Risk Prevention Manual in Road Works V1
Risk Prevention Manual in Road Works V1
an al of the risks
E_ Signaling
the works vials
F_ B ibliography
G_
ACHS
Documents
H_ Annex support
os
Sais #len
Prevention
_ The objective of this manual is to serve as a basis for supervisors,
prevention experts and operators of companies in the construction sector to
be informed about the risks of the processes carried out during the execution
of a road works project.
In order to get the most out of this material, we recommend carrying out the
following activities:
2. Take into account the content to complete and improve the company's
own induction process for new workers.
Index
Introduction 03 page . The escarpment
. Recommendations for excavations, cutting and
Scope and objectives 03 page filling
. Scope and objectives . Preparation and placement of asphalt
. Scope for pavements
. Goals . Pavement concreting
. Pipe installation
The main processes . Installation of sills and sills
in road works 04 page . . Construction of civil works
. Implementation of installation of tasks . The use of machinery
. Rubbing tasks, material removal and tree felling . The use of tools and equipment
. pavement demolition . Working with explosives
. The escarpment . Storage warehouses
. Cutting or excavating land . The workshops
. Land filling and compaction . Fire prevention
. Asphalt for pavements
. Pavement concreting Signage in the
. Installation of pipes roadworks 32 page .
. Installation of sills and sills . The signage plan and security measures
. Construction of civil works . The work areas
. Signs and safety devices
Risks prevention . Basic signaling schemes
in road works 11 page . . Recommendations and duties of workers
. The design and implementation of the
slaughter facilities Bibliography 36 p.
. Electrical installations
. General measures ACHS Supporting Documents37 page
. Recommendations for operations
friction, removal of material and felling of trees
Annexes 38 p.
2
E
S
A
•mm
Introduction
Road works are the construction works of a surrounding the workplace.
communication route, which may be a road, a These situations must be considered from the
railway or a viaduct. beginning of the project and included in the
technical specifications of the tenders, so that the
In their construction and conservation stages, road companies that are awarded the contracts adopt in
works present risks that can be the cause of their organization the measures and resources that
accidents with serious consequences for people, are necessary to carry out work in good conditions.
facilities, equipment and the environment acceptable safety standards.
In this sense, the development of processes to build roads, bridges or other works that have interaction with
third parties, as well as adverse weather conditions and other external factors, give rise to additional risks.
A/B
3
p Risk prevention on construction
sites
roads for the Construction Sector
The next chapter analyzes the risk control measures applicable or recommended in each case.
A work facility is the set of minimum necessary facilities used as physical support during the
development of the project and is made up of buildings or containers, sheds, installation of water,
heating, electricity, sewage, gas or other services whose purpose is to provide administrative
support. and logistical for the work, which may be offices, laboratories, parking lots, dining rooms,
booths for the caretaker or guard, warehouses, hygienic services for staff, workshops for the
maintenance of vehicles and/or machines, waste collections, collections for materials, camps,
perimeter closures, among others.
The natural surface of the land must be cleared of all vegetation (trees and trunks, roots, bushes,
grass). This work must be carried out in the areas intended for the construction of roads,
embankments, structures and, in general, it is carried out before the construction of the works, so
its partial execution can be scheduled according to needs.
Rubbing: Removal of plant material and garbage on the surface of the work area.
c
4
Machinery and tools used
The following machinery is used in this activity: motor graders, front loaders, backhoes and hopper trucks, chainsaws,
among others.
3 _ Pavement demolition
It is the demolition of existing asphalt or concrete pavements when they interfere with the
execution of the works or must be replaced by a new paving structure, considering the cutting,
demolition, removal and transportation to the authorized dump.
Machinery used
In this activity the following machinery is used: cargo trucks, mini loaders adapted with hydraulic hammer, excavators,
backhoe; and manual demolition and cutting equipment such as jackhammers and saws.
_
4 The escarpment
The escarpment is the extraction and removal of the surface layer of topsoil. It is carried out in all
those areas where embankments are supported, slopes of existing embankments in the case of
widening and in general, where indicated in the project specifications.
Machinery used
The machines used in this stage are hopper trucks, motor graders, front loaders, excavators,
tank trucks and hand tools such as saws, shovels and pickaxes.
This task is necessary to reach the levels established in the project, in order to reach the
foundation seal in areas that will be paved and those where the different road infrastructure works
c
5
p Risk prevention on construction
sites
roads for the Construction Sector
will be founded.
Machinery used
The machines used in this stage are backhoes, excavators, motor graders, front loaders, hopper
trucks, tank trucks and compactor rollers, among others.
6_
Filling and compaction of land
The fills can be carried out with soil from the same excavation, from ditches or any nearby area
(treated in a site aggregates plant, in some cases), as long as they are selected clean and natural
materials that comply with the technical specifications defined in the project.
The material is placed on the ground using trucks or other dumping equipment and spread using
motor graders, loaders or other similar equipment.
This stage also includes the compaction work required to form the road platform at subgrade level,
leaving it in suitable conditions to receive the following layers, such as sub-bases, bases or any
other specified.
Friction: That which is formed by placing and compacting the material in horizontal layers. The
thickness depends on the technical specifications of the project, as well as the humidity required
by the material depending on the Proctor test (laboratory test) for maximum compaction.
To measure the humidity and density of soils, bases, concrete and asphalt, the Nuclear Density
Meter is used, which is a portable device that emits ionizing radiation and is classified as 3rd
category radioactive equipment.
Machinery used
The following machinery is used in this activity: excavators, motor graders, front loaders, hopper
trucks, tank trucks, compaction rollers, vibrating plates and topographic equipment, among
others.
c
6
7 _ Asphalt for pavements
The first phase of this process is the Then the asphalt mixture of rolling and binder
application of an asphalt spray on a base or is added, which is used on the underlying
sub-base to waterproof, prevent capillarity, layer or an old pavement, in order to provide
cover and bind loose particles and provide structure to the new pavement and support
adhesion between the base or sub-base and vehicular traffic directly.
the layer immediately above.
On some occasions, asphalt mixtures can be prepared in plants installed on the same job site.
These plants combine aggregates with heated asphalt cement and carry out the drying and mixing
process.
Machinery used
Machines used in laying asphalt: Asphalt rollers, asphalt compaction rollers, primer truck, slurry
truck, finisher.
8 _ Pavement concreting
The molding system used in this process can be fixed or mobile molds and finished by hand or by
machine. Concrete curing is done with waterproof membranes, wet burlap or water mist.
Contraction and expansion joints are constructed with mechanical cutters, by sawing a slit in the
pavement using diamond concrete discs. The joints will finally be sealed.
Machinery used
Concreting: Manufacture,
Machines and tools used for Concreting: Mixer
transportation, arrangement, spreading,
truck, paving train, vibrating truss, equipment for
leveling and compacting of concrete for
curing membrane application.
pavement and sidewalks
c
7
p Risk prevention on construction
sites
roads for the Construction Sector
9 _ Pipe installation
This task consists of the installation of a set of pipes for sewage, drinking water, rainwater, canals
or others.
1. 2. 3. 4. 5.
Opening Fillings Sewer system Compaction Others
of ditches soil processes
^//////////////////////////////////////////////// /////////z
All of this requires adequate knowledge of subsoil conditions, so a study must be carried out to
locate existing installations, cable channels and other underground works. These pipes are
supported on a bed of sand, which is used to stabilize the bottom of the excavation and which is
built as a template on site to receive the pipe.
Machinery used
Machines and tools used for pipe laying: boom truck or crane, mobile crane, fusion equipment.
They can fulfill functions such as restriction limits for pavements, sidewalks, passages and
pedestrian circulation routes or as separation elements for gardens and squares, among others.
_
11 Construction of civil works
Civil works are complementary to road works. For example: overpasses, retaining walls in
underpasses, walkways, bridges or others, coupling and union of prefabricated reinforced
c
8
concrete structural elements or metal drop structures.
> Accidents
Generally due to unsafe actions by pedestrians and drivers or due to lack or poor
signage. The operation of trucks, machines or vehicles in reverse.
> Entrapments
> Injuries
c
9
p Risk prevention on construction
sites
roads for the Construction Sector
> Falls
And injuries in excavations, traffic areas and non-standard work surfaces (ladders, runs, scaffolding).
> Accidents
Moment when the truck hopper may come into contact with
nearby overhead power lines.
> Poisoning
> Hits
1
0
1 _ The design and implementation of work facilities
Some factors that must be kept in mind for the design of the layout or floor plan of the work facility and the
traffic routes within the area:
To install a site, it is necessary to have the corresponding municipal and sector permits and comply with
current regulations – for example, the General Environmental Bases Law.
1
p Risk prevention on construction
sites
roads for the Construction Sector
1.1
_ The provision of drinking water
Every workplace must have drinking water for human consumption, basic hygiene and personal
hygiene needs. The facilities, artifacts, pipes and complementary devices of drinking water services
must comply with current legal provisions on the matter 1 .
1.2
_ The disposal of liquid and solid waste
Flammable or explosive substances, corrosive or abrasive water, living organisms and, in general,
any substance or industrial waste that could cause a risk or damage to the health of workers or a
deterioration of the environment cannot be emptied into the public sewage network. .
1.3 _
Hygienic services and wastewater evacuation
Every workplace must be provided with hygienic services with a toilet and sink, according to the
amount established in DS 594 2 , according to the number of workers on the job.
Each toilet should be placed in a doored compartment with permanent divisions; If it is not possible to
install toilets connected to the sewer network, it is recommended to install chemical toilets.
The installation of heaters for hot water service must comply with current regulations, especially the
combustion gas discharge systems.
Where men and women work, there must be independent and separate toilet services, which must
be kept protected from the entry of vectors, in good working order and cleanliness.
1
2
y
e
DS 594. Regulation on basic sanitary and environmental . DS 594. Regulation on basic sanitary and environmental
conditions in workplaces. conditions in workplaces, article 27.
. DS 594. Regulation on basic sanitary and environmental . DS 594. Regulation on basic sanitary and environmental
conditions in workplaces, article 21. conditions in workplaces, article 9.
p Risk prevention on construction
sites
roads for the Construction Sector
2_ Electrical installations
This task consists of the installation of a set of pipes for sewage, drinking water, rainwater, canals
or others.
1
6
eit
he
Y
o
> CRANE INSTALLATION > RESTRICTED ACCESS
Construction work carried out near energized Access by unauthorized persons to areas where
overhead power lines must consider the location energized equipment is located must be prohibited.
planned for the installation of cranes and other fixed
equipment and the radius of action of their parts.
1
p Risk prevention on construction
sites
roads for the Construction Sector
3 _ General measures
Before starting work, the personnel involved must be instructed on the risks to which they are
exposed, the correct work methods and the risk prevention measures to apply in each case.
Personnel must be provided with all protective elements, with the mandatory use of a helmet,
glasses, hearing protectors, reflective vest, safety shoes and leather gloves, in addition to
what is stipulated in the Highway Manual, chapter 6.8 .
Workers involved in the assembly of structures at height must wear a safety harness attached to
a lifeline during the entire time of risk of falling.
4_
Recommendations for rubbing operations, material
removal and tree felling
To carry out this type of work, it is To minimize the occurrence of wildfires, bushes, prior to cutting them and
necessary to have municipal permits workers should be instructed not to clearing the area, especially in places
when applicable and comply with produce sparks, open flames, or smoke where there are overhead electrical
current regulations (for example, the in brush removal or tree cutting areas. wiring.
Forest Law). Determine the angle of fall of trees and
8 Chapter 6 of the Highway Manual, called “Road Signage”, MOP-DGOP, Directorate of Roads, Chile 2013.
1
8
The demolition of 6 _ The escarpment
pavement
To carry out this process, vehicular and located less than 0.6 m from the edge of the
pedestrian traffic must be controlled through excavation.
the use of road signs (See Road Works
Before starting the work, fix low and high voltage
Signage Manual) with the support of a
electrical cables on the lighting poles, be aware
signalman, as established in the Highway of electrical chambers, sewage, gas supplies,
Manual, chapter 6 69 : drinking water, oil pipelines or any other
interference in the work that causes an accident.
. The cutting or demolition layout area must or material damage.
be kept fenced, marked and clear. The
transit of vehicles or outsiders is not permitted Keep the personnel involved out of the turning
inside the work area. radius of the backhoe and its boom, if it is
tracked, and out of the forward and reverse axis
. Demolition of the pavement with pneumatic
of the motor grader, not allowing personnel, not
hammers is carried out by checking the even the driver, on the sides of the trucks while
condition of the air compressor, hoses they are are loaded.
and their connections. Staff must use
hearing protectors.
. If the pavement demolition is carried out
with a hydraulic drill mounted on
machinery, it must have a qualified
operator and the hydraulic system must be
verified for leaks or oil spills.
. The removal and loading of the debris onto
a truck must be carried out in compliance
with the safety measures established for
the installation of the tent in order to cover the
hopper.
The work area must be marked and there
must also be personnel to control the exit of
trucks when they enter directly into the
circulation routes and to support the
machinery when it refers to setbacks that are
complicated by the configuration of the
terrain or the entry and transit of personnel
outside the work.
2
0
7 _ Recommendations for excavations10 , cut and fill
•2
1D---------------------------- No person should be located on the
The material from the excavation and
edges of the excavation, at the back or Excavations must be properly protected
the fill material should be stored as far
in the vicinity of the turning radius of the around their perimeter and marked with
as possible at a distance equal to or
backhoe or boom if it is on a track, or warning or danger signs, depending on
greater than half the depth of the on the sides of the trucks when they are
their magnitude.
excavation. The stockpile should never being loaded. Before carrying out the
be located less than 0.60 m from the excavations, any risk conditions such
edge of the excavation. as electrical, aerial or underground
lines, cameras and underground lines,
whether sewage, gas, electrical or
telephone lines, must be verified. Also
verify that there are no oil pipelines in
the sector.
•4-------------------------------------------------- -5
The excavation slope must comply with the The shoring system must be complied
angle defined in the soil mechanics report, with, if the soil mechanic has
2
p Risk prevention on construction
sites
roads for the Construction Sector
established it.11 . •6
Ladders should be installed at least
every 15 m so that workers can enter
and exit the excavation.
2
2
•7 •8 •9
To determine the density of the land, the The operator must be authorized by the You should always carry your personal
nuclear densimeter 11
is used. Ministry of Health, after completing the dosimeter, and check the accumulated
radiation protection course and having dose periodically.
obtained its operating license.
• 10 • 11 • 12
You must always comply with the When transporting the equipment, it must The densimeter must not be transported
minimum distancing for yourself and third be carried inside the box, anchored to in the vehicle cabin. It must be tied to
prevent damage or theft, and inside the
parties and mark the work area. the vehicle, with a lock and at the point of
box the emergency procedure in case of
the vehicle furthest from personnel.
theft or loss must be placed, detailing the
name of the company, emergency
telephone numbers and address. You
must also have a log that indicates days
and hours of entry and exit from the
storage warehouse site and the name of
the operator.
2
p Risk prevention on construction
sites
roads for the Construction Sector
Although asphalt, under normal environmental conditions, is considered non-toxic, its contact with
the skin can cause inflammation or dermatitis in some people. Likewise, the preparation process
and its use at high temperature and mixing with solvents may present the following risks:
1.
Dangers of
2.
Injuries from
3.
Contact at
4.
inhalation of
fire Burns discharge toxic gases
All asphalt materials can burn if heated sufficiently. The fire risk of diluted asphalt varies
according to the class and grade of the product. Among the main factors that influence its
flammability is the volatility of the petroleum solvents mixed with the base materials.
'^/^^//////^^^^
ATTENTION
When handling these materials, the information contained in the safety sheet
provided by the manufacturer must be studied.
^/////////^^
2
4
8.2_ Burn injuries 8.4_ Inhalation of vapors and gases
from hot asphalt
Skin contact with hot asphalt (160°C) can
cause serious burns. During the loading/unloading stages of
If molten asphalt comes into contact with the asphalt, gases and vapors emanate from
skin, it should be cooled quickly with cold asphalt cement or some of its solvents,
water, while removal of the asphalt from the which can cause dizziness or suffocation,
skin should only be carried out by a doctor. and irritation of the skin and/or eyes.
In case of extensive burns, cover with sterile If a worker comes into contact with the
cloths and take the patient immediately to material, they should immediately rinse
the hospital. their skin or eyes with plenty of running
water and soap for at least 15 minutes, in
addition to removing contaminated
8.3_ The discharge of asphalt into shoes and clothing.
ponds
9 _ Pavement concreting
For concreting pavements, the areas with unevenness and working radius of the equipment must
2
p Risk prevention on construction
sites
roads for the Construction Sector
be delimited, verifying the stability of the slope edges for the operation of trucks and other
machines.
The operating status of the irrigation truck must be verified, such as that of the irrigation bar
nozzles and the use of visual protection elements and gloves.
_
10 Pipe installation
To guarantee the reliability of the lifting elements, the cables, slings, slings and all the elements
used must be inspected daily. The lifting elements must be certified for their use and must be
suitable for the load they must support.
The rigger or signalman is in charge of coordinating the maneuvers with the crane operator for
the installation of the pipes. For tasks with the risk of falling from an uneven level, the signalman
must use a safety harness with its respective strobe and lifeline.
When making cuts to these elements, respiratory and hearing protection must be used.
_
12 The construction of civil works
Due to the great variety of civil works that may be required during the execution of a project,
specialists must carry out detailed analyzes of the risks present in each case, according to their
nature, scope and form of work, and develop work procedures. safe and instruct the workers who
participate in its execution.
In general, the use of scaffolding and work platforms is regulated by technical standards.
2
6
E
S
>7 >8
Special care must be taken during fuel loading operations in Mechanical inspection and maintenance must be carried out
vehicles in order to avoid a fire. by qualified personnel in order to avoid accidents due to
entrapment or contact with hot surfaces.
27
p Risk prevention on construction
sites
roads for the Construction Sector
The most used tools and equipment in road work tasks are: pavement cutter, vibro-
rammer, plate compactor, demolition hammer, immersion vibrator (electric and gasoline)
and generators, among others.
Inspect equipment daily. The worker who will operate them must check
if it has a ground connection, the condition of its cable and plug, and if
its casing and handle are in good condition.
The piping from the control panel to the engine must be protected from
impacts, abrasion, acids, oils or other corrosive agents.
Fuel must be filled with the engine stopped and, before resuming work,
>8 any fuel spills that may exist must be cleaned.
2
8
E
S
_
15 Working with explosives12
The personnel that handles, programs and extinguishers and must carry a flag with the
calculates the use of explosives must be regulatory colors.
registered with the General Directorate of . Vehicles must be fueled before loading
National Mobilization and the companies explosives.
The explosives must be transported separately
that handle explosives must be registered
from the detonators, they must be wedged and
with the competent authority as well as
tied, and only 80% of the truck's capacity will
their workers, who must have their license.
be used.
To transport explosives, you must have a free
To load or unload the trucks, they must be
transit guide.
located at a minimum distance of four meters
from the place where the explosives are
. For the transport of explosives, the good stored, and the loading and unloading must be
general, mechanical and electrical carried out by authorized personnel and with
condition of the vehicles must be
natural light.
guaranteed, their body must be made of
The place where explosives are stored must
material with antistatic characteristics (that
does not produce sparks), closed and the be approved by resolution of the General
surfaces must be clean and dry. Directorate of Recruitment of the Armed
Additionally, it must have a grounding Forces, and the magazine must meet certain
device for static electricity. Engine exhaust requirements, according to Law 17,798.
pipes must have spark suppression Frozen, exuded or damaged explosives cannot
devices. be delivered to workers.
. Vehicles must carry at least two fire In the event of an electrical storm in the area,
12 Decree 400, year 1978, Establishes consolidated, coordinated and systematized text of Law No. 17,798, on arms control. Supreme
Decree No. 77 Complementary Regulation of Law No. 17,798 on arms control and similar elements of the Ministry of National Defense,
Undersecretary of War.
29
p Risk prevention on construction
sites
roads for the Construction Sector
3
0
E
S
16 _ Electrical installations
Warehouses must have sufficient space for truck access, equipped with unloading platforms or
forklifts, if the volumes and quantity of the cargo justify it. The interior area must be calculated for
storage, personnel traffic, and access for smaller vehicles for material handling.
>1 >2
Have good ventilation and lighting and Have hand scales designed to Have chemical powder
avoid storing flammable materials and reach upper shelves. extinguishers inside and near the
materials. Minor items and spare parts these fuel warehouses, at least
Compressed gases, oxygen and acetylene are located near the workshops, outside them,
protected from heat and marked. The premises must be ventilated, placing oxygen and acetylene
in separate rooms. Cylinders must be kept with their lids permanently, especially when
transported or handled.
31
y
e
s
13 DS 47 year 1992, General Urban Planning and Construction Ordinance, Ministry of Housing and Urban Planning.
14 Safe Storage of Chemicals Manual
15dangerous, Subdepartment of Risk Prevention and Occupational Health, Regional Ministerial Secretary of Health Metropolitan Region.
p Risk prevention on construction
sites
roads for the Construction Sector
17 _
The workshops
Mechanical, electrical, concrete iron preparation, carpentry and signage workshops must be built
in strategic locations previously analyzed in order to facilitate access, avoid noise and smoke
pollution to the office sectors and control the spread of fires.
>4D--------------------- >5
To use reflective paints, inhalation of vapor or spray mist must
When welding or oxy-cutting on elements that contain
be avoided, and when applied with a spray gun, the worker
reflective paints, respiratory protection must be used, due to
must use respiratory and visual protection. The evaluation of
the dust and smoke that will be released, and it must be done
the specific risks of these products must be carried out through
in a well-ventilated place.
the use of the safety sheets provided by their suppliers.
3
0
18 _
Fire prevention
During the execution of a road works project, fire risks arise that can affect facilities and equipment.
Among the main control measures to prevent its occurrence are indicated below:
Keep workplaces clean and remove garbage in places where explosive mixtures are present.
periodically, while rags soaked in oil or grease and
other combustible substances should be placed in Know the electrical capacity of the circuits so as not
covered containers and emptied regularly. to overload and overheat the electrical conductors.
Never change a lower amperage fuse for one with a
Prohibit smoking in places where fuels, hydraulic higher amperage.
oils are worked or stored, and explosives are
handled or transported. Avoid improvised installations on already calculated
circuits.
When using flammable substances, good
ventilation must be provided. In addition, containers Hot work (welding, oxycutting) must be controlled. It
containing flammable liquids must be grounded to is recommended to use a hot work permit
avoid sparks due to static electricity.
procedure, especially when these are carried out in
the vicinity of combustible materials or machines.
Repair electrical installations and equipment that
have damaged insulation.
Control the use and storage of the fuel gases used
(acetylene, liquefied gas) in accordance with the
Eliminate or repair defective tools or electrical
provisions of Chilean NCh standards.
equipment, as they can cause explosions and fires
3
p Risk prevention on construction
sites
roads for the Construction Sector
Current legislation 16 clearly indicates that anyone carrying out work on public roads is
obliged to install and maintain, day and night, signage and safety measures appropriate
to the nature of the work.
Regarding the responsibility for damages caused in accidents due to non-compliance with the
provisions of the previous paragraph, this falls on those who execute the work and those who
commission it.
The purpose of this chapter is to define the concepts and technical indications related to
signaling and its security measures.
1_
The signage plan and security measures
In accordance with the provisions of current legislation, whoever carries out work on public
roads, whether streets or roads, must develop a signage plan and safety measures.
The signage plan for the work establishes how the normal movement of vehicles, cyclists and
pedestrians will be affected and the measures to mitigate adverse effects. You must consider
all the construction phases that the work entails and how the signage and safety devices will
evolve according to said changes.
to. Definition
Signage and safety measures plan: Document that clearly establishes the way in which
road safety will be addressed as a result of the execution of work. This document will be
prepared by an accredited professional in the field and will have to be approved by the
respective entity or the Highway Department.
A
N
The work areas
It is essential to identify the work area on the road. Areas in the work zone
f.01
From the point of view of road safety, areas or
sectors are defined that allow, as a whole, to
improve the operating conditions and the safety of
the different users.
>1
Warning zone: That prior to geometric changes. There is no
construction in this area and it is used to warn users that
©
road conditions will change. In this area, the driver must
Channelin
modify his or her driving style and be attentive, following the g Element
indications of the signs provided. What the driver must
understand is that the use of the tracks and the maximum
speed at which they must travel will probably change. At the
beginning of this warning zone there will always be the sign
“Road Work”, the first temporary sign in all types of work.
Safety
Length
>2
Transition zone: That in which vehicles begin to gradually
deviate towards the lanes that have been left for circulation.
This is the beginning of the detour and must be done with
channeling elements, as described later. This area is also
Transition
known as the initial wedge. Length
>3
Safety zone: Protection area that separates traffic from the
work area. Its purpose is to have a clear sector in case a
driver who accidentally crosses this area has enough space
to exit it before entering the work area.
Lenght of
Warning
A
N
• •p Risk prevention at construction
sites
roads for the Construction Sector
> 6D
>4 >5
End of work zones: Area used for
Work area: That intended for Transit zone: That intended for traffic to return to the traffic
works, worker operations, vehicular flow, it being necessary to conditions it had before the work
machinery and materials collection. set and sign the maximum speed at
zone.
which it must be traveled through.
If required, restraint barriers should
This speed must be credible and
be included when the risk of falling
corresponds to the maximum speed
is significant or when it is required at which vehicles can travel safely.
to provide additional protection to
workers who, due to the nature of
the work, get too close to the traffic
area.
_ 4_
3 The signs and The schemes
safety devices signaling basics
To enable each of the work areas on The most common schemes used in
the road, it is necessary to install works carried out in urban or rural
different types of signs and elements: areas are shown in the ACHS
Signage Manual for Road Works.
. Vertical signs
. Pipeline elements
. Demarcations
. Traffic control systems
. Elements to increase the visibility
of workers and vehicles
A
N
Recommendations and duties
from the workers
To avoid incidents that could cause injuries to workers, general instructions must be established:
Do not cross the security zone Personal protective equipment Do not cross the traffic area
unless absolutely necessary and must be used and available at all unexpectedly.
with the utmost caution. times.
Keep the security area clear and Do not carry out traffic control Maintain respect for pedestrians
clean. tasks if you do not have adequate and cyclists.
training.
A
N
Heavy machinery operators must A traffic control crew must be in
take extreme driving precautions charge of and keep signage
and consider that third-party traffic related to the work in good
condition and in place.
will be at a speed
elderly.
A
N
p Risk prevention on construction
sites
roads for the Construction Sector
Bibliography
NCh 349 Of.1999. Construction . Safety provisions in excavation.
Supreme Decree No. 594. Regulation on basic sanitary and environmental conditions in
workplaces.
Decree 400, year 1978. Establishes consolidated, coordinated and systematized text of Law
No. 17,798, on arms control.
Supreme Decree No. 77. Complementary regulation of Law No. 17,798 on weapons control
and similar elements of the Ministry of National Defense. Undersecretary of War.
DS 47, year 1992. General Urban Planning and Construction Ordinance. Ministry of housing
and urbanism.
Manual for safe storage of hazardous chemicals. Risk Prevention and Occupational Health
Subdepartment, Regional Ministerial Secretary of Health Metropolitan Region.
Decree 78, year 2012. Traffic Signaling Manual. Ministry of Transport and
Telecommunications.
F
36
ES
ACHS Supporting
Documents
. Data sheet:
A. Channeling elements.
B. Vertical signs.
C. Traffic control systems.
D. Types of soil.
E. Slopes.
F. Shoring.
. File by Job:
G. Compactor roller operator.
H. Vibrating plate operator.
I. Backhoe operator.
J. Mini loader operator.
K. Hopper truck operator.
L. Front loader operator.
M. Nuclear densimeter operator.
N. Bulldozer operator.
O. Motor grader operator.
P. Excavator operator.
Annexes
Appendix 1
Inspection guideline
“Verification of safety conditions in road works”
CODE LV-037 V_01
h
38
Appendix 1
Inspection guideline
“Safety conditions for work at height.”
Company
Associated Company Number
Ruth
Branch Address
Commune
No. Workers No. of Own Workers: No. of Contractor Workers:
ACHS Expert Name
Agency
OBJECTIVE: Verify compliance with the safety conditions necessary for the Road Works process.
SCOPE: This list applies to all construction companies associated with the ACHS, which carry out Road Works.
Highway
3. Do you have properly signposted pedestrian
Manual Verify on the ground.
traffic routes?
Cap.6/2013
4. Is the electrical installation at work approved by NCh 350 Request Annex 1 granted by the Superintendence of
the competent authority? Of.2000 Electricity and Fuels.
h
39
p Risk prevention on construction
sites
roads for the Construction Sector
6. Is there a specific place for parking locked
vehicles and machinery during and after the work
day? Verify on the ground.
Law 20,001
13. Is the distribution of drinking water on the Year 2005
ground in drums that do not exceed 50 liters?
Verify on the ground.
14. Are the drums labeled on both sides indicating
“Drinking Water” and the number of liters?
h
40
yes
ns 594
21. In the event that men and women work? DS 594
Women, do you have separate toilet services?
Art.22
25. Are there chemical toilets in places where it is Verify on the ground.
not possible to install toilets connected to the DS 594
Art.24
sewer network?
ns 594
26. Are the toilets and/or bathrooms D.5
h
41
p Risk prevention on construction
sites
roads for the Construction Sector
chemicals are located less than 75 m. of the work
area? Art.25
h
42
COMPL LEGAL OBSERVATION
5. FIELD WORK Y REGULAT GUIDANCE/EVIDENCE S
YES/NO ION
27. Have the hazards been identified and the risks Request hazard identification
Highway
Verify in the field that workers
Manual
29. Do workers have appropriate personal use a helmet, safety shoes,
Cap.6/2013
protection elements to perform tasks? goggles, reflective vest or other
appropriate element.
h
43
p Risk prevention on construction
sites
roads for the Construction Sector
38. Do machine and truck operators have a valid Request operators license.
driver's license?
COMPL LEGAL OBSERVATION
7. ROAD SIGNAGE GUIDANCE/EVIDENCE
Y REGULAT S
YES/NO ION
39. Do you have a signage plan and safety
Request the written document.
measures for the work?
44. Have the flaggers passed the course that Request training registration.
DS 78
accredits them as such?
Of.2000 MTT
h
44
COMPL LEGAL OBSERVATION
8. NUCLEAR DENSIMETER GUIDANCE/EVIDENCE
Y REGULAT S
46. Is the operator of the nuclear densimeter YES/NO ION
Request a license from the
authorized by the Ministry of Health?
densimeter operator.
DS 78
Of.2009 Request explosive storage
52. Is there a storage procedure?
MINSAL procedure.
h
45