Commissioning Concept
Commissioning Concept
COMMISSIONING CONCEPT
BMU
Virtual
Quality higher education
02/02/218
1
“UMBVirtual
U Quality higher education
CONTENT
CONTENT...............................................................................................................................2
COMMISSIONING:...............................................................................................................5
RETRO-COMMISSIONING..................................................................................................5
RE-COMMISSIONING..........................................................................................................5
ONGOING COMMISSIONING.............................................................................................6
1. COMMISSIONING PLANNING.......................................................................................7
2. Construction and acceptance Phase:..............................................................................11
2. ORGANIZATION OF THE COMMISSIONING............................................................12
3. DOCUMENTATION GENERATED............................................................................25
4. ROLE OF THE SUPERVISOR OR ENGINEER.........................................................26
Commissioning Agencies: will include:................................................................................27
5. TYPICAL RESPONSIBILITIES...................................................................................28
6. EXECUTION OF COMMISSIONING.........................................................................32
MEETINGS...........................................................................................................................32
Sensor Calibration Methods..................................................................................................34
REPORTS..............................................................................................................................35
11. MECHANICAL COMPLETION....................................................................................36
Electric Area..........................................................................................................................37
Structural...............................................................................................................................38
Protection...............................................................................................................................39
Architecture...........................................................................................................................39
12. PRE-COMMISSIONING ACTIVITIES.........................................................................39
Design capabilities.................................................................................................................40
13. COMMISSIONING ACTIVITIES............................................................................40
14. START UP.................................................................................................................41
15. Bibliography...............................................................................................................41
2
“UMBVirtual
U Quality higher education
14.
3
“UMBVirtual
U Quality higher education
4
“UMBVirtual
U Quality higher education
RETRO-COMMISSIONING
5
“UMBVirtual
U Quality higher education
RE-COMMISSIONING
It is the application of the start-up process that applies to projects that have
previously been commissioned. During construction operations, systems may be out
of balance or may be adjusted. As a result, it cannot operate in an efficient manner.
Additionally, the needs of a facility may change as usage, maintenance, and
changing technologies. The Re-commissioning Process underway brings a high
quality delivered project to the standards set by either the owner's original or revised
project requirements. An ongoing Re-Commissioning Process can usually be
implemented relatively cheaply as the documentation is available at the original
commissioning.
ONGOING COMMISSIONING
It is the constant application of the commissioning process of a building that has been
previously commissioned or Commission-retro. Continuous commissioning ensures
that a facility does not stray away from the current owner's Project Requirements;
requirements that must be updated as part of the process. Continuous commissioning
is a very effective method for keeping energy costs low and minimizing system
problems caused by neglect and changes to construction operations.
6
“UMBVirtual
U Quality higher education
7
“UMBVirtual
U Quality higher education
correctly, and was rejected most successfully for the user and reasonably ensures
the next step verification so that regulated industries will be successful.
Given this definition, engineers have always commissioned projects to a degree.
Example, when a new pump is installed, proper rotation and flow are verified. Before
it is installed, the model number and construction materials are confirmed.
8
“UMBVirtual
U Quality higher education
very useful, especially for application to comparable situations. They are also
systematic, in a way, especially in providing templates and checklists to guide
professionals.
However, there is a lack of holistic or integration models. At the next highest level of
abstraction, that is the process of putting it in general. At this level we are not so
interested in the specific experiences of each case, but rather in the fundamental
principles and methodology. What exists at this level is mainly in the area of
instrumentation and control.
Thus, existing start-up strategies can be classified into three types. These are: (a)
informal, which is action-oriented problem-solving; and (b) template, which involves
using a checklist or operating procedure that you worked on before or in another
situation. Both (a) and (b) are based on the assumption that startup is a routine set of
tasks. The third strategy challenges that premise and requires a deliberately
thoughtful approach. Thus, the third category is (c) methodological, which involves
the analysis of situational needs and the deliberate selection of the most relevant of
the different possible commissioning methods.
In the planning phase, getting the project underway may involve creating a rubric to
evaluate progress at various stages and keep the project on track. If the client is a
university building a new science laboratory, for example, the first step would be to
indicate what type of facility the university needs, and the launch of the project may
include researching the codes. construction and solicit feedback from university staff
members to find out what type of facilities are needed and develop a plan for building
them.
As the project moves out of planning and the development team begins to work on it,
the commissioning of the project continues. Staff will periodically evaluate the project
to see if the needs and objectives remain the same and to confirm that the
development is left blank. As circumstances require, they must be resolved, and
these may include the need to address new requests or failure to properly
accommodate a goal during the project planning stage.
Once the project is completed, the project commissioning moves into the final stage
with a rigorous check and investigation of all the systems in the project to see if they
are working properly. Ideally, as systems are implemented, developers will be able to
test them, but they have to check them again on target. In something like a building,
9
“UMBVirtual
U Quality higher education
this includes tasks like flipping all the light switches, summoning elevators, and
adjusting thermostats to test heating and cooling systems. It may also involve
pushing systems to their limits to see how they respond, such as loading an elevator
to its maximum stated capacity and then measuring their performance.
This approach to quality control is not only useful for new projects. Project
commissioning is also valuable for the rehabilitation and renewal of existing projects.
The same series of steps provides continuous information about the progress of the
project. In the planning stages, team members can discuss what they want to do, how
they plan to achieve it, and the methods they can use to measure success. During
project development they will continually re-evaluate, and will finish with a thorough
audit of the project before handing it off to the recipient.
a. COMMISSIONING PROCESS
The commissioning always bases its planning within the framework of the start-up
documents.
The pre-commissioning plan provides guidance in executing the commissioning
process. The specifications will have priority over the Commissioning Plan.
Commissioning the process: The following is a brief overview of typical
commissioning tasks during construction and the general order in which they occur
on any project:
4. The Planning Officer works with the Contractor in each discipline in developing
commissioning plans and start-up documentation formats, including providing
the Contractor with construction checklists to be completed during installation
and commissioning during the process. .
1
0
“UMBVirtual
U Quality higher education
6. Contractors, under their own direction, will execute and document the
completion of construction checklists upon start-up and initial departure.
Commissioning documents must be in accordance with the checklists and
commissioning were carried out in accordance with the approved plans. This
may include the planner's assistance in witnessing the commissioning of
selected equipment.
7. The project planner develops, organizes the work team and the functional
system, specifies performance testing procedures.
8. Functional testing procedures are reviewed with the project engineer, planner,
and contractors.
10. During the initial functional tests and for critical equipment, the Engineer will
witness the tests.
13. The project will not be considered complete until substantially the conclusion
of the functional commissioning tests and procedures defined in the
Commissioning Plan are complete and documented with results to complete
satisfaction in accordance with the objectives set from the first commissioning
meeting.
14. The planner's opinions and coordination of the training provided by the
Contractors should be verified as being completed.
1
1
“UMBVirtual
U Quality higher education
a. Facilitate the coordination of commissioning work between the planner, and with
the GC where they ensure that commissioning activities are being scheduled in the
master schedule.
b. Include the start-up cost in the total contract price.
c. Provide a copy of all construction documents, additions, change orders, approved
submissions, plans, schematics and diagrams related to the equipment ordered by
the planner.
d. In each written purchase order or subcontract, include requirements for shipping
data, operation and maintenance data, commissioning tasks, and training.
e. Ensure that all Contractors executing the commissioning plan agree to
responsibilities with the Contract Documents and schedule. F. A representative may
attend the first commissioning, meetings and other necessary meetings scheduled by
the commissioning engineer or project planner to facilitate the process.
g. Coordinate and schedule staff training.
h. Provide all requested Submission data, including detailed start-up procedures and
the Owner's specific responsibilities to maintain performance warranties in force.
i. Assist in equipment testing per agreements with subcontractors.
j. Include all special tools and instruments required to test equipment in accordance
with the project drawings, schematics and documentation, except for independent
data recording equipment that may be used by the issuing entity, through contractors
that may be used by the issuing entity. supply products, analyze the specified
products and verify that the Designer has specified the newest or most up-to-date
version of equipment, and that they must be reasonable for the scope and budget of
the project.
1
2
“UMBVirtual
U Quality higher education
End-user requirements and start-up plans are developed for a variety of projects that
use automated systems, including batch and continuous manufacturing processes,
regulated pharmaceutical and food manufacturers, creating start-up applications,
construction automation systems, fire protection and safety systems, machinery
safety applications, instrumentation commissioning, heating, ventilation and air
conditioning commissioning, nuclear power, and energy construction projects
electrical. There are currently more than a dozen professional societies, government
agencies, and other national and international regulatory bodies that have issued
guidance documents and standards related to the commissioning of applications that
use automated systems. These include: American National Standards Institute
(ANSI), American Society of Heating, Refrigerating and Air-Conditioning Engineers
(ASHRAE), ASME (founded as the American Society of Mechanical Engineers),
American Society for Testing and Materials (ASTM), Commissioning Building
Partnership (BCA), German Institute for Standardization (DIN), US Environmental
Protection Agency (EPA), International Atomic Energy Agency (IAEA), International
Electrotechnical Commission (IEC), Institute of Engineers Electrical and Electronics
(IEEE), International Institute of Ammonia Refrigeration (IIAR), International
Organization for Standardization (ISO), International Society of Pharmaceutical
Engineering (ISPE), National Electrical Contractors Association (NECA), National Fire
Protection Association (NFPA), the Injecting Drug Association (PDA), the US
Department of Agriculture (USDA), and the US Green Building Council (USGBC).
These Requirements will constitute the basis of the construction phase start-up
process and procedures. The Service Agent shall add, modify and refine the
commissioning procedures to accommodate field conditions and the actual
manufacturer's equipment, incorporate test data and procedure results, and provide a
detailed schedule for all commissioning. start-up tasks.
Several sections of the project specifications require equipment start-up, testing and
adjustment services. Requirements for commissioning, testing and specification
1
3
“UMBVirtual
U Quality higher education
When training or educational services are needed and specified in other areas of the
project, these services are intended to provide in addition to the training and
educational services copied to the project records files.
1. Verify that equipment and application systems are installed in accordance with
contact documents and in accordance with the manufacturer's recommendations.
2. Verify and document adequate integrated performance of equipment and systems.
3. Verify that Operations and Maintenance documentation is complete.
4. Verify that all components requiring maintenance can be accessed, cleaned and
removed without disturbing nearby components including ducts, pipes, cables or
wiring.
5. Verify that operating personnel have adequate training to enable them to operate,
monitor, adjust, maintain, and construct repair systems effectively and energy-
efficiently.
1
4
“UMBVirtual
U Quality higher education
IEC 62381 Activities during Factory Acceptance Test (FAT), Site Acceptance Test
(SAT) and Site Integration (SIT) for automation systems is being reviewed by the
ISA105 committee to describe best practices related to these capabilities.
ISPE Guide for Pharmaceutical Facilities describes the design, commissioning, and
qualification practices recommended and approved by the Food and Drug
Administration (FDA). The guide is being updated by ISPE.
NFPA Fire Protection Systems Describes test procedures for alarm systems,
pumps, and smoke control systems.
ASTM E-2500 Standard Guide for the Specification, Design, and Verification of
Pharmaceutical and Biopharmaceutical Manufacturing Systems and Equipment used
in regulated industries.
1
5
“UMBVirtual
U Quality higher education
unregulated industries.
The standard is organized primarily using the concept of phases on a timeline. Each
item defined in the standard concludes a phase of activities as summarized below:
1
6
“UMBVirtual
U Quality higher education
Completion of the screening item verifies all mechanical systems are installed in
accordance with the design drawings, applicable codes, and safety requirements, as
outlined in the project specifications, which are approved by the owner. The
contractor is responsible for generating and completing test forms, which identify, in
sufficient detail, the systems being tested, date and time of the test, and the
requirements of the test. The owner must participate in witnessing the tests as
required by the contract. Deficiencies recorded during testing can be managed at
closing with a punchlist, ensuring the owner approves the closing of said items. It also
indicates that the items are closed, the systems have been delivered, and the
completed test forms have been approved by the owner.
Pre-Commissioning
The pre-Commissioning phase of the project begins the second sequence of testing
by the contracting staff. IEC 62337 includes an extensive list of specific pre-
commissioning test procedures in Appendix B. These tests ensure the project
documents and project specifications have been met. Relevant specifications include
P&IDs, equipment and instrumentation indices, equipment drawings, circuit diagrams,
power line diagrams, documentation, software and operating manuals. The contractor
and owner must agree on the scope of responsibilities related to equipment-specific
and general test procedures. Examples of these procedures are listed below.
1
7
“UMBVirtual
U Quality higher education
Upon acceptance of the mechanical completion certificate, the contractor may begin
cold commissioning followed by hot commissioning. Unlike the pre-commissioning
phase, which broadly includes inspection testing, the cold and hot commissioning
phase involves functional testing. Extension of the contractor and owner's personnel
involved in the pre-commissioning phase into service is recommended. Examples of
general categories of functional test procedures used during hot and cold
commissioning are listed below.
1
8
“UMBVirtual
U Quality higher education
Functional testing must be carried out in the appropriate sequence and in a planned
manner to ensure that the systems are operated safely. Commissioning plans and
test forms must be pre-approved by the owner and are used by the contractor to
record observations and control system data. Only trained contractor or supplier
personnel should verify the acceptability of test data. If data is required to fail and a
change to the system is required, the change must be documented in the form
approved by the owner.
Performance Test
After successfully completing the commissioning phase and closing any relevant
punchlist items, the contractor may proceed to the performance testing verification
phase with owner approval. The purpose of performance testing is to verify the
process is operating in a control state. The test must be reviewed and approved in
advance by the owner and must include acceptance criteria, measurement
requirements, sample requirements, and reference to necessary analytical
procedures. The owner, not the contractor, must conduct sample testing unless given
permission to use a third party. The contractor is responsible for submitting a report to
the owner evaluating the results and noting any observations that have failed. The
owner must provide a written response accepting the results or in the case of a
failure, the contractor must be required to remedy the situation in accordance with
contractual requirements. The commissioning process must conclude with a formal
acceptance of the plant through the use of a certificate approved by the contractor
and the owner.
1
9
“UMBVirtual
U Quality higher education
A risk-based approach" It describes methods such as risk management and the use
of quality systems to minimize the risk to public health of adverse events that occur in
pharmaceutical manufacturing facilities. . These concepts were adopted by ASTM
E2500, Standard Guide for the Specification, Design and Verification of
Pharmaceutical and Biopharmaceutical Manufacturing Systems and Equipment. This
standard serves as a model for the regulated industrial start-up process.
ASTM E2500
What exactly is ASTM E2500 and what does it say about the commissioning of
automated manufacturing systems? One should begin with a definition of the term
verification: A systematic approach to verifying that manufacturing systems, acting
individually or in combination, are fit for their intended use, have been installed
correctly, and are operating correctly. This is a general term that covers all types of
approaches to ensuring systems are fit for use, such as training, commissioning and
training, verification, system validation, or other types.
V Risk-based approach
V Scientific basis approach
V Critical aspects of manufacturing systems
V Quality by design
V Good engineering practices
V Skilled
V The use of supplier documentation
V Continuous process improvement
V Risk-based approach
Risk assessments are used to determine the magnitude of potential harm and the
likelihood of it occurring. This principle should be applied to the commissioning
(verification) process to determine, for example, that automated manufacturing
2
0
“UMBVirtual
U Quality higher education
systems pose the greatest risk to patient health if not installed or used improperly. A
contractor for example, could focus on the manufacturing stages when generating
test forms to ensure that verification procedures are robust and well documented.
These features are also known as "enhanced documentation."
Start-up activities should also focus on the critical aspects of manufacturing. They
have been defined as "the functions, characteristics, skills and performance or
characteristics necessary for the manufacturing process and systems to ensure
consistent product quality and safety." For example, commissioning an air treatment
temperature control loop for a cold water supply line, serving an office area, would be
under an unregulated commissioning plan. . However, this would not be considered a
critical aspect of manufacturing and therefore would not be of significant stakeholder
interest to the FDA. The commissioning plan should clearly identify critical aspects as
well as the logic used to determine criticality.
Quality By Design
Design specifications, which refer directly to CQAs and CPPs, must be verified after
installation and during performance runs and monitored during the life cycle of the
installation. The verification process continues after the turnover is made for the
owner, up to the point of disassembly at a regulated facility.
2
1
“UMBVirtual
U Quality higher education
AND
Design Calibration Internal audits
Design Reviews Asset Management Waste management
Construction Seller / Management Decommissioning and
Of Removal
Suppliers
Storage Of Background For
-GMP Non-Compliance Engineering Equipment
Commissioning and Inheritance and Recycling
Training
Billing
To the
SMEs are those people who have the training and experience to properly plan,
execute and approve verification activities. They must lead the manufacturing
systems verification effort. It is a regulatory requirement that only appropriately
trained individuals sign and pass verification test forms.
Supplier documentation may be used for verification activities, provided the vendor
has an acceptable quality system. A quality system can be defined as those
procedures and processes necessary to produce a product, which consistently meets
approved quality standards. Should the owner determine that there are gaps in the
supplier or vendor provided documentation quality systems, they can use additional
verification testing to mitigate the risk or repeat the testing entirely. Examples of
supplier documentation that can be leveraged are FAT, SAT, and SIT.
Continuous Improvement
Change management should be used throughout the facility lifecycle and involve the
2
2
“UMBVirtual
U Quality higher education
quality unit when critical aspects of the manufacturing process are being changed.
After release and final acceptance of the facility, but before production batches, the
operational change management system must be applied. Operational change
management is a more rigorous system that requires prior approval of all changes
related to critical aspects.
The verification process, as defined by E2500, is a phase within the overall life cycle
of the automated manufacturing facility. The main phases of the life cycle presented
in the standard are listed below.
2
3
“UMBVirtual
U Quality higher education
Verification test forms should be developed to ensure that high-risk areas of the
manufacturing process receive the greatest amount of rigorous verification by the
contractor. Unlike IEC 62237, E2500 requires a risk assessment to be carried out to
determine the level of detail of verification testing. Additionally, the quality assurance
unit must approve all verification plans, tests, and acceptance criteria related to CQAs
and CPPs. Supplier documentation assembled in rotation packages or vendor-
supplied testing requires additional levels of scrutiny by the quality unit. No such
quality function is required for unregulated applications. Control inspections must be
reviewed and approved by SMEs that had not carried out the test independently. The
SME also reviews and approves deviations from the verification test plan or failed
tests and approves corrective actions.
The standard defines the role of Quality Risk Management (QRM). QRM should be
used to develop the scope of the commissioning program, which includes controls
and verification methods for critical aspects of the manufacturing operation. The
2
4
“UMBVirtual
U Quality higher education
greater the risk to the patient, the more rigorous the verification process should be.
Design reviews should be a planned activity completed by SMEs in all phases of the
facility life cycle. The scope of design reviews includes project specifications, design
documents, and continuous improvement changes. Change Management should be
used throughout the life cycle of the facility and involve the quality unit when critical
aspects of the manufacturing process are being changed. After release and final
acceptance of the facility, but before production batches, the operational change
management system must be applied. Operational change management is a more
rigorous system that requires prior approval of all changes related to critical aspects.
3. DOCUMENTATION GENERATED
The design documents base how each criterion in the Owner's Project requirements
is implemented in the design. For any criteria that cannot be met, documentation
details what was done, its impact on the Project Requirements Manual, and how the
project requirements will include the respective modifications.
EQUIPMENT DOCUMENTATION REQUIREMENTS
Team Matrix:
A complete list of all equipment, devices and systems, with certain information as
noted herein, must be submitted within the stipulated time of issuance of the Notice to
Proceed with Construction. This list is known as the Team Matrix.
The application forms contain all the information you need to participate in the
program - eligibility requirements, indicators, rates, equipment performance
2
5
“UMBVirtual
U Quality higher education
Application forms are available on the program website and a separate form is
available for each of the project types supported by the program:
Standard lighting
Steam Process / Steam Trap
HVAC Standard / Water Heaters
VFD Standard
Custom projects
Leak Recognition and Repair
New Construction Lighting
Specialized Team
Viability study
Measurement and Monitoring
PWGSC Project Manager: who has overall responsibility for the project and is the
sole point of contact between the client, the designer, the PWGSC Commissioning
Manager and all other members of the project team.
PWGSC Design Quality Review Team: conducts detailed reviews during all stages
of design to ensure appropriate design criteria, design intents, design solutions, that
designs are well developed, commissioning specifications are appropriate for this lab,
transmits technical design information to the Designer. During construction, you can
periodically survey the facilities to observe overall progress.
2
6
“UMBVirtual
U Quality higher education
Designer (i.e. Consultant): Designs the facility to meet the Client's functional and
operational needs and budget, prepares all work documents, including incorporating
commissioning specifications for construction specifications, supervising construction
activities commissioning, testify and certify the accuracy of reported results, testify
and certify TAB and other tests, develops the PI and PV Report Forms, develops the
Building Management Manual, ensures the implementation of this Commissioning
Plan, verification of the operation of all installed systems, application of the Training
Plan.
Agency TAB: Equipment and systems related to measuring and adjusting flow rates
and pressures to meet indicated or specify values (e.g., air and hydraulic duct
systems, fans, pumps).
All Commissioning Agencies will be available for emergency service during the first
year of user occupancy for adjustments and modifications outside the responsibility of
the operation and maintenance personnel. These include costs to comply with
changes in facilities and changes in control strategies beyond the level of training
provided to operation and maintenance personnel.
2
7
“UMBVirtual
U Quality higher education
Client Movement: The step or conditions provided for erection and fit-out, although
not part of commissioning should be given serious consideration by the designer in
order to ensure only minimal disruption to their program activities.
Property Manager: has the responsibility of receiving the renovated premises and is
responsible for the day to day operation and maintenance of the premises and plays
the lead role in the Operation Phase and thereafter.
5. TYPICAL RESPONSIBILITIES
Responsibilities of startup team members are provided in this section to clarify the
startup process.
2
8
“UMBVirtual
U Quality higher education
2
9
“UMBVirtual
U Quality higher education
3
0
“UMBVirtual
U Quality higher education
Test, Adjust and Function and responsibilities when involved in the project:
3
1
“UMBVirtual
U Quality higher education
commissioning.
V Review graphics and performance testing for accuracy, note deficiencies.
V Provide TAB data to Contractor and Teaming before Contractor begins
functional performance testing.
6. EXECUTION OF COMMISSIONING
To execute a commissioning plan, submit a draft Commissioning Plan for review after
issuance of the order to proceed with construction prior to the installation of materials
and equipment that will undergo commissioning and functional performance testing,
according to what is indicated by him.
Contractor shall incorporate user review comments and resubmit the revised
Proprietary Commissioning Plan within the time determined for receipt of comments
following the review.
MEETINGS
TO. Commissioning Meeting: At the beginning of construction, a commissioning
meeting will be scheduled, planned and carried out with the entire
commissioning team.
- General Commissioning Requirements
There are other meetings and conducted by the commissioning coordinator as
construction progresses. These meetings will cover coordination, deficiency
resolution and planning issues with specific contractors. The coordinator will plan
these meetings and will minimize the necessary time spent by contractors. For large
projects, these meetings may be held monthly, until the final one.
COMMISSIONING
A. The following procedures apply to all teams to be commissioned. Some systems
that are not composed as much of current dynamic machinery, for example, electrical
system power quality, may have very simplified control circuits and commissioning.
B. General: Construction checklists are important to ensure that equipment and
systems are properly connected and operating.
The checklists also ensure that functional performance testing (in-depth system
check) can be carried out without unnecessary delays. Each piece of equipment
receives full build checkout. No sampling strategies are used. The construction test
for a given system must be completed successfully prior to the formal, functional
testing of the equipment or subsystems of the given system.
C. Startup and Initial Order Plan: The coordinator will assist team members
3
2
“UMBVirtual
U Quality higher education
responsible for the startup commissioning of any team in developing detailed startup
plans for all teams.
The coordinator's primary role in this process is to ensure that there is written
documentation that each of the manufacturer's recommended procedures has been
completed.
Parties responsible for construction and commissioning checklists are identified at the
initial commissioning meeting and on the checklist forms.
1. The coordinator adapts, if necessary, the representative construction checklists
and procedures of the related sections. These checklists indicate the procedures to
be executed as required start and initial verification of the systems and party
responsible for their execution.
2. The commissioning coordinator provides these checklists and tests. Determine
who is responsible for executing and documenting each of the line item tasks and
take note of potential suppliers. Each form will have more than one merchant
responsible for its execution.
3. The person responsible for purchasing the equipment develops the complete start-
up plan by combining (addition) to the AC Checklists with the manufacturer's detailed
start-up and checking procedures from the operation and maintenance manual and
normality check sheets. of field used. The plan will include checklists and procedures
with specific boxes or log lines and documentation of the verification and inspection of
each procedure and a summary with a signature block at the end of the plan.
to. The complete commissioning plan could consist of something as simple as:
1) The commissioning coordinator's construction checklists.
3) Typically using the manufacturer's check field sheets, the complete commissioning
plan is presented for review and approval.
5. The coordinator views and approves the procedures and format for documenting
them, noting which procedures should be added.
3
3
“UMBVirtual
U Quality higher education
be field-calibrated.
2. All procedures used shall be thoroughly documented on construction checklists or
other approved forms, clearly referencing the procedures followed and written
documentation of initial, intermediate and final results.
Reconnect the sensor. Take a reading with a calibrated test instrument within 6
inches of the site sensor. Check that the sensor reading (via permanent thermostat,
gauge, or system of
automation]) is found within the tolerances in the table below of the instrument-
measured value. If not, change the sensor and repeat. For pressure sensors, perform
a similar process with an appropriate signal generator.
3
4
“UMBVirtual
U Quality higher education
All documentation will be discussed and all procedures and testing forms will be
critical for approval with the coordinator. Contractor will prepare an outline outlining
the responsibilities of the various parties involved in Commissioning for review at this
meeting.
The Laying Plan will be reviewed with all attendees and the scope of work discussed.
Contractor must be prepared to distribute copies of the relevant parts to the various
subcontractors involved in the Commissioning.
REPORTS
• Status reports will be provided on frequencies directed by the commissioning
coordinator.
• You must communicate at least monthly with all members of the start-up team,
keeping them informed of start-up programming and changes.
• Non-compliance and deficiency reports will be submitted to the commissioning
coordinator days following the date of the
non-compliance or deficiency is observed first.
• Final commissioning documentation will be provided to the owner to provide
project closure Procedures, which will become part of the Commissioning and
Closing Manual.
3
5
“UMBVirtual
U Quality higher education
The basis for the execution and documentation of mechanical activities is formed.
Mechanical completion is carried out through all phases of the project, starting with
equipment supplier and continuing through manufacturing to phasing.
• Mechanical completion encompasses all disciplines.
• Development responsibilities are outlined in the commissioning plan.
• Executor of the activities of the Department Coordinator. Mechanical Engineer is
responsible for establishing and compiling mechanical completion records and
reporting status in PCS.
3
6
“UMBVirtual
U Quality higher education
The COWR Number point and the cross reference to the drilling list Record / Check
records must be given.
COWR work will be marked on drawings or sketches and included in the records.
COWR Material Status List (MSL) and marking drawings/instruction shall contain
sufficient information for configuration of work at a later stage.
Typical mechanical finishing activities
Mechanical completion activities include verification of fabrication and installation.
• Visual inspection of the complete and correct installation.
• Internal inspection of tanks and containers.
• Alignment.
• Load testing of lifting equipment.
• Tension screw.
• Dimension Control.
• Preservation.
Electric Area
• Visual inspection of the complete and correct installation.
• Insulation and continuity testing of cables.
• Insulation test of the generator, transformers and motors, panels, distribution
board, etc.
• Grounding controls.
• Static testing of switches and control devices.
• Lighting and outlet socket checks.
• Area Completion.
Instruments / Telecommunications
• Calibration and testing of instruments before installation.
• Visual inspection of the complete and correct installation.
• Insulation and continuity testing of cables.
• Pneumatic and hydraulic pipe cleaning, washing, pressure and leak service.
• Adjust control, alarm and stop settings.
• Tests with feedback.
• Testing the function of control systems.
• Testing the function of field instruments.
• Area Completion.
• Preservation.
Pipelines
• ECM performs.
3
7
“UMBVirtual
U Quality higher education
• Welding procedures.
• Removal of all items subject to damage during washing, cleaning and pressure
testing.
• Reddening of pipes.
• Cleaning and testing chemical pipes.
• Proven pipe drying.
• Pipe preservation tested.
• Resetting all items after testing.
• Final pipe inspection.
• ISO testing and P&ID reveal the magnitude of each pressure test.
• Tire and hydraulic tube.
• Tension screw.
• Pipe supports completed.
• Isolation.
• Coding flow.
HVAC
• Visual inspection of the complete and correct installation.
• Duct cleaning.
• Checking the tightness of the ducts.
• Alignment checks.
• Mechanical functions inspections of devices.
• Preservation.
• Coding flow.
Security
• Visual inspection of the complete and correct installation.
• Preservation.
• Area Completion
3
8
“UMBVirtual
U Quality higher education
Protection
Surface, Insulation and Fire Testing
• Visual inspection for complete and correct application.
• Thickness controls carried out.
• adhesion checks carried out.
• Preservation.
• Isolation.
• Paint.
• Protection against the fire.
Architecture
• Visual inspection of the complete and correct installation.
• Preservation.
• Doors.
3
9
“UMBVirtual
U Quality higher education
Design capabilities
The maximum design capacity and minimum design capacity are defined in the
tender document elsewhere.
You must write necessary procedures and obtain company approval before beginning
work and perform the work in accordance with approved procedures. In addition to
completing as many of the pre-commissioning activities underway as possible in the
manufacturing yard to minimize work time.
A guide to carry out pre-commissioning activities in the yard/offshore is given below.
4
0
“UMBVirtual
U Quality higher education
4
1
“UMBVirtual
U Quality higher education
4
2