].][ Provide complete coverage consisting of the
coverage of the entire lift to be compacted with the roller specified.][
A complete coverage must consist of the application of compactive effort
to the entire lift to be compacted with a single roller drum having the
characteristics as specified in paragraph SELF-PROPELLED. The use of
four-drum self-propelled equipment that is laterally separated by
operator's cab and differential may be used; however, two complete
coverages of the lift to be compacted will be achieved by a subsequent
offset trip of the roller for coverage of the previously uncompacted
central portion of the roller path.] Place portions of the fill which are
not accessible to the roller [_____] mm inch layers loose measurement and
compacted with power tampers to a degree equal to that obtained on the
other portions of the compacted fill by rolling as specified in accordance
with paragraph BACKFILL. Dumping, spreading, sprinkling, and compacting
may be performed at the same time at different points along a section when
there is sufficient area to permit these operations to proceed
simultaneously.
After each layer of pervious material has been dumped and spread, and the
moisture content is in accordance with the provisions of paragraph
PERVIOUS SECTION, compact the entire surface of the layer [to an average
of [_____] percent minimum relative density][by not less than [_____]
complete coverages of [the rubber-tired roller][the vibratory roller]].
**************************************************************************
SECTION 35 73 13 Page 29
NOTE: The following paragraph for Transition Layers
does not include bedding for riprap slope
protection, which should be provided under Section
35 31 19 STONE, CHANNEL, SHORELINE/COASTAL
PROTECTION.
**************************************************************************
After the rock fill has been dumped and spread to the thickness specified,
compact the entire surface of the layer by not less than [_____] complete
coverages of the vibratory roller specified in paragraph VIBRATORY
ROLLERS. Provide a complete coverage consisting of the entire coverage of
the area with one trip of the equipment specified. Each trip of the
roller must overlap the adjacent trip not less than [_____] mm feet.
3.6 BACKFILL
3.6.1 General
SECTION 35 73 13 Page 30
3.6.2 Placement
**************************************************************************
NOTE: FAR Part 46.312 establishes a requirement for
Contractor Quality Control (CQC) in construction
contracts and ER 1180-1-6 requires that a CQC
section based on Section 01 45 00 QUALITY CONTROL be
included in contracts of $1,000,000 or more. Use of
Section 01 45 00 for contracts of less than
$1,000,000 is discretionary. This part of the
specifications must be consistent with the CQC
section.
Establish and maintain field quality control for embankment and backfill
operations to assure compliance with contract requirements and maintain
detailed records of field quality control for all operations including but
not limited to the following:
**************************************************************************
NOTE: Types of tests and frequency of testing
should be detailed below. Types of tests and
frequency of testing will be dependent upon the
types of materials utilized, configuration of
foundation and embankment, placement and compaction
procedures required, moisture control requirements
etc. Testing requirements are material type
specific rather than embankment fill type specific.
It is desirable to present the testing frequency and
type in tabular form.
**************************************************************************
SECTION 35 73 13 Page 31
Perform sufficient testing to ensure that the fill is being constructed as
specified. The testing program specified below will be considered the
minimum acceptable frequency of testing. This does not relieve the
Contractor from the responsibility of performing additional testing, if
required to ensure compliance with these specifications.
**************************************************************************
NOTE: Edit the following to comply with the method
selected to determine the optimum properties (i.e.,
density and moisture content, LL, PL, PI).
**************************************************************************
**************************************************************************
SECTION 35 73 13 Page 32
NOTE: The designer should pick the method or
methods of In-place density which are acceptable.
If uncompacted fill is specified density control may
not be required.
SECTION 35 73 13 Page 33
k. Wet density by each test method and the deviation.
l. Pass/Fail.
m. Retest.
n. Comments.]
Run not less than one relative density test for every [3,000] [_____]
cubic m[3,900] [_____] cubic yards of cohesionless fill in accordance with
ASTM D4253 and ASTM D4254.
SECTION 35 73 13 Page 34
][3.7.1.6.4 Additional Testing
]]3.7.1.7 Materials
Surveys to verify that the dimensions, slopes, lines and grades conform to
those shown on the drawings.[ Surveys to monitor settlement gages to
measure foundation settlement.] [ Surveys to locate core boring locations
and elevations to determine foundation settlement.]
During the life of this contract, the Government [or its Contractors] will
perform quality assurance tests. Make available to the Government [or its
Contractors] the equipment to perform these test.
3.7.1.11 Reporting
On a daily basis, furnish the inspection records and all material testing
results, [the quantity of fill placed,] as well as the records of
corrective action taken, in accordance with Section 01 45 00 QUALITY
CONTROL.
3.8 SLIDES
**************************************************************************
NOTE: The installation of instrumentation is not
strictly speaking an activity of construction of an
embankment dam. This activity should be placed
within its own specification division as an item of
SPECIAL CONSTRUCTION. There is presently no UFGS
guide specification for this item. The
SECTION 35 73 13 Page 35
specification writer should consider the use of a
section for SPECIAL CONSTRUCTION, and if so, delete
the following paragraphs.
SECTION 35 73 13 Page 36
] -- End of Section --
SECTION 35 73 13 Page 37